Académique Documents
Professionnel Documents
Culture Documents
This type of works involves the measurement of a number of components comprising a combination of concrete, steel reinforcement and formwork. The measurement of a reinforced concrete structure requires a clear and logical approach to the order of the take-off so that items are not missed. The work may be subdivided into several parts of the building then taken off floor by floor, measuring the concrete, formwork and reinforcement for each floor. In some instances it may be more practical to measure all of one type of structural components, such as columns, throughout the building. It is also advisable to measure the associated formwork after the concrete so that is not overlooked, and in any case the same dimensions are usually applicable.
Columns
Columns should be measured between floors; in counting the number of columns, one column is taken at each grid point on every floor level. n two story building there would therefore be two columns at each point, one on the ground floor and one on the first floor. The concrete is measured in cubic metres. The formwork to simple columns is measured as a superficial item, taking the concrete length multiplied by the girth and stating the total number of columns. This allows the estimator to value the cost of forming the column kickers, which are not measurable, and to add on allowance per square metre to the column formwork
!
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
4
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
5
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
+
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
Beam
%eams should be measured between the columns. 6here these are attached to concrete slabs then the volume of concrete is added to the slab concrete ,/+.a-. this does not affect the description of the slab because it is the general thickness that is given in the description. The formwork to the sides and soffit of the beams is measured as a superficial item using the concrete length and cross - section si0es to obtain the superficial area. 6here beam sides and floor edges coincide, the floor edge is added to the girth of beam formwork. There is no need to make any deduction from the measurements for 7unctions of members,1!!-.
)
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
8
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
Walls
6alls are measured in the same way as slabs and it should be noted that they include attached columns in the same way that the beams were added to the slabs. It is common practice to cast a small part of the wall with the slab. This is called a wall kicker, although it makes no difference to the concrete measure, it does affect the formwork. & linear item is taken for the wall kicker and measured on the center line of the wall; the price is to include for formwork to both sides. .ormwork to walls e(ceeding 5m high needs to be identified and kept separate.
9
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
:
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
Reinforcement
The '11 requires that the weight of bars shall include that for bends and hooks2 for each hook, one can usually add nine times the diameter of the bar rounded to the ne(t !* mm. if the length of the concrete is used for calculating the length of the bar, then the concrete cover must be deducted, i.e. in the case of a !4mm bar !!*mm must be added at each end less the amount of concrete cover. It is measured linear and then converted to weight prior to billing. The calculation of number of bars generally follows the approach used in dealing with rafter or floor 7oist. The distance between first and last bars is divided by the spacing of the bars, and by adding one to the result the number of bars can be calculated. .abric reinforcement is measured superficially to the actual area covered, the estimator allowing in the price for the loss of material due to the laps.
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
The concrete and formwork items are followed by the steel reinforcement measured linearly in the firs instance, to subsequently converted to weight. 'traight, bent and curved bars are distinguished from those in links, which include stirrups and binders, and each diameter of bar is kept separate ,35*2.!.!.!-+.*-. The remaining items in the staircase are then taken, including the surface treatment of concrete, where appropriate, granolithic paving to treads and risers and associated work. The metal balustrading is measured under an appropriate heading in metres with a dimensioned or component drawing ,$5!2.4-, followed by e(tra over enumerated items for ornamental ends and the likes to handrails. .inally painting to balustrading is measures in m< as 18*29.!.!.*
E05:13
E20:9
Group E ercise =ead the 'ection 3!*, 34* and 35* and identify the relevant classification, measurement rules, definition rules and coverage rules which describe the above work items.
!*
"T# $okuliyana %C&'
Advanced Measurement Lecture note No: 2 outcome No: 1 Reinforced Concrete Structures
References
Standard Method of Measurement of Building Works, Seventh Edition Revised 1998 ,$ondon2 =IC' %ooks, !;;:-. >atric ,#. ? >atric, 1. ,4**9-SMM7 Ex lained !nd "llustrated, =IC', pp)9 to ;4 'andra, $.,6illiam, T.,?6illis, &. ,4**)- Willis#s Elements of $uantit% Surve%ing& 5rd,ed., %lackwell, pp 4**-4*5
!!
"T# $okuliyana %C&'