Académique Documents
Professionnel Documents
Culture Documents
Introduction
An air-conditioning system which enables the conditions inside to be maintained can
be explained as a series of cycles:-
1. The Refrigeration Cycle.
2. The Air cycle.
3. The cooling water cycle.
The Refrigeration Cycle
For all compression type mechanical refrigeration systems, the refrigeration cycle
consists of four processes i.e.
1. Heat gain by the refrigerant in the evaporator
2. Pressure rise in the compressor
3. Heat loss in the condenser
4. Pressure loss in the expansion valve.
Compression process, that is the pressure rise is accomplished at the expense of
energy added to the compressor in the form of shaft work. The expansion, i.e. pressure loss is
allowed to occur adiabatically (with no loss or gain, of heat) in the expansion valve where the
energy released by the expanding refrigerant is not utilised for doing any external work but
causes evaporation of a portion of liquid. Basically in a refrigeration cycle the heat transfer
process does not involve any work and the pressure change processes do not involve any heat
transfer.
The four processes of refrigeration cycle can be explained in the four steps
-Thermodynamic processes.
1. Evaporation
Liquid refrigerant at low pressure absorbs heat from the space or room to be cooled
and evaporates in the evaporator or cooling coil.
In this plant chilled water cycle is additional to that of the three cycles provided in
direct A/C plants.
In this system, the heat inside the air conditioned space is picked up by cold supply air, which
gets heated up and this warm return air gives up its heat to the chilled water in the
dehumidifier (cooling coil) after passing over the preheater and mechanical filter. In chilled
water system, heat picked up by the chilled water is given up to the refrigerant at the chiller.
Refrigerant vapor gets compressed in the compressor and gives up the heat at the condenser
to the water, which is taken to the cooling tower and given up in the atmosphere. Thus by a
series of heat transfer process, both the heat entering the conditioned space and the heat
produced inside it are given back to the outside atmosphere. In chilled water plant, the boiling
refrigerant is not used to extract heat directly from the air. It is used for chilling water to a
low temperature and this chilled water is circulated through the cooling coil, where it picks
up heat from the air passing over its surface and comes back to the chiller to be chilled again.
A separate pump set is used for circulating this chilled water. This is known as the chilled
water system or indirect system because heat is first removed by chilled water. Where as in
direct system the heat is directly picked up from return air and given up at cooling tower.
1. Introduction: -
With the advancement of science and technology, specially the
Besides the industrial need, the Air conditioning is used for human comforts.
Even in the household it serves the people in the form a refrigerator, deep
fridger, so, its need is felt from household to the office, work place, industries,
shops etc.
This booklet includes giving the reader the most basic knowledge of Air
conditioning and refrigeration.
2. Objective:
The objective of this booklet is to give the knowledge which will make a
person capable to attend the minor defects arising out of day to day working and to
carry out the preventive maintenance of the Air-cooled Air Conditioning system or
units.
3. Terminologies:
Air conditioning engineering required some technical terms to be
frequently used. These terms are described below.
b) To maintain humidity:
As per the latest practice in the department the relative humidity in the
switch room to be maintain at 45% ± 15 %. Means the switch room relative humidity
range is to be 30% to 60%.
The relative humidity in the switch room is controlled by apparatus dew point
temperature. It is well known fact that cooling coil or the evaporator does two
functions. One is removal of heat by absorbing heat from the air conditioned area
and other function is to remove moisture by condensing it into water droplets. The
former one is sensible cooling and the later one is latent cooling. The total cooling of
the evaporator remains same. Only the division between these two functions can be
adjusted by regulating the apparatus dew point temperature.
d) Fresh Air:
Many times the air conditioned space is also utilized for human
occupancy. The human being requires oxygen for his breathing. So fresh air is
supplied to the air conditioned space to provide sufficient oxygen for human
occupancy. The fresh air is taken from outside, from a place which has high oxygen
content. The fresh air contains higher quantum of heat, moisture and dust particles.
So the fresh air is provided with coarse and fine filters. As per the latest circular of
the department the quantum of fresh air to be supplied is half air change per hour.
However the capacity of the fresh air fan should be one air change per hour.
Example:
The volume of the room, say – 18000cu.ft.(510 cu.mtr.)
Per hour half of this volume is to be replaced by fresh air fan i.e. 9000 cu.Ft. (205
cu. Mtr).
The air conditioners for telephone exchange are different from other
buildings. Here heat is continuously generated in the telecom racks (suite). The
quick dissipation of heat from the components is the basic need of air conditioning of
exchange building. So sufficient air velocity must be available to the racks for quick
transfer of heat from the heat generating components. So A.C system provided in the
exchange must be capable of supplying enough air with sufficient velocity to each
rack.
INTRODUCTION :-
There are various types of Air Conditioning systems and units are being used
through out the work. Keeping in view the present needs and situations a few types
of these units have been adopted by the Bharat Sanchar Nigam Limited for their use
in the Telephone Buildings.
OBJECTIVE :-
In this lesson the discussion will be done regarding the types of the A.C
units being used in the telephone exchange buildings, so that the trainees will be
able to select them as per requirement of the buildings.
Now a days the Department is installing electronic exchanges which
require constant air conditioning to maintain the desired temperature. These
exchanges are generally housed in small buildings. So, following types of Air
Conditioning units are found to be more suitable. These units are air cooled
condenser type.
1) Window Unit.
2) Split Unit
3) Package Unit.
1) WINDOW UNIT : -
It is compact unit having air cooled condenser. The design of this unit has
been done such a way that it can easily be installed or fitted in a window or a
small hole made in the wall where sufficient atmospheric air is available for
cooling of the condenser. That is why this unit is called Window unit. It is
a) Compressor
b) Condenser
c) Capillary
d) Evaporator
2. SPLIT UNIT
It is also just like window unit. It is operated on single phase A.C. supply
and having the similar components of window unit. The major difference of this unit
from that of window unit is that compressor and condenser is put together on a bed
place and installed outside of the building. The evaporator unit is made compact and
can be installed at any place of the building. The compressor condenser unit is
connected with the evaporator unit through two number of refrigerant pipes and
control cables. It means we have splitted the window A.C unit in two portions.
It has the advantage of the window A.C. unit that it does not require any
window for the installation, merely a small hole is required to draw the refrigerant
pipes and cables. It decreases the infiltrations of outside air into the room. Other
characteristics of this unit are more or less same to those of window unit.
It has some disadvantages over the window unit.
a. Length of refrigerant pipe is more increasing the cost and decreasing the
efficiency and effecting the performance of the unit.
b. It requires separate platform for installation of the
condenser compressor unit.
c. More maintenance cost than that of Window unit.
The evaporator of split unit is very handy and compact and can be
installed in horizontal and vertical positions. It is generally available in 3 TR.
5. LIGHT :
Light adds reasonable quantity of heat load. The total wattage
consumed by the light fitting/bulb is considered as heat load to the room. Now a
day’s fluorescent fitting is provided. Generally one number 4’ (feet) tube consumes
nearly 50 watts.
6. TELECOM EQUIPMENTS :
In B.S.N.L, in the switch room only Telecom Equipments are provided
with the computers etc. The heat load of the Telecom Equipments is to be taken from
D.O.T. circular No. 3-1/Director/EW/97 dated 17.7.97 (Guidelines for Optimization of
sub Station Capacities).
8. FRESH AIR :
Purpose :- Now a days every Telephone Exchange requires Air Conditioning. The
modern Telephone Exchanges install the Electronics Equipments. So, the installation
of package A.C. units is one of the most important activities pertaining to the
electrical wing.
Objective :- After discussion of this the trainees will be able to install the package
A.C units in a proper &correct method, so that during their use there will be minimum
complaints.
4.1 Co-ordination :-
The installation of package A.C. system in any building required utmost
caution and coordination from the very beginning of the construction of the
building/Exchange. After obtaining the working drawing the JTO(E)has to study the
schedule of Accommodation thoroughly, specially the package room and the rooms
which are to be air conditioned. During construction of the building following
openings are to be made either in the walls or in the floors.
a) Opening for the delivery duct.
b) Opening for the return air duct/boxing.
c) Opening for fresh air fan in the package room wall.
d) Opening for refrigerant pipes and condenser cables.
e) Opening for main cable entry.
f) Opening for supply water pipe for humidification package unit and drainage pipe
for condensed water.
4.5 Foundation :-
Foundation for the following items are to be made as per agreement.
a) Package unit
b) Control panel
c) Condenser
4.7 Ducting :
Generally G.I. sheets are brought at site and fabrication is done at
site. So following checks are to be conducted specially besides the specifications.
4.9 Brazing :-
a) brazing should be done with good quality of material and flux. If possible 3%
silver rod may be used.
b) Acid should not be used at all as flux.
c) Before brazing surfaces of the pipes are to be cleaned.
4.10 Cabling :-
4.12 Vacuumisation:
After getting the system completely leak proofed we can put the system
to the vacuumisation. For this purpose a good quality vacuum pump should be used
which is capable of evacuation the system upto 5 micron. A two stage rotary vacuum
pump is suitable for this purpose. The vacuum pump should evacuate at least
vacuum upto 100 micron. However the pump should be run for 4 hours at least, so
that the moisture content in the oil and in the system will get sufficient time to
evaporate. Now let the system be kept on vacuum for 24 hours. Slight fall in vacuum
may occur. This is due to the evaporation of moisture/water particles in side the
system. After that vacuum should stabilized. If further fall of vacuum occurs, if means
that there is some leakage in the system.
4.13 Purging :-
After leak test and vacuumisation we should do the purging. Purging
means to break the vacuum with same type of refrigerant gas and have a positive
pressure of 5 PSI. Again vacuum is to be done and purging is to be done again. After
two nos. of purging the system should be vacuumised for gas charging.
1. WINDOW AC UNIT:
a) The quantity of refrigerant gas is to be measured before charging. The quantity is
specified in the technical booklet of the machine.
b) Suction pressure should match with the operating parameters of the machine or
of the compressor.
c) Ampere taken by the machine should match with the rated ampere specified on
the machine.
d) Charging should preferably done in the summer month.
2. PACKAGE A.C.
a) Suction and discharge pressure should match with the operating parameters.
Where these parameters are not mentioned they should be obtained from the
temperature.
b) Super heat i.e. the temperature difference between the ends of the Evaporator
should be around 100F (5.60C).
c) Ampere taken by the machine should match with the rated ampere specified on
the machine.
d) We should also observed that most of the refrigerant tubes of the evaporator
should have equal temperature except the last tube, which is responsible for
super heating.
OPERATION :-
We have discussed various topics about planning design and
installation of the Air Conditioning units. To get the best out of the air conditioning
system we must keep the unit in healthy condition. Operation is the vital activity
responsible for better performance of the air conditioning unit. Normally we use
window A.C. split A.C and air cooled type package A.C. unit. Now we shall discuss
the points to be observed for better operation. Through the operation and
maintenance are interrelated we shall discuss these items separately.
MAINTENANCE :
Maintenance in Air Conditioning system is the main activity responsible
for better performance of the system. Now we will discuss the method of servicing,
repair i/c attending the defects.
1. Cleaning of Filters :-
Most of the complaints are occurred due to dirty filters. The filters may
be of various types., viz – Coir filters, synthetic filters or metallic filters. These filters
require regular cleaning. Normally cleaning once in a week may be sufficient.
However in the dusty area the frequency of cleaning may be increased.
Accumulation of dust particles on the filters chokes it and reduces the
air flow drastically. It may cause ice formation on the evaporator coil. This occurs due
to insufficient air flow through the coil and liquid refrigerant does not get enough heat
to vaporize. It may cause liquid flood back to the compressor and damage the
compressor. The choking of the filter causes overloading of the blower motor. So,
dirty filter is the major factor causing damage of the window A.C. unit.
Capacity required for SMPS , Battery, Air-conditioning , DG set and MSEB Supply
1. For the purpose of the calculating Eng Alternator capacity, following load and
their peak demand may be considered.
VII Air Conditioning Load 2.25 KVA/Ton 100% for main units
(A/C Load – Essential and nil for s/by. (*)
only)
(i) C-DOT :-
(As per information received from ADG(XT))
2K 2.5K 3K 3.5K 4K 5K 6K
7.5KW 8.5KW 9.25KW 11KW 11KW 12.75KW 15.65KW
(ii) E-10B:-
As per information received from ADG(ES-II)
2. For calculation of Eng Alternator load, telecom bldgs may be classified into
three categories.
a. G+1 bldg. at Tehsil For substation purpose, load may be taken for
Taluka (H/Q) full A/C and ultimate capacity of switch room.
capacity.
Annexure - I
Department Of Telecommunications Engineering Instructions
Clause 3: Standard operating conditions:
The standard operating conditions are:-
a) Mean barometric pressure 736 mm of mercury, corresponding to altitude
of 300 meters above mean sea level.
b) Intake air temperature 35º C
Note:- For water cooled engines, in view of the wide choice of size and type of
radiators available to meet particular site requirements, the Indian Standard rating
specified in 4.1 shall be the power which the engine would develop if the radiator fan
was not driven by the engine.
The normal power requirements of an engine driven radiator fan and a starter
battery charging dynamo shall be stated for those engines which are commonly so
equipped.
Note:- The reduction for humidity is related to the percentage (relative) humidity and
the corresponding temperature of the surrounding atmosphere.
Care should be taken to use the percentage humidity actually corresponding
to the maximum atmospheric temperature being considered. It is very rarely that high
percentage humidity is combined with very high temperature of values which justify
more than 6 percent de-rating for humidity in any part of the world, and this figure
may normally be taken as a maximum.
Inlet air at actual engine intake is, in many installation heated significantly
above the ambient atmospheric temperature, and this increase the reduction for
temperature. The reduction for humidity should not be wrongly enhanced by applying
a fitter for atmospheric percentage humidity to that locally elevated inlet air
temperature.
Where the site conditions are more favorable to the engine than the standard
conditions, an increased rating for the engine to suit the site conditions may be
agreed to between the manufacturer and the purchaser.
Example 1 –
A kirloskar engine of 200 BHP is installed at a place whose worst site condition are
given below . The engine is four stroke turbo charged without after cooling .
A) Altitude – 500 mtr
B) Maximum temp. in summer – 45 0 C
C) Humidity –30 %
Calculate the output of the engine under above mentioned conditions.
Solution :-
500 - 150
A) Duration due to altitude = x 2.5 = 1.75 %
500
113 - 86
B) Duration due to temperature = x 3 = 8.1%
10
Fuel Consumption
The engine manufacturer shall state the specific fuel consumption (SFC) at
no load and the specific fuel consumption (SFC) at rated output under the standard
reference conditions specified in section 1 of IS:- 10000(Part II) – 1980 for engines
of all ratings . All engines above 20 KW , SFC shall also be declared at 110 , 75 ,
50 and 25 % of the rated load . The consumption shall be stated in grams per brake
horse power in the case of liquid fuel engines and in terms of heat units per brake
horse power hour in the case of gas engines (based on the higher calorific value). A
typical generating set will consume above 0.3 ltrs . of fuel per KWH generated .
Power stroke
Both the valves remain closed. Fuel is injected in the form of very fine spray through
injector. Fuel ignites due to temperature . Due to heavy expansion, the piston moves
towards the BDC and the energy is stored in the fly wheel.
Exhaust stroke
. Connecting Rod: It connects the piston to the crank shaft. The function is to
transmit the force in either direction form the piston to the crank on the crank
shaft.
.
. Fly wheel: This is the heavy wheel attached to the one end of the crank shaft. It
stores up the surplus energy of the Power stroke and returns this stored energy
during other strokes.
. Cam Shaft: This is driven by the crank shaft. It controls and operates the fuel
injection pump. It also opens the inlet and exhaust valves at the appropriate time.
. Valve Gear : This is the gear wheel of crank shaft which drives the cam shaft via
spur gear.
. Spur Gear : This is the gear connected to the cam shaft. Spur gear’s and valve
gear’s teeth are so arranged that the cam shaft rotates only once for every two
rotations of the crank shaft.
.
.
. External Governor Lever: Small diesel engines are stopped by operating the
“external Governor Lever” by hand.
. Decompression Lever: It is used to leak the compression pressure of Air inside
the cylinder to some extent for making “ easy manual (starting) cranking” while
starting the small capacity engines.
Lubrication of IC Engines
Lubrication is the admittance of oil between two surfaces that are in contact
and in a relative motion, one to another may accomplish one or several of the
following purposes.
a) Reduce friction and wear.
b) Cool the surfaces by carrying away heat generated by friction.
c) Clean the surfaces by washing away carbon and metal particles caused by
wear.
d) Seal a space adjoining the surfaces, such as piston moving in a cylinder.
Methods of cooling
a. Air cooling b. Liquid cooling.
Liquid cooling
Mostly water cooling is adopted. The cylinder block is essentially a box
incorporating the cylinder barrels. Surrounding the barrels is the cooling water which
also circulates round the cylinder head. From the head a tube communicates with
upper tank of the radiator and from the bottom of cylinder block, a pipe is connected
to the lower tank of the radiator.
Radiator consists of upper tank, lower tank and radiator tubes provided with
fins or mesh called grill. The water while flowing from upper tank to lower tank gets
cooled by the flow of atmospheric air with fan through grill.
In radiator soft water is to be filled. Hard water can be changed into soft water by
adding two ounces of sodium dichromate (Na 2Cr 2O7 ) mixed with four gallons of
water.
NEW ENGINES WHEN DISPATCHED FROM THE WORK HAVE THEIR PORTS
AND OPENING SEALED WITH APPROPRIATE COVERS . ENSURE THAT ALL
COVERS ARE REMOVED BEFORE COMMISSIONING THE ENGINE .
LUBRICATION :
• Fill recommended grade of fresh oil in the sump to the high mark of the dip stick.
Add half litre more to compensate for the lub oil filter .
• Fill up the fuel pump governor with the same grade of lub oil from the plug
provider at the top of the governor housing . To check oil level in the governor .
Loosen the oil level control plug , painted red , provided on the inspection cover at
the rear of the governor housing .
• After starting the engine again check lub oil level in the oil sump and top up if
required .
FUEL :
• Check the fuel tank is cleaned fro inside .
• Fill the tank with cleaned HSD .
• Bleed the system as shown in the maintenance manual .
COOLENT:
• Fill the radiator with either fresh treated water or with coolant .
• Grease the water pump bearings with suitable grease .
• After starting the engine recheck water level in radiator and top up if required .
ELECTRICALS :
• Check battery for correct voltage and current capacity .
• Check battery cable are correctly connected and secure .
• Ensure correct polarity .
Before starting :-
• Check oil , water and fuel levels – top up if required .
• Check air cleaner choke indicator – on dry type of air cleaner .
• Clean engine with a dry cloth .
• Drain water from water separator provided in the fuel line .
• Crank the engine . As soon as engine fire , release the starter switch . keep
the ignition switch in ON position .
• Do not crank the engine for more than 10 sec at a time .
• If engine fails to start , wait for a minute and try again .
On Starting :-
• Check the oil pressure .
• Check battery charging .
• Check for leakages .
• Allow the engine to idle for 3 minute before loading the engine.
• While the machine is in operation , check engine oil pressure , water
temperature and battery charging rate at regular intervals .
Before Stopping :-
• Unloaded the engine and let it be idle for about 5 minute .
• Check the lube Oil pressure and water temperature.
• Stop the engine with the engine stopping lever .
After Stopping :-
• Check oil level after 30 minute and top up .
• Top up fuel tank .
• Check for leaks and rectify
1.2: At the end of day's work fill the fuel tank completely. Before starting drain the
moisture accumulated in the tank by loosening drain plug at the bottom of the
tank.
2: Every 50 hours:
2.1: Clean the air cleaner element by lightly tapping it on wooden block.
2.2: After initial run of 50 hours tighten all external nuts and bolts, especially the
4: Clean the intake and exhaust system and spray the preservative into it.
5: Remove the injector and spray 1lit. of preservative oil for fuel system in the
cylinder bores. Replace the nozzles.
6: Clean the engine externally and apply rust-proof oil to all exposed machined parts
or unpainted parts. The recommended rust proof oils are Shell ensis fluid 260 or
BOC RCF 260 Caltex rust-proof compound.
7: Cover the engine to protect it from rain, sun and dust. When recommissioning
such an engine, first remove all preservative from the engine and then fill it with
new lubricating oil and fuel oil.
LT
Engine gives Valve clearance out of Re-adjust valve clearance, renew
poor adjustment, valve spring valve spring.
performance or broken
engine lacks
power
Dirty air cooling fins on Clean air fins
cylinder heads
Loose fan belt Tighten belts
Valve leakages Regrind the valves
Broken/seized/worn out Replace with new piston rings
piston rings
Worn out liner and piston Replace with new one
Damaged main and Change bearings
connecting rod bearings
Incorrect valve and fuel Set to correct settings
timings
Faulty governor setting Set governor properly
One or more cylinders not Contact nearest distributor
working
Exhaust Too much oil in sump Drain off until level reaches low
smokes badly mark on dipstick
Oil level in oil bath air Pour off until level agrees with
cleaner too high mark hole
Inefficient compression due Have compression rings and
to sticking or broken pistons inspected by a specialist,
compression rings or readjust valve clearance
incorrect valve clearance
De-rating due to altitude and Calculate de-rating due to
temperature altitude and temperature and
reduce load on the engine if
necessary
Poor quality of fuel Change to quality fuel
Engine Cooling fins on cylinders and Clean cooling fins, particularly
overheats cylinder heads, very dirty the vertical ones on the cylinder
(shut down heads
engine Injectors defective Have inspected by a specialist
Immediately)
Injection pump delivery out Have adjusted by a specialist
of
adjustment
Insufficient cooling air input Ensure the cooling air flow
to blower
Blower V-belt broken Renew V-belt
A/C Generators are also called 'ALTERNATORS'. Here the mechanical energy is
converted into electrical energy. Basically a generator produces electricity by the
rotation of a group of conductors in a magnetic field. Hence the input of the
generator is the mechanical energy to rotate the conductors. The output of a
generator is the e.m.f. induced in the conductors as they move through the magnetic
field. The principle used here is Law of Electromagnetic Induction.
1.1 . STATOR :
Slip ring series :- The Stator frame is made up of rolled steel plates with welded
feet . It forms the yoke of magnetic circuit .The laminated pole bricks are bolted to
frame with impregnated field coils .
Brush less series : The stator frame is of solid cast / fabricated structure
designed to ensure correct distribution of air flow over the stator core and windings
. Main core is built up of insulated silicon steel sheets , pressed together suitably
. Armature winding is housed in stator core pack . Stator core pack has skewed
construction for better wave from .
1.2 ROTOR :
Slipring series :- Rotor forms a built up construction of high grade electrical
steel lamination on a steel shaft . Rotor lamination have a semi closed slot
construction for reduced losses , in which armature winding is housed . Rotor
core is formed with skewed construction for better wave form.
Brush less series : Rotor core is made up of cruciform laminations having four
projections , forming four poles . Laminations are stacked and held under pressure
in place by core clamp plate and key . Pole windings are well supported by
specially designed aluminum alloy support block and bright bars offering good
mechanical support to prevent bulging of winding due to heavy centrifugal forces .
The poles carry continuous damper windings to facilitate parallel operation .
1.4 BEARINGS : The bearings are of anti-friction type and are grease
lubricated . Normally a ball bearing is provided on the non driving end
(NDE ) and a ball or roller bearing on the driving end (DE).
1.5 SHAFT : The shaft is of high grade carbon steel machined and ground on
fitting surfaces . The shaft is designed for overload conditions .
1.7 ARMATURE WINDING : Armature coils are made from super enameled
copper wire which are formed on special formers . The coils are
held in slots by epoxy wedges . The overhangs are held in position by special
varnished fibre glass tape banding . The insulating materials s used are of class
F for all frames .
1.0 ALTERNATOR
Alternator when driven through prime mover i.e. Engine ,
generates A.C. power . Thus , it is energy conversion device which converts
mechanical energy into electrical energy .
Above all , this feature also protects the prime mover from getting over loaded
under such slow speed condition .
Voltage regulation up to ± 0.5 % can be obtained under following
conditions .
(i) Variation of load from no load to full load .
(ii) Variation of power factor between 0.8 and unity .
(iii) Hot and cold condition of generator and
(iv) For prime mover speed variation of ± 4 %
Filter circuit can be provided for unbalanced and thyristor load
application .
Should be cleared from oil and dust by blowing out frequently at least
once in three month .
C) Connections
All the external and internal connections should be checked for
tightness at joints and continuity . For links should be made good fit in the holders .
4.0 Earthing
The alternator frame shall be earthed thru the conductor heavy enough
to carry momentary short circuit without burning out . Earthing screws are
provided on alternator at two distinct point . It should be checked that earthing is
provided effectively.
5.0 Ventilation
It should be checked that all ventilation guide , glance plate and
corners are fruity and correctly fitted and generator inlet and outlet ventilation
ducts are not obstructed in any way.
***********************