PIPING FABRICATION AND ERECTION
00.05.15
00.05.15
1300-102
01
00
Elaborou:
J . van Eck
Verificou: Aprovou:
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 2 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
INDEX
SECTION PAGE
1. SCOPE 3
2. DEFINITIONS 3
3. CONTRACTOR'S RESPONSIBILITY 3
4. REFERENCE DOCUMENTS 4
5. DESIGN 5
6. MATERIALS 5
7. FABRICATION 7
8. INSTALLATION 14
9. INSPECTION AND TESTING 28
10. CLEANING 30
11. PAINTING/COATING 31
12. DOCUMENTATION 32
13. PREPARATION FOR SHIPMENT 33
14. ADDITIONAL REQUIREMENTS 34
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 3 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
1. SCOPE
This specification covers the minimum requirements for fabrication and installation of
steel piping, including pipe supports.
Fabrication and installation of tubing, lined pipe and nonmetallic piping are excluded
from the scope of this specification and shall be executed in accordance with
ASME B31.3 and manufacturer's requirements and recommendations.
Additional or deviating requirements for duplex stainless steel piping, piping containing
oxygen, underground piping, steam tracing and jacketed piping, are listed in
specifications mentioned in section 14.
2. DEFINITIONS
For this specification the following definitions are applicable:
Principal : Petrleos de Portugal S.A. (Petrogal) or the company acting on
principals behalf.
Contractor : The party which carries out engineering (if applicable), supply of
materials, fabrication and installation/construction.
Supplier : Any manufacturer or supplier who is appointed by the principal or
contractor and responsible for the supply of materials or equipment
or services.
Shall : Is to be understood mandatory.
Should : Is to be understood as strongly recommended.
May be : Is to be understood as giving a freedom of choice.
3. CONTRACTOR'S RESPONSIBILITY
3.1 Any conflict between the requirements of this specification and reference documents
shall be referred to principal for clarification.
3.2 Contractor shall fully describe all proposed deviations from this specification and
referenced codes, standards and specifications for review and approval by principal.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 4 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
3.3 Assumptions to cover lack of information are not allowed. Contractor is obliged to obtain
reliable information from principal.
3.4 Contractor shall field verify all (existing) dimensions and conditions shown on principal's
drawings.
4. REFERENCE DOCUMENTS
4.1 CODES
DL 101/74, DL 102/74 Authority Requirements.
ASME B31.1 (...) Power Piping.
ASME B31.3 (...) Process Piping.
Note: (...) Fill in applicable issue date.
4.2 STANDARDS
The version valid on the date of contract award shall be used.
ASME B16.25 Butt-welding Ends.
4.3 SPECIFICATIONS/DRAWINGS, ETC.
BES-1300-101 Piping Materials.
BES-1300-103 Coating and Wrapping of Underground Piping.
BES-1300-104 Process and Utility Piping Design Requirements.
BES-1300-105 Pressure Testing, Flushing and Reinstatement of Piping
Systems.
BES-1300-106 Steam Tracing.
BES-1300-107 Insulation of Piping and Equipment.
BES-1300-109 Welding of Carbon, Low-alloy and Austenitic Stainless
Steel Piping.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 5 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
BES-1300-110 Pipe Stress and Support Design Data.
BES-1400-104 Underground Piping.
BES-2300-101 Surface Preparation and Painting.
BES-2700-102 Hot Tapping.
5. DESIGN
5.1 Contractor shall supply plan drawings and/or isometrics showing piping design.
5.2 Piping designed by contractor shall meet the requirements of ASME B31.1/B31.3
(depending on selected design code) and specification BES-1300-104 "Piping Design
Requirements".
5.3 Contractor is fully responsible for all design. Principal may perform spot checks to ensure
that specifications are being properly applied.
6. MATERIALS
! All materials included in the finished piping systems (free-issue materials and
material purchased by contractor) shall be undamaged and fully in accordance
with the piping material class and pipe support drawings indicated on the piping
drawing and/or P&ID. For piping material classes, see specification BES-1200-
121 "Piping Materials".
! Material substitutions or deviations from the piping material classes shall not be
made without prior written approval of principal.
6.1 STORAGE/HANDLING OF MATERIALS
! Piping shall be stored in a clean, dry or well-drained area on elevated dunnage and
protected against contact with salts or salty water.
! Stainless-steel and duplex stainless steel piping shall be stored on wooden blocks,
separately from carbon, alloy and galvanized carbon steel.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 6 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
! Stainless-steel and duplex stainless steel materials shall not be loaded, unloaded or
handled with hoisting devices (e.g. steel ropes and forklift trucks) containing zinc
or other harmful materials.
6.2 MATERIAL IDENTIFICATION
! Materials issued to contractor shall be adequately marked in accordance with the
requirements of the applicable material specifications and the additional
requirements of the purchase order requisitions and/or local codes and regulations.
! In case material identification symbols are located near the weld or on a piece of
material to be cut off, material shall be restamped prior to welding or cutting to
avoid loss of traceability.
! The governing principle shall be that in the installed piping systems, all
components can be identified and traced to their origin and complete
specifications.
! Marking and remarking by contractor's representatives shall be executed by hard
dye stamping or engraving, whichever is applicable.
! All hard stamping shall be done by means of low stress stamps on
pressure-bearing parts. Low stress stamps shall have a round nose with a radius of
0.25 mm minimum.
! In case of ferrous materials with a thickness less than 5 mm and austenitic steels
less than 10 mm, marking shall be performed by engraving.
! When similar materials (e.g. carbon - low-temperature carbon steel or 304-316
stainless steel) are used for the same project, materials will be supplied with
additional color coding to be able to make a quick visual identification of different
types of material.
Note: Color coding needs not be transferred prior to welding or cutting.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 7 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
7. FABRICATION
Fabricated metal piping shall meet local authority requirements for all piping requiring
inspection and approval by local authorities.
All other fabricated metal piping shall meet the requirements of ASME B31.1/B31.3
(depending on selected code).
In order to prevent corrosion of stainless steel, duplex stainless steel and other high-alloy
steels, fabrication of carbon steel, galvanized carbon steel and low-alloy steel shall be
done in a separate area.
Area means different shops or two (2) areas in one (1) shop separated by suitable
(temporary) walls.
For the same reason as above, tools used for fabrication of carbon steel, galvanized steel
and low-alloy steel may not be used for fabrication of stainless steel, duplex stainless
steel and other high-alloy steel. Only tools made of stainless steel are allowed for
grinding, brushing, clamping, etc.
These requirements apply to shop and field fabrication.
7.1 SHOP FABRICATION
Shop fabrication under this specification shall include all the components of the pipeline
or parts thereof entering into fabricated assemblies (spools), but shall exclude all piping
specialties other than those with welding end constructions such as bolting, gaskets,
flanged valves and fittings, blind flanges, orifice plates and similar items. Contractor is
responsible for selection of piping to be shop fabricated on site or off site.
For some piping systems principal has strong preference for shop fabrication to a
maximum extent possible, e.g.:
! Lined piping.
! J acketed piping.
7.2 LOCATION OF FIELD WELDS
The size of spools and location of field welds shall be determined by contractor.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 8 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Field welds shall be located so that the spools shall be as large as possible and consistent
with shipping limitations. Field weld locations shall be governed by the following:
! Lengths of spools shall not be limited by "match lines" that appear on drawings. A
line and its branches which appear on more than one (1) drawing is not intended
to mean that a field weld is desired at the continuation point from one drawing to
another.
! Where piping is shown passing through a wall or floor, the first weld point on
either side of the wall or floor shall be made a field weld, provided it is located at
least 150 mm away from the end of the pipe sleeve.
! Erection conditions shall be considered in determining the size of spools.
7.3 FIELD FABRICATION
Field fabrication under this specification covers, but is not necessary limited to, the
following operations:
! Erection of shop-fabricated piping.
! Fabrication and erection of all field-fabricated piping.
! Design, routing, fabrication and erection of all field-fabricated piping for which
no piping drawings are available.
! Fabrication and erection of all pipe supports and auxiliary steel as detailed in the
pipe support drawings.
! Design, fabrication and erection of all pipe supports for small bore piping, which
shall be executed in line with the available drawings for supports.
7.4 VERIFICATION OF FIELD DIMENSIONS
Fabrication of piping and pipe supports shall be in accordance with the supplied
drawings. However, due to equipment location and fabrication tolerances, field
verification of overall dimensions shall be made by contractor prior to erection, to ensure
a proper fitup at all connections to equipment and other piping.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 9 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
7.5 MAKE-UP LENGTH
Contractor shall apply 150 mm make-up lengths in order to make adjustments, necessary
due to construction deviations. The required material shall be taken from the construction
allowances/contingencies.
7.6 TOLERANCES
7.6.1 Overall Dimensions
The dimensional tolerances of all fabricated lines shall not exceed the values given
below:
Less 1.5 m
Length than 1.5 m and longer
Center to center }
Center to flange face } 1.5 mm 3 mm
Flange face to flange face }
7.6.2 Thinning of Wall Thickness and Ovality in Bends
The maximum decrease of wall thickness shall not exceed 10% of the nominal wall
thickness.
For tolerances on the maximum flattening, see ASME B31.1/ B31.3.
7.6.3 Flange Face Alignment
Flange faces shall be aligned to the design plane within 1 mm in 200 mm measured
across any diameter.
7.6.4 Position of Bolt Holes for Flanged Piping
Flange bolt holes shall be aligned within 3 mm maximum offset.
Unless otherwise detailed on the drawings, flange bolt holes shall straddle the north-south
centerline when the flange face is in the horizontal position and shall straddle the vertical
flange centerline when the flange is in the vertical position.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 10 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
7.7 MINIMUM DISTANCE BETWEEN WELDS
! The minimum distance between weld edges shall be 50 mm or three (3) times the
wall thickness, whichever is greater.
! Welded joints, including longitudinal welds, shall not be placed less than 50 mm
or three (3) times the wall thickness, whichever is greater, from openings, branch
welds, reinforcements, attachment devices, supports, etc. Principal reserves the
right to specify additional requirements (such as radiography, ultrasonic
inspection or postweld heat treatment) in case of deviations.
! The longitudinal welds of two (2) adjacent rings or tubes shall be staggered
approximately 90. Longitudinal welds shall not be situated at the bottom of the
pipe.
7.8 BRANCH CONNECTIONS
Branch connection type shall be in accordance with the piping drawing or the piping
material class, when no drawing is supplied.
Where openings for branches are cut in run of pipe, all materials which may drop inside
the pipe, shall be completely removed before the branch line is welded into place.
Branch connection cutouts shall be carefully bevelled and accurately matched to form a
suitable groove for welding and to permit complete penetration of the welds at all points,
resulting in a quality comparable with girth welds, in the same piping system.
Weld details for branch welds shall be included in the welding procedure specification.
Reference is made to the relevant section of ASME B31.1/ B31.3.
The centerline of the branch connections shall intersect the centerline of the header,
unless otherwise specified on the piping drawing.
Nozzle joints shall be of the "set-on" type, made so that the branch connection abuts the
outside surface of the run wall.
Half couplings attached to the line shall be inserted to the inside of the run wall and
welded. Threaded couplings shall subsequently be checked with a thread gauge to ensure
against thread damage or distortion.
Pipe to pipe branches shall be of the weld-on type unless otherwise specified on the
piping drawing.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 11 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Welded pipe-to-pipe branch connections shall be reinforced as required by the piping
drawings. Additional weld metal, saddles or rings shall be used for reinforcement.
Prior to welding, saddles or rings shall be drilled with one (1) " NPT threaded hole for
testing and venting. Threaded hole to be sealed with compound after testing. No gap
larger than 3 mm shall exist between the OD of the pipe and ID of the ring or saddle.
7.9 GALVANIZED PIPING
Galvanized piping up to and including 2" (DN 50) nominal size shall in general be
assembled from threaded galvanized components. Piping larger than 2" (DN 50) nominal
size shall be prefabricated in accordance with this specification and subsequently hot-dip
galvanized. Contractor shall take into account that after the spools have been galvanized
no welding is allowed. This implicates that field breaks shall be located at flanged
connections or connections using flexible couplings and that welded-on pipe supports
shall be welded to the spools before galvanizing.
Contractor shall consider maximum dimensions of the galvanizing facilities he intends to
use, when determining spool dimensions and locations of field breaks.
Visual and dimensional inspections, nondestructive weld examinations and hydrostatic
testing shall be executed before spools are hot-dip galvanized.
Threaded connections shall be reworked to clean thread depth.
7.10 END PREPARATION
7.10.1 Cutting
Cutting pipes may be done either by mechanical means (preferred) or by flame cutting or
plasma cutting when the following is taken into account:
! For carbon steel, flame (or arc) cutting and bevelling is acceptable only if the cut
is reasonably smooth and all oxides are removed from the surface by grinding to
bright metal.
! For low and intermediate alloy steel, flame cut bevels are acceptable only where
machine cutting is not feasible. After flame cutting approximately 2 mm of
material shall be removed from the surface of the bevel by grinding.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 12 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
! For stainless steel, flame cutting is prohibited, but plasma cutting may be applied
instead.
! Preheating during thermal cutting shall be the same as applied during welding (see
specification "Welding of Carbon, Low-alloy and Austenitic Stainless Steel
Piping").
7.10.2 Bevelling
End profiles of pipes and fittings to be butt welded shall be in accordance with
ASME B16.25. Bevelling is not required when a make-up length is provided.
7.10.3 Tapering
Weld alignment shall be in accordance with ASME B31.1/B31.3, but with the exception
that the internal trimming shall be 1:4, instead of 30.
7.10.4 Threading
The threading of pipe shall be in accordance with the applicable standard. The type of
thread is indicated on the piping drawing or in the applicable pipe class.
7.10.5 Plain Ends
Pipes for socket weld joints shall be cut square.
7.11 WELDING
The following activities shall be executed in accordance with the requirements as
described in specification "Welding of Carbon, Low-alloy and Austenitic Stainless Steel
Piping".
! Alignment.
! Preheating.
! Tack welding.
! Welding.
! Repair welding.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 13 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
! Postweld heat treatment.
7.12 BENDING
7.12.1 General
Bending of pipes shall only be done where indicated on the isometric drawings or when
allowed by the applicable pipe class, otherwise welding elbows shall be used. The pipe
bending procedure shall be approved by Contractor.
If the pipe contains a longitudinal weld, this weld shall be located in the neutral zone.
At site, only cold pipe bending up to DN 80 (3 inch nominal size) is allowed, provided it
is done in pipe-bending machines or presses using formers. No wrinkling, excessive
thinning or flattening is allowed. Excessive scratches, gauges or die marks will be
grounds for rejection.
Hot bending at site is not allowed, but shall be executed with induction pipe-bending
machines. A pipe bending procedure shall be issued for approval by principal.
The bending radius for cold bending at site shall be as given on the isometric drawing,
but shall in principle not be less than five (5) times the nominal pipe diameter. The
amount of thinning permissible is specified in paragraph 7.6.2.
7.12.2 Additional Requirements for Ferritic Steels
For ferritic steels, with the exception of the quenched and tempered grades, a normalizing
heat treatment shall be applied when the hardness increase in Vickers or Brinell is more
than 100, unless local regulations are more stringent.
For quenched and tempered ferritic steels an appropriate stress-relieving heat treatment
shall be applied when the hardness increase in Vickers or Brinell is more than 100, unless
local regulations are more stringent. Stress relieving shall be at least 10C below the
tempering temperature.
The use of water for cooling is not permitted.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 14 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8. INSTALLATION
Contractor is responsible for installation of all piping spools including pipe supports, all
piping components, such as bolting, gaskets, flanged valves and fittings, blind flanges,
etc., and all other items, such as flow meters, control valves, orifice plates and similar
items necessary to complete final piping erection with all lines cleaned, supported,
pressure tested and ready for plant operation.
Alignment of piping to equipment (machinery, vessels, exchangers, etc.) shall permit
fitup without bending or springing the pipe under any circumstances. Alignment shall be
checked and approved by principal prior to bolt-up.
Where a discrepancy between drawing dimensions and field dimensions exists, sufficient
modifications shall be made to eliminate unintended cold springing and cold forcing.
Deviations from the arrangement shown on drawings shall only be made after consulting
principal. Contractor shall submit alternative routing for review and approval by
principal.
Alternative routing shall keep clear all access ways and equipment openings and shall
maintain accessibility of valves and instruments.
Cutting, welding and making attachments to structural members, vessels, exchangers and
other equipment, not detailed in the piping and piping support drawings, shall not be
permitted without prior approval of principal.
Stainless steel, duplex stainless steel and high-alloy steel shall be suitably protected
during installation or modification of carbon-steel, low-alloy steel and galvanized carbon-
steel piping at site.
All stainless steel pipe potentially exposed to zinc dust contamination shall be protected
with polythene sheeting. This applies in particular to piping under, or close to at the same
level, as galvanized steel (grating/structural members/etc.). The sheeting shall be securely
wrapped against tearing by wind and shall be removed upon completion of the works.
Galvanized scaffolding pipe shall be kept at a distance of at least of 20 cm from stainless
steel pipe in order to prevent the possibility of surface contamination.
Pulling of pipe along piperacks is forbidden unless rollers are used.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 15 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Vents, drains, condensate drip legs, pressure instrument and other connections shall be
installed where indicated on the isometric drawings, in accordance with engineering
standards included in specification "Piping Materials".
Protective devices on pipe ends, flanges and equipment openings shall remain in place
until the piping connection is ready to be made.
8.1 FLANGE ASSEMBLY
8.1.1 Tools
8.1.1.1 Use of adjustable wrenches (Bahco) or wrench hammers is prohibited.
8.1.1.2 For application of correct tool related to flange size and rating, see table I.
8.1.1.3 The calibration of torque wrenches and tensioners shall be checked against
manufacturer's specifications upon receipt. Any tools that are out of calibration shall be
rejected.
A recheck of the calibration shall be made as per tool manufacturer standard. Any tool
found to be out of calibration shall immediately be taken out of service for repair.
All flanged joints secured with tools found to be defective shall be rechecked with a
properly functioning tool.
8.1.2 Flange Identification
Flanges subject to hydraulic bolt tensioning shall be numbered on the isometric or on the
general arrangement drawing by the contractor. Starting with the flow direction of each line
number within one (1) unit, the flange sets shall be identified as F1, F2, F3, etc., followed
by the line number, e.g. F1-P30006.
The numbering system for flanged joints at equipment not part of a piping system, e.g.
manholes, etc., shall be such that each equipment flange set is identified with the nozzle
number as shown on the equipment drawing, followed by the equipment number, e.g. M1-
R1101.
The above described numbering system shall be used to relate each "assembly record" as
described in section 8.1.9 to the relating flange set.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 16 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.1.3 Torque Values
8.1.3.1 In case torque wrenches (manual or hydraulic) are used, bolts shall be tightened until
torque values, as indicated in table II, are reached.
In case tensioning equipment is used, bolts shall be tightened until bolt force values, as
indicated in table II are reached.
8.1.3.2 Listed values are NOT APPLICABLE for designed flanges over 60 inch. For these
flanges the equipment manufacturer shall indicate on his drawings the bolt torque value
used in the calculation made for the design of the flange.
8.1.3.3 For bolt material not listed in table II contact principal to obtain correct torque and bolt
force values.
8.1.3.4 a. Listed values are based on the empiric bolt force in flanges according to ASME
Section VIII, div. 1, Appendix S.
b. Torque moments are based on the pitch of the thread, the friction resistance
between the thread surfaces and the bearing surfaces of the nut on the flanges.
c. Friction coefficient f =0,12.
8.1.4 Installation
8.1.4.1 Inspection of Material
8.1.4.2 Inspect the gasket material for possible damage or defects such as bends or creases.
8.1.4.3 Inspect the mating flange facings for dirt, parallelism, flatness, surface roughness,
mechanical damage and corrosion. Use a suitable solvent to clean the surfaces.
The contact area of the flanges shall be free of excessive pitting, radial tool marks and
scratches.
Flange facings that are found to be damaged during construction, shall be remachined at
contractor's expense.
8.1.4.4 Inspect the studs and nuts. They should be free of dirt and corrosion and well lubricated.
The studs shall be straight and the threads free of nicks, burrs and chips.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 17 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.1.5 Assembly of Flange Connection
8.1.5.1 Align the flanges properly. For tolerances on flange joints see specification paragraph
7.6. The bolt holes shall match so that the studs can be inserted freely. Install the gasket.
Gaskets shall not be lubricated.
8.1.5.2 Use four (4) studs at 0, 90, 180 and 270 degree angle as centering guides for the gasket.
In the case of spiral-wound gaskets, ensure that the inner diameter of the centering ring is
at all points within the outside diameter of the raised face. Clamp securely in place.
8.1.5.3 Insert the balance of the studs. Apply a suitable lubricant to the threads and the face of the
nut that contacts the flange.
8.1.5.4 Hand tighten all studs and nuts. Center studs between nuts so an equal number of threads
projects at each end. When hydraulic bolt tensioning is required, a threaded length equal
to the bolt diameter should protrude at the end where the bolt tensioner is to be placed.
8.1.6 Bolt Torquing
8.1.6.1 Standard Wrench
a. Tighten bolts crosswise in at least two (2) stages. First stage to approximately 50%
if the estimated value based on experience. Second stage to 100% of the estimated
value. Bolting shall be tightened in a sequence assuring equal distribution of bolt
loading.
b. Check all bolts for even distribution of required load. Steel to cast iron flanged
joints shall be made up with extreme care. In order to avoid breaking of cast iron
equipment flanges, piping flanges shall be brought up flush with gasket and
equipment flanges into close parallel and lateral alignment, before uniformly
tightening bolts.
8.1.6.2 Manual or Hydraulic Torque Wrench
a. Tighten bolts crosswise in at least three (3) stages:
First stage to 40% of recommended value as per table II.
Second stage to 80% of recommended value.
Third stage to 100% of recommended value.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 18 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
b. Check all bolts at 100% of recommended value.
8.1.7 Hydraulic Bolt Tensioning
8.1.7.1 The application of bolt-tensioning equipment shall be in strict accordance with supplier's
instruction manual and safety procedures.
8.1.7.2 Contractor shall propose a supplier for hydraulic bolt tensioning equipment and/or
services, for approval by principal. The personnel using the equipment shall be
adequately trained in the application of such equipment.
8.1.7.3 The tensioning of the bolts is carried out crosswise in a number of cycles, depending on
the number of tools that can be applied simultaneously.
As a minimum following number of tensioners shall be applied during each cycle:
NUMBER OF BOLTS NUMBER OF TENSIONERS TO
USE
32 and less 50% of bolts
36 to 60
1
/
3
of bolts
64 and up of bolts
8.1.7.4 Bolt tensioning shall be executed in two (2) steps. Contractor shall issue a tensioning
procedure for approval by principal.
8.1.7.5 After completion of bolt tensioning four (4) bolts at 90 degrees angle each shall be
checked for the break loose point. Flanges not meeting the required values shall be
retensioned.
8.1.7.6 After bolt tensioning has been completed, the extended threaded part shall be greased and
covered with suitable caps to prevent damage and corrosion during operation of the plant.
8.1.7.7 Upon completion of bolt tensioning each flange shall be provided with a wire seal(s) as
indicated below.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 19 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.1.7.8 Flange numbers as described in paragraph 8.1.2 shall be low stress dye stamped on the
rim of one of the flanges .
8.1.8 Leaking Flange Assemblies
8.1.8.1 Flange assemblies found to be leaking during hydrotesting shall be tightened as listed
below:
a. Flanges assembled with standard wrenches shall be tightened with manual torque
wrenches using procedure as described in subsection 8.1.6.2.
b. Flanges assembled with manual torque wrenches shall be tightened with hydraulic
torque wrenches using procedure as described in subsection 8.1.6.2.
8.1.8.2 Flange assemblies tightened with hydraulic torque wrenches or hydraulic bolt tensioning
equipment and found to be leaking during hydrotesting shall be disassembled, inspected
and reassembled in accordance with the requirements of this specification.
8.1.8.3 Flange assemblies still leaking after tightening as described in subsection 8.1.8.1 shall
also be disassembled, inspected and reassembled in accordance with the requirements of
this specification.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 20 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Reassembly shall be done with tools as described in subsection 8.1.8.1a and 8.1.8.1b. In
case of reassembly a new gasket is recommended.
8.1.8.4 Contractor shall prepare an assembly record for all flanges which are disassembled and
reassembled because of leakage problems.
8.1.9 Documentation
8.1.9.1 Contractor shall prepare design calculations for all applicable flange sizes, in order to
determine the required bolt loads and, consequently, the required pressures in the
hydraulic bolt tensioning equipment.
Calculations shall take into account the following design factors:
! Minimum and maximum gasket seating stress.
! Allowable bolt stress.
! Flange material.
! Design pressure.
! Hydrostatic test pressure.
! External loadings.
8.1.9.2 Contractor shall issue a hydraulic bolt tensioning procedure for approval by the principal.
The procedure shall show all required information such as:
! Type of bolt tensioning equipment.
! Operation manual.
! Record preparation instructions.
! Establishment of the "break loose" pressure, based on minimum four (4)
tensioners.
! Any precautions to be taken.
8.1.9.3 Contractor shall prepare an assembly record for each flange joint which needs to be
tensioned. These records shall be issued as part of the turn-over packages.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 21 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Information to be shown on the assembly record shall be at least:
! Identification:
Unit.
Line number.
Pipe class.
Flange set number.
Flange size/rating.
Principal representative's name and signature.
! Inspection of the flange facing:
Roughness.
Damage: Dents, tool marks.
Cleanliness.
Principal representative's name and signature.
! Flange fit-up:
Gasket type.
Gasket size.
Bolt diameter and length.
Number of bolts.
Bolt material.
Flange alignment.
Principal representative's name and signature.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 22 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
! Bolt tensioning:
Pressure A, (the higher tool pressure, taking into account the maximum
bolt stress, that is applied to obtain at least the average bolt stress).
Pressure B, (the lower tool pressure, required to obtain the average bolt
stress).
Tool number.
"Break loose" pressure (check B pressure at four (4) bolts at 90% each) or
bolt torque value.
Principal representative's name and signature.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 23 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.1.10 TABLE I Selection of Tools
FLANGE RATING (ANSI CLASS)
150 300 600 900 1500 2500
1 1 1 1 1 1
1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 2
2 1 1 1 1 1 2
F 3 1 1 1 1 2 2
L 4 1 1 1 2 2 3
A 6 1 1 1 2 3 4
N 8 1 1 2 3 4 4
G 10 1 1 2 3 4 4
E 12 1 2 2 3 4 4
14 1 2 3 3 4 -
S 16 1 2 3 4 4 -
I 18 2 2 4 4 4 -
Z 20 2 2 4 4 4 -
E 24 2 3 4 4 4 -
26 2 4 - - - -
28-30 2 4 - - - -
32-36 3 4 - - - -
38-48 3 4 - - - -
50-60 4 4 - - - -
above
60
4 - - - - -
LEGEND
TOOL BOLT SIZE
1. Standard wrench 1 inch
2. Torque wrench 1 inch
3. Hydraulic torque wrench 1 inch
4. Bolt tensioning equipment >1 inch
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 24 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.1.11 TABLE II Bolt Torque and Bolt Force Values
BOLT DIAMETER
(INCH)
THREADS/INCH A193 B7, A193 B16 AND A320 L7, 26 IN. AND LARGER FOR 150 LB & 300 LB
ASME B16.47 SERIES A (MISS)
A193 B7, A193 B16 AND A320-L7, OTHER
SIZES/RATINGS ASME B16.5
TORQUE VALUE IN Nm BOLT FORCE IN N (note 1) TORQUE VALUE IN Nm
Nm
BOLT FORCE IN N
(note 2)
Carbon steel Stainless steel Carbon steel
(note 1)
Stainless
Steel
(note 3)
1/2 13 70 70
5/8 11 125 125
3/4 10 195 195
7/8 9 290 290
1 8 300 200 71400 47600 400 95200
1 1/8 8 420 280 88940 59295 560 118590
1 1/4 8 560 370 107670 71780 740 143560
1 3/8 8 740 490 127640 85090 980 170180
1 1/2 8 900 600 148650 99100 1200 198200
1 5/8 8 1120 745 170770 113850 1490 227700
1 3/4 8 1360 905 193950 129300 1810 258600
1 7/8 8 1620 1080 218030 145350 2160 290700
2 8 1920 1280 243000 162000 2560 324000
2 1/4 8 2610 1740 295440 196960 3480 393920
2 1/2 8 3420 2280 351750 234500 4560 469000
Notes: 1. 65% of empiric value to ASME Section VIII, div. 1, Appendix S
2. 85% of empiric value to ASME Section VIII, div. 1, Appendix S
3. 43% of empiric value to ASME Section VIII, div. 1, Appendix S
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 25 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
8.2 THREADED CONNECTIONS
All threaded connections shall be seal welded, except the following:
! Connections in galvanized piping.
! Screwed plugs in valved drains and vents.
! Screwed thermowells and instrument connections.
! Screwed control valves and safety/relief valves.
Seal welding shall be executed by qualified welders and shall not be considered as
contributing to the strength of the joints. All exposed threads shall be covered by the seal
weld.
Use sealing compound or teflon tape for all connections not to be seal welded.
Teflon tape is only allowed in utility services, at a design temperature of maximum
200C.
8.3 PIPE SUPPORTS
8.3.1 Temporary Supports
During erection, piping shall be adequate temporary supported until the final supports are
installed. Temporary supports shall rest on paving, or direct or indirect on concrete or
structural beams.
Piping shall not be temporarily supported from platform grating or from scaffolding.
Temporary supports shall consist of wooden blocks and/or steel hoisting ropes. Synthetic
ropes or strings are not acceptable as temporary supports.
Steel temporary supporting materials for stainless and duplex stainless steel materials
shall preferably be stainless steel. Galvanized temporary supporting material shall not be
used.
8.3.2 General
Pipe supports shall be designed, fabricated and installed in accordance with the piping
drawings on which the locations shall be indicated.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 26 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
Contractor shall adjust the pipe support to overcome construction measure deviations.
Shims used to achieve full bearing between a pipe and/or a pipe attachment and the main
support member must have sufficient area to carry the load. After erection, shims shall be
welded to the main steel to prevent slippage when the pipe moves during operation.
Shims shall not be welded to the pipe. Shims which are to be welded to pipe shoes shall
extend the full length and width of the shoe.
Alternative supports shall only be installed after approval by principal.
Contractor shall remove fireproofing locally from steel columns and beams for a proper
installation of pipe support according to the pipe support drawings. Fireproofing shall be
repaired on the main structure and need not to be installed on the additional pipe support,
unless otherwise shown. Fireproofing around directional anchors from pipes which are
free to move in the transverse direction shall be kept free minimum 50 mm from the pipe
anchor parts.
Where expansion bolts have to be applied in concrete members, care shall be taken not to
undercut retaining bars in the concrete. Pipe supports shall be adjusted to suit the final
location of the expansion bolts.
8.3.3 Variable Spring Supports
Installation
The spring hanger list included in the pipe support drawings shall give, for each spring:
a. The operating load.
b. The cold set load.
c. The amount and direction of travel.
When the spring is delivered, it will have been loaded to the preset load and locked into
this position by means of the cold setting stops. Depending upon the manufacturer, the
cold setting stops will take the form of a plain rivet through section bar inserted above
and below the piston plate inside the load scale slot.
The cold setting stops must remain undisturbed until the hydrostatic test on the line has
been satisfactorily completed, after which the following procedure shall be carried out:
a. At some time between the hydrostatic test and start-up, the cold setting stops shall
be removed. Ultimate force must not be used.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 27 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
With the cold setting stops removed, it may be noticed that the line has a tendency
to bow up or sag down. This is to be expected as when the line is cold and empty
it is obvious that it can be either oversupported or undersupported since it is
designed to be correctly supported at the hot operating condition. Do not readjust
the spring load, but contact principal when there is doubt.
8.4 COLD SPRING
Where specified on the drawings, cold spring or fullness (cold strain) shall be
accomplished by observing the following procedures:
! Piping shall be installed while the field weld as shown on the drawings is left
unwelded until the remainder of the line is completely erected. All line anchors,
guides and other supports shall be installed without using ultimate force.
! The gap between the pipe ends shall then be measured. If not equal to the
specified gap, the necessary modifications shall be made by cutting or extending
the pipe.
! The gap shall then be closed by jacking the line and clamping and bracing
securely in place.
! The field weld shall then be made.
8.5 EXPANSION J OINTS
Expansion joints shall be installed following thoroughly the instructions of the
manufacturer regarding the removal of shipping supports and attachments, adjusting tie-
rod nuts, precompressing bellows, flow direction, etc. If the joints have welding ends,
protection shall be given to the bellows to prevent any injurious effects during welding.
8.6 FINAL CORRECTIONS
8.6.1 Carbon Steel, 0.3 Mo and 0.6 Mo Steel Piping
If corrections are required after fabrication, they may be carried out by a method
approved by principal.
8.6.2 Chromium Molybdenum Steel Piping
After the final heat treatment all corrections to the piping should preferably be made in
the cold condition.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 28 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
If this is not possible the piping may be heated, for which written approval by principal is
required. The heating shall be applied uniformly and carefully controlled, the temperature
shall not exceed the maximum temperature limit of postweld heat treatment as indicated
in ASME B31.3 and shall be minimum 10C below the tempering temperature. Reheat
treatment will then not be required.
8.6.3 Austenitic Chromium Nickel and Chromium Nickel Molybdenum Steel Piping
All corrections to the piping should preferably be made in the cold condition.
If cold correction is not possible the piping may be heated after written approval by
principal. The heating shall be applied uniformly and carefully controlled. The
temperature shall not exceed 400C.
9. INSPECTION AND TESTING
9.1 GENERAL
Inspectors representing either Contractor or Principal shall have access to the Suppliers
shop or work area, with freedom to observe fabrication and inspect materials intended for
fabrication.
! Test and measuring equipment used shall be calibrated every six (6) months and
this calibration shall be supported by calibration certificates.
! All inspection and testing is the responsibility of contractor. Principal shall always
have the right to witness inspection.
! Pipe bends manufactured by contractor shall be thoroughly visual inspected for
cracks and surface laminations. If any doubt exists about the presence of cracks
and laminations, contractor shall apply magnetic particle or liquid penetrant
examination to show the absence of subject surface defects.
! All cold pulled bends with service temperatures over 425C, or ANSI ratings
900 lbs and higher regardless of service temperature, shall be subjected to
magnetic particle examination or dye penetrant testing.
! Hardness of all fabricated ferritic steel bends shall be checked. Heat treatment
shall be executed as described in paragraph 7.12.2 when hardness is too high.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 29 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
The supplier shall provide records of examination as requested in ANSI B.31.3. In
addition, he shall prepare records if any are required by ortuguese authorities
(DIRECO GERAL DE ENERGIA).
! Any defects revealed by any of the examinations performed shall be reworked and
retested. All assemblies indicating irremediable defects, excessive repairs,
improper fabrication or not being in accordance with the requirements of this
specification shall be subject to rejection, even if the conditions are discovered
after acceptance at contractor's shop or revealed during field testing. All costs
related to repairs and/or refabrication shall be for contractor's account.
9.2 POSITIVE MATERIAL IDENTIFICATION
9.2.1 Positive material identification shall be executed as follows:
a. Incoming materials in principals warehouse shall be examined at random by
principal to check attached certificates.
b. Installed material shall be checked at random by contractor to eliminate
possibility of accidental material substitution.
c. All installed materials with poor readability of heat numbers or materials where
doubt exists concerning the accuracy of the heat numbers shall be checked by
contractor.
At random is defined as a random check of materials per material type
(independent of size, rating, wall thickness and type of piping item) up to a
maximum of 1% of the total installed quantity of material.
9.2.2 PMI is only required for the following materials:
MATERIAL SERVICE
Cr.Mo Steel All Services
Stainless Steel When Indicated
Duplex Stainless
Steels
All Services
High Alloy Steels All Services
9.2.3 Contractor is responsible for execution and documentation of PMI as described under
paragraph 9.2.1b. and paragraph 9.2.1c.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 30 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
9.3 WELD EXAMINATION
For weld examination requirements, see specification "Welding of Carbon, Low Alloy
and Austenitic Stainless Steel Piping".
9.4 PRESSURE TESTING AND FLUSHING
! For pressure testing and flushing of completed piping systems, see specification
"Pressure Testing, Flushing and Reinstatement of Piping Systems".
! Except when specifically noted on the drawings, spools shall not require shop
hydrostatic testing. This shall not, however, relieve contractor of the responsibility
for any defects in materials and/or fabrication that may be revealed during field
hydrostatic testing.
! The space between a reinforcing pad and header shall be air/soap pressure tested
with an air pressure of 1.75 barg preferably prior to erection of the line.
10. CLEANING
10.1 WELD ENDS
During weld preparation ends of all components shall be freed from any trace of oil,
grease, paint, rust, scale, etc., over a distance of 50 mm minimum from the weld edge.
10.2 PIPING
10.2.1 Internal
During fabrication and installation, contractor shall prevent foreign materials such as oil,
grease, sand, dirt, scale, loose particles from cutting and grinding, etc., from entering the
pipe or pipe component.
If foreign materials have entered the pipe or pipe component, they shall immediately be
removed before assembly of the parts by a suitable cleaning method, such as blowing
through with air or degreasing with suitable cleaning agent or solvent.
Cleaning agents and solvents used for degreasing shall not have any properties causing
corrosion of the piping.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 31 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
10.2.2 External
Piping to be painted shall be cleaned in accordance with the requirements of specification
"Surface Preparation and Painting".
Piping which needs not be painted shall be cleaned by a suitable cleaning method to
remove excessive rust, scale or grease only.
Cleaning agents and solvents used for degreasing shall not have any properties causing
corrosion of the piping.
10.3 COMPLETED PIPING SYSTEMS
Unless otherwise indicated in the pipe class or on the piping drawings or P&ID's, only
flushing as described in specification "Pressure Testing, Flushing and Reinstatement of
Piping Systems" is required.
10.4 DEGREASING
For certain services, lines need to be degreased to prevent operation problems. This
requirement is indicated in the pipe class or on the piping drawings or P&ID's and shall
be executed in accordance with additional specifications supplied by principal.
Cleaning agents and solvents used for decreasing shall not have any properties causing
corrosion of the piping.
10.5 CHEMICAL CLEANING
Requirements for chemical cleaning of lines shall be indicated on the piping drawings
and/or the P&ID's. If chemical cleaning is applicable, principal shall issue a chemical
cleaning procedure for approval by principal.
The contractor responsible for chemical cleaning shall check whether all materials
included in the piping system are compatible with the intended cleaning liquid.
11. PAINTING/COATING
For painting requirements, reference is made to specification "Surface Preparation and
Painting".
Underground piping shall be coated and wrapped in accordance with specification
Coating and Wrapping of Underground Piping.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 32 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
12. DOCUMENTATION
12.1 Both shop and field fabrication include administration of material certificates, welding
operations, destructive and nondestructive examinations and all testing operations as
required by the applicable specifications and codes.
12.2 Contractor is responsible for planning and documenting all activities and controls which
include, but are not necessarily limited to, the following operations:
! Material receiving (including administration/filing of certificates).
! Cutting.
! Bending (on site and at contractors for induction bending).
! Welding.
! Heat treatment.
! Destructive and nondestructive testing.
! Hydraulic bolt tensioning and/or torquing.
! Hydrotesting.
! Flushing.
! Cleaning/chemical cleaning.
12.3 Contractor shall provide principal with two (2) copies of material test certificates for all
materials purchased by contractor.
12.4 Documents relating to assemblies to be shipped shall be submitted to principal.
Documents shall be available to principal at all times.
12.5 For each piping system (defined as piping items welded together of same material and
same design pressure/temperature, e.g. line from a pump to a vessel) contractor shall
provide a fabrication book containing documents showing all above-listed operations,
signed by a third party inspection, if required.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 33 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
13. PREPARATION FOR SHIPMENT
Before shop-fabricated assemblies are prepared for shipping, principal shall check
following:
! Overall dimensions as per piping drawing.
! Required documentation as per subsections 12.2 and 12.3.
! Material identification as per subsection 6.2.
After assembly has been released by principal, contractor shall prepare material for
shipping as follows:
! All assemblies shall be dry and free from water, dirt and loose or foreign
materials.
! Flange faces, machined surfaces and threads in carbon-steel piping shall be coated
with a corrosion preventive compound (Rust Ban 324, or equal) before applying
the cover, cap or plug.
! Plastic caps shall be used over all plain, bevelled or threaded open ends.
! Wood, metal or plastic covers shall be bolted or strapped to open flanged ends.
! All protective coverings of piping for shipment and shipping containers shall be of
sturdy construction in order to withstand normal shipping abuse.
Provisions shall be made to prevent damage to all subassemblies during loading,
unloading or shifting of the cargo in transit.
Small items shall not be shipped loose, but shall be bagged, boxed or crated. Each
container shall be tagged with a description of the contents and destination.
Carbon, low-alloy and galvanized carbon steel, stainless steel and duplex stainless steel
shall be shipped separately from each other.
For stainless-steel and duplex stainless steel spools, contractor shall not use steel hoisting
devices as described in subsection 6.1 and shall provide suitable transport packing to
prevent spools from contacting surfaces containing zinc or other harmful materials during
the transportation.
Petrogal
MANUAL DE PROCEDIMENTOS
Edio: 01
Data: 00.05.15
ESPECIFICAES DE ENGENHARIA
Reviso: 00
Data: 00.05.15
BES 1300-102 Pg. 34 de 34
Mod. Q-01 Reproduo proibida
Impresso a partir da PETRONET
13.1 SPOOL PIECE MARKING
The appropriate pipe identification, consisting of the line number and spool number, shall
be hard dye stamped into the spool. Marking shall be circled with yellow paint.
Note: When spools are shop painted the marking shall be protected against shot blasting
and priming.
14. ADDITIONAL REQUIREMENTS
For additional or deviating requirements concerning fabrication and erection of steel
piping, see specifications listed below:
! "Hot Water and Steam Tracing".
! "Insulation of Piping and Equipment".
! "Underground Piping".
! "Coating and Wrapping of Underground Piping".