Vous êtes sur la page 1sur 2

Item # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Description Fix rip on expantion joint on Eastn side of Economizer. Grout all supports Pull the slip blind from the Fuel Gas Tie-in Send Valves to Western to Get Tested Adjust all Spring Cans Insulation Missing Anchor Bolts Hydro Boiler Trim Pipe and NDE Fix hole in wall where drain pipe comes out Fix 1 1/2" Flanged tie from blow-down pipe to boiler. (Mis-Alignment) Pull all Blinds from the Boiler. Missing bolts on Ladders. And missing Safety Gates on Ladders as well. Missing U-Bolt on Cooling Water Line on the west side of the boiler. Install Silencer Missing Supports on Utility Air Lines Pull out shims underneath BFW393 Anchor down and grout support on BFW393 Anchor down support on Ladder on North side of Boiler Turn Check Valve on Blow Down Piping on North East Side of Boiler Power Piping Paper Work Install TI on SH379 Iso 138 Install TI on BFW391 Iso 57 Install TI on SH455 Iso 163 Install TI on SH379 Iso 145 Missing 300# RF Ball Valve Tag# FV-165A on Blow Down By Pass Iso # 044 Ping The Bolts on the East side of the Economizer Blind Flanges Install Inserta seal on drain on North Side of Boiler Mud Drum Install Unions on drains on North Side of Boiler Install Teflon pads undernesth all Stainless Pipe and structure steel Blow a hole in the Fuel Gas Skid so that it can drain. Install U-Bolt on stainless pipe at loading rack. Ping The Bolts on the on all stainless piping Run Pipe down from the high point vents from the BFW piping all the way to the ground. Fix support on Iso 143
1 of 2

Punch List Items F-1013 Boiler


Status Complete Complete Complete Complete Complete In Progress Complete Complete

Comments/Remarks

Civil Crew Has been informed Complete Complete In Progress Complete Need Crane Complete Complete Complete Complete Complete In Progress Complete Complete Complete Complete We have not received item yet Complete Complete Complete Complete Waiting on instructions as what we are going to do their. Complete Complete Complete Complete Ladder has been bolted down

Item # 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Description Cut anchors/stops off of 110# Steam Piping Iso 177 item 14 Install Missing Guides and Supports on Stainless Pipe Ping all bolts on Boiler Flanges Weatherproof top of boiler at penetrations. F-001 Missing Contriol valve F-019 Missing TI F-003 Two anchor bolts missing F-003 grout base plate F-003 TI missing Iso #065 Ammonia piping- Need mechanical completion sign off Check tightness on flanges of the round ducts BFW Missing supports Install missing covers on each end of mud drum Complete all insulation Ping/check manway covers on economizer &ducts. Found loose fasteners. Finish with the Concrete

Punch List Items F-1013 Boiler


Status Complete Complete Complete Complete Repeat Repeat Repeat Repeat ? Complete Complete Complete Repeat Complete

Comments/Remarks Leave as is.

Same as Item 25 Same as Item 23 Same as Item 17 Same as Item 17 Iso # 65 does not require a TI per the Drawing

Same as Item 6

Probably Friday or Monday

2 of 2

Vous aimerez peut-être aussi