Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1.4 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.4 Telecom/Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1 Before Going On-Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3 Scenario Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.2 Add TRE Logical . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.3 Install TRE Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.4 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.5 Lock Test Frequency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3.6 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4 Reverse Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.1 Activate backup PRC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.2 Uninstall TRE Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.3 Call Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4.4 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 7 8 8 8 8 9 10 10 10 10 11 12 13 13 14 14 15 16 17 17 17 18 18 18 21 23 23 24 25 25 25 27 27
3 / 28
Contents
4 / 28
Preface
Preface
Purpose Whats New
This document describes how to add a TRE to an equipped 9100 BTS. Applicable to BSSs at technical release level B10.
In Edition 04
Update with the new equipment naming.
In Edition 03
Delivered in release. Section Install TRE Hardware (Section 2.3.3) was updated. The following sections have been updated due to system evolution: Applicable Documents (Section 1.5.3) Install TRE Hardware (Section 2.3.3) Uninstall TRE Hardware (Section 2.4.2)
In Edition 02
Old Alcatel-Evolium logo was changed in Alcatel-Lucent logo.
In Edition 01
Section Install TRE Hardware (Section 2.3.3) has been updated due to system behavior. The following sections have been updated due to system evolution: Options (Section 1.1.2) Prerequisites (Section 1.2.1) Install TRE Hardware (Section 2.3.3) First official release of the document for B10.
5 / 28
Preface
Audience
This document is intended for: Field service technicians Specialists Project managers Foremen.
Assumed Knowledge
You must have a basic understanding of the following: For planning purposes: Network architecture and reshuffling principles Scheduling. For realization purposes: Alcatel-Lucent operations and maintenance concepts for BSS 9153 OMC-R operation Equipment (BSC, BTS, MFS) hardware configurations Windows environment.
6 / 28
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, for presentation to the customer and for site planning.
7 / 28
1 Overview
1.1 Presentation
The presence of transcoding rate, adaption, and radio transmission capacity in the BTS, meaning the needed BTS equipment is present, is reflected by the value "equipped" of the status attribute "equipped status". "HR Flexibility" introduces the possibility of defining the speech-coding rate at the TRE/TWIN TRA and TRX level. Full Rate TREs/TWIN TRAs are treated before Dual Rate TREs/TWIN TRAs. If a TRE/TWIN TRAs is added to a cell split on two BTSs, the TRX attribute is set to "main" or "secondary", depending on where the TRE/TWIN TRA is added. The scenario uses configuration management rules specific to the 9153 OMC-R. In order to create a required configuration, it is possible to add more than one TRE/TWIN TRA.
1.1.1 Cases
The following case applies: C1: TRE allocation mode: on demand C2: TWIN TRA allocation mode: on demand C2.1: TWIN TRA is configured as 1 TRX, Non-TX-Div, 2 RX-Div C2.2: TWIN TRA is configured as 1 TRX, TX-Div, 4 RX-Div C2.3: TWIN TRA is configured as 2 TRX, Non-TX-Div, 2 RX-Div
Note:
1.1.2 Options
The method takes into account two options (O1, O2). The default is a BTS without frequency hopping where the frequency for the new TRE/TWIN TRA is known and the TRE/TWIN TRA remains in traffic after the operation. O1: BTS with frequency hopping system declared O2: New TRE/TWIN TRA does not have a frequency allocated and after the operation it remains OPR.
1.1.3 Restrictions
This procedure does not cover adding aTRE to a low loss configuration, which implies antenna reconfiguration.
8 / 28
1 Overview
BTS
Final Checks
9 / 28
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply: BTS sites are clean, tidy, easily reachable. The OMC-R is in release B10. The BSC must be operational and running in release B10. There are enough resources (Abis time slots and TCUCs) to handle new TREs/TWIN TRAs(TCH, SDDCH, LAPD). If not enough perform Attach Secondary Abis. Test frequencies must be available In case of adding a TWIN TRA, the BTS must be equipped with SUMA The BTS must not contain any G3 TREs for a configuration with more than 12 TREs.
10 / 28
1 Overview
1.3 Scheduling
Time based on technical constraints The number of resources shown in the following table does not take into account individual customer or safety requirements.
Grouped Task Initial Checks. Add TRE/TWIN TRA-Logical. Install TRE/TWIN TRA Hardware. Final Checks. TOTAL TIME
MSC -
TC -
BSC -
BTS -
Time/Task 20 min. 15 min. + 9 min./ cell + 1 min./ TRX + 3 min./ O1 15.5 min.+12 min./ TRE+1 min./ C1, C2 25 min. +1 min./O2 75.5 min. + 12 min./ TRE + 9 min./ cell + 1 min. / TRX O1: + 3 min. O2: + 1 min. C1, C2: + 1 min.
1 Team
1 Team 1 Team
1 ope. 1 ope.
ope. Team
11 / 28
1 Overview
Out. Ref. 1
Tel. Red -
Oper. Impact -
Impacts... None. During PRC activation: Supervision Outage Telecom and GPRS outage,if is the case.
None or 24 sec.
Outage if added TRE/TWIN TRA(s) will be multiplexed with the existing TRE/TWIN TRA(s). This means moving existing TRE/TWIN TRA(s) from the initial TCUC. None.
1.5 min.
12 / 28
1 Overview
1.5 Resources
1.5.1 Tools
The following tables describe the necessary hardware tools, software tools, and forms.
1.5.1.3 Forms
None.
13 / 28
1 Overview
1.5.2 Supplies
The following table describes the necessary supplies. Item Part Number Contents Use at...
BTS
14 / 28
2 Scenario
2 Scenario
This Scenario presents all checks needed before beginning the scenario, and all detailed tasks to be performed on each site.
15 / 28
2 Scenario
16 / 28
2 Scenario
17 / 28
2 Scenario
Note: the PRC backup is needed for the reverse procedure. The PRC opens automatically. Copy OMC Cells to PRC backup. OMC-R 1 min. 30 sec./ cell None.
Note: Copy only the impacted cells. Check PRC (without forcing Cell Administrative State). Close PRC backup. OMC-R 2 min. None.
OMC-R
30 sec.
None.
18 / 28
2 Scenario
Note: Copy the impacted cells. Change Cell Type for the existing cell to concentric, if necessary. Set Cell Telecom Parameters, change frequency range from p_gsm to p_gsm_dcs, if necessary. OMC-R 0.5 min./ cell None.
OMC-R
None.
Note: Check PC parameters min. toggle and change the parameters, if necessary. OMC-R 1 min. None.
Add a new frequency according to the Frequency Plan. O1 Modify Frequency Hopping System. Create TRX. Configure TRX. OMC-R OMC-R OMC-R 2 min. 0.5 min./ TRX 0.5 min./ TRX None. None. None.
Set TRX attributes to "main" or "secondary" and "inner" or "outer" depending on the BTS and cell zone where the TRE is added. Also set the value of TRX_PREF_MARK, if needed. O1 Configure Logical Channels. Configure TRX Channel Hopping Law. Synchronize PRC with SC. Check PRC without forcing Cell Administrative State. OMC-R OMC-R OMC-R OMC-R 2 min. 1 min. 1 min. 2 min. None. None. None. None.
19 / 28
2 Scenario
Note -
Task Description Activate PRC (PRC1). Choose to activate using these options: Queued Activation, With Cell clean-up, and Without forcing Cell Administrative State. Display Pending Activations List, to see when the activation is finished.
Site OMC-R
To do 5 min./ cell
The activation time depends on the number of cells. During the activation: supervision outage for 1.5 min. Telecom and GPRS outage: 1 min./cell only for O1. As there is a new TRX, if it has a biggest priority than the old TRX calls and packet traffic are cut on the less priority TRX. ATTENTION: During the activation the impacted cell(s) becomes yellow and the GSM Alarm is "Loss-of-TCH". This alarm disappears when the TRE hardware installation is finished.
Optionally, View Last PRC log Activation. Close PRC (PRC1). Inform the BTS site when the PRC activation is finished.
OMC-R
1 min.
None.
EXCH
OMC-R OMC-R
1 min. 1 min.
None. None.
20 / 28
2 Scenario
Note -
Note: Use the BTS Hardware Description for the appropriate BTS type. Install and cable TWIN TRA accordingly. Init Single TRE (the added TRE). BTS BTS 3 min./ board 2 min./ TRE None. None.
Note: This task is not performed for TWIN TRA. End Commissioning. BTS 2 min. -
Note: This task is not performed for TWIN TRA. Stop HW Modification. BTS 8 min. None.
Note1: "TWIN TRE Mode Configuration" window automatically opens if the BTS is equipped with a TWIN TRA module. Note2: This triggers the BTS to poll equipment. TWIN TRA Settings if a TWIN TRA has been added. BSC sends report to OMC-R. BTS 1 min. -
Note: Automatic action. Concurrent with the action below. BTS triggers Hardware audit. -
21 / 28
2 Scenario
Note -
Task Description For the TWIN TRA from the BTS NEM perform: Disable SBLs Other Than BTS_TEL. Init Single TRE (the added TWIN TRA).
Site BTS
To do 1 min./ TRE
Outage -
BTS
2 min./ TRE
Note: For 2 TRX configuration both TREs are initialized. End Commissioning if a TWIN TRA has been added. For the TWIN TRA from the BTS NEM perform:Init. Create BTS Sector and/or TRE (add TRE/TWIN TRA on concerned sector). BTS 2 min. -
BTS OMC-R
None.
Create BTS Sector and/or TRE (add 2 TREs for each TWIN TRA added on the concerned sectors) BSC allocates TCU and Abis time slots.
OMC-R
1 min.
None.
None.
Note: Automatic action. BSC configures BSC transmission settings. 6 min. for 9120 BSC. 15 sec. for 9130 BSC Evolution. Note: Automatic action. If moving existing TREs from initial 9120 BSC TCUC: 24 sec. Telecom Outage for the impacted TREs. BSC configures BTS transmission settings. 2 min. for 9120 BSC. 15 sec. for 9130 BSC Evolution. Note: Automatic action. On BTS site, wait 15 minutes from the last operator action (from "Finish HW Configuration Modification"). BTS None. START2 END2
22 / 28
2 Scenario
This task must be done in parallel with the OMC-R tasks in order to save time. Unlock Cell from Call Test detailed task is not necessary here. CHECK Display USD Detailed Cell Information to check if calls are made on impacted cells. OMC-R 5 min./ cell -
23 / 28
2 Scenario
OMC-R
10 min.
None.
Note: Compare the status of Managed Objects and alarms with the results printed in the Initial Checks.
24 / 28
2 Scenario
Activation time is 5minutes for one cell. Total time depends on the number of cells.
Note:Action performed at the: BTS Terminal for G1/G2 BTS. SBL is FU/CU for G1/G2 BTS BTS NEM for 9100 / 9110 BTS Note:For the 2 TRX configuration disable both SBLs related to the TWIN TRA. Start HW Modification. Uninstall TRE/TWIN TRA hardware from the BTS. BTS BTS 1 min. 3 min./ board 1 min. 5 min.
BTS BTS
EXCH BSC sends report to OMC-R. Note: Automatic action. Concurrent with the action below.
25 / 28
2 Scenario
Site
To do
Outage
Note: Automatic action. C1 C2.1 C2.2 C2.3 Delete BTS Sector and/or TRE(delete both TREs from the concerned sectors). BSC allocates TCU and Abis time slots. OMC-R 1 min. Delete BTS Sector and/or TRE (delete TRE/TWIN TRA on concerned sector). OMC-R 1 min.
Note: Automatic action. BSC reconfigures BSC transmission settings. 2 min. for 9120 BSC. 15 sec. for 9130 BSC Evolution. Note: Automatic action. If moving existing TREs from initial 9120 BSC TCUC: 24" Telecom Outage for the impacted TREs. BSC configures BTS transmission settings. 2 min. for 9120 BSC. 15 sec. for 9130 BSC Evolution. Note: Automatic action.
26 / 28
2 Scenario
This task must be done in parallel with the OMC-R tasks in order to save time. Unlock Cell from Call Test detailed task is not necessary here. CHECK Display USD Detailed Cell Information to check if calls are made on impacted cells. OMC-R 5 min./ cell -
OMC-R
10 min.
None.
Note: Compare the status of Managed Objects and alarms with the results printed in the Initial Checks.
27 / 28
2 Scenario
28 / 28