Académique Documents
Professionnel Documents
Culture Documents
Cashow forecasts
Introduction
At tender stage, a contractor sets up his nancial and time objectives by calculating construction costs and producing a project programme. By linking the two sets of data, an estimator can rst help a client produce his forecast of payments and second compare this with his likely payments (to suppliers and sub-contractors) to produce his own cashow forecast. In this way a contractor is in a unique position to give accurate information to the building team. There is seldom enough time at tender stage to produce detailed cashow forecasts. The contractor knows the objective is to win the contract, so there must be good reasons for putting in this effort. Obviously if a client has asked for a tenderstage programme and cashow forecast it must be done.The contractor may also need to assess the cashow benet of taking on a job, because this is part of his assessment of risk. A spreadsheet model may be able to answer questions such as: are there any sudden cash commitments? How much early money will be needed to make the contract self-nancing? Construction costs for Private Finance Initiative (PFI) projects are produced by an estimator usually working for one of the parties making up a consortium. Construction is only one constituent of the PFI bid, the others being facilities management, equipment, project management and nance. The estimator must produce his capital costs in the form of a monthly draw down chart. The rst payment is usually very large because considerable design and bidding costs need to be refunded early.
Cashow calculations
There are two methods commonly used to predict the value of project work over time. First, cost models can be used at various pre-contract stages to produce approximate forecasts and second, the estimators calculations form the basis of a more detailed technique. If a client needs a schedule of payments, the simplest model would be a straight line relationship of value against time from which the clients commitments can be shown (see Fig. 16.1). The assumption being that all payments are of an equal
217
1000s
218
Retention Interim @ 5% payments
Week nos
Gross value
1000s
83
600
165
500
400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 637
1000s 22 44 65 87 109 131 152 174 196 218 239 261 283 305 327 348 370 392 414 435 457 479 501 522 544 566 588 609 631 653
1000s 1 2 3 4 5 7 8 9 10 11 12 13 14 15 16 17 19 20 21 22 23 24 25 26 27 28 29 30 32 16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Week numbers
Cashow forecasts
amount based on the full value divided by the number of payments with a small adjustment for retention money. A slightly more sophisticated technique assumes that a construction project accumulates costs in a way which can be represented by an S-curve graph (Fig. 16.2). This model is based on the presumption that only one quarter of the costs are incurred during the rst third of a project duration, half the costs arise from the second third (in a linear fashion) and the remaining quarter of costs occur in the nal third of the project duration. The S-curve can be created manually by drawing a straight line between the rst and second third points and sketching the parabolic end portions. The contractors cumulative cost curve can be superimposed on the chart by deducting the prot margin from the cumulative value curve.The S-curve method is of course a theoretical technique which is difcult to change to take account of the nature of individual projects and contractors pricing methods, but is successfully used at early stages when detailed pricing information is not available. The GC/Works/1 Edition 3 form of contract has introduced the S-curve principle as a basis for stage payments. The printed form gives charts for projects with contract values over 5.5 million, and others are available for smaller jobs. Figure 16.3 shows the S-curve produced from the data given for a 100-week project. Clearly, the project manager is able to predict the clients payments and a great deal of time is saved each month in producing valuations.The same is true for the contractor, but there will be a shortfall in payments if the establishment costs are high. An estimators calculations and programme are the best starting-point for a contractors cashow forecast.The rates calculated by the estimator can be linked with the relevant activities on a tender programme.The total costs associated with each activity are divided by the duration to arrive at a weekly cost.The information used to produce the value curve is simply taken from the sums inserted in the clients bill with adjustments for retention. The contractors income can be predicted by taking the value at each valuation date and allowing a delay for payments. To calculate the weekly cost commitment (the contractors outgoings) each element of cost should be viewed separately. This is because spending on labour, materials, plant and specialist contractors develops in different ways. Direct labour, for example, is a weekly commitment, and credit arrangements for materials can delay payments for up to nine weeks. Expenditure and income can be plotted on a graph against time.The combined effect is a cumulative cashow diagram which will show the extent to which the job needs nancing by the contractor.
1000s
220
Cost forecast
Week nos
Gross value
1000s
1000s
600
163
147
490
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 0 588
653
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Week numbers
Fig. 16.2 Simple S-curve for cumulative value and costs, calculated at third points
100.00
80.00
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
0.00 0.85 2.85 5.89 9.84 14.58 19.99 25.97 32.37 39.10 46.02 53.03 59.99 66.80 73.33 79.46 85.08 90.06 94.28 97.64 100.00
221
monthly and retention has been set at 5%. A sum of 18 000 has been included for prot, and the rates in the bill of quantities exclude any on-site or off-site overheads. Following a careful review of the estimate, the construction director asked for all sub-contract discounts to be taken from the estimate but made an adjustment to the prot margin. During the mobilization period, the estimator was asked to produce a forecast of payments for the client and a cashow forecast for the commercial department.The estimator priced the bill of quantities analytically using estimating software.The rst task was to ensure that all the adjustments made at the nal review stage had been made to the rates in the bill of allowances.This fully adjusted bill would become the budget for the construction team to monitor the nancial progress of the job. The next stage was to assign sums of money to each activity on the tender programme.This was done using a spreadsheet program because each cell on the screen can hold text, graphics, numbers or formulae. Each row on the spreadsheet can show weekly values with shading used to locate the activity bars. Figure 16.4 shows the tender programme with contract values taken from the bill of quantities, which was submitted, to the client.The main assumptions used for this graph were that: 1. Each activity will be completed on time. 2. Sums are divided equally for the duration of an activity. 3. Provisional sums and daywork are not included. The total for project overheads has been split equally over the whole duration. This is not a good interpretation for the contractor because he will incur more expenditure setting up his site facilities at the start of a job.The nal presentation to the client did not include the costed programme or a graph. The commercial department felt the client would want a simple list of payments, and included it in a letter to the quantity surveyor. The contractors cashow diagram was created on a spreadsheet program which had the facility to use multiple sheets in the same le. Figure 16.5 shows the contents of the costed programmes for labour, plant, materials and subcontractors. The bottom sheet was used to consolidate the cost commitment drawn from each of the other sheets with the forecast income.The cashow forecast is simply the difference between income and expenditure.The results were plotted, by the program, on a single diagram (Fig. 16.6) and submitted to the commercial manager in the form of a graph linked to the consolidated costed programme. Since all the information was held in a single spreadsheet le, the computer was able to answer what if questions which allowed the commercial manager to minimize the borrowing requirement. Clearly this information can be the basis of a cost monitoring system (which is beyond the scope of this book).The cumulative value curve can help the construction team in monitoring progress of their work and that of the sub-contractors. This technique is sometimes adopted by project managers as a check on the progress of contractors.
222
CB CONSTRUCTION LIMITED
Contract Value 1 4 5 8 9 10 13 14 17 18 19 21 22 23 26 27 30 February 6 7 March 11 12 April 15 16 May 20 June 24 25 July 28 29 August 31 32 2004 January 2 3
Proposed Offices for Fast Transport Limited Tender Programme No: T354/P1
Activity
6 450 3225 3225 7160 7160 7160 3852 3852 3852 3852 3852 6950 6950 6950 6950 2605 2605 8235 8235 1350 2778 2778 2778 2778 2778 2778 2778 2778 7047 7047 7047 9823 9823 9823 9823 9823 9823 9823 9823 3117 3117 3117 9515 9515 6375 6375 6375 6375 7167 7167 7167 7167 7167 7167 5438 5438 5438 5438 5438 5438 5438 5438 5209 5209 5209 5209 5209 5209 5209 5209 4600 4600 4600 4600 4600 5600 5600 5600 5600 5600 2050 2050 2050 2050 2050 2050 4100 4100 4100 6092 6092 6092 6092 6092 6092 6092 6092 6092 6092 1502 1502 1502 1502 1350 21 480 19 260 27 800 5 210 16 470 6 007 2 700 22 220 21 140 78 580 9 350 19 030 25 500 43 000 43 500 41 670 23 000 28 000
12 300
1 Mobilization & set up 2 Excavation and filling 3 Foundations formwork 4 Foundations concrete 5 Underslab drainage
6 Concrete ground floors 7 Columns formwork 8 Columns concrete 9 Floors and beams formwork 10 Floors and beams concrete
11 External walls 12 Roof timbers 13 Roof covering 14 Windows 15 Services 1st fix
23 Preliminaries
653.3 k 6.81 20.1 20.7 21.5 18.5 19.8 26.9 9.21 21.6 16.2 16.2 23.2 16.2 23.2 74 440 70 718 69 095 65 640 653 337 k 620 670
32 667
3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582 3582
20.6
30.1
30.1
35.2
21.4
14.2
22.4
22.4
30.5
27.1
27.1
26 104 942
21.4
7.68 82 261
93 414 88 743
98 728
118 998
99 695
78 148 32 667
After completion 1 2 3 4 5 6 7 8 9 10 11 12
week number
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
>>
223
CB CONSTRUCTION LIMITED
Activity lab plt mat sub
1 2 3 4 5 6 7 8 9 10
Mobilization & set up Excavation and filling Foundations formwork Foundations concrete Underslab drainage Concrete ground floors Columns formwork Columns concrete Floors and beams formwork Floors and beams concrete
2 800 7 800 12 480 4 600 1 920 3 420 3 907 750 14 570 3 750
2 800 7 800 12 480 4 600 1 920 0 3 420 3 907 750 14 570 3 750
2 3 5 4 2 2 4 2 8 3
CB CONSTRUCTION LIMITED
Activity lab plt mat sub
1 2 3 4 5 6 7 8 9 10
Mobilization & set up Excavation and filling Foundations formwork Foundations concrete Underslab drainage Concrete ground floors Columns formwork Columns concrete Floors and beams formwork Floors and beams concrete
2 3 5 4 2 2 4 2 8 3
CB CONSTRUCTION LIMITED
Activity
lab
plt
mat
sub
contract Value
1 2 3 4 5 6 7 8 9 10
Mobilization & set up Excavation and filling Foundations formwork Foundations concrete Underslab drainage Concrete ground floors Columns formwork Columns concrete Floors and beams formwork Floors and beams concrete
1 250 5 700 6 780 23 200 1 540 11 300 2 100 1 700 7 650 15 640
1 250 5 700 6 780 23 200 1 540 0 11 300 2 100 1 700 7 650 15 640
2 3 5 4 2 2 4 2 8 3
625
CB CONSTRUCTION LIMITED
Activity
lab
plt
mat
sub
16 0
17 0
12 13 14 15 16 17 18 19 20
Roof timbers Roof covering Windows Services 1st fix Plasterwork and partitions Joinery Ceilings Services 2nd fix Painting
Activity
2 800 7 800 12 480 4 600 1 920 3 420 3 907 750 14 570 3 750 36 700 4 140 1 350 25 500 43 000 43 500 2 360 1 800 28 000 12 300 12 300 16 700 119 047 57 430 35 490 11 230 3 300 107 450 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 28 430 151 810 246 600 545 887 3.2 16.5 17.1 18.0 14.9 16.3 23.3 5.6 18.1 12.6 12.6 19.6 3.6 12 550 19 870 11 800 60 920 6092 6092 12.6 3.6 19.6 3.6 17.0 3.6 26.5 3.6 26.5 3.6 31.6 3.6 28.5 3.6 17.8 3.6 10.6 3.6 12 300 6092 18.8 3.6 6092 18.8 3.6 12 300 28 000 2050 2050 1 400 19 800 23 000 5 310 34 000 41 670 43 500 43 000 25 500 1 280 16 400 19 030 5 210 9 350 3117 3117 3117 9515 9515 6375 6375 6375 6375 7167 7167 7167 7167 7167 7167 5438 5438 5438 5438 5438 5209 5209 5209 5438 5209 5438 5438 41 880 78 580 9823 9823 9823 9823 9823 9823 9823 9823 1 750 15 640 21 140 7047 7047 7047 7 650 22 220 2778 2778 2778 2778 2778 2778 2778 2778 250 1 700 2 700 1350 1350 2 100 6 007 1502 1502 1502 1502 1 750 11 300 16 470 8235 8235 1 750 1 540 5 210 2605 2605 23 200 27 800 6950 6950 6950 6950 6 780 19 260 3852 3852 3852 3852 3852 7 980 5 700 21 480 7160 7160 7160
1 2 3 4 5
2 400 1 250 6 450 3225 3225
Mobilization & set up Excavation and filling Foundations formwork Foundations concrete Underslab drainage
6 7 8 9 10
Concrete ground floors Columns formwork Columns concrete Floors and beams formwork Floors and beams concrete
11 12 13 14 15
External walls Roof timbers Roof covering Windows Services 1st fix
16 17 18 19 20
23 Preliminaries
delayed delayed delayed week after payment received 653.3 k 653 337 69 095 6.81 20.1 20.7 21.5 18.5 19.8 3.31 10.9 19.6 30.1 43.9 60.7 26.9 249 900 (retention ignored) 3 3 79.5 9.21 6 wks 163 040 1 6 4 wks 63 920 2 9 14 18 20 12 3
1 wk
176 477
11
20
28
35
43
53
58
65 22 21 3
73 24 30 3
82 25 39 3
91 28 54 3
100 29 57 3
109 30 69 3
116 32 76 4
123 33 82 4
131 35 94 4
135 36 100 4
138 37 112 38
140 39 118 38
142 40 125 38
146 41 133 38
150 42 135 38
Resource cost analysis Cumulative labour value Cumulative plant value Cumulative materials value Cumulative sub-contract value
92.2 21.6
130 16.2
150 23.2
176 16.2
189 23.2
227 30.1
243 30.1
264 35.2
326 21.4
335 14.2
467 30.5
474 27.1
65 640
70 718
88 743
98 728
118 998
26 After completion 1 2 3
week number
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
225
1000s
226
Cashflow forecast for Fast Transport Ltd
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
700.00
600.00
500.00
400.00
300.00
200.00
100.00
100.00
Week numbers
Cumulative cost commitment Net interim payments Cashflow forecast Cumulative value forecast
17