Académique Documents
Professionnel Documents
Culture Documents
Examination Committee:
Dr. Soud Al Dajah Dr. Mousa Hussein Dr. Imad Barhumi Fall 2013/2014
UAE University College of Engineering Industrial Training and Graduation Projects Unit
Osamah Tasks 1. Literature review 2. Data collection 3. Draft 1 4. Decision matrices 5. Progress presentations 6. Equipment selection 7. Draft 2 8. Final report and presentation * The total percentage for each task should be 100. Project Advisor Name and Signature: _______________________________________
Student signature
ahmed
Student signature
48 53 42 55 45 57 51 46
52 47 58 45 55 43 49 54
ii
ACKNOWLEDGEMENTS
We would like to express our deepest gratitude and appreciation to our project advisor Prof. Hassan Noura for his guidance, continuous encouragement and support to complete this work. Also, we would like to thank Dr. Mousa Hussein, Dr. Imad Barhumi and Dr. Saud Aldajah for serving as members of our final examination committee. Our thanks go also to the Training and Graduation Projects Unit, represented by the administration staff and our project coordinator Dr. Hend Al-Qamzi for her helpful comments, guidance and suggestions. Finally, we wish to express our appreciation to our family members for their unlimited help and support during our study.
EXECUTIVE SUMMARY
PV arrays take usually a large area and require a decent effort in terms of fault monitoring, location, and diagnostic. The smart monitoring system aims at implementing a fault detection and monitoring system for PV arrays. The system shall be able to detect, locate, and isolate faults based on PV cell failure criteria. Also, the system will have an easy user friendly Graphical User Interface (GUI), which allows an easy experience for a PV array operator to monitor, diagnose, and protect the system. The software shall be done using LABVIEW and the data acquisition from the PV array is done using NI (National Instruments) CompactRIO. An operating prototype of addition to two standby cells shall be delivered at the end of the project. PV array, in
Table of Contents
EXECUTIVE SUMMARY .................................................................................... 1 Table of Contents .................................................................................................... 3 LIST OF FIGURES ................................................................................................ 6 LIST OF TABLES .................................................................................................. 7 LIST OF SYMBOLS, ABBREVIATIONS, NOMENCLATURE ......................... 8 CHAPTER 1 .......................................................................................................................9 INTRODUCTION .................................................................................................. 9 1.1 1.2 1.3 1.4 Problem Statement and Purpose .......................................................................... 9 Project and Design Objectives ............................................................................ 9 Intended Outcomes and Deliverables ................................................................ 11 Summary of report structure: ............................................................................ 12
CHAPTER 2 .....................................................................................................................22 BACKGROUND LITERATURE AND MARKET SURVEYError! not defined. 2.1 2.2 2.3 2.4 2.5 Relevant Literature Search .................................Error! Bookmark not defined. Error! Bookmark not defined. Target Market and their needs: ...........................Error! Bookmark not defined. Prioritized Needs / Requirements: ......................Error! Bookmark not defined. Potential Ethical and/or Environmental Issues: ................................................ 26 Bookmark
CHAPTER 3 .....................................................................................................................27 3
CONCEPTUAL DESIGN .................................................................................... 27 3.1 3.2 3.3 3.4 3.5 3.6 Problem Review .................................................Error! Bookmark not defined. Design Specifications: ........................................Error! Bookmark not defined. Generation of Conceptual Alternatives: .............Error! Bookmark not defined. Selected Alternatives and Reasoning: ................Error! Bookmark not defined. Formal Decision-Making Process and Final Concept Selection ....................... 32 Discussion and Perceived problems: ..................Error! Bookmark not defined.
CHAPTER 4 .....................................................................................................................34 PRELIMINARY DESIGN.....................................Error! Bookmark not defined. 4.1 4.2 4.3 Block Diagram: ................................................................................................. 34 Preliminary design: ............................................Error! Bookmark not defined. Safety consideration ...........................................Error! Bookmark not defined.
CHAPTER 5 .....................................................................................................................34 ECONOMICAL, ETHICAL, AND CONTEMPORARY ISSUES ...................... 34 5.1 5.2 5.3 5.4 5.5 Preliminary Cost Estimation and Justification .................................................. 35 Relevant Codes of Ethics and Moral Frameworks ............................................ 36 Relevant Environmental Considerations ........................................................... 37 Relevance to UAE and Region (Social, Cultural, and Political) ....................... 37 Ethical Dilemmas and Justification of Proposed Solution ................................ 38
Tasks and Schedule ........................................................................................... 40 Problems faced and solutions ............................................................................ 42 Resources .......................................................................................................... 42 Each Students Responsibilities ........................................................................ 43
CHAPTER 7 .....................................................................................................................44
CONCLUSION AND PLAN FOR GP2 ............................................................... 44 7.1 7.2 7.3 7.4 7.5 Restatement of Purpose of Report and Objectives ............................................ 44 Summary of how each Objective and Deliverable has been met ...................... 44 Summary of Final Design Solution ................................................................... 45 New skills learnt ................................................................................................ 45 Plan for GP2 .......................................................Error! Bookmark not defined. References ............................................................................................................. 47 APPENDIX A ....................................................................................................... 52
LIST OF FIGURES
LIST OF TABLES
CHAPTER 1 INTRODUCTION
1.1 Problem Statement and Purpose
One considerable problem in PV arrays is its large spread in a single area, which requires a considerable amount of maintenance, and fault detection efforts. This Project aims at implementing a fault detection and monitoring system for PV arrays. The system shall be able to detect, locate, and isolate faults based on certain PV cell failure criteria. Thus, facilitating maintenance and lower its operating expenses (OPEX). Also, the system will have an easy user friendly GUI, which allows an easy experience for PV array operators to monitor, diagnose, and protect their system. The software shall be done using LABVIEW and the data acquisition from the PV array is taken using NI CompactRIO. The goal of this project is to provide an efficient, real time, and automated system that is able to locate, identify, and isolate the fault to ease the maintenance and minimize the failure probabilities of a real-world solar farm. Which in turn can minimize the cost of solar farms operations.
locate the faults, isolate the faulty panel, and replace it with the stand by cell. The design objectives can be described as follows: Use of an efficient algorithm to detect faulty panels before system failure. Real-time monitoring and alerting system to the array operator. Ease and increase the efficiency of the maintenance process. Have a friendly GUI that shows real-time system status and fault locations. Prevent single panel failure from causing full system failure. To fulfill the objectives, the project was divided into four main blocks shown in Figure 1. The PV array block is our main monitoring target for any faults or abnormal operation. The PV array is monitored using sensors connected to each panel within the array, in addition to general monitoring sensors. The sensors data is passed to the DAQ system, which contains the LabVIEW program which identifies any faulty condition and take immediate action through the isolation relays. At the same time, the LabVIEW program will inform the operator through a GUI program the health state of the array or any taken action to prevent a full system failure.
10
11
The software shall be written using LabVIEW and the data acquisition will be done using NI CompactRIO. Prototype: An actual PV array prototype shall be built. The prototype will have an adequate volume to enable easy mobility and demonstration of the system characteristics and features. In addition, the prototype shall demonstrate the capabilities of applying such system in real world. A 4x2 array (three series panels in each of the two array columns) shall be integrated with the prototype to have a real preview on the system performance. The prototype shall be operating as a 4x2 array in real-time with two panels as stand by in each column (i.e. parallel connection). In conclusion, the project shall deliver the following outcomes: A complete functioning prototype of 4x2 PV array. A friendly and easy to use GUI. A functioning algorithm for fault monitoring and detection. An automatic ability to locate, isolate, and replace a faulty panel.
12
Monocrystalline Silicon Solar Cells: Advantages: Monocrystalline cells have the highest efficiency rates, since they are made out of the highest-grade silicon. The efficiency rates of Monocrystalline solar panels are typically 15-20% [3]. Monocrystalline silicon solar panels are space-efficient. When compared to thin-film, Monocrystalline can produce up to four times of electricity in a specified area. Monocrystalline panels have a decent life span, which makes most manufacturers put a 25-year warranty on their Monocrystalline solar panels [3]. Disadvantages: Monocrystalline panels are the most expensive panels to get. Which can be a difficult choice for homeowners from a financial point of view. [3]
14
If the solar panel is partially covered with shade, dirt or snow, the entire circuit can break down. Micro inverters should be considered in case a coverage problem is expected. Micro inverters make sure that the entire solar array is not affected by shading issues with only one of the solar panels. The process used to produce monocrystalline silicon is called Czochralski process. It results in large cylindrical ingots. Four sides are cut out of the ingots to make silicon wafers, which leads to a significant amount of waste out of the original silicon [3]. Performance of monocrystalline panel tends to be more efficient in warm weather; yet, it starts to suffer as temperature goes up. Still, monocrystalline heat performance is better than the polycrystalline ones. Polycrystalline Silicon Solar Cells: Advantages: The process used to create polycrystalline silicon is simpler, less cost, and produces less waste when compared to the production process of monocrystalline panels [3]. Polycrystalline panels have lower heat tolerance when compared to the monocrystalline. Heat can affect the performance of solar panels and shorten their lifespans. However, this effect is minor, and most homeowners do not need to take it into account. Disadvantages: 15
Because of the lower silicon purity, polycrystalline-based solar panels have typical efficiency of 13-16%. Which is noticeably less than typical monocrystalline panels efficiency. A larger surface area is needed to output the same electrical power as a solar panel made of monocrystalline silicon. Thin-Film solar cells (TFSC): Advantages: Easier to mass-produce and potentially cheaper to manufacture than crystalline-based solar cells. Thin film cells can be made flexible which opens a variety of potentially new applications. High temperature and shading have less impact on thin film solar panels performance when compared to crystalline-silicon based panels. [3] Disadvantages: Poor space-efficiency, which also means that the costs of support structures, cables and other PV equipment increase. Thin-film solar panels tend to degrade faster than crystalline-silicon based solar panels, which is why they usually come with a shorter warranty.
16
2.2.2
Batteries
The power generated by the PV panels can be connected directly to a load or connected to a battery. There are several types of batteries used for PV systems storage. The two most famous batteries are discussed as follows: 2.2.2.1 Gel Batteries: Gel batteries are a subcategory of the VRLA (Valve Regulated Lead Acid) batteries which is a subcategory of the lead-acid rechargeable batteries. The gel contained in these batteries is a combination of sulfuric acid and silica and replaces the liquid acid in the traditional acid batteries. The addition of silica to the solution thickens it and make it easier to maintain since the user does not need to check the level of the liquid or replenish it. The batteries contain a valve regulating system that expels any gases that build up inside the battery to avoid any ruptures in the battery [4]. The charging of the gel battery is a critical operation on both ends, overcharging and undercharging. The overcharging of the battery dries it up and creates holes that do not heal. Undercharging the battery may cause on the long run- the creation of a sulfate layer around the positive plate which prevents the battery from recharging [4]. The main advantages of the gel batteries are [4]: 1- Do not spill or leak. 2- Do not corrode. 3- Highly resistive to change in temperature, and shocks.
17
2.2.2.2 Lithium Ion Batteries: Lithium has the highest electromechanical potential in the periodic table and also the lightest metal. This made those batteries very effective for handheld devices. The Liion batteries has many advantages [5]: 1- High electric capacity. 2- Low self-discharging. 3- Low maintenance. 4- Can be specialized to high current applications. There are several drawbacks for the Li-ion batteries like: 1- Requires a protection circuit for voltage and current limits. 2- Aging effect even when not used. 3- Expensive manufacturing cost. 2.2.3 PV cell models:
To simulate a solar panel, a model is used. The most widely used is the equivalent circuit model. There are two main models that are widely used: 2.2.3.1 Single diode model: It is the simplest model for simulating solar panels. It consists of a linear independent current source in parallel with a diode (Figure 2). The required parameters for this model are three: open circuit voltage ( ), short circuit current ( ) and diode
ideality factor ( ). The main advantage of this model is that it has a very low computational burden. The model can be improved by adding a series resistance ( ).
This model is called Rs-model. This model is deficient in cases of high temperature. 18
) and thus it is
called Rp-model. The latter has better accuracy but has inaccurate response in cases of low irradiance and large computational burden. The equation is: ( )
2.2.3.2 Double diode model: The double diode model is more complicated than the single diode model obviously- and it counters most of the shortcomings of the one diode model. The tradeoff is in the computational burden. It contains an independent current source, two diodes in parallel, a series resistance and a shunt resistance (Figure 3). As the components increase, the number of parameters needed and computed increases. The parameters needed from the datasheet of the PV panel are: number of cells in the panel and their connection scheme, irradiation ( ), cell temperature ( ), open circuit voltage ( current ( ), temperature coefficient of ), short circuit ( ),
( ), temperature coefficient of , ).
maximum power voltage and maximum power current ( calculated in this model are: the illumination current ( 19
The parameters ),
diodes currents (
), series resistance (
). Further
acts as a DAQ and controller for the system. it contains a voltage output module to control the relays and rearrange the solar panel arrangement as required.
Item Solar panel GEL batteries Charge controller Prototype stand Voltage sensors Current sensors Thermocouple Pyranometer Wind speed sensor Relays IV tracer Total estimated cost
quantity Unit price (AED) Price (AED) 6 2 1 1 6 6 7 1 1 6 1 300 700 950 1500 62 60 36 735 25 4 14840 0 2225 8 1800 1400 950 1500 372 360 252 735 25 24 1484
The final deliverables for the project will be: o A complete functioning prototype of 4x2 PV array. o A friendly and easy to use GUI. o A functioning algorithm for fault monitoring and detection. 21
Charge controllers are current and voltage regulators to protect the batteries from being overcharged. Since solar panels provide a variable current and voltage depending on solar irradiation and other factors-, charge controllers are essential to many solar systems [1]. There are mainly three types of charge controllers: 3.1.1.1 Simple controllers: They are also called two stage controllers. They are basically are relays with a condition upon reaching a certain voltage. They are the oldest types basically dinosaurs as some described them [1]- but they are extremely reliable and very cheap. The two stages are the bulk stage of charge and the float stage of charge. The bulk stage charges the battery quickly up to 90%. At this percentage, the float stage of charge kicks in and the battery is charged very slowly [2]. 3.1.1.2 PWM controllers: Also called three stage controllers. as all know, PWM stands for Pulse Width Modulation. These charge controllers use pulses to charge the 22
batteries. The width of the pulses depend on the state of charge for the battery. A discharged battery will receive wide pulses that will almost look like a continuous signal. On the other hand, a charged battery will receive narrow pulses. The charge controller reads the state of charge for the battery [1]. The three stages are: bulk stage, float charge and the absorption stage. The first two stages are the same as the simple controllers, however, the third stage is added to charge the battery up to 99% [2]. A problem in these controllers is that they may overcharge the batteries in case of a load present. Therefore, some PWM controllers switch to two stages in the presence of load [2]. The three stages are shown in Figure 4.
23
3.1.1.3 MPPT controllers: MPPT stands for Maximum Power Tracking Point. These controllers are used to change the electrical operating point of the PV panels to produce the maximum power the PV system can provide. Batteries require certain voltage to charge. Increasing the voltage will overcharge the battery. The MPPT charge controllers track the voltage that will allow the PV system to provide maximum power. This voltage is called the Maximum Power Voltage ( ) and it is usually higher than the
charging voltage of the batteries. The MPPT controller sets the PV system voltage to this point. Using a DC-to-DC power converter, the charge controller converts the voltage to the charging voltage of the batteries with increased charging current, thus utilizing the maximum power that can be achieved from the system safely [3]. Figure 5 shows a simple block diagram for the MPPT charge controller. The MPPT controller varies the voltage to find maximum power point to set the DC-to-DC converter on it.
24
3.1.2
Relays:
Relays are an extremely powerful but simple electromechanical devices. There are four parts for the relay: (1) an electromagnet, (2) a magnetic armature, (3) a spring and (4) electrical contacts [7]. They are numbered as in Figure 6. The electromagnet is controlled by the control voltage. After the application of the control voltage, the electromagnet attracts the armature. After the control voltage is dropped, the armature returns to its original state because of the spring. In Figure 6, the armature was originally open.
25
26
- Each wheel is fixed to the box with four (10mm x 6cm) bolts and double nuts. 4.1.1.3 The cover: - The cover for the box is aluminum sheets. - The upper and lower sides are of 2mm thickness. The upper sheet is one piece and it is fixed to the box with same bolts. The lower side is made of intersecting sheets of aluminum to strengthen the parts that hold the equipment. - The sides are made of complete sheets of 1mm thickness and are fixed with same bolts of the box. - The front and rear (along the length) sheets are the doors to the box. Each sheet if fixed to the top of the box with five hinges. 4.1.1.4 The panel stand: - The panels are placed on iron pipes. The iron pipes are hollow with 4cm diameter. There are two lengths, four long pipes with a length of 150cm in the rear and four short pipes with a length of 60cm in the front. This is to prevent shading of panels on each other. - The pipes are welded on iron plates of width of, length of, and thickness of. Each two pipes one short and one long pipes- are fixed using bolts and double nuts on two upper support bars. On the top of the iron pipes, a
28
xxcm length iron angle was welded to allows us to adjust the panels angle. The - The panels are fixed with bolts and nuts on an iron skeleton as shown in Figure 8. The skeleton is then connected to the iron pipes and fixed with a bolt and double nuts. The panel is first adjusted to the desired angle and then fixed with the bolt. 4.1.2 Equipment:
The equipment used in this project are: o x8 (40 Watts) solar panels. o x4 (12V, 100 AH) GEL batteries. o x2 (24V, 20A) charge controller: each two batteries has one charge controller. o x8 voltage sensors (i.e. one for each panel). o x8 current sensors (i.e. one for each panel). o x9 thermocouple (i.e. one for each panel + one for ambient). o x2 pyranometer (in-plain of the panels, horizontal) o x1 wind speed sensor. o x1 wind direction sensor. o x8 relays.
29
4.1.3
Simulation:
As discussed in chapter 2, the chosen model for simulating the PV panels is the two diode model. The matlab program used for simulation is shown below: delta_T = T-T_stc; I_pv = (I_pv_stc + K_i*delta_T)*G/G_stc; V_T = N_s*(T+273)*1.3806488E-23/1.60217657E-19; pass_vec=[ I_pv_stc,K_i,T,T_stc,G,G_stc,delta_T,I_pv,I_ sc,V_oc,I_m,V_m,a_1,N_s,V_T,K_v ]; 30
%clc par0=[1e-5 1e-5 0.3 150 1.2]; options=optimset('MaxFunEvals',1000,'MaxIter',1000,'Tol Fun',1e-6); %'Algorithm','active-set' [sol resnorm residual exitflag]=lsqnonlin(@sys_eq,par0,zeros(1,5),[],options, pass_vec); I_o1=sol(1); I_o2=sol(2) ; R_s=sol(3); R_p=sol(4) ; a_2=sol(5); V=0:.1:V_oc+2; I0=linspace(0,I_sc,length(V)); y=(-exp(I0)+exp(I0(length(I0))))/I0(2); for i=1:length(V) Eq1 =@(I) I_pv - I_o1*(exp((V(i)+I*R_s)/(a_1*V_T))-1) I_o2*(exp((V(i)+I*R_s)/(a_2*V_T))-1) - (V(i)+I*R_s)/R_p - I; I(i)=lsqnonlin(Eq1,y(i)*I_sc/max(y),0,[],options); end
The inputs to this program are: Open circuit voltage ( ): it is provided by the manufacturer. In this project it is 21 V. Short circuit current ( ): it is provided by the manufacturer. In this project it is 2.777 A. Illumination current at STC ( ): which is equal to the value of the short circuit current under STC. This is because the current passing through the diodes is extremely low and the series resistance is also extremely low in comparison to the shunt resistance-. Temperature coefficient of ( ): it is provided by the manufacturer. In this o project it is 0.00180505 A/ C 31
Temperature coefficient of ( ): it is provided by the manufacturer. In this o project it is -0.08 V/ C. Maximum power point voltage and current ( , ): provided by the manufacturer. In this project they are 2.473 A and 16.891 V Irradiation ( ): this value is the in-plane irradiation sensor. Temperature ( ): this value is obtained from the temperature sensor that is attached to the back of each cell. Ideality factor of the first diode ( ): this value is chosen to be 1 for simplicity and it is a sound judgement. Number of connected cells in series ( ): obtained from the manufacturer. It is the number of series connected cells in the panel. For this project, it is 36.
Some of the
There were three types of solar cells compared: Monocrystalline Silicon Solar Cells, Polycrystalline Silicon Solar Cells and Thin-Film solar cells (TFSC). The decision matrix for the solar cells is shown in Table 2.
Table 2: Decision matrix for choosing the most adequate PV panel type
size
performance
cost
weight lifespan
sum
25%
17%
30% 13%
5%
10%
100%
9 8 5
8 7 3
5 8 9
7 6 8
9 8 6
8 7 1
32
4.3.2
DAQ:
Arduino Uno and CompactRIO were considered for DAQ. Arduino Uno is an open hardware/software with cheap cost. However, it lacks the rigidity and high performance that is provided by CompactRIO. Moreover, CompactRIO is already available in the department and is supported by several training workshops. Table 3 shows the decision matrix for the DAQ devices.
Criteria Price Weighting factor Alternatives CompactRIO Arduino UNO 1 10 7 8 10 4 10 10 25% 7% 8% Ruggedness Performance
Ease of Programming
Availability
sum
25%
35%
100%
10 0
75% 59%
4.3.3
Table 4 shows the decision matrix for the I-V Curve-Tracer selection.
Table 4: Decision Matrix for the I-V curve tracer
Criteria Weighting factor Alternatives Daystar DS-100C EKO MP-160 HT-Italia Solar I-V
Price 40% 2 4 9
Range 25% 10 5 8
Portability 35% 1 3 10
33
9 10
7 5
8 10
81.50% 87.50%
4.3.4
PV models:
There are three models proposed to simulate the PV system: Rs model, Rp model and double diode model. The three criteria in choosing between these models are: performance in low radiation, performance in high temperature and the computational burden. Since the system involves computer handling the computational process and the parameters does not change quickly (irradiance and temperature) in most cases-, the main criteria will be the performance. Table 1 shows the decision matrix for chose PV model.
Table 5: Decision matrix for choosing the PV model
34
Item Solar panel GEL batteries Charge controller Prototype stand Voltage sensors Current sensors Thermocouple Pyranometer Wind speed sensor Relays IV tracer Total estimated cost
quantity Unit price (AED) Price (AED) 8 4 2 1 8 8 7 2 1 8 1 300 700 950 2800 62 60 36 735 25 4 14840 0 2749 5 0 25 32 1484 2400 2800 1900 2800 496 480 252 1,47
35
- Honesty and realistic claims or estimates based on available data had a decent attention in the project (Code #3).
- The work was distributed between team members according to their major and interests (Code #6).
- The project will be available for all people regardless to their religion, gender and nationality (Code #8). - The system will not disturb publics privacy (Code#9).
5.2.2 NSPE code of ethics [28]: - Team members shall avoid deceptive acts (Rules of practice #5).
- Team members shall be guided in all their relations by the highest standards of honesty and integrity (Professional Obligations #1).
36
- All information used in the report was referenced (Professional Obligations #3.c) (Professional Obligations #9.a).
37
38
39
Tue 19-02-13 Thu 14-02-13 Tue 19-02-13 3 Mon 18-02-13 4SS+1 day Sun 02-06-13 2 Mon 25-02-13 Mon 25-02-13 7SS Thu 28-02-13 8SS Tue 05-03-13 9 Wed 08-05-13 10 Tue 12-03-13 Thu 28-03-13 10,12 Mon 22-04-13 10,13 Wed 08-05-13 10,14 Sun 19-05-13 15 Sun 02-06-13 16 Sun 13-10-13 6 Mon 09-09-13 Sun 15-09-13 19 Sun 29-09-13 20 Sun 13-10-13 20 Tue 28-01-14 18 Sun 27-10-13 Sun 24-11-13 24 Sun 15-12-13 25 Tue 31-12-13 26 Tue 28-01-14 26,27 Mon 27-01-14 23 Mon 27-01-14 Thu 28-02-13 Thu 28-02-13 Thu 28-02-13 Thu 25-04-13 10 Thu 07-03-13 Thu 25-04-13 Thu 25-04-13 Sun 10-02-13
40
41
7.3 Resources
The internet, university lectures and papers were used as sources of information in this project. Most of the literature background, like fault types, devices specifications and data sheets, was obtained from the internet. Fault detection methods and data were obtained mainly from papers in IEEE Xplore and ScienceDirect. University lectures were very useful in obtaining the knowledge about the CompactRIO operation and LabVIEW
42
programming. For the prototype stand, the mechanical engineers and students were very helpful in designing and building.
43
CHAPTER 8 CONCLUSION
8.1 Restatement of Purpose of Report and Objectives and the Proposed deliverables
The purpose of this report is to document the outcomes of GP-II phase. The objective of this project is to create a smart fault detection and monitoring system for a mobile PV array. The mobile array should be easy to move and built to endure. The system shall be able to detect, locate, and isolate faults based on PV cell failure criterions. Also, the system will have an easy user friendly GUI, which allows an easy experience for a PV array operator to monitor, diagnose, and protect the system. A functioning prototype shall be delivered at the end of December 2013. This project shall help large PV farms owners to minimize their maintenance cost and improve overall system efficiency.
8.2 Summary of how each Objective and Deliverable has been met
A brief discussion on how the chosen technologies are helping in meeting the objective and deliverable is done in this section. The solar panels are the main scope of this study, and shall be used to have a real-time data, that reflects real world faulty situations. The panels are equipped with many sensors to measure its operation condition. The sensors readings are passed to the DAQ (i.e. CompactRIO) to interpret them and decide a normal or faulty operation condition. In case of faulty condition detection, the system shall isolate the faulty panel and transfer its operation to a standby panel using the 44
relays, which controls the interconnection between the PV array panels. The prototype is designed to be mobile, rigid and easy to disassemble. In addition, this report and a presentation were prepared to describe the work done in GP-I and GP-II phase.
Furthermore, many skills concerning wiring of electrical devices and arrangement of various equipment in a confined space. Sensors calibration was a painful experience but it provided much knowledge and experience for the future. Other skills learnt were in testing, debugging and fault detection of electrical equipment.
46
References
[ 1]
Wikipedia,
"Solar
energy,"
May
2013.
[Online].
Available:
http://en.wikipedia.org/wiki/Solar_energy. [ G. Whitburn, "13 Fundamental Advantages and Disadvantages of Solar [Online]. Available: http://exploringgreentechnology.com/solar-
2]
Energy,"
energy/advantages-and-disadvantages-of-solar-energy/. [Accessed 2013]. [ 3] M. A. Mhlum, "Which Solar Panel Type is Best?," [Online]. Available:
http://energyinformative.org/best-solar-panel-monocrystalline-polycrystalline-thinfilm/. [Accessed 2013]. [ A. Burke, "How Does a Gel Battery Work?," eHow, [Online]. Available: [Accessed 23
4]
I. Buchmann, "Is Lithium-ion the Ideal Battery?," Battery University, 20 2010. [Online]. Available:
5]
October
http://batteryuniversity.com/learn/article/is_lithium_ion_the_ideal_battery. [Accessed May 2013]. [ C. Honsberg and S. Bowden, Photovoltaic Education Network, [Online].
47
6]
Available: http://pveducation.org/pvcdrom/. [Accessed April 2013]. [ P. Hernday, "Field Applications for I-V Curve Tracers," SolarPro, pp. 77-
7]
8]
9]
http://en.wikipedia.org/wiki/Pyranometer. [Accessed May 2013]. [ R. Ringoir and K. &. Z. , "Pyranometer v. [Online]. Reference Cell," Available:
10] renewableenergyworld,
11] acquisition/what-is/. [Accessed May 2013]. [ "Acronyms," Farlex, Inc., [Online]. Available:
12] http://acronyms.thefreedictionary.com/CRIO. [Accessed May 2013]. [ "CompactRIO," National Instruments, [Online]. Available:
13] http://www.ni.com/compactrio/whatis/. [Accessed May 2013]. [ "What is Arduino?," Arduino, [Online]. Available:
48
15] http://arduino.cc/en/Main/arduinoBoardUno. [Accessed 30 April 2013]. [ C. H. a. D. Media, "The Effects of Temperature on Solar Panel Power National Geographic, [Online]. Available:
16] Production,"
http://greenliving.nationalgeographic.com/effects-temperature-solar-panel-powerproduction-20500.html. [Accessed May 2013]. [ "Atmel AVR 8-Bit Microcontroller," Amtel Corporation, June 2011.
17] [Online]. Available: http://www.atmel.com/Images/doc8025.pdf. [Accessed April 2013]. [ 18] Uno," S. Fitzgerald, R. Guido, D. Cuartielles, F. T. Igoe and D. A. Mellis, "Arduino Arduino, 28 January 2013. [Online]. Available:
http://arduino.cc/en/Main/ArduinoBoardUno?action=diff. [Accessed 11 May 2013]. [ A. Chouder, S. Silvestre, B. Taghezouit and E. Karatepe, "Monitoring,
19] modelling and simulation of PV systems using LabVIEW," SciVerse ScienceDirect, vol. 91, pp. 337-349, 2013. [ E. Molenbroek, D. W. Waddington and K. A. Emery, "Hot spot susceptibility
20] and testing of PV modules," IEEE Photovoltaic Specialists Conference, pp. 547-552, 1991. [ G. TamizhMani, B. Li, T. Arends, J. Kuitche, B. Raghuraman, W.Shisler, K.
49
qualification testing: 2007 VS. 2005," IEEE Photovoltaic Specialists Conference, pp. 1-4, 2008. [ A. M. Bazzi, K. A. Kim, B. B. Johnson, P. T. Krein and A. Dominguez-
22] Garca, "Fault Impacts on Solar Power Unit Reliability," IEEE, no. 11, 2011. [ L. Schirone, F. Califano, U. Moschella and U. Rocca, "Fault finding in a 1
23] MW photovoltaic plant by reflectometry," IEEE, 1994. [ Y. Liu, B. Li and Z. Cheng, "Research on PV module structure based on
24] Fault detection," IEEE, 2010. [ Y. Liu, B. Li and D. Zhong, "Research on Domestic PV Module Structure
25] Based on Fault Detection," IEEE, 2010. [ N. Gokmen, E. Karatepe, B. Celik and S. Silvestre, "Simple diagnostic
26] approach for determining of faulted PV modules in string based PV arrays," SciVerse ScienceDirect, no. 86, pp. 3364-3377, 2012. [ IEEE, "IEEE Code of Ethics," [Online]. Available:
27] http://www.ieee.org/about/corporate/governance/p7-8.html#top. [Accessed 2013]. [ NSPE, "NSPE Code of Ethics for Engineers," [Online]. Available:
28] http://www.nspe.org/Ethics/CodeofEthics/index.html. [Accessed 2013]. [ "Waste Collection," The Center of Waste Management - Abu Dhabi, Available: http://www.cwm.ae//index.php?page=waste-collection.
29] [Online].
50
51
APPENDIX A
Table 8 : comparison between different types of PV cells using an applied credentials Area Required per MW (in Acre) Plant Load Factor (%) Many solar plants installed wit h c-Si Reliable, Time tested, Durable
Parameters / Technology
Material
Vendors
Credentials
Positives
Crystalline silicon
Polycrystalline
19
Waaree/Tat a BP
Amorphous Silicon
Amorphous Silicon
8.5
20
Schott/Tian wei
-csi Tandem
7.5
20
Nex Power/Dupo nt
Cd-Te
Cadmium Telluride
6.5
20
First Solar/Aboun d
52
Table 9: comparison between Crystalline Silicon cells and thin films from theoretical point of view Cell Technology Types of Technology Crystalline Silicon Mono-crystalline silicon (c-Si) Poly-crystalline silicon (pc-Si/ mc-Si) String Ribbon Thin Film Amorphous silicon (a-Si) Cadmium Telluride (CdTe) Copper Indium Gallium Selenide (CIG/ CIGS) Organic photovoltaic (OPV/ DSC/ DYSC) Voltage Rating (Vmp/ Voc) (Higher is better as there is less gap in Voc and Vmp) Temperature Coefficients Higher Lower (Lower is beneficial at high ambient temperatures) I-V Curve Fill Factor (Idealized PV cell is 100%) Module construction With Anodized Aluminum Frameless, sandwiched between glass; lower cost, lower weight Module efficiency Inverter Compatibility and Sizing 13%-19% Lower temperature coefficient is beneficial 4%- 12% System designer has to consider factor such as temperature coefficients, Voc-Vmp difference, isolation resistance due to external factors Mounting systems Industry standard Special clips and structures may be needed. In some cases labor cost is significantly saved May require more number of circuit combiners and fuses Commercial/ Utility May require up to %50 more space for a given project size Example Brands Q-Cells, Kyocera, Evergreen, Sanyo, Schuco, Canadian Solar, Sharp, Yingli, Solon Schott, REC, Solarworld First solar, Solyndra, UniSolar, Konarka Dye Solar, Bosch Solar,Sharp, Abound Solar 73%-82% 60%-68% 80%-85% 72%-78%
53
54
55
56
57
58
59