How to get the map/drawings approved?

After obtaining the Bye Laws from PIEDMC @ Rs. 1000.00, drawings/construction plans are submitted with Customer Services Department at SIE and approved by Building Control Division. Scrutiny fee for construction plans approval is charged @ Rs.6 per acre.

How to get Gas connection?


Submit a application form with Rs. 10,000.00 for industrial or Rs.1,000 for commercial connection in favor of SNGPL.

How to apply for Environment Approval?


Apply through a request to PIEDMC or EPA directly

WATER CONNECTION
Request letter for water connection. Charges for water connection are Rs. 20,000/-

INDUSTRIAL ELECTRICITY CONNECTION


Request letter for industrial connection, on company letter head. Submission of Industrial Electricity form. NIC Copies of Owner & Witness. Copy of application submitted to obtain Environment Approval from EPD. Collection of Demand Note from PIEDMC office. Payment of Electric Demand Note through pay order. Electrical Inspection Report from Electrical Inspector office Govt. of Punjab. All dues should be cleared Site verification by Building Department. Connected load verification by electrical Department. Energization of connection.

BUILDING MAP SUBMISSION


Copy of owners NIC, Possession slip & Agreement to Sell. Three sets of Drawings on ammonia print signed by owner & architect. Soft copy of map on CD. Architect Registration Certificate (PCATP copy). Structure Stability Certificate (Engineer PEC copy). Submit PIEDMC s Building Bylaws book, each page Signed and Stamped by Owner & Architect. Letter of nature of business as per application form. Map scrutiny charges are as follow: First & revised plan Revised plan Rs. 6/S ft. of covered area

Rs. 4/S ft. of covered area Rs. 6/S ft. of covered area

Addition & Alteration

COMPLETION CERTIFICATE
3 sets of As Built Drawings (Ammonia prints). Soft copy on CD. Environment Approval (Govt. of Punjab Environment Department. Registration with Labour Department. Registration with EOBI. Registration with Social Security Certificate. Electrical Design Certificate. Fire Fighting Equipment and Network Plan. Insurance Registration Certificate.

REGISTRATION WITH LABOUR DEPARTMENT


Submission of Complete set of documents required for submission to Labour Welfare department. Details are as follows; Request for registration on Letter head Notice of occupation List of workers List of Machinery

Certificate of stability Copy of Approve Plan of factory Building Examination / review visit of labour welfare department officer. Registration certificate issued and sent directly to customer by the labour welfare department. After registration, Examination / review visit by officer of Labour welfare department, if required

ENVIRONMENT APPROVAL
Environment Policy 1. All the industries established in PIEDMC industrial estates have to comply with the Pakistan Environmental Protection Act- 1997 (PEPA-1997). 2. Industries that have significant hazardous environmental impacts and aspects are not allowed in the Industrial Estate. 3. All Industries should comply with National Environmental Quality Standards (NEQS). 4. After the submission of Environmental Impact Assessment (EIA) or Initial Environmental Examination (IEE). Under the Section-12 of PEPA-1997, all industries for their construction and operational phase must obtain Environmental Approval from Punjab Environment Protection Department (EPD). A) The first step involved is the submission of the Environmental approval request to EPD. B) EPD reply the proponent to either to submit EIA or IEE report according to regulations mentioned in PEPA-1997 under Section 12. C) The proponent will be awarded with Environmental Approval after the Submission of report. Environmental Approval is mandatory for the attainment of the completion certificate. For change of nature of business, proponent should give an Environmental Compliance Undertaking Procedure for Environmental Approval