Vous êtes sur la page 1sur 95

SHORT FORM

ANNEXURE - A

OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

19. CEMENT PLASTER, POINTING WORK, WASHING WORK


Item No. 123(a-i) (i) (ii) (iii) iv) (a-ii) (a-iii) (i) (ii) (iii) iv) (b). (i) (ii) (iii) (iv) (c) (i) (ii) (iii) (iv) (d) Ground floor. Add for each additional floor up to 5
th th

Description of items Minimum 12 mm thick cement plaster (1:4) on walls.

Unit

Unit Rate

sqm floor. sqm sqm sqm sqm

Tk. Tk. Tk. Tk. Tk.

98.00 4.26 6.38 8.51 113.00

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor Minimum 12 mm thick cement plaster with neat cement finishing to plinth wall and upto 150 mm below ground level (1:4). Minimum 12 mm thick cement plaster with neat cement finishing to dado and plinth wall (1:4). Ground floor and upto 150 mm below ground level Add for each additional floor up to 5th floor. Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor Minimum 12 mm thick cement plaster (1:6) to wall. Ground floor. Add for each additional floor up to 5
th th

sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm sqm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

122.00 4.26 6.38 8.51 89.00 4.26 6.38 8.51 80.00 4.26 6.38 8.51 85.00 4.26 6.38 8.51 50.00 4.26 6.38 8.51 63.00

floor.

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor Minimum 6 mm thick cement plaster (1:4) on RCC surfaces. Ground floor. Add for each additional floor up to 5
th th

floor.

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor do-do cement plaster (1:3) in walls -do-doGround floor. Add for each additional floor up to 5
th th

floor.

sqm sqm sqm sqm sqm sqm sqm sqm

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor 124 (i) (ii) (iii) (iv) 125 (i) Flush pointing to brick wall with cement mortar (1:2). Ground floor. Add for each additional floor up to 5
th th

floor.

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor Rule pointing to brick wall with cement mortar (1:2). Ground floor.

ahsan/aqa

(196)

SHORT FORM

ANNEXURE - A

OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. (ii) (iii) (iv) 126 (i) (ii) (iii) (iv) 127 i) ii) iii) iv) 128 129

Description of items Add for each additional floor up to 5th floor. Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor Raised / tack pointing work to brick wall with cement mortar (1:2). Ground floor. Add for each additional floor up to 5
th th

Unit sqm sqm sqm sqm sqm sqm sqm

Unit Rate Tk. Tk. Tk. Tk. Tk. Tk. Tk. 4.26 6.38 8.51 154.00 4.26 6.38 8.51

floor.

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor Providing drip course/ nosing/ throating at the edge of sunshade or cornice. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor White washing by three coats. Colour wash with yellow orchred/any otherr colour pigment by two coats over a prime coat of white wash.

rm rm rm rm sqm sqm

Tk. Tk. Tk. Tk. Tk. Tk.

37.00 1.30 1.95 2.59 6.35 7.43

20. PAINTING, DISTEMPERING, POLISHING & VARNISHING


130 131 132. 133. 134. Cement Paint of approved quality and colour. Painting to door and window frames and shutters in two coats with best quality approved colour of synthetic enamel paint. Synthetic polyvinyl distempering to wall & ceiling in 2 coats over a coat of brand specified primer or sealer. Plastic emulsion painting of best quality and approved colour to wall and ceiling two coats over a coat of brand specified primer or sealer. Acrylic emulsion painting (silky finish) of best quality and approved colour to wall and ceiling two coats over a coat of brand specified primer or sealer. Textured of best quality and approved colour paint to wall and ceiling. Jesoline clorinated rubber painting of best quality and approved colour to concrete surfaces & steel structures. French polishing to door and window frames and shutters three coats over a coat of priming. Wood varnishing using brand specified thinner to door and window frame and shutter three coats. Varnish (Yacht) Varnish (Egg shell) Varnish (Matt) sqm sqm sqm sqm Tk. Tk. Tk. Tk. 57.00 82.00 69.00 76.00

sqm sqm

Tk. Tk. Tk. Tk.

80.00 288.00 122.00 75.00

135. 136. 137. 138. (a) (b) (c)

sqm sqm

sqm sqm sqm

Tk. Tk. Tk.

68.00 72.00 65.00

ahsan/aqa

(197)

SHORT FORM

ANNEXURE - A

OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No.

Description of items

Unit

Unit Rate

21. DRAIN AND APRON


139. 140. 141. 142.(a) (b) Constructing surface drain of 300 mm clear width and depth up to 300 mm in brick masonry. Constructing surface drain of 600 mm (Av) depth and 225 mm clear width. Providing apron with 50 mm thick cement concrete (1:2:4). Supplying, laying, fitting and best quality fixing 225 mm dia (internal) machine made R.C.C. pipe. -do- with 300 mm dia ( (internal) R.C.C. pipe. rm rm sqm rm rm Tk. Tk. Tk. Tk. Tk. 541.00 1,117.00 387.00 792.00 1,103.00

22. FALSE CEILING, WALL PANELING


143.(a) (b) Supplying, fitting and fixing plain particle board ceiling of 12 mm thick with best quality and well seasoned Garjan wood frame. For auditorium and other type of tall structures beyond 4 m up to 8 m which do not cover the above item (Item No.143(a). sqm (c) 144. Supplying, fitting and fixing of 12 mm thick melamine board. (a) Supplying fitting and fixing gypsum board ceiling of 12 mm thick board. (b) -do- with 12 mm thick veneered board. (a) Supplying, fitting and fixing 12 mm thick BT Veneered board in walling. -do- 12 mm thick particle board sqm sqm sqm sqm sqm Tk. Tk. Tk. Tk. Tk. Tk. 1,206.00 752.00 1,151.00 1,124.00 1,652.00 954.00 sqm Tk. 1,129.00

145. (b)

23. COLLAPSIBLE GATE, M.S. GATE, ROLLING SHUTTER ETC.


146(a) 146 (b) Manufacturing, supplying, fitting and fixing collapsible gate of any design & shape made of 3/4" x 3/8" x 1/8" channel . - do - -do- collapsible gate made of 3/4" x 3/4" x 1/8" M.S. angle as vertical member and 3/4" x 1/8" F.I bar as scissors sqm 146 (c) 147.(a) 147.(b) 148. - do - -do- collapsible gate made of 1" x 1" x 1/8" M.S. angle as vertical member and 1" x 1/8" F.I bar as scissors Supplying, fitting, fixing, and installation of ordinary type M.S. gate (double leaf). Supplying, fitting, fixing, and installation of ordinary type M.S. security gate. Supplying, fitting, fixing and installation of ordinary type M.S. gate (double leaf). sqm sqm sqm sqm Tk. Tk. Tk. Tk. Tk. 1,382.00 1,644.00 2,017.00 3,534.00 1,780.00 sqm Tk. 1,200.00

ahsan/aqa

(198)

SHORT FORM

ANNEXURE - A

OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. 149. 150. 151.

Description of items Supplying, fitting, fixing and installation ordinary type M.S. gate (double leaf). Manufacturing, supplying, fitting and fixing G.I. pipe gate. Supplying. fitting and fixing of rolling shutterof.

Unit sqm sqm sqm

Unit Rate Tk. Tk. Tk. 2,691.00 3,924.00 1,744.00

24. STAIR RAILING & VERANDAH RAILING


152. 153. 154. (a) (b) 155.(a) (b) Manufacturing, supplying, fitting and fixing stair railing with 3/4" x 3/4" M.S. square box. Manufacturing, supplying, fitting and fixing stair railing with 1" x 1" M.S. square box. Supplying, fitting and fixing 12 mm dia G.I pipe stair railing. With Hnadrail (150 x 62 mm) (finished) With Handrail (112 x 62 mm) Providing veranda railing with 38 mm dia G.I. Pipe hand rail. -do- with 50 mm dia G.I. Pipe hand rail sqm sqm sqm sqm Tk. Tk. Tk. Tk. 1,401.00 1,589.00 1,665.00 1,863.00 sqm sqm Tk. Tk. 1,357.00 2,217.00

25. GRILL FENCING, BARBED WIRE FENCING


156. 157. 158 Supplying, fitting and fixing steel grill fencing in bundary wall of any design & shape with 31 x 6 mm F.I. Bar. Supplying, fitting and fixing steel grill fencing of any design & shape made with 19 mm x 3 mm tube. Manufacturing, supplying, fitting and fixing M.S. grill fencing as per desin with outer frames having 38 x 38 x 6 mm M.S. angle and inner members having 6 mm dia M.S. rod. Manufacturing, supplying, fitting and fixing M.S. tube (angle box) post (bottom end bifurcated) made by thorough welding of two nos. 38 x 38 x 6 mm M.S. angle. Providing barbed wire fencing with R.C.C (1:2:4) pillars. Providing barbed wire fencing with average 100 mm dia best quality local bullah post. Supplying, fitting and fixing 12 BWG barbed wire (2 ply, 4 points) in fencing work @ 150 mm c/c in both horizontally and vertically, supported by 38 x 38 x 6 mm M.S. angle post. sqm sqm Tk. Tk. 655.00 1,532.00

sqm

Tk.

793.00

159

rm sqm sqm

Tk. Tk. Tk.

318.00 39.00 69.00

160 161 162

sqm

Tk.

234.00

ahsan/aqa

(199)

Analysis of rates of P.W.D. Schedule, May 2002 (10th Edition, Ist Revision) (For Dhaka P.W.D. Circle-1/2/3/4/Savar/Maintenance)

BASIS AND CONSIDERATION MARK-UPS 1. 2. 3. Contractor's profit Overhead expenses VAT MATERIAL AND LABOUR Head mason Mason Skilled labour Ordinary labour Carpenter Helper to carpenter Machine operator Skilled technician Plumber Helper to plumber Painter Helper to painter Welder Helper to welder Point welding Line welding Scaffolding Hire charge of paint spray machine Ordinary portland grey cement: 50 kg bag 0.8 F.M. fine local sand 1.2 F.M. coarse sand 2.5 F.M. sylhet sand Colour pigment Pumic stone Garjan/ Jam / local Shal timber Chittagong teak M.S. sheet/plate M.S. angle, T and Z-section, M.S. channel etc. M.S. bar and F.I. bar (non-structural) M.S. rod: 40 grade M.S. rod: 60 grade 2" dia G.I. pipe 1.5" dia G.I/ pipe 3/4" G.I. pipe 1/2" dia G.I. pipe Polythene sheet G. I. wire Nails Nut-bolt screw 9" dia RCC pipe 12" dia RCC pipe 12 mm thick Plain particle board Malamine Board (8 mm thick): 8' -0" x 4'-0" size 12 mm thick gypsum board 12 mm thick laminated vinyle board 12 mm thick B.T. veneered board Aluminium T-section (main Tee) for false ceiling Aluminium T-section (cross Tee) for false ceiling Aluminium L-section for false ceiling 12 BWG barbed wire Rivet, washer, wire nails etc. 1.5" dia M.S. wheel for collapsible gate 3" - 6" M.S. clamp 10.00% 3.50% 4.50% 18.6075% Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 180.00 150.00 120.00 100.00 160.00 120.00 160.00 250.00 160.00 120.00 160.00 120.00 160.00 120.00 1.50 2.00 3.00 1.00 250.00 625.00 990.00 1,330.00 30.00 140.00 710.00 1,400.00 23,920.00 19,195.00 17,010.00 22,660.00 24,120.00 80.00 72.00 33.00 25.00 117.00 50.00 40.00 60.00 89.94 120.12 22.97 1,150.00 48.00 45.85 75.00 11.00 9.00 8.00 1,450.00 40.00 10.00 10.00 Per day Per day Per day Per day Per day Per day Per day Per day Per day Per day Per day Per day Per day Per day Per point Per inch Per sft. Per sft. Per bag Per % cft. Per % cft. Per % cft. Per Ib. Each Per cft. Per cft. Per Ton Per ton Per ton Per ton Per ton Per rft. Per rft. Per rft. Per rft. Per % sft. Per kg Per kg Per kg. Per rft. Per rft. Per sft. Per pc. Per sft. Per sft. Per sft. Per rft. Per rft. Per rft. Per cwt. Per kg Each Each

(200)

Analysis of rates of P.W.D. Schedule, May 2002 (10th Edition, Ist Revision) (For Dhaka P.W.D. Circle-1/2/3/4/Savar/Maintenance)

Electrodes in/c electricity Greese/lubricant etc. 1.5 inch dia heavy type gate wheel Clamp with huskel dumney Heavy duty gate locking arrangement 5" M.S. hinges 5/8" socket bolt China made spring for rlling shutter Spring box for rolling shutter 1/2 dia nut-bolt 1.5" screw Rowl plug Wall bit Slaked lime Gum Blue Pigment for colour washing PAINTS Cement paint S.E paint Paint Under-coat Thinner for oil-based paint S.P. Distemper Distemper Primer /sealer Acrylic Plastic Paint Acrylic Plastic paint Acrylic Plastic Paint sealer Acrylic Emulsion Paint Acrylic Emulsion Paint Acrylic Emulsion Paint Primer/under-coat Chlorinated Rubber Paint Chlorinated Rubber Paint Chlorinated Rubber Paint Sealer Chlorinated Rubber Paint Thinner Texured Paint (Bontile) Texured paint Wood varnishing: Yacht Yacht Egg-shell Matt Thinner French-polishing work French powder Spirit Gala Mostaki Karpa Sand paper Putty Markin cloth Cotton Earth work in excavation: Brick-flat soling: Cement concrete (1:3:6): Cement concrete (1:2:4): 5" thick brick work (1:4):

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

4.00 40.00 80.00 70.00 125.00 15.00 100.00 10.00 60.00 5.00 8.00 0.25 25.00 5.00 35.00 85.00 90.00

Each Per Ib. Each Each Each Each Each Per rft. Each Each doz. Each Each Per kg Per kg Per kg Per kg.

52.00 Per kg 151.00 Per liter 126.50 Per liter 45.00 Per liter 80.00 Per liter 148.00 Per liter 150.00 Per liter 150.00 Per liter 160.00 Per liter 153.00 Per liter 260.00 Per liter 240.00 Per liter 106.00 Per liter 155.00 Per liter 170.00 170.00 130.00 42.00 Per liter Per liter Per liter Per liter

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

120.00 30.00 350.00 75.00 110.00 6.00 40.00 20.00 35.00 1,475.00 1,171.25 7,491.10 8,991.10 2,971.80

Per kg Per Ib. Per kg Per kg Per kg Each Per kg Per Yard Per Ib. % 0 cft. % sft. % cft. % cft. % sft.

(201)

Analysis of rates of P.W.D. Schedule, May 2002 (10th Edition, Ist Revision) (For Dhaka P.W.D. Circle-1/2/3/4/Savar/Maintenance)

1/2" thick cement plast:er (1:4) 1/2" thick cement plast:er (1:4) with neat cement finish: S.E. Paint French polishing

Tk. Tk. Tk. Tk.

694.50 882.00 642.50 587.63

% sft. % sft. Per % sft. % sft.

(202)

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

18. CEMENT PLASTER, POINTING WORK, WASHING WORK

ANALYSIS FOR ITEM No. 123(a-i) Minimum 1/2" thick cement plaster (1:4) to walls (average of 1/2" on one side and 3/4" on other side of

the walls).
A. 1/2" thick cement plaster (1:4) on one side of the walls. Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) Cement Labour i ) Head mason ii) Mason iii) Ordinary labour d) 0.25 No. @ 1.00 No. @ 1.00 No. @ Tk. Tk. Tk. 180.00 150.00 100.00 5.00 cft. 1.00 Bag @ @ Tk. Tk. 990.00 250.00 Per % cft. = Tk. Per bag = Tk. = each = Tk. each = Tk. each = Tk. L.S. = Tk. Total = Tk. Contractor's profit Overhead expenses VAT 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. B. 3/4" thick cement plaster (1:4) on other side of the walls. Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) 7.50 cft. @ Tk. Cement 1.50 Bags @ Tk. Labour i ) Head mason 0.25 No. @ Tk. ii) Mason 1.00 No. @ Tk. iii) Ordinary labour 1.00 No. @ Tk. Washing of sand, local carriage, scaffolding, curing, & sundries etc. 990.00 250.00 180.00 150.00 100.00 Per % cft. = Tk. Per bag = Tk. = each = Tk. each = Tk. each = Tk. L.S. = Tk. Total = Tk. 10.00% = Tk. 74.25 375.00 45.00 150.00 100.00 100.00 844.25 84.43 45.00 150.00 100.00 100.00 694.50 69.45 24.31 788.26 35.47 823.73 49.50 250.00

Washing of sand, local carriage, scaffolding, curing, & sundries etc.

d)

Contractor's profit
- 347 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

Overhead expenses

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Average of A & B = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

29.55 958.23 43.12 1,001.35 912.54 9.13 98.28

i)
ii) iii) iv)

For ground floor

Say,

Tk.

98 .00 Per sqm.


Per sqm = Tk. Per sqm = Tk. Per sqm = Tk. 4.26 6.38 8.51

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

ANALYSIS FOR ITEM No. 123(a-ii) Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to plinth walls upto 150 mm below ground level. Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) 5 cft. @ Cement 1.5 Bag @ Labour i ) Head mason 0.25 No. @ ii) Mason 1.25 Nos. @ iii) Ordinary labour 1.25 Nos. @ Washing of sand, local carriage, curing, & sundries etc. Tk. Tk. Tk. Tk. Tk. 990.00 250.00 180.00 150.00 100.00 Per % cft. = Tk. Per bag = Tk. each each each L.S. = = = = Tk. Tk. Tk. Tk. 49.50 375.00 45.00 187.50 125.00 100.00

d)

Total = Tk. 882.00 Contractor's profit 10.00% = Tk. 88.20 Overhead expenses 3.50% = Tk. 30.87 Tk. 1,001.07 VAT 4.50% = Tk. 45.05 Grand total = Tk. 1,046.12 Rate per sft. = Tk. 10.46 Rate per sqm. = Tk. 112.59 Say, Tk. 113 .00 Per sqm.

- 348 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM No. 123(a-iii) Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to dado (average of 1/2" on one side

and 3/4" on other side).


For 3/4" thick plaster with neat cement finish on walls Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) 7.5 cft. @ Cement 2 Bags @ Labour i ) Head mason 0.25 No. @ ii) Mason 1.25 Nos. @ iii) Ordinary labour 1.25 Nos. @ Washing of sand, local carriage, curing, & sundries etc. Tk. Tk. Tk. Tk. Tk. 990.00 250.00 180.00 150.00 100.00 Per % cft. = Tk. Per bag = Tk. = each = Tk. each = Tk. each = Tk. L.S. Total 10.00% 3.50% 74.25 500.00 45.00 187.50 125.00

d)

= Tk. 100.00 = Tk. 1,031.75 Contractor's profit = Tk. 103.18 Overhead expenses = Tk. 36.11 Tk. 1,171.04 VAT 4.50% = Tk. 52.70 Grand total = Tk. 1,223.74 Average of 1/2"[from item No. 123 (a-ii)] and 3/4" = Tk. 1,134.93 Rate per sft. = Tk. Rate per sqm. = Tk. 11.35 122.17

i)

Ground floor

Say,

Tk.

122 .00 Per sqm.

ii) iii) iv)

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

Per sqm = Tk. Per sqm = Tk. Per sqm = Tk.

4.26 6.38 8.51

ANALYSIS FOR ITEM No. 123(b) Min 1/2" thick cement plaster (1:6) to walls (average of 1/2" on one side and 3/4" on other side). Considering 100 sft. of work A. For 1/2" thick cement plaster (1:6) to walls a) Sand (F.M. 1.2) 6 cft. b) Cement 0.75 Bag c) Labour

@ @

Tk. Tk.

990.00 250.00

Per % cft. = Tk. Per bag = Tk.

59.40 187.50

- 349 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

d)

i ) Head mason 0.25 No. @ Tk. 180.00 ii) Mason 1.00 No. @ Tk. 150.00 iii) Ordinary labour 1.00 No. @ Tk. 100.00 Washing of sand, local carriage, scaffolding, curing, & sundries etc. Contractor's profit Overhead expenses VAT

each each each L.S. Total 10.00% 3.50%

= = = = =

= =

4.50% = Grand total =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

45.00 150.00 100.00 100.00 641.90 64.19 22.47 728.56 32.79 761.35

B. For 3/4" thick cement plaster (1:6) to walls a) b) c) Sand (F.M. 1.2) 8.25 cft. @ Tk. Cement 1.1 Bag @ Tk. Labour i ) Head mason 0.25 No. @ Tk. ii) Mason 1.00 No. @ Tk. iii) Ordinary labour 1.00 No. @ Tk. Washing of sand, local carriage, scaffolding, curing, & sundries etc. Per % cft. = Tk. Per bag = Tk. = 180.00 each = Tk. 150.00 each = Tk. 100.00 each = Tk. L.S. = Tk. Total = Tk. Contractor's profit 10.00% = Tk. Overhead expenses 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Average of A & B = Tk. Rate per sft = Tk. Rate per sqm. = Tk. Say,
ii) iii) iv) Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

990.00 250.00

81.68 275.00 45.00 150.00 100.00 100.00 751.68 75.17 26.31 853.16 38.39 891.55 826.45 8.26 88.91

d)

i)

Ground floor

Tk.

89 .00 Per sqm.


Per sqm = Tk. Per sqm = Tk. Per sqm = Tk. 4.26 6.38 8.51

ANALYSIS FOR ITEM No. 123(c) 1/4" thick cement plaster (1:4) to ceiling, column, beams etc. and all other RCC surfaces Considering 100 sft. of work a) Sand (F.M. 1.2) 2.5 cft. @ Tk. 990.00 Per % cft. = Tk. 24.75

- 350 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

b) c) d)

Cement 0.5 Extra cement for grouting 0.125 Labour i ) Head mason 0.25 ii) Mason 1.00 iii) Ordinary labour 1.00 (iv) Extra labour for chiping RCC surface

Bag Bag

@ @

Tk. Tk. Tk. Tk. Tk.

250.00 250.00 180.00 150.00 100.00 100.00

Per bag = Tk. Per bag = Tk. each = Tk. each = Tk. each = Tk. each L.S. Total 10.00% 3.50% = Tk. = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

125.00 31.25 45.00 150.00 100.00 50.00 100.00 626.00 62.60 21.91 710.51 31.97 742.48 7.42 79.87

No. @ No. @ No. @

e)

0.50 No. @ Tk. Washing of sand, scaffolding, curing, sundries, local carriage etc.

Contractor's profit Overhead expenses VAT

4.50% Grand total Rate per sft. Rate per sqm.

i)
ii) iii) iv)

For ground floor

Say,

Tk.

80 .00 Per sqm.


Per sqm = Tk. Per sqm = Tk. Per sqm = Tk. 4.26 6.38 8.51

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

ANALYSIS FOR ITEM No. 123(d) Min 1/4" thick cement plaster (1:3) to walls Considering 100 sft. of work A. For 1/2" thick cement plaster (1:3) to walls a) Sand (F.M. 1.2) 4.7 b) Cement 1.25 c) Labour i ) Head mason 0.25 ii) Mason 1.00 iii) Ordinary labour 1.00 d)

cft. Bag

@ @

Tk. Tk. Tk. Tk. Tk.

990.00 250.00 180.00 150.00 100.00

Per % cft. = Tk. Per bag = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Total = Tk. 10.00% = Tk.

46.53 312.50 45.00 150.00 100.00 100.00 754.03 75.40

No. @ No. @ No. @

Washing of sand, local carriage, scaffolding, curing, & sundries etc. Contractor's profit
- 351 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

Overhead expenses

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk.

26.39 855.82 38.51 894.33

B. For 1/4" thick cement plaster (1:3) to walls a) Sand (F.M. 1.2) 2.35 b) Cement 0.625 c) Labour i ) Head mason 1/4 ii) Mason 1.00 iii) Ordinary labour 1.00 d)

cft. Bag

@ @

Tk. Tk. Tk. Tk. Tk.

990.00 250.00 180.00 150.00 100.00

Per % cft. = Tk. Per bag = Tk. each = Tk. each = Tk. each = Tk. L.S. Total 10.00% 3.50%

23.27 156.25 45.00 150.00 100.00 100.00 574.52 57.45 20.11 652.08 29.34 681.42 787.88 7.88 84.82

No. @ No. @ No. @

Washing of sand, local carriage, scaffolding, curing, & sundries etc.

= Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Average of A & B = Tk. Rate per sft = Tk. Rate per sqm. = Tk.

i)

Ground floor

Say,
ii) iii) iv) Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges

Tk.

85 .00 Per sqm.


Per sqm = Tk. Per sqm = Tk. Per sqm = Tk. 4.26 6.38 8.51

Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

ANALYSIS FOR ITEM No. 124 Flush pointing with cement mortar (1:2) to walls Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) Cement Labour I ) Head mason 1.0 cft. 0.4 Bag @ @ Tk. Tk. Tk. 990.00 250.00 180.00 Per % cft. = Tk. Per bag = Tk. each = Tk. 9.90 100.00 45.00

0.25 No. @

- 352 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

d)

ii) Mason 0.5 No. @ Tk. iii) Ordinary labour 1 No. @ Tk. Washing of sand, scaffolding, curing, sundries, local carriage etc.

150.00 100.00

each = Tk. each = Tk. L.S. = Tk. Total = Tk. 10.00% = Tk.

75.00 100.00 60.00 389.90 38.99 13.65 442.54 19.91 462.45 4.62 49.73

Contractor's profit Overhead expenses

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. 50 .00 Per sqm.
Per sqm = Tk. Per sqm = Tk. Per sqm = Tk.

i)
ii) iii) iv)

For ground floor

Say,

Tk.

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

4.26 6.38 8.51

ANALYSIS FOR ITEM No. 125 Ruled pointing with cement mortar (1:2) to walls Considering 100 sft. of work a) b) c) Sand (F.M. 1.2) 1.5 cft. @ Tk. Cement 0.5 Bag @ Tk. Labour I ) Head mason 0.25 No. @ Tk. ii) Mason 1 No. @ Tk. iii) Ordinary labour 1 No. @ Tk. d) Washing of sand, scaffolding, curing, sundries, local carriage etc. 990.00 250.00 180.00 150.00 100.00 Per % cft. = Tk. Per bag = Tk. each each each L.S. Total 10.00% 3.50% = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 14.85 125.00 45.00 150.00 100.00 60.00 494.85 49.49 17.32 561.66 25.27 586.93 5.87 63.18

Contractor's profit Overhead expenses VAT

= = =
= = =

4.50% Grand total Rate per sft. Rate per sqm.

i)

For ground floor

Say,

Tk.

63 .00 Per sqm.

- 353 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

ii) iii) iv)

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

Per sqm = Tk. Per sqm = Tk. Per sqm = Tk.

4.26 6.38 8.51

ANALYSIS FOR ITEM No. 126 Raised / Tack pointing with cement mortar (1:2) to walls Considering 100 sft. of work a) b) c) d) Sand (F.M. 1.2) 3 cft. @ Tk. Cement 1 Bag @ Tk. Cost of pumic stone 0.25 No. @ Tk. Labour I ) Head mason 0.5 No. @ Tk. ii) Mason 2 Nos. @ Tk. iii) Skilled labour 2 Nos. @ Tk. iv) Ordinary labour 2 Nos. @ Tk. Washing of sand, scaffolding, curing, sundries, local carriage etc. 990.00 250.00 140.00 180.00 150.00 120.00 100.00 Per % cft. = Tk. Per bag = Tk. each Tk. each each each each L.S. Total 10.00% 3.50% 29.70 250.00 35.00

e)

Contractor's profit Overhead expenses VAT

4.50% Grand total Rate per sft. Rate per sqm.

= Tk. 90.00 = Tk. 300.00 Tk. 240.00 = Tk. 200.00 = Tk. 60.00 = Tk. 1,204.70 = Tk. 120.47 = Tk. 42.16 Tk. 1,367.33 = Tk. 61.53 = Tk. 1,428.86 = Tk. 14.29 = Tk. 153.82

i)

For ground floor

Say,

Tk.

154 .00 Per sqm.

ii) iii) iv)

Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % sft.) in/c charges

Per sqm = Tk. Per sqm = Tk. Per sqm = Tk.

4.26 6.38 8.51

- 354 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM No. 127

Providing drip course / noising / throating with cement mortar (1:2). Considering 25 rft. of work a) b) c) Sand (F.M. 1.2) 0.52 cft. @ Tk. Cement 0.08 Bag @ Tk. Labour i) Mason 1.0 No. @ Tk. ii) Ordinary labour 0.5 No. @ Tk. Washing of sand, scaffolding, curing, sundries, local carriage etc. 990.00 250.00 150.00 100.00 Per % cft. = Tk. Per bag = Tk. each = Tk. each = Tk. L.S. = Tk. 5.15 20.00 150.00 50.00 10.00 235.15 23.52 8.23 266.90 12.01 278.91 11.16 36.62

d)

Total = Tk. Contractor's profit 10.00% = Tk. Overhead expenses 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per rft. = Tk. Rate per rm. = Tk. Say, Tk. 37 .00 Per rm.

ii) iii) iv)

Add for each addl. floor up to 5th floor (1/3 lab. per % rft.) in/c charges Add for each addl. from 6th floor to 9th floor (1/2 lab. per % rft.) in/c charges Add for each addl. floor above 9th floor (2/3 lab. per % rft.) in/c charges

Per rm = Tk. Per rm = Tk. Per rm = Tk.

1.30 1.95 2.59

ANALYSIS FOR ITEM No. 128 White washing: 3 coats Considering 1000 sft. of work a) b) c) d) Slaked lime Gum Blue Labour i) Mason 18.66 Kg 0.3 Kg 0.2 Kg @ @ @ Tk. Tk. Tk. Tk. 5.00 35.00 85.00 150.00 Per kg. = Tk. Per kg. = Tk. Per kg. = Tk. each = Tk. 93.30 10.50 17.00 225.00

1.5 Nos. @

- 355 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

e)

ii) Ordinary labour Scaffolding, sundries, local carriage etc.

1 No. @

Tk.

100.00

Contractor's profit Overhead expenses VAT

each L.S. Total 10.00% 3.50%

4.50% Grand total Rate per sft. Rate per sqm.

= Tk. = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

100.00 50.00 495.80 49.58 17.35 562.73 25.32 588.05 0.59 6.35

Say,

Tk.

6.35 Per sqm.

ANALYSIS FOR ITEM No. 129 Colour washing: 3 coats Considering 1000 sft. of work

a) b) c) d) e)

f)

Slaked lime Gum Blue Colour pigment Labour i) Mason ii) Ordinary labour Scaffolding, sundries, local carriage

18.66 0.3 0.2 1

Kg Kg Kg Kg

@ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk.

5.00 35.00 85.00 90.00 150.00 100.00

Per kg. Per kg. Per kg. Per kg. each each L.S. Total 10.00% 3.50%

= = = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

93.30 10.50 17.00 90.00 225.00 100.00 50.00 585.80 58.58 20.50 664.88 29.92 694.80 0.69 7.43

1.5 Nos. @ 1 No. @

Contractor's profit Overhead expenses VAT

= = =
= = =

4.50% Grand total Rate per sft. Rate per sqm.

Say,

Tk.

7.43 Per sqm.

- 356 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

19. PAINTING, DISTEMPERING, POLISHING & VARNISHING


ANALYSIS FOR ITEM No. 130 Cement paint 3 coats (one coat is for priming) Considering 100 sft. of work 1. Skilled labour for cleaning, washing and wetting etc. 0.10 No. 2. Painter for applying paint 3. Helper to painter 4. Labour for 7 days curing: 5. Scaffolding, local carriage, sundries etc. 6. Cement paint 3.25 kg. @ Tk. 52.00 0.50 No. 0.50 No. 1.00 No. @ Tk. 120.00 @ Tk. 160.00 @ Tk. 120.00 @ Tk. 100.00 each = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Per kg. = Tk. Tk. Contractor's profit Overhead expenses VAT 10.00% = 3.50% = 4.50% = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Grand total = Rate per sft. = Rate per sqm. = Say, Tk. 57 .00 Per sqm. 12.00 80.00 60.00 100.00 25.00 169.00 446.00 44.60 15.61 506.21 22.78 528.99 5.29 56.94

ANALYSIS FOR ITEM No. 131 Painting to doors and windows frame and shutters with synthetic enamel paint two coats over a coat of priming Considering 100 sft. of work 1. 2. 3. 4. 5. 6. Painter Ordinary labour Scaffolding, sundries etc. Paint Sealer Thinner 1.00 1.00 1.00 1.00 1.00 No. No. liter liter liter @ @ @ @ @ Tk. 160.00 Tk. 100.00 Tk. 151.00 Tk. 126.50 Tk. 45.00 each each L.S. Per liter Per liter Per liter = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. 160.00 100.00 60.00 151.00 126.50 45.00

- 357 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

10.00% = 3.50% =

VAT 4.50% Grand total Rate per sft. Rate per sqm. Say, Tk.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

642.50 64.25 22.49 729.24 32.82 762.06 7.62 82.02

82 .00 Per sqm.

ANALYSIS FOR ITEM No. 132 Synthetic polyvinyl distempering 2 coats over a coat of priming Considering 100 sft. of work 1. 2. 3. 4. 5. Painter Painter helper Scaffolding, sundries etc. Distemper Under-coat/sealer 1.00 1.00 1.00 1.00 No. No. liter liter @ @ @ @ Tk. 160.00 Tk. 120.00 Tk. 80.00 Tk. 148.00 Contractor's profit Overhead expenses each each L.S. Per liter Per liter Total 10.00% 3.50% = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 160.00 120.00 33.33 80.00 148.00 541.33 54.13 18.95 614.41 27.65 642.06 6.42 69.10

= = =
= = =

VAT 4.50% Grand total Rate per sft. Rate per sqm. Say, Tk.

69 .00 Per sqm.

ANALYSIS FOR ITEM No. 133 Plastic emulsion paint to walls and ceiling 2 coats over a coat of primer Considering 100 sft. of work 1. Painter 2. Painter helper 1.00 1.00 No. No.
- 358 -

@ @

Tk. 160.00 Tk. 120.00

each = Tk. each = Tk.

160.00 120.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

3. Scaffolding, sundries etc. 4. Plastic emulsion paint 5. Sealer / under-coat

1.00 0.90

Litre Litre

@ @

Tk. 150.00 Tk. 150.00 Contractor's profit Overhead expenses

L.S. Per litre Per litre Total 10.00% 3.50%

= = = =

= = =
= = =

VAT 4.50% Grand total Rate per sft. Rate per sqm. Say, Tk.

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

30.00 150.00 135.00 595.00 59.50 20.83 675.33 30.39 705.72 7.06 75.99

76 .00 Per sqm.

ANALYSIS FOR ITEM No. 134 Acrylic emulsion paint to walls and ceiling 2 coats over a coat of acrylic sealer Considering 100 sft. of work 1. Painter 2. Painter helper 3. Scaffolding, sundries etc. 4. Acrylic emulsion paint 5. Sealer / under-coat 1.00 1.00 1.00 1.00 No. No. Litre Litre @ @ @ @ Tk. 160.00 Tk. 120.00 Tk. 160.00 Tk. 153.00 Contractor's profit Overhead expenses each = Tk. each = Tk. L.S. = Tk. Per litre = Tk. Per litre = Tk. Total = Tk. 10.00% = 3.50% = Tk. Tk. Tk. Tk. Tk. Tk. Tk. 160.00 120.00 30.00 160.00 153.00 623.00 62.30 21.81 707.11 31.82 738.93 7.39 79.55

VAT 4.50% = Grand total = Rate per sft. = Rate per sqm. = Say, Tk. 80 .00 Per sqm.

ANALYSIS FOR ITEM No. 135 Textured painting with sealer coat, texure coat and top coat Considering 100 sft. of work

- 359 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

1. 2. 3. 4. 5.

Machine operator 1.00 Helper 1.00 Cost of electricity, machinery hire charges Scaffolding, sundries etc. Texured paint 12.12

No. No.

@ @

Tk. 160.00 Tk. 120.00

liters

Tk. 155.00 Contractor's profit Overhead expenses

each each L.S. L.S. Per liter

= = = = =

10.00% = 3.50% =

VAT 4.50% Grand total Rate per sft. Rate per sqm. Say, Tk.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

160.00 120.00 70.00 30.00 1,878.60 2,258.60 225.86 79.05 2,563.51 115.36 2,678.87 26.79 288.37

288 .00 Per sqm.

ANALYSIS FOR ITEM No. 136 Chlorinated rubber painting of best quality & approved colour. Considering 100 sft. of work

1. Painter 2. Painter helper 3. Scaffolding, sundries etc. 4. Chlorinated rubber paint 5. Sealer / under-coat 6. Thinner : T-2

1.00 1.00 1.10 1.10 0.60

No. No. Litre Litre Liter

@ @ @ @ @

Tk. 160.00 Tk. 120.00 Tk. 260.00 Tk. 240.00 Tk. 106.00 Contractor's profit Overhead expenses

each = Tk. each = Tk. L.S. = Tk. Per litre = Per litre = Per litre = Total= 10.00% = 3.50% =

160.00 120.00 60.00

VAT 4.50% Grand total Rate per sft. Rate per sqm. Say, Tk.

=
= = =

Tk. 286.00 Tk. 264.00 Tk. 63.60 Tk. 953.60 Tk. 95.36 Tk. 33.38 Tk. 1,082.34 Tk. 48.71 Tk. 1,131.05 Tk. 11.31 Tk. 121.74

122 .00 Per sqm.

ANALYSIS FOR ITEM No. 137

- 360 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

French polishing 3 coats Considering 100 sft. of work a) b) c) d) e) f) g) h) i) j) k) l) French powder Spirit Gala Mostaki Karpa Sand paper Putty Markin cloth Cotton Painter Helper Scaffolding, sundries etc. 0.25 4 0.15 0.15 0.05 4 0.5 0.5 0.03 1 1 kg. Ibs. kg. kg. kg. Nos. kg. yard Ibs. Nos. Nos. @ @ @ @ @ @ @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 120.00 30.00 350.00 75.00 110.00 6.00 40.00 20.00 35.00 160.00 120.00 Per kg = Per Ib. = Per kg = Per kg = Per kg = each = Per kg = Per yard = Per Ib. = each = each = L.S. = Total= 10.00% = 3.50% = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 30.00 120.00 52.50 11.25 5.50 24.00 20.00 10.00 1.05 160.00 120.00 30.00 584.30 58.43 20.45 663.18 29.84 693.02 6.93 74.59

Contractor's profit Overhead expenses VAT

4.50% = Grand total Rate per sft.= Rate per sqm.=

Say, Tk. ANALYSIS FOR ITEM No. 138(a) Wood varnishing with varnish (Yacht) Considering 100 sft. of work 1. 2. 3. 4. 5. 6. 7. Sand paper Markin cloth Painter Ordinary labour Scaffolding, sundries, T & P etc. Cost of varnish: Yacht Thinner 4 0.5 1 1 1.00 0.91 Nos. Yard. Nos. Nos. Litre Litre @ @ @ @ @ @

75 .00 Per sqm.

Tk. 6.00 Tk. 20.00 Tk. 160.00 Tk. 100.00 Tk. 170.00 Tk. 42.00 Contractor's profit Overhead expenses

each Per yard each each L.S. Per litre Per litre

= = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk.

24.00 10.00 160.00 100.00 30.00 170.00 38.22

Total = Tk.
10.00% = Tk. 3.50% = Tk. Tk.

532.22
53.22 18.63 604.07

- 361 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

VAT

4.50% = Grand total Rate per sft.= Rate per sqm.=

Tk. Tk. Tk. Tk.

27.18 631.25 6.31 67.92

Say, Tk.

68 .00 Per sqm.

ANALYSIS FOR ITEM No. 138(b) Wood varnishing with varnish (Egg-shell) Considering 100 sft. of work 1. 2. 3. 4. 5. Sand paper Markin cloth Painter Ordinary labour Scaffolding, sundries, T & P etc. 4.00 0.50 1.00 1.00 1.33 0.34 Nos. Yard. No. No. Litre Litre @ @ @ @ @ @ Tk. 6.00 Tk. 20.00 Tk. 160.00 Tk. 100.00 Tk. 170.00 Tk. 42.00 Contractor's profit Overhead expenses each Per yard each each L.S. Per litre Per litre Total 10.00% = = = = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 24.00 10.00 160.00 100.00 30.00 226.10 14.28 564.38 56.44 19.75 640.57 28.83 669.40 6.69 72.01

6. Cost of varnish: Egg-shell 7. Thinner

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total Tk. Rate per sft.= Tk. Rate per sqm.= Tk. 72 .00 Per sqm.

Say, Tk. ANALYSIS FOR ITEM No. 138(c) Wood varnishing with varnish (Matt) Considering 100 sft. of work Sand paper Markin cloth Painter Ordinary labour Scaffolding, sundries, T & P etc.

1. 2. 3. 4. 5.

4 0.5 1 1

Nos. Yard. No. No.

@ @ @ @

Tk. 6.00 Tk. 20.00 Tk. 160.00 Tk. 100.00

each Per yard each each L.S.

= = = = =

Tk. Tk. Tk. Tk. Tk.

24.00 10.00 160.00 100.00 30.00

- 362 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

6. Cost of varnish: Matt 7. Thinner

1.30 0.35

Litre Litre

@ @

Tk. 130.00 Tk. 42.00 Contractor's profit Overhead expenses VAT

Per litre Per litre Total 10.00% 3.50%

= = = = =

4.50% = Grand total Rate per sft.= Rate per sqm.=

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

169.00 14.70 507.70 50.77 17.77 576.24 25.93 602.17 6.02 64.80

Say, Tk.

65 .00 Per sqm.

- 363 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

20. DRAIN AND APRON

ANALYSIS FOR ITEM NO. 139 Construction of 1'-0" clear width and depth upto 1'-0" masonry surface drain Considering 10 rft. of work a) Earth work in excavation: 10'-0" x 1'-10" x 1'-3"(av.) = b) Brick-flat soling: 10'-0" x 1'-10"= 18.33 sft. @ c) Cement concrete (1:3:6): 10'-0" x 1'-10" x 0'-3"(av.) = 4.58 cft. @ d) 5" thick brick work (1:4): 2 x 10'-0" x 0'-9"= 15 sft. @ e) 1/2" thick cement plast:er (1:4) with neat cement finish: 10'-0" x 4'-0"= 40 sft. @ Tk. 1,171.25 Tk. 7,491.10 Tk. 2,971.80 Tk. 882.00 Per % sft. = Per % cft. = Per % sft. = Per % sft = Total = 10.00% = 3.50% = 4.50% Grand total Rate per rft.. Rate per rm = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 214.69 343.09 445.77 352.80 1,390.16 139.02 48.66 1,577.84 71.00 1,648.84 164.88 540.97

22.92 cft.

Tk. 1,475.00

Per % 0 cft. =

Tk.

33.81

Contractor's profit Overhead expenses VAT

= = =

Say,

Tk.

541 .00 Per rm.

ANALYSIS FOR ITEM NO. 140 Construction of surface drain of 2'-0" (av.) depth and 0'-9" clear width at bottom and 1'-0" at top having 5" thick cement concrete curb etc. masonry surface drain Considering 10 rft. of work a) Earth work in excavation: 10'-0" x (2'-7" + 1'-7")/2 x 2'-7"=

53.66 cft.

Tk. 1,475.00

Per % 0 cft. =

Tk.

79.15

- 364 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

b) c) d) e) f)

Brick-flat soling: 10'-0" x 1'-10"= 18.30 sft. Cement concrete (1:2:4): 10'-0" x 3'-7" x 0'-5"= 14.93 cft. 5" thick brick work (1:4): 2 x 10'-0" x 1'-0"= 20 sft. 1/2" thick cement plast:er (1:4) with neat cement finish: 10'-0" x 6'-7"= 65.83 sft. Cost of polythene: 10'-0" x 6'-0"= 50 sft. @ @ @ @ @ Tk. 1,171.25 Tk. 8,991.10 Tk. 2,971.80 Tk. Tk. 882.00 117.00 Per % sft. = Per % cft. = Per % sft. = Per % sft. = Per % sft. Total = 10.00% = 3.50% = 4.50% Grand total Rate per rft. Rate per rm. = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 214.34 1,342.37 594.36 580.62 58.50 2,869.34 286.93 100.43 3,256.70 146.55 3,403.25 340.33 1,116.62

Contractor's profit Overhead expenses VAT

=
= =

Say,

Tk.

1,117 .00 Per rm.

ANALYSIS FOR ITEM NO. 141 Providing apron with 2" or 50 mm thick cement concrete (1:2:4) and one layer brick flat soling at bottom. Considering 100 sft. of work A) For concrete of (1:2:4) 100 cft. @ Tk. 8,991.10 Per % cft. = Cost for 2" thick 100 sft. concrete = Tk. Tk. Tk. 150.00 100.00 250.00 each = each = Per bag = = = Per % sft. = Per % 0 cft. = (A+B+C) = 10.00% = 3.50% = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 8,991.10 1,498.52 75.00 100.00 125.00 300.00 1,798.52 1,171.25 61.46 3,031.23 303.12 106.09

Labour cost for 2" thick 100 sft. concrete i) Mason for neat finish 0.5 No. 1 No. ii) Ordinary lab. for neat finish iii) Extra cement for neat finish 0.5 bag.

@ @ @

B) C)

Total cost for 100 sft. concrete One layer brick flat soling 100 sft. @ Tk. 1,171.25 Earth work: 100 sft. x 0'-5"= 41.67 cft. @ Tk. 1,475.00 Total Contractor's profit Overhead expenses

- 365 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

Tk. VAT 4.50% = Grand total = Rate per sft. = Rate per sqm. = Say, Tk. 387 .00 Per sqm. Tk. Tk. Tk. Tk.

3,440.44 154.82 3,595.26 35.95 386.97

ANALYSIS FOR ITEM NO. 142(a) Supplying and laying, fitting, fixing of 9" or 225 mm inside dia RCC pipe excluding cost of earth cutting & back filling. Considering 18 rft. of work a) Cost of machine made best quality 9" dia RCC pipe in/c all necessary fittings 18 rft. b) @ Tk. 89.94 each = Per % sft. = Tk. Tk. 1,618.92 438.52

One layer brick flat soling: 18'-0" x 2'-1"= 37.44 sft. @ Tk. 1,171.25 c) Cement concrete(1:3:6): bottom: 18'-0" x 2'-1" x 0'-4"= 12.48 cft. sides: 2 x 18'-0" x 10" x 10"/2= 6.25 cft. = 18.73 cft. @ Tk. 7,491.10 d) Labour charge for laying pipe maintaining proper slope in/c cost of gasket etc. 0.25 No. @ Tk. 180.00 i) Head mason ii) Mason 0.25 No. @ Tk. 150.00 iii) Skilled labour 1 No. @ Tk. 120.00 Contractor's profit Overhead expenses VAT

Per % cft. = each each each Total = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

1,403.08 45.00 37.50 120.00 3,663.02 366.30 128.21 4,157.53 187.09 4,344.62 241.37 791.93

10.00% = 3.50% = 4.50% = Grand total = Rate per rft. = Rate per rm. =

Say,

Tk.

792 .00 Per rm.

- 366 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 142(b) Supplying and laying, fitting, fixing of 12" or 300 mm inside dia RCC pipe excluding cost of earth cutting & back filling. Considering 18 rft. of work Cost of machine made best quality 12" dia RCC pipe in/c necessary fittings. 18 rft. @ Tk. 120.12 c) One layer brick flat soling: 1 x 18'-0" x 2'-8"= 48 sft. @ Tk. 1,171.25 d) Cement concrete(1:3:6): bottom: 1 x 18'-0" x 2'-8" x 0'-4"= 16.0 cft. sides: 2 x 18'-0" x 14" x 7"/2= 12.25 cft. = 28.25 cft. @ Tk. 7,491.10 e) Labour charge for laying pipe maintaining proper slope in/c cost of gasket etc. 0.25 No. @ Tk. 180.00 i) Head mason ii) Mason 0.25 No. @ Tk. 150.00 iii) Skilled labour 1.5 No. @ Tk. 120.00 a) Contractor's profit Overhead expenses VAT

each = Per % sft. =

Tk. Tk.

2,162.16 562.20

Per % cft. = each each each Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm. = = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

2,116.24 45.00 37.50 180.00 5,103.10 510.31 178.61 5,792.02 260.64 6,052.66 336.26 1,103.27

= = =

Say,

Tk.

1,103 .00 Per rm.

21. FALSE CEILING, WALL PANELING


ANALYSIS FOR ITEM NO. 143(a) 1/2" thick plain particle board ceiling screwed up with wooden frame for normal room height

Considering a panel of 12' x 16'= 192 sft. of work

- 367 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

a)

Cost of Garjan wood: (7 x 16' + 9 x 12') x 3" x 2"= Add 5% wastage= 9.17 cft. cft. cft. sft. sft. sft. @ Tk. 710.00 Per cft. = Tk. 6,837.30 0.46 9.63 Cost of 1/2" thick plain particle board 12'-0" x 16'-0"= 192 Add 5% wastage= 9.6 201.6

b)

Tk.

22.97

Per sft. =

Tk.

4,630.75

c) Cost of G.I. wire, rowel plug, nails and screws etc. necessary for fabricating, hoisting and hanging frame and board

(7.5% of cost of wood and board)


d) Cost of fitting, fixing, levelling, finishing, scaffolding etc (upto 3.5 m height) i) Carpenter 10 Nos. @ Tk. 160.00 ii) Carpenter helper 10 Nos. @ Tk. 120.00 e) Painting 2 coats over a coat of priming (rate is 50% more than the normal rate) 192 sft. @ Tk. 963.75

Tk.

860.10

each = each = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk.

1,600.00 1,200.00 1,850.40 16,978.55 1,697.86 594.25

Contractor's profit Overhead expenses VAT

Per %sft. Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm

= = =

Tk. 19,270.66 Tk. 867.18 Tk. 20,137.84 Tk. 104.88 Tk. 1,128.93

Say,

Tk.

1,129 .00 Per sqm.

ANALYSIS FOR ITEM NO. 143(b) 1/2" thick plain particle board ceiling screwed up with wooden frame for auditorium and other tall structures beyond 3.5 meter upto 6 meter height. Consider 1 No. panel Considering a panel of 12'-0" x 16'-0"= 192 sft. of work a) Cost of materials and labour

Same as item No. 143(a)

Tk.

16,978.55

- 368 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

b)

Scaffolding beyond 12' upto 20' (double stage) 2 x 16'-0" x 12'-0"= 384 sft. @ Tk. 3.00 Per sft. = Total = Contractor's profit Overhead expenses VAT 10.00% = 3.50% = 4.50% = Grand total = Rate per sft. = Rate per sqm = Say, Tk. 1,206 .00 Per sqm. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 1,152.00 18,130.55 1,813.06 634.57 20,578.18 926.02 21,504.20 112.00 1,205.57

ANALYSIS FOR ITEM NO. 143(c) Supplying, fitting and fixing of 8 mm thick melamine board laminated by mechanical hot press with a milk white PVC membrance with aluminum frame suspended from ceiling. Consider 16'-0" x 10'-0"= 160 sft. of work A. 1. MATERIAL Malamine board (8 mm thick) : 8' -0" x 4'-0" size 5 Pcs. 2. Aluminium section & accessories (a) 1" main T-section 64.00 rft. (b) 1" cross T-section 30.00 rft. (c) 1" L-section 63.00 rft. (d) Revit (e) G.I. wire 1.50 kg. (f) 1.5" screw 10.50 doz. (g) Rowl plug 120.00 Nos. (h) Wall bit 2.00 Nos. B. LABOUR i) Carpenter 6.00 Nos. ii) Helper to carpenter 6.00 Nos. iii) Carrying to site in/c sundries

@ @ @ @ @ @ @ @ @ @

Tk. 1,150.00 Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 11.00 9.00 8.00 50.00 8.00 0.25 25.00 160.00 120.00

Per pc. = Per rft. Per rft. Per rft. L.S. Per sft. Per doz. each each each each L.S. Total 10.00% 3.50% = = = = = = = = = = = = = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,750.00 704.00 270.00 504.00 75.00 75.00 84.00 30.00 50.00

Contractor's profit Overhead expenses

Tk. 960.00 Tk. 720.00 Tk. 200.00 Tk. 9,422.00 Tk. 942.20 Tk. 329.77 Tk. 10,693.97

- 369 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

VAT

4.50% Grand total Rate per sft. Rate per sqm

= = =

Tk. Tk. Tk. Tk.

481.23 11,175.20 69.85 751.87

Say,

Tk.

752 .00 Per sqm.

ANALYSIS FOR ITEM NO. 144(a) Supplying, fitting and fixing of 12 mm thick gypsum board laminated by mechanical hot press with a milk white PVC membrance with aluminum frame suspended from ceiling. Consider 10'-0" x 10'-0"= 100 sft. of work a) Cost of materials i) Aluminium sections Main T-section: 4 x 10' - 0" = Coss T-section 4 x 10' - 0" = Angle or L-section: 4 x 10' - 0"=

40.00 rft. 40.00 rft. 40.00 rft.

@ @ @

Tk. Tk. Tk. Tk.

11.00 9.00 8.00 48.00 40.00%

Per rft. = Per rft. = Per rft. = Per sft. = of cost of aluminium sections = each each each Per sft. Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm = = = = = = = =

Tk. Tk. Tk. Tk.

440.00 360.00 320.00 4,800.00

ii) Gypsum board 100.00 sft. @ iii) Accessories, rowel bolts, G.I. wire, machine charges for 100.00 sft. @

Tk.

448.00

b) i) ii) iii) iv)

Cost of labour Skilled technician Skilled labour Ordinary labour Scaffolding

5.00 5.00 5.00 100.00

Nos. Nos. Nos. sft.

@ @ @ @

Tk. Tk. Tk. Tk.

250.00 120.00 100.00 3.00

Contractor's profit Overhead expenses VAT

= = =

Tk. 1,250.00 Tk. 600.00 Tk. 500.00 Tk. 300.00 Tk. 9,018.00 Tk. 901.80 Tk. 315.63 Tk. 10,235.43 Tk. 460.59 Tk. 10,696.02 Tk. 106.96 Tk. 1,151.32

Say,

Tk.

1,151 .00 Per sqm.

- 370 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 144(b) Supplying, fitting and fixing of 12 mm thick vinyl board laminated by mechanical hot press with a milk white PVC membrance with aluminum frame suspended from ceiling. Consider ing 100 sft. of work a) b) Cost of false ceiling work excluding cost of board Cost of vinyle board 100.00 @ Same as item No. 144(a) 45.85 Per sft. Total Contractor's profit 10.00% Overhead expenses 3.50% Tk. VAT 4.50% Grand total Rate per sft. Rate per sqm = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 4,218.00 4,585.00 8,803.00 880.30 308.11 9,991.41 449.61 10,441.02 104.41 1,123.87

= = =

Say,

Tk.

1,124 .00 Per sqm.

ANALYSIS FOR ITEM NO. 145(a) Supplying, fitting and fixing of 12 mm thick B.T. veneered board in walling. Consider 1 No. panel Consider 12'-0" x 10'-0"= 120 sft. of work a) Cost of materials i) Garjan wood: batten: 7 x 10'-0" x 3" x 1.5"= 6 x 12'-0" x 3.25" x 1.5"= = Add wastage 5%= = ii) Cost of 12 mm B.T. veneered board: 12'-0" x 10'-0"= 120.00 sft. Add wastage 5%= 6.00 sft.
- 371 -

2.19 cft. 2.25 cft. 4.44 cft. 0.22 cft. 4.66 cft. @ Tk. 710.0 Per cft. = Tk. 3,308.60

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

= 126.00 sft.

Tk.

75.00

Per sft. = =

Tk. Tk.

9,450.00 330.86

iii) Cost of M.S. clamps, wooden block, screws, nails etc. (10% of cost of wooden frame) b) Cost of fitting, fixing, cutting to sizes, levelling, finishing, scaffolding i) Carpenter ii) Carpenter helper c) d) Local carriage French polishing 120.00 sft. @ Tk. 587.63 6.00 Nos. 6.00 Nos. @ @ Tk. Tk. 160.00 120.00

each = each = L.S = Per % sft. = Total = 10.00% = 3.50% = 4.50% = Grand total = Rate per sft. = Rate per sqm =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

960.00 720.00 50.00 705.16 15,524.62 1,552.46 543.36 17,620.44 792.92 18,413.36 153.44 1,651.63

Contractor's profit Overhead expenses VAT

Say,

Tk.

1,652 .00 Per sqm.

ANALYSIS FOR ITEM NO. 145(b)

Supplying, fitting and fixing of 12 mm thick particle board walling with wooden frame.

Consider 12'-0" x 10'-0"= 120 sft. of work a) b) Cost of walling excluding cost of board Cost of 12 mm thick particle board in/c 5% wastage 126 sft. @

Same as item No. 145(a) =


Tk. 22.97 Per sft. Total 10.00% 3.50% = = = =

Tk.

6,074.62

Contractor's profit Overhead expenses VAT

4.50% =

Tk. 2,894.22 Tk. 8,968.84 Tk. 896.88 Tk. 313.91 Tk. 10,179.63 Tk. 458.08

- 372 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October 2002

Grand total = Rate per sft. = Rate per sqm = Say, Tk. 954 .00 Per sqm.

Tk. Tk. Tk.

10,637.71 88.65 954.23

- 373 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

22. COLLAPSIBLE GATE, M.S. GATE, ROLLING SHUTTER ETC.


ANALYSIS FOR ITEM NO. 146(a) Manufacturing, supplying, fitting and fixing of collapsible gate with 3/4" x 3/8" 1/8" size M.S. channel excluding cost of paint. Considering 1 No. collapsible gate Considering 8'-0" x 8'-0"= 64.00 sft. in two parts a) Cost of materials i) 3/4" x 3/8" x 1/8" channel: @ 0.53 Ibs per rft. 2 x 12 x 2 x 8'-6"= 384 rft. Add wastage 5%= 19.2 rft. = 403.2 rft. = 213.696 Ibs. @ ii) 3/4" x 1/8" M.S. flat bar diagonals at 3 levels of length 1'0" to 2'-0": @ 0.32 Ibs per rft. 2 x 9 x 2 x 3 x 2'-0"= 2 x 2 x 2 x 3 x 1'-9"= = Add wastage 5%= = 216.00 rft. 42.00 rft. 258.00 rft. 12.90 rft. 270.90 rft. 7.71 Per Ib. = Tk. 668.38

Tk.

8.71

Per Ib. = Tk.

1,861.29

= 86.69 Ibs. @ Tk. iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail) and locking arrangement: @ 1.70 Ibs per rft. 34 rft. 2 rft. 36 rft. Add wastage 5%= 1.8 rft. = 37.8 rft. = 64.26 Ibs. @ Tk. iv) 3/4" x 3/16" F.I. bar for making handle: @ 0.48 Ibs per rft. 4 x 0'-10"= Add wastage 5%= = = b) Hardwares, fittings and consumables: i) Rivet and washer ii) 1.5" dia M.S. wheel 2.00 kg. 6.00 Nos.
- 374 -

4 x 8'-6"= 2 x 2 x 0'-6"=

7.71

Per Ib. = Tk.

495.44

3.30 rft. 0.17 rft. 3.47 rft. 1.67 Ibs. @ @ @ Tk. Tk. Tk. 7.71 40.00 10.00 Per Ibs = Tk. Per kg. = Tk. each = Tk. 12.88 80.00 60.00

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

iii) M.S. clamp: iv) Locking arrangement v) Electrodes vi) Greese c) Making gate in work-shop i) Welder/ fabricator ii) Helper to welder iii) Ordinary labour d)

10 Nos. 2 pairs 20 Pc. 0.5 Ibs. 3.5 Nos. 3.5 Nos.

@ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk.

10.00 20.00 4.00 40.00 160.00 120.00 100.00

each = Tk. each pair = Tk. Per pc. = Tk. Per kg. = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

100.00 40.00 80.00 20.00 560.00 420.00 350.00 150.00 4,897.99 489.80 5,387.79 84.00 48.00 89.91 166.68 105.84 75.00 60.00 6,017.22 601.72 210.60 6,829.54 307.33 7,136.87 111.51 1,200.29

3.5 Nos. @ Carrying cost: steel materials from market to workshop & finished gate from workshop to site. Workshop charge Ancillary work for fitting-fixing the gate: i) Making holes ii) Making groove (channel) on floor: 1 x 8'-0"= iii) Cost of CC (1:2:4): 14 x 6" x 4" x 4"= iv) 1/2" thick plaster (1:4) 3 x 8'-0" x 1'-0"= 1 x 8'-0" x 1'-6"= 14.00 Nos. 8.00 rft. 1.00 cft (say) 24.00 sft. 12.00 sft. 0.5 No. 0.5 No. @ @ @ @ @ @ @

e) f)

Tk. Tk.

6.00 6.00

each = Tk. Per rft. = Tk. Per % cft. = Tk. Per % sft. = Tk. Per % sft. = Tk. each = Tk. each = Tk. Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

Tk. 8,991.10 Tk. Tk. Tk. Tk. 694.50 882.00 150.00 120.00

v) Repairing floor and plaster with neat cement finish: g) Labour for fitting-fixing the gate: iii) Mason iv) Skilled labour

Contractor's profit Overhead expenses VAT

Say,

Tk.

1,200 .00 Per sqm.

- 375 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

ANALYSIS FOR ITEM NO. 146(b) Manufacturing, supplying, fitting and fixing of collapsible gate with 3/4" x 3/4" x 1/8" M.S. angle excluding cost of paint. Considering 1 No. collapsible gate Considering 8'-0" x 8'-0"= 64.00 sft. in two parts a) Cost of materials i) 3/4" x 3/4" x 1/8" angle: @ 0.585 Ibs per rft. 2 x 12 x 2 x 8'-6"= 384 rft. Add wastage 5%= 19.2 rft. = 403.2 rft. = 235.872 Ibs. @ ii) 3/4" x 1/8" M.S. flat bar diagonals at 3 levels of length 1'0" to 2'-0": @ 0.32 Ibs per rft. 2 x 9 x 2 x 3 x 2'-0"= 2 x 2 x 2 x 3 x 1'-9"= = Add wastage 5%= = = 216.00 rft. 42.00 rft. 258.00 rft. 12.90 rft. 270.90 rft. 86.69 Ibs. @ Tk. 7.71 Per Ib. = Tk. 668.38

Tk.

8.71

Per Ib. = Tk.

2,054.45

iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail) and locking arrangement: @ 1.70 Ibs per rft. 4 x 8'-6"= 2 x 2 x 0'-6"= Add wastage 5%= = = b) Hardwares, fittings and consumables: i) Rivet and washer ii) 1.5" dia M.S. wheel iii) M.S. clamp: iv) Locking arrangement v) Handle with 5/8" dia M.S rod v) Electrodes vi) Greese 2.50 kg. 6.00 Nos. 10 Nos. 2 pairs 4 Nos 70 pcs. 0.5 Ibs. @ @ @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. Tk. Tk. 40.00 10.00 10.00 20.00 12.00 4.00 40.00 Per kg. = Tk. each = Tk. each = Tk. each pair = Tk. each = Tk. Per pc. = Tk. Per kg. = Tk. 100.00 60.00 100.00 40.00 48.00 280.00 20.00 34 rft. 2 rft. 36 rft. 1.8 rft. 37.8 rft. 64.26 Ibs.

Tk.

7.71

Per Ib. = Tk.

495.44

- 376 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

c)

Making gate in work-shop i) Welder/ fabricator ii) Helper to welder iii) Ordinary labour 4.5 Nos. 4.5 Nos. 4.5 Nos. @ @ @ Tk. Tk. Tk. 160.00 120.00 100.00 each = Tk. each = Tk. each = Tk. L.S. Sub-total 10% Total @ @ @ @ @ @ @ Tk. Tk. 6.00 6.00 = = = = Tk. Tk. Tk. Tk. 720.00 540.00 450.00 150.00 5,726.27 572.63 6,298.90 84.00 48.00 89.91 166.68 105.84 75.00 60.00 6,928.33 692.83 242.49 7,863.65 353.86 8,217.51 128.40 1,382.10

d) e)

Carrying cost: materials & finished gate. Workshop charge

f) Anciliary work for fitting-fixing the gate: i) Making holes 14.00 Nos. ii) Making groove (channel) on floor: 1 x 8'-0"= 8.00 rft. iii) Cost of CC (1:2:4): 14 x 6" x 4" x 4"= 1.00 cft (say) iv) 1/2" thick plaster (1:4) 3 x 8'-0" x 1'-0"= 24.00 sft. v) Repairing floor and plaster with neat cement finish: 1 x 8'-0" x 1'-6"= 12.00 sft. Labour for fitting-fixing the gate: iii) Mason 0.5 No. iv) Skilled labour 0.5 No. each = Tk. Per rft. = Tk. Per % cft. = Tk. Per % sft. = Tk. Per % sft. = Tk. each each Total 10.00% = = = = Tk. Tk. Tk. Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 1,382 .00 Per sqm.

Tk. 8,991.10 Tk. Tk. Tk. Tk. 694.50 882.00 150.00 120.00

g)

Contractor's profit Overhead expenses

3.50% = Tk.

ANALYSIS FOR ITEM NO. 146(c) Manufacturing, supplying, fitting and fixing of collapsible gate with 1" x 1" x 1/8" M.S. angle excluding cost of paint. Considering 1 No. collapsible gate Considering 8'-0" x 8'-0"= 64.00 sft. in two parts

- 377 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

a)

Cost of materials i) 1" x 1" x 1/8" angle: @ 0.8 Ibs per rft. 2 x 12 x 2 x 8'-6"= Add wastage 5%= =

384 rft. 19.2 rft. 403.2 rft. Per Ib. = Tk. 2,809.50

= 322.56 Ibs. @ Tk. 8.71 ii) 1" x 1/8" M.S. flat bar diagonals at 3 levels of length 1'-0" to 2'-0": @ 0.43 Ibs per rft. 2 x 9 x 2 x 3 x 2'-0"= 2 x 2 x 2 x 3 x 1'-9"= = Add wastage 5%= = 216.00 rft. 42.00 rft. 258.00 rft. 12.90 rft. 270.90 rft. 7.71

= 116.49 Ibs. @ Tk. iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail) and locking arrangement: @ 1.70 Ibs per rft. 4 x 8'-6"= 2 x 2 x 0'-6"= Add wastage 5%= = = b) Hardwares, fittings and consumables: i) Rivet and washer ii) 1.5" dia M.S. wheel iii) M.S. clamp: iv) Locking arrangement v) Handle with 5/8" dia M.S rod v) Electrodes c) vi) Greese Making gate in work-shop i) Welder/ fabricator ii) Helper to welder d) e) iii) Ordinary labour Carrying cost: materials & finished gate. Workshop charge 34 2 36 1.8 rft. rft. rft. rft. @ @ @ @ @ @ @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

Per Ib. = Tk.

898.14

37.8 rft. 64.26 Ibs. 3.00 6.00 10 2 kg. Nos. Nos. pairs

7.71 40.00 10.00 10.00 20.00 12.00 4.00 40.00 160.00 120.00 100.00

Per Ib. = Tk. Per kg. each each each pair = = = = Tk. Tk. Tk. Tk.

495.44 120.00 60.00 100.00 40.00 48.00 280.00 20.00 800.00 600.00 500.00 150.00 6,921.08 692.11 7,613.19

4 Nos 70 pcs. 0.5 Ibs. 5 Nos. 5 Nos. 5 Nos.

each = Tk. Per pc. = Tk. Per kg. = Tk. each = each = each = L.S. = Sub-total = 10% = Total = Tk. Tk. Tk. Tk. Tk. Tk. Tk.

- 378 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

f)

Anciliary work for fitting-fixing the gate: i) Making holes ii) Making groove (channel) on floor: 1 x 8'-0"= iii) Cost of CC (1:2:4): 14 x 6" x 4" x 4"= iv) 1/2" thick plaster (1:4) 3 x 8'-0" x 1'-0"= 8.00 rft. 1.00 cft (say) 24.00 sft. @ @ @ @ @ @ Tk. 6.00 Per rft. = Tk. Per % cft. = Tk. Per % sft. = Tk. Per % sft. = Tk. each each Total 10.00% 3.50% Tk. Tk. Tk. Tk. Tk. Tk. 4.50% = Tk. = = = = = 48.00 89.91 166.68 105.84 75.00 60.00 8,242.62 824.26 288.49 9,355.37 420.99 9,776.36 152.76 1,644.31 14.00 Nos. @ Tk. 6.00 each = Tk. 84.00

Tk. 8,991.10 Tk. Tk. Tk. Tk. 694.50 882.00 150.00 120.00

v) Repairing floor and plaster with neat cement finish : 1 x 8'-0" x 1'-6"= 12.00 sft. g) Labour for fitting-fixing the gate: iii) Mason iv) Skilled labour 0.5 No. 0.5 No.

Contractor's profit Overhead expenses VAT

Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 1,644 .00 Per sqm.

ANALYSIS FOR ITEM NO. 147(a) Manufacturing, supplying, fitting and fixing of ordinary type M.S.gate (double leaf) with 5/8" dia M.S. rod and 1.5" x 1.5" x 1/4" angle frame excluding cost of painting. Considering 1 No. of gate Considering 10'-0" x 6'-8"= 66.67 sft. in two parts a) Cost of materials i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft. 2 x 2 x 6'-0"= 2 x 3 x 5'-0"= 1 x 3'-6"= 2 x 2'-0"= 2 x 3-6"= 24.0 rft. 30.0 rft. 3.5 rft. 4.0 rft. 7.0 rft.

- 379 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

68.5 rft. Add wastage 5%= = = 2 x 2 x 5'-7"= 2 x 2'-6"= 2 x 5'-0"= = Add wastage 5%= = = 2 x 3.142 x 10'-0"/4= Add wastage 5%= 3.425 rft. 71.93 rft. 168.32 Ibs. 22.32 rft. 5.00 rft. 10.00 rft. 37.32 rft. 1.866 rft. 39.19 rft. 50.16 Ibs. 15.71 rft. 0.79 rft. 16.50 rft. 28.05 Ibs. @ Tk. 7.71 Per Ib = Tk. 216.27 @ Tk. 7.71 Per Ib. = Tk. 386.73 @ Tk. 8.71 Per Ib. = Tk. 1,466.07

ii) 1.5" x 1/4" M.S. flat bar: @ 1.28 Ibs per rft.

iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft.

= iv) 5/8" M.S. rod: @ 1.043 Ibs per rft.: 2 x 21 x 0'-8"= 28.14 rft. 2 x 19 x 3'-6"= 133.00 rft. 19.00 180.14 Add wastage 5%= 9.01 = 189.15 = 197.28 v) 1/8" thick M.S. plate: @ 5.10 lbs per sft. 4.00 1 5.00 Add wastage 5%= 0.25 = 5.25 = 26.78 vi) 1/4" thick M.S. plate: @ 10.2 Ibs per sft. 2 x 0-6" x 0'-6"= 0.50 Add wastage 5%= 0.03 = 0.53 = 5.41 vii) 18 BWG M.S. plate: 2.04 Ibs per sft. 2 x 5'-0" x 2'-6"= 2 x 2 x 1'-0" x 1'-0"= 2 x 1'-0" x 6" = 2 x 38 x 0'-3"=

rft. rft. rft. rft. Ibs. sft. sft. sft. sft. sft. Ibs. sft. sft. sft. Ibs.

Tk.

7.71

Per Ib. = Tk.

1,521.03

Tk.

10.85

Per Ib. = Tk.

290.56

Tk.

10.85

Per Ib. = Tk.

58.70

25.00 sft.

- 380 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

b)

Add wastage 5%= = = Fittings and consumables i) Hinges for pocket gate: ii) 1.5" dia heavy duty wheel iii) Locking arrangement iv) Clamp with huskel dumney v) Clamp for rails vi) Electrodes

1.25 sft. 26.25 sft. 53.55 Ibs. 2 Nos. 2 Nos. 3 Nos. 6 Nos. 16 Nos. 200 Pc. 6 Nos. 5 Nos. 5 Nos.

@ @ @ @ @ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

10.85 15.00 80.00 125.00 70.00 10.00 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

581.02 30.00 160.00 375.00 420.00 160.00 800.00 960.00 600.00 500.00 150.00 8,675.38 867.54 9,542.92 30.00

c)

Making steel gate in work-shop i) Welder / fabricator ii) Helper iii) Ordinary labour

d) e) f)

Carrying materials to work-shop & gate to site Work-shop charges Ancillary work for fitting -fixing the gate: i) Making holes 6 Nos. ii) Plain concrete: (1:2:4) 6 x 10" x 6" x 6"= 1.25 cft. 16'-0" x 6" x 4"= 2.67 cft. 2 x 4 x 6" x 4"= 1.33 cft. 5.25 cft. Labour charge for hoisting the gate in position i) Mason 1 No. ii) Mason helper iii) Ordinary labour 2 No. 1 No.

Tk.

5.00

each = Tk.

@ @ @ @

Tk. 8,991.10 Tk. Tk. Tk. 150.00 120.00 100.00

Per % cft. = Tk. each = Tk. each = Tk.

472.03 150.00 240.00

g)

each = Tk. 100.00 Total = Tk. 10,534.95 10.00% = Tk. 3.50% = Tk. 1,053.50 368.72

Contractor's profit Overhead expenses VAT

Tk. 11,957.17 4.50% = Tk. 538.07 Grand total = Tk. 12,495.24 Rate per sft. = Tk. Rate per sqm. = Tk. 187.42 2,017.39

- 381 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Say,

Tk.

2,017 .00 Per sqm.

ANALYSIS FOR ITEM NO. 147(b) Manufacturing, supplying, fitting and fixing of security door with 7/8" dia M.S. rod and 2" x 2" x 1/4" angle frame excluding cost of painting. Considering 1 No. of gate Considering 3'-4" x 7'-0"= 23.31 sft. in two parts a) Cost of materials i) 2" x 2" x 1/4" angle for frame: @ 3.19 Ibs per rft. Vertical: 2 x 7'-0"= Horizontal: 2 x 3'-4"= Clamp: 4 x 1'-6"= = Add wastage 5%= = = ii) 7/8" M.S. rod: @ 2.04 Ibs per rft.: 10 x 6'-11.5"= Add wastage 5%= = = iii) 2" x 1/4" F.I. bar: @ 1.7 Ibs per rft. Horizontal: 4 x 3'-3.5= Rails: 2 x 3.142 x 3'-4"=

14.0 6.67 6.00 26.67 1.33 28.00 89.32

rft. rft. rft. rft. rft. rft. Ibs.

Tk.

8.71

Per Ib. = Tk.

777.98

69.60 3.48 73.08 149.08

rft. rft. rft. Ibs.

Tk.

7.71

Per Ib. = Tk.

1,149.41

b)

15.71 20.93 36.64 Add wastage 5%= 1.83 38.47 = 65.40 v) 1/8" thick M.S. plate: @ 5.10 lbs per sft. 1 x 2'-0" x 3'-0"= 6.00 Add wastage 5%= 0.3 = 6.30 = 32.13 Fittings and consumables i) Hinges for pocket gate:

rft. rft. rft. rft. rft. Ibs. sft. sft. sft. Ibs.

Tk.

7.71

Per Ib = Tk.

504.23

@ @

Tk. Tk.

10.85 15.00

Per Ib. = Tk. each = Tk.

348.61 30.00

2 Nos.
- 382 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

ii) 1.5" dia heavy duty wheel iii) Locking arrangement iv) Clamp with huskel dumney v) Clamp for rails vi) Electrodes c) Making steel gate in work-shop i) Welder / fabricator ii) Helper iii) Ordinary labour d) e) f)

2 Nos. 2 Nos. 3 Nos. 6 Nos. 98 Pc. 3 Nos. 3 Nos. 3 Nos.

@ @ @ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

80.00 125.00 70.00 10.00 4.00 160.00 120.00 100.00

each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

160.00 250.00 210.00 60.00 392.00 480.00 360.00 300.00 53.00 5,075.23 507.52 5,582.75 400.00

Carrying materials to work-shop & gate to site Work-shop charges Ancillary work for fitting -fixing the gate: i) Making holes ii) Plain concrete: (1:2:4) 2 x 10" x 6" x 6"= 3'-4" x 6" x 4"= 2 x 3 x 6" x 4"= 80 Nos. @ Tk. 5.00

each = Tk.

g)

0.41 cft. 0.55 cft. 0.99 cft. 1.95 cft. Labour charge for hoisting the gate in position i) Mason 0.5 No. ii) Mason helper 1 No. iii) Ordinary labour 1 No.

@ @ @ @

Tk. 8,991.10 Tk. Tk. Tk. 150.00 120.00 100.00

Per % cft. = Tk. each each each Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm. = = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

175.33 75.00 120.00 100.00 6,453.08 645.31 225.86 7,324.25 329.59 7,653.84 328.35 3,534.36

Contractor's profit Overhead expenses VAT

=
= =

Say,

Tk.

3,534 .00 Per sqm.

ANALYSIS FOR ITEM NO. 148

- 383 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Manufacturing, supplying, fitting and fixing of ordinary type M.S. gate (double leaf) with 1 x 1/4" F.I. bar, M.S. plate and 1.5" x 1.5" x 1/4" angle outer frame (without pocket gate) excluding cost of paint. Considering 1 No. of gate Considering 10'-0" x 6'-8"= 66.67 sft. in two parts a) Cost of materials i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft. 2 x 2 x 6'-8"= 2 x 4 x 5'-0"= 26.70 rft. 40.00 rft. 66.70 rft. Add wastage 5%= 3.34 rft. = 70.04 rft. = 163.89 Ibs. ii) 1.5" x 1/4" M.S. flat bar: @ 1.28 Ibs per rft. 2 x 5'-0"= 2 x 3'-4"= 2 x 2 x 4'-8.5" Add wastage 5%= = 10.00 rft. 6.70 rft. 18.80 rft. 35.50 rft. 1.775 rft. 37.28 rft. @ Tk. 7.71 Per Ib. = Tk. 367.92

Tk.

8.71

Per Ib. = Tk.

1,427.48

= 47.72 Ibs. iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft. 2 x 3.142 x 10'-0"/4= Add wastage 5%= = iv) 1" x 1/4" F.I. bar : 0.85 Ib per rft. 2 x 2 x 9 x 1'-8"= Add wastage 5%= = 15.71 rft. 0.79 rft. 16.50 rft. 28.05 Ibs. 60.12 rft. 3.01 rft. 63.13 rft.

Tk.

7.71

Per Ib = Tk.

216.27

= 53.66 Ibs. v) 1/8" thick M.S. plate: @ 5.10 lbs per sft. 4 x 1'-0" x 1'-0"= Add wastage 5%= 4.00 sft. 0.2 sft.

Tk.

7.71

Per Ib. = Tk.

413.72

= 4.20 sft. = 21.42 Ibs. vi) 1/4" thick M.S. plate as gusset plate

Tk.

10.85

Per Ib. = Tk.

232.41

- 384 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

2 x 0-6" x 0'-6"= Add wastage 5%= =

0.50 sft. 0.03 sft. 0.53 sft. @ Tk. 10.85 Per Ib. = Tk. 58.70

= 5.41 Ibs. vii) 18 BWG M.S. plate: @ 2.04 Ibs per sft. 2 x 5'-0" x 3'-4"= 33.30 sft. Add wastage 5%= 1.67 sft. = = b) Fittings and consumables i) Locking arrangement ii) 1.5" dia heavy duty wheel iii) Clamp with huskel dumney iv) Clamp for rails v) Electrodes Making steel gate in work-shop i) Welder / fabricator 2 Nos. 2 6 16 160 Nos. Nos. Nos. Pc. 34.97 sft. 71.3388 Ibs.

@ @ @ @ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

10.85 125.00 80.00 70.00 10.00 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each each each each = = = = Tk. Tk. Tk. Tk.

774.03 250.00 160.00 420.00 160.00 640.00 960.00 720.00 600.00 150.00 7,550.53 755.05 8,305.58 30.00

c)

6 Nos.

each = Tk. each each L.S. Sub-total = = = = Tk. Tk. Tk. Tk.

d) e) f)

ii) Helper 6 Nos. iii) Ordinary labour 6 Nos. Carrying materials to work-shop & gate to site Work-shop charges Ancillary work for fitting-fixing the gate: i) Making holes 6 ii) Plain concrete: (1:2:4) 6 x 10" x 6" x 6"= 1.25 16'-0" x 6" x 4"= 2.67 2 x 4 x 6" x 4"= 1.33

10% = Tk. Total = Tk. Nos. cft. cft. cft. @ @ @ @ Tk. 8,991.10 Tk. Tk. Tk. 150.00 120.00 100.00 Per % cft. = Tk. each = Tk. each = Tk. each = Tk. Total = Tk. @ Tk. 5.00 each = Tk.

g)

5.25 cft. Labour charge for hoisting the gate in position i) Mason ii) Mason helper iii) Ordinary labour 1 No. 2 No. 1 No.

472.03 150.00 240.00 100.00 9,297.61

Contractor's profit Overhead expenses VAT


- 385 -

10.00% = Tk. 929.76 3.50% = Tk. 325.42 Tk. 10,552.79 4.50% = Tk. 474.88

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Grand total = Tk. 11,027.67 Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 1,780 .00 Per sqm. 165.41 1,780.47

ANALYSIS FOR ITEM NO. 149 Manufacturing, supplying, fitting and fixing of ordinary type M.S. gate (double leaf) with 1.5" x 1.5" x 1/4" M.S. angle box and channel. Considering 1 No. of gate Considering 13'-8" x 5'-2"= 70.67 sft. in two parts a) Cost of materials i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft. 2 x 2 x 2 x 6'-10"= 2 x 3 x 2 x 5'-2"= = Add wastage 5%= = 54.64 62.04 116.68 5.83 122.51 rft. rft. rft. rft. rft. @ Tk. 8.71 Per Ib. = Tk. 2,496.90

= 286.67 Ibs. ii) 1" x 2" x 1" x 3/16" M.S. channel: @ 2.32 Ibs per rft. Horizontal: 2 x 19 x 1'-3"= 47.50 rft. 0 217.14 rft. 45 inclined: 2 x 21 x 5'-2"(av)= 264.64 rft. Add wastage 5%= 13.232 rft. = = 277.87 rft. 644.66 Ibs.

Tk.

8.71

Per Ib. = Tk.

5,614.99

iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft . 2 x 3.142 x 13'-8"/4= 21.46 rft. Add wastage 5%= 1.07 rft. @ Tk. 7.71 Per Ib = Tk. 295.29 22.53 rft. = 38.30 Ibs. iv) 1/8" thick M.S. plate: @ 5.10 lbs per sft. 4 x 1'-0" x 1'-0"= Add wastage 5%= = 4.00 sft. 0.2 sft. 4.20 sft.

- 386 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

= b) Fittings and consumables i) Locking arrangement ii) 1.5" dia heavy duty wheel iii) Clamp with huskel dumney iv) Clamp for rails v) Electrodes c) Making steel gate in work-shop i) Welder / fabricator ii) Helper iii) Ordinary labour d) e) f)

21.42 Ibs. 2 Nos. 2 6 8 240 Nos. Nos. Nos. Pc.

@ @ @ @ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

10.85 125.00 80.00 70.00 10.00 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each each each each = = = = Tk. Tk. Tk. Tk.

232.41 250.00 160.00 420.00 80.00 960.00 800.00 600.00 500.00 150.00

5 Nos. 5 Nos. 5 Nos.

each = Tk. each = Tk. each = Tk. L.S. = Tk.

Carrying materials to work-shop & gate to site Work-shop charges Ancillary work for fitting -fixing the gate: i) Making holes 6 Nos. ii) Plain concrete: (1:2:4) 6 x 10" x 6" x 6"= 1.25 cft. 22'-0" x 6" x 4"= 3.67 cft. 2 x 4 x 6" x 4"= 1.33 cft. @ @ @ @ Tk. 8,991.10 Tk. Tk. Tk. 150.00 120.00 100.00 6.25 cft. Labour charge for hoisting the gate in position i) Mason 1 No. ii) Mason helper 2 No. iii) Ordinary labour 1 No.

Sub-total = Tk. 12,559.59 10% = Tk. 1,255.96 Total = Tk. 13,815.55 @ Tk. 5.00 each = Tk. 30.00

Per % cft. = Tk. each each each Total 10.00% = = = = =

561.94

g)

Contractor's profit Overhead expenses VAT

Tk. 150.00 Tk. 240.00 Tk. 100.00 Tk. 14,897.49 Tk. 1,489.75 521.41

3.50% = Tk.

Tk. 16,908.65 4.50% = Tk. 760.89 Grand total = Tk. 17,669.54 Rate per sft. = Tk. 250.03 Rate per sqm. = Tk. 2,691.32

Say,

Tk.

2,691 .00 Per sqm.

ANALYSIS FOR ITEM NO. 150


- 387 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Manufacturing, supplying, fitting and fixing of G.I. pipe gate excluding cost of painting. Considering 1 No. of gate Considering 10'-0" x 6'-8"= 66.67 sft. in two parts a) Cost of materials i) 1.5" dia G.I. pipe 2 x 4 x 5'-0"= 4 x 6'-8"= = Add wastage 5%= = ii) 3/4" dia G.I. pipe Vertical post: 2 x 19 x 6'-8"= Pocket gate: 2 x 2'-0"= 2 x 4'-5"= 1 x 2'-2"= = Add 5% wastage= 40.00 26.67 66.67 3.33 70.00 rft. rft. rft. rft. rft.

Tk.

72.00

Per rft. = Tk.

5,040.00

253.33 rft. 4.00 rft. 8.83 rft. 2.17 rft. 268.33 rft. 13.42 rft. 281.75 rft. @ iii) 18 BWG M.S. plate for middle part: @ 2.04 lbs per sft. 2 x 5'-0" x 3'-4"= Add wastage 5%= = = Fittings and consumables i) Locking arrangement ii) 5" long hinges iii) Clamp with huskel dumney iv) 5/8" dia M.S. socket bolt v) Electrodes c) Making steel gate in work-shop i) Welder / fabricator ii) Helper iii) Ordinary labour d) e) 33.33 1.67 35.00 71.40 sft. sft. sft. Ibs.

Tk.

33.00

Per rft. = Tk.

9,297.75

@ @ @ @ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

10.85 125.00 15.00 70.00 100.00 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk.

774.69 250.00 30.00 420.00 200.00 480.00 640.00 480.00 400.00

b)

2 Nos. 2 Nos. 6 Nos. 2 Nos. 120 Pc. 4 Nos. 4 Nos. 4 Nos.

Carrying materials to work-shop & gate to site Work-shop charges

L.S. = Tk. 150.00 Sub-total = Tk. 18,162.44 10% = Tk. 1,816.24 Total = Tk. 19,978.68

- 388 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

f)

Ancillary work for fitting -fixing the gate: i) Making holes ii) Plain concrete: (1:2:4) 6 x 10" x 6" x 6"= 1.25 cft. @ @ @ @ Tk. 8,991.10 Tk. Tk. Tk. 150.00 120.00 100.00 Per % cft. = Tk. each each each Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm. = = = = = = = 112.39 6 Nos. @ Tk. 5.00 each = Tk. 30.00

g)

Labour charge for hoisting the gate in position i) Mason 1 No. ii) Mason helper 1 No. iii) Ordinary labour 1 No.

Contractor's profit Overhead expenses VAT

=
= =

Tk. 150.00 Tk. 120.00 Tk. 100.00 Tk. 20,491.07 Tk. 2,049.11 Tk. 717.19 Tk. 23,257.37 Tk. 1,046.58 Tk. 24,303.95 Tk. 364.54 Tk. 3,923.91

Say,

Tk.

3,924 .00 Per sqm.

ANALYSIS FOR ITEM NO. 151 Manufacturing, supplying, fitting and fixing of rolling shutter made of 24 SWG G.P. sheet excluding cost of painting. Considering 1 No. rolling shutter Considering 10'-0" x 6'-0"= 60 sft. of work a) Cost of materials: i) 24 SWG G.P. sheet with 1/2" dia folding at the other end (@ 1 Ibs per rft.) 44 (2.75"+3.14 x 0.5"+3.14 x 0.375) x 10'-0" = 121.00 sft. Side patty: 2 x 10'-0" x 0'-3"= 5.00 sft. 126.00 sft. Add 5% wastage= 6.05 sft. 132.05 sft. = 132.05 lbs @ Tk. 10.85 iii) 26 SWG cover sheet: @ 0.85 Ibs per sft. 6'-0" x 4'-0"= 24.0 sft. Add 5% wastage= 1.2 sft. = 25.2 sft. 21.42 Ibs. @ Tk. 10.85

Per Ib. = Tk.

1,432.74

Per Ib. = Tk.

232.41

- 389 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

iv) 1.5" dia G.I. pipe 1 x 6'-0"=

6.33 rft. 6 rft.

Tk.

72.00

Per rft. = Tk.

455.76

iii) 1" x 1" x 1/8" M.S. angle: @ 0.8 per rft.: = 4.8 lbs v) 1/4" thick M.S. plate: @ 10.21 lbs per sft. Side guide: 2 x 2 x 4" x 10'-6"= 14.0 sft. Mid guide: 2 x 6" x 10'-6"= 10.5 sft. 4 x 0'-2" x 0'-3"= = Add wastage 5%= 0.17 sft. 24.67 sft. 1.23 sft. @ Tk. 8.71 Per lb = Tk. 2,303.27 @ Tk. 8.71 Per Ib. = Tk. 41.81

25.90 sft. = 264.44 Ibs. vi) 1" x 1/8" F.I. bar: @ 0.425 Ibs per rft. Side guide channel: 2 x 2 x 10'-0"= 40 rft. Mid guide channel: 2 x 10'-0"= Guide channel to punkha: 2'-3"= Guide channel 2 toxhandle: 2 x 0'-9"= = Add 5% wastage=

b)

20 rft. 4.5 rft. 1.5 rft. 66.0 rft. 3.3 rft. 69.3 rft. = 29.4525 Ibs. @ Tk. 7.71 vii) 1/8" thick M.S. plate for punkha & folded plate: @ 5.10 lbs per sft. 2 x 1'-3" x 1'-0"= 2.50 sft. 1 x 6'-0" x 0'-3"= 1.50 sft. = 4.00 sft. Add 5% wastage= 0.20 sft. 4.20 sft. = 12.75 Ibs. @ Tk. 10.85 Fittings, hardwares and consumables i) Best quality china made spring: 3 x 11'-0"= 33 rft. @ Tk. 10.00 ii) Spring box 3 Nos. @ Tk. 60.00 iii) Nut bolt, 1/2" dia maximum 2.5" long 18 Nos. @ Tk. 5.00 iv) Rivet: Side patty= For fixing top tail= For fixing lower plate= = For guide channel= 176 Nos. 9 Nos. 40 Nos. 225 Nos. 20 Nos. @ @ Tk. Tk. 0.40 0.60

Per lb = Tk.

227.08

Per Ib. = Tk.

138.34

Per rft. = Tk. each = Tk. each = Tk.

330.00 180.00 90.00

each = Tk. each = Tk.

90.00 12.00

- 390 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

v) 1" x 1/4" x 0'-9" clamps vi) Electrodes vii) Lubricant, greese: c)

8 Nos. 30 Nos. 1 Ibs.

@ @ @

Tk. Tk. Tk.

10.00 4.00 40.00

each = Tk. each = Tk. Per Ib. = Tk.

80.00 120.00 40.00

Cost of Labour: i) Cutting, folding both sides, rolling, locking individual strip, stitching or riveting side patty etc. 44 pcs. @ Tk. 6.00 ii) Making other component of rolling shutter and assembling: Welder/fabricator 2 Nos. @ Tk. 160.00 Welder helper Ordinary labour 2 Nos. 1 No. @ @ Tk. Tk. 120.00 100.00

Per piece = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

264.00 320.00 240.00 100.00 150.00 6,847.41 684.74 7,532.15 40.00 89.91 208.35 75.00 60.00 50.00 80.00 60.00 8,195.41 819.54 286.84 9,301.79 418.58 9,720.37 162.01 1,743.88

d) Carrying materials to work-shop and shutter to site e) Work-shop charges f) Ancillary work for fitting-fixing the gate: i) Making holes ii) Plain concrete: (1:2:4) 8 x 6" x 6" x 6"= 1.00 iii) 1/2" plaster (1:4) to repair walls. 3 x 10'-0" x 1'-0"= 30 sft. @ Tk. Tk. Tk. Tk. Tk. Tk. 694.50 150.00 120.00 100.00 160.00 120.00 cft. @ Tk. 8,991.10 8 Nos. @ Tk. 5.00

each = Tk. Per % cft. = Tk. Per % sft. = Tk. each = Tk. each = Tk. each each each Grand total = = = = Tk. Tk. Tk. Tk.

g) Labour charge for hoisting and commissioning the gate in position i) Mason 0.5 No. @ ii) Mason helper 0.5 No. @ iii) Ordinary labour iv) Welder/ fabricator v) Welder helper 0.5 No. 0.5 No. 0.5 No. @ @ @

Contractor's profit Overhead expenses VAT

10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

Say,

Tk.

1,744 .00 Per sqm.

- 391 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

23. STAIR RAILING & VERANDAH RAILING


ANALYSIS FOR ITEM NO. 152 Supplying, fitting and fixing of stair railing of any height with square box made with 2 Nos. 3/4" x 3/4" x 1/8" angle welded with each other (excluding cost of wood for hand rail). Considering 1 No. of railing Considering 9'-9" x 2'-10"= 27.6 sft. exposed surface a) Cost of materials: i) M.S. angle: 3/4" x 3/4" x 1/8" @ 0.60 lbs. per rft. 2 x 20 x 3'-1"= Add wastage 5%= = = 122.3 rft. 6.12 rft. 128.42 rft. 77.052 Ibs. @ Tk. 8.71 Per Ib. = Tk. 671.12

b) c)

ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft. 20 x 2" x 2"= 0.56 sft. Add wastage 5%= 0.03 sft. = 0.59 sft. = 6.02 Ibs. iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft. 1 x 9'-9"= 9.75 rft. Add wastage 5%= 0.49 rft. = 10.24 rft. = 13.11 lbs. Fittings, hardwares and consumables:

Tk.

10.85

Per lb. = Tk.

65.32

Tk. Tk.

7.71 4.00

Per Ib. = Tk. each = Tk.

101.08 560.00

Electrodes with electricity: 140.00 Nos. @ Cost of labour for fabrication and making square post and railing support etc. Welder / fabricator 2.00 Nos. @ Welder helper 2.00 Nos. @

Tk. Tk.

160.00 120.00

each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Ttotal = Tk.

320.00 240.00 200.00 100.00 2,257.52 225.75 2,483.27

d) e)

Ordinary labour 2.00 Nos. @ Tk. 100.00 Carrying of materials to work-shop and fabricated materials to site: Work-shop charges:

f) Ancillary works for fitting-fixing the railing: i) Labour charge for cutting

- 392 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

2" x 2" x 6" size grooves ii) CC (1:2:4): 20 x 2" x 2" x 6"= i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper

20 Nos 0.28 cft. 0.50 No. 0.50 No. 0.50 No. 0.50 No. 0.50 No.

@ @ @ @ @ @ @

Tk. 5.00 Tk. 8,991.10 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

each = Tk. Per % cft. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

100.00 25.18 75.00 60.00 50.00 80.00 60.00 2,933.45 293.35 102.67 3,329.47 149.83 3,479.30 126.06 1,356.91

g) Labour charge for fitting fixing the stair railing

Contractor's profit Overhead expenses VAT

Say,

Tk.

1,357 .00 Per sqm.

ANALYSIS FOR ITEM NO. 153 Supplying, fitting and fixing of stair railing of any height with square box made with 2 Nos. 1" x 1" x 3/16" angle welded (full welding) with each other (excluding cost of wood for hand rail).

Considering 1 No. railing Considering 9'-9" x 2'-10"= 27.6 sft. of work a) Cost of materials: i) M.S. angle: 1" x 1" x 3/16" @ 1.16 lbs. per rft. 2 x 10 x 3'-1"= Add wastage 5%= = 61.67 rft. 3.08 rft. 64.75 rft. @ Tk. 8.71 Per Ib. = Tk. 654.21

= 75.11 Ibs. ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft. 10 x 2" x 2"= Add wastage 5%= 0.28 sft. 0.01 sft.

- 393 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

= =

0.29 sft. 2.96 Ibs. @ Tk. 10.85 Per lb. = Tk. 32.12

iii) 2" x 1/4" M.S. F.I. bar: @ 1.70 Ibs. per rft. 1 x 9'-9"= 9.75 rft. Add wastage 5%= 0.49 rft. = 10.24 rft. = 17.41 lbs. @ Fittings, hardwares and consumables: Electrodes: 100.00 Nos. @ Nut-bolt screws etc. 0.25 kg @ Cost of labour for fabrication and making square post and railing-support F.I. bar etc. Welder / fabricator 1.50 Nos. @ Welder helper Ordinary labour d) e) f) 1.50 Nos. 1.50 Nos. @ @

Tk. Tk. Tk.

7.71 4.00 60.00

Per Ib. = Tk. each = Tk. Per kg = Tk.

134.23 400.00 15.00

b)

c)

Tk. Tk. Tk.

160.00 120.00 100.00

each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

240.00 180.00 150.00 100.00 1,905.56 190.56 2,096.12

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Ancillary works & materials for fitting-fixing the railing: i) Labour charge for cutting: 2" x 2" x 6" size grooves 10 Nos ii) CC (1:2:4): 10 x 2" x 2" x 6"= 0.14 cft. iii) C.T. wood plank: 2 x 10'-0" x 0'-9.5" x 1.25"= i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper 1.65 cft. 0.50 No. 0.50 No. 0.50 No. 0.50 No. 0.50 No. @ @ @ @ @ @ @ @ Tk. 5.00 Tk. 8,991.10 Tk. 1,400.00 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

each = Tk. Per % cft. = Tk. Per cft. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk.

50.00 12.59 2,310.00 75.00 60.00 50.00 80.00 60.00 4,793.71 479.37 167.78 5,440.86 244.84 5,685.70

g) Labour charge for fitting fixing the stair railing

Contractor's profit Overhead expenses VAT

- 394 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 2,217 .00 Per sqm.

206.00 2,217.38

ANALYSIS FOR ITEM NO. 154(a) Manufacturing, supplying, fitting and fixing G.I. stair railing with the provision of 6" x 2.5" hand rails (excluding cost of wood for hand rail) excluding cost of painting. Considering 1 No. of railing Considering 9'-9" x 2'-10"= 27.6 sft. of work a) Cost of materials: i) 1/2" dia G.I. pipe: 2 x 10 x 3'-1"= 61.6 rft. Add wastage 5%= 3.08 rft. = 64.68 rft. @ Tk. 25.00 ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft. 20 x 2" x 2"= 0.56 sft. Add wastage 5%= 0.03 sft. = 0.59 sft. = 6.02 Ibs. @ Tk. 10.85 iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft. 1 x 9'-9"= 9.75 rft. Add wastage 5%= 0.49 rft. = 10.24 rft. = 13.11 lbs. @ Tk. 7.71 b) Fittings, hardwares and consumables: Electrodes: 20.00 Nos. @ Tk. 4.00 c) Cost of labour for fabrication and making post and railing support etc. i) Welder / fabricator 1.00 Nos. @ Tk. 160.00 ii) Welder helper 1.00 Nos. @ Tk. 120.00 iii) Ordinary labour 1.00 Nos. @ Tk. 100.00 d) Carrying of materials to work-shop and fabricated materials to site: e) Work-shop charges:

Per rft. = Tk.

1,617.00

Per lb. = Tk.

65.32

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

101.08 80.00 160.00 120.00 100.00 100.00 2,343.40 234.34 2,577.74

- 395 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

f)

Ancillary works for fitting -fixing the railing: i) Labour charge for cutting: 2" x 2" x 6" size grooves 20 Nos ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft. i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper 0.50 No. 0.50 No. 0.50 No. 0.50 Nos. 0.50 Nos.

@ @ @ @ @ @ @

Tk. 5.00 Tk. 8,991.10 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

each = Tk. Per % cft. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. 4.50% Grand total Rate per sft. Rate per sqm. = Tk. Tk. Tk. Tk. Tk.

100.00 25.18 75.00 60.00 50.00 80.00 60.00 3,027.92 302.79 105.98 3,436.69 154.65 3,591.34 130.12 1,400.61

g) Labour charge for fitting fixing the stair railing at site

Contractor's profit Overhead expenses VAT

=
= =

Say,

Tk.

1,401 .00 Per sqm.

ANALYSIS FOR ITEM NO. 154(b) Manufacturing, supplying, fitting and fixing G.I. stair railing with the provision of 4.5" x 2.5" hand rail (excluding the cost of wood for hand rails) excluding cost of painting.

Considering 1 No. of railing Clear G.I. pipe height 32.5" + hand rail 4.5" = clear height of railing = 37" Considering 9'-9" x 3'-1"= 30.06 sft. of work a) Cost of materials: i) 1/2" dia G.I. pipe 2 x 10 x 3'-2.5"= 64.17 rft. Add wastage 5%= 3.21 rft. = 67.38 rft. ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft. 20 x 2" x 2"= Add wastage 5%= 0.56 sft. 0.03 sft.
- 396 -

Tk.

25.00

Per rft. = Tk.

1,684.50

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

= 0.59 sft. = 6.02 Ibs. iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft. 1 x 9'-9"= 9.75 Add wastage 5%= 0.49 = 10.24 = 13.11 Fittings, hardwares and consumables: Electrodes with electricity: c) rft. rft. rft. lbs.

Tk.

10.85

Per lb. = Tk.

65.32

@ @

Tk. Tk.

7.71 4.00

Per Ib. = Tk. each = Tk.

101.08 280.00

b)

70.00 Nos.

Cost of labour for fabrication and making square post and railing support etc. i) Welder / fabricator 2.00 Nos. @ ii) Welder helper iii) Ordinary labour 2.00 Nos. 2.00 Nos. @ @

Tk. Tk. Tk.

160.00 120.00 100.00

each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

320.00 240.00 200.00 100.00 2,990.90 299.09 3,289.99

d) e) f)

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Ancillary works for fitting -fixing the railing: @ @ @ @ @ @ @ Tk. 5.00 Tk. 8,991.10 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

i) Labour charge for cutting 2" x 2" x 6" size grooves 20 Nos. ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft. g) Labour charge for fitting fixing the stair railing i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper 0.50 No. 0.50 No. 0.50 No. 0.50 No. 0.50 No.

each = Tk. Per % cft. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

100.00 25.18 75.00 60.00 50.00 80.00 60.00 3,740.17 374.02 130.91 4,245.10 191.03 4,436.13 147.58 1,588.55

Contractor's profit Overhead expenses VAT

Say,

Tk.

1,589 .00 Per sqm.

- 397 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

ANALYSIS FOR ITEM NO. 155(a) Manufacturing, supplying, fitting and fixing 1/2" dia G.I. pipe verandah railing @ 5" c/c with 1.5" dia G.I.

pipe hand rail.

Considering 1 No. of railing Clear G.I. pipe height 35.5" + hand rail 1.5" = clear height of railing = 3'-1" Considering 10'-0" x 3'-1"= 30.83 sft. of verandah railing a) Cost of materials: i) 1/2" dia G.I. pipe 25 x 3'-2.5"= Add wastage 5%= = ii) 1.5" dia G.I. pipe: 1 x 10'-6"= Add wastage 5%= = 80.21 rft. 4.01 rft. 84.22 rft. 10.5 rft. 0.53 rft. 11.03 rft.

Tk.

25.00

Per rft. = Tk.

2,105.50

Tk.

72.00

Per rft. = Tk.

794.16

iii) 2" x 2" x 1/4" M.S.plate: @ 10.2 Ibs. per rft. 25 x 2" x 2"= 0.694 Add wastage 5%= 0.03 = 0.724 = 7.38 Fittings, hardwares and consumables: sft. sft. sft. lbs.

@ @ @ @ @

Tk. Tk. Tk. Tk. Tk.

10.85 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

80.07 100.00 80.00 60.00 50.00 100.00 3,369.73 336.97 3,706.70

b) c)

i) Electrodes in/c electricity 25.00 Nos. Cost of labour for making verandah grill at workshop i) Welder / fabricator 0.50 Nos. ii) Welder helper iii) Ordinary labour 0.50 Nos. 0.50 Nos.

d) e) f)

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Ancillary works for fitting-fixing the verandah railing: i) Labour charge for cutting 25 Nos @ 2.5" x 2.5" x 3" size grooves ii) CC (1:2:4):
- 398 -

Tk.

5.00

each = Tk.

125.00

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

27 x 2.5" x 2.5" x 3"= i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper

0.29 cft. 0.25 No. 0.25 0.25 0.25 0.25 No. No. Nos. Nos.

@ @ @ @ @ @

Tk. 8,991.10 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

Per % cft. = Tk. each = Tk. each each each each = = = = Tk. Tk. Tk. Tk.

26.07 37.50 30.00 25.00 40.00 30.00 4,020.27 402.03 140.71 4,563.01 205.34 4,768.35 154.67 1,664.87

g) Labour charge for fitting-fixing the verandah railing

Grand total = Tk. Contractor's profit Overhead expenses VAT 10.00% = Tk. 3.50% = Tk. Tk. 4.50% Grand total Rate per sft. Rate per sqm. = Tk. = Tk. = Tk. = Tk.

Say,

Tk.

1,665 .00 Per sqm.

ANALYSIS FOR ITEM NO. 155(b) Manufacturing, supplying, fitting and fixing 1/2" dia G.I. pipe verandah railing @ 5" c/c with 2" dia G.I.

pipe hand rail.

Considering 1 No. of railing Clear G.I. pipe height 32.5" + hand rail 4.5" = clear height of railing = 3'-1" Considering 10'-0" x 3'-1"= 30.83 sft. verandah railing a) Cost of materials: i) 1/2" dia G.I. pipe 25 x 3'-2.5"= Add wastage 5%= = ii) 2" dia G.I. pipe: 1 x 10'-6"= Add wastage 5%= = 10.5 0.53 rft. 11.03 rft. 80.21 rft. 4.01 rft. 84.22 rft.

Tk.

25.00

Per rft. = Tk.

2,105.50

Tk.

80.00

Per rft. = Tk.

882.40

- 399 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

iii) 2" x 2" x 1/4" M.S.plate: @ 10.2 Ibs. per rft. 25 x 2" x 2"= 0.694 Add wastage 5%= 0.03 = 0.724 = 7.38 Fittings, hardwares and consumables: i) Electrodes in/c electricity c) sft. sft. sft. lbs.

@ @ @ @ @

Tk. Tk. Tk. Tk. Tk.

10.85 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. = Sub-total = 10% = Total = Tk. Tk. Tk. Tk.

80.07 100.00 160.00 120.00 100.00 100.00 3,647.97 364.80 4,012.77

b)

25.00 Nos.

Cost of labour for making verandah grill i) Welder / fabricator 1.00 Nos. ii) Welder helper iii) Ordinary labour 1.00 Nos. 1.00 Nos.

d) e) f)

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Ancillary works for fitting-fixing the verandah grill: @ @ @ @ @ @ @ Tk. 5.00

i) Labour charge for cutting 2" x 2" x 6" size grooves 27 Nos ii) CC (1:2:4): 27 x 2.5" x 2.5" x 3"= 0.29 cft. g) Labour charge for fitting-fixing the verandah grill i) Mason ii) Mason helper iii) Ordinary labour iv) Welder/fabricator v) Welder helper 0.50 0.50 0.50 0.50 0.50 No. No. No. No. No.

each = Tk. Per % cft. = Tk. each each each each each Grand total = = = = = = Tk. Tk. Tk. Tk. Tk. Tk.

135.00 26.07 75.00 60.00 50.00 80.00 60.00 4,498.84 449.88 157.46 5,106.18 229.78 5,335.96 173.08 1,863.03

Tk. 8,991.10 Tk. Tk. Tk. Tk. Tk. 150.00 120.00 100.00 160.00 120.00

Contractor's profit Overhead expenses VAT

10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

Say,

Tk.

1,863 .00 Per sqm.

- 400 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

24. GRILL FENCING, BARBED WIRE FENCING

ANALYSIS FOR ITEM NO. 156 Manufacturing, supplying, fitting and fixing steel grill fencing in boundary wall with 1.25" x 1/4" F.I. bars 6" c/c placed vertically and welding with 2 Nos. horizontal 1.25" x 1/4" F.I. bars etc excluding cost of painting. Considering 1 No. of steel grill fencing Considering 8'-9" x 3'-1"= 26.98 sft. grill work a) Cost of materials: i) 1.25" x 1/4" F.I. bars: @ 1.06 lbs per rft. Vertical: 17 x 3'-1"= Horizontal: 2 x 9'-9"= = Add wastage 5%= = = b) c) i) Electrodes in/c electricity i) Welder / fabricator ii) Welder helper iii) Ordinary labour d) e) f) 52.42 rft. 19.5 rft. 71.92 rft. 3.60 rft. 75.52 rft. 80.05 Ibs. 15.00 Nos. 1.00 No. 1.00 No. 1.00 No. @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. 7.71 4.00 160.00 120.00 100.00 Per lb. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk. 617.19 60.00 160.00 120.00 100.00 50.00 1,107.19 110.72 1,217.91

Fittings, hardwares and consumables: Cost of labour for making fencing grill

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Ancillary works for fitting-fixing the grill fencing: i) Labour charge for cutting 3" x 3" x 6" size grooves 4 Nos ii) CC (1:2:4): 4 x 3" x 3" x 6"= 0.13 cft. Labour charge for fitting-fixing the grill fencing i) Mason 0.50 No. @ @ @ Tk. 5.00

each = Tk. Per % cft. = Tk. each = Tk.

20.00 11.69 75.00

Tk. 8,991.10 Tk. 150.00

g)

- 401 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

ii) Mason helper

0.50 No.

Tk.

120.00

Contractor's profit Overhead expenses VAT

each Grand total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm.

= = = = =

=
= =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

60.00 1,384.60 138.46 48.46 1,571.52 70.72 1,642.24 60.87 655.20

Say,

Tk.

655 .00 Per sqm.

ANALYSIS FOR ITEM NO. 157 Supplying, fitting & fixing of steel grill fencing in boundary wall with 3/4" x 3/4" x 1/8" angle box 6" c/c placed vertically and welding with 2 Nos. horizontal 1" x 1" x 1/4" angle box, the whole thing again welding with 1.5" x 1.5" x 1/4" M.S. angle box post @ 6'-0" c/c etc. Considering 1 No. steel grill fencing Considering 2 panels: 12'-1.5" x 3'-0"= 36.38 sft. fencing work a) Cost of materials: i) 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs. per rft. @ 6'-0" c/c: 3 x 2 x 4'-6"= 27.00 rft. Add wastage 5%= 1.35 rft. = 28.35 rft. = 66.34 Ibs. @ Tk. 8.71 ii) 1" x 1" x 1/4" M.S. angle box horizontally at top and bottom.: @ 1.49 lbs per rft. 2 x 2 x 2 x 6'-0"= 48.00 rft. Add wastage 5%= 2.40 rft. = 50.40 rft. = 75.10 lbs. @ iii) 3/4" x 3/4" x 1/4" M.S. angle for box: @ 0.585 lbs. per rft. : 22 x 2 x 3'-0"= 132.00 Add wastage 5%= 6.60 = 138.60 = 81.08 b) Fittings, hardwares and consumables: i) Electrodes in/c electricity rft. rft. rft. lbs.

Per lb. = Tk.

577.82

Tk.

8.71

Per Ib. = Tk.

654.12

@ @

Tk. Tk.

8.71 4.00

Per Ib. = Tk. each = Tk.

706.21 560.00

140.00 Nos.

- 402 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

c) Cost of labour for making grill fencing i) Welder / fabricator ii) Welder helper iii) Ordinary labour 3.00 Nos. 3.00 Nos. 3.00 Nos. @ @ @ Tk. Tk. Tk. 160.00 120.00 100.00 each = Tk. each = Tk. each = Tk. = Sub-total = 10% = Total = Tk. Tk. Tk. Tk. 480.00 360.00 300.00 150.00 3,788.15 378.82 4,166.97

d) Carrying of materials to work-shop and fabricated materials to site: e) Work-shop charges:

f) Ancillary works for fitting -fixing the grill fencing: i) Labour charge for cutting 3" x 3" x 12" size grooves 4 Nos ii) CC (1:2:4): 4 x 3" x 3" x 12"= 0.25 cft. g) Labour charge for fitting-fixing the grill fencing: i) Mason ii) Mason helper 0.50 No. 0.50 No. @ @ @ Tk. 8,991.10 Tk. Tk. 150.00 120.00 Per % cft. = Tk. each each Grand total 10.00% 3.50% = = = = = Tk. Tk. Tk. Tk. Tk. 22.48 75.00 60.00 4,364.45 436.45 152.76 4,953.66 222.91 5,176.57 142.29 1,531.61 @ Tk. 10.00 each = Tk. 40.00

Contractor's profit Overhead expenses VAT

Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

Say,

Tk.

1,532 .00 Per sqm.

ANALYSIS FOR ITEM NO. 158 Supplying, fitting & fixing of steel grill fencing with outer frame having 1.5" x 1.5" x 1/4" M.S. angle and inner member having 1/4" dia M.S. rod placed 4.5" c/c diagonally on both directions. Considering 1 No. steel grill fencing Considering a panel of 7'-9" x 3'-3"= 25.19 sft. fencing work a) Cost of materials: i) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs. per rft. 2 x 3'-3"= 6.50 rft.
- 403 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Horizontal: 2 x 7'-9"= = Add wastage 5%=

b) c)

= ii) 1/4" dia M.S. rod: @ 0.167 lbs. per rft. 20 x 3'-3"= 65.00 8 x 7'-9"= 62.00 127.00 Add wastage 5%= 6.35 = 133.35 = 22.27 Fittings, hardwares and consumables: i) Electrodes in/c electricity i) Welder / fabricator ii) Welder helper iii) Ordinary labour Cost of labour for making grill fencing

15.50 22 1.1 23.1 54.05

rft. rft. rft. rft. Ibs. rft. rft. rft. rft. rft. lbs.

Tk.

8.71

Per lb. = Tk.

470.78

@ @ @ @ @

Tk. Tk. Tk. Tk. Tk.

10.28 4.00 160.00 120.00 100.00

Per Ib. = Tk. each = Tk. each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk.

228.94 140.00 160.00 120.00 100.00 75.00 1,294.72 129.47 1,424.19 80.00 60.00 1,564.19 156.42 54.75 1,775.36 79.89 1,855.25 73.65 792.77

35.00 Nos. 1.00 No. 1.00 No. 1.00 No.

d) e) f)

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges: Labour charge for fitting-fixing the grill fencing: i) Welder / fabricator ii) Welder helper 0.50 No. 0.50 No. @ @ Tk. Tk. 160.00 120.00

each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk.

Contractor's profit Overhead expenses VAT

Say,

Tk.

793 .00 Per sqm.

ANALYSIS FOR ITEM NO.159

- 404 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Supplying, fitting & fixing of M.S. angle post made thorough welding of 2 nos. 1.5" x 1.5" x 1/4" M.S. angle. Considering 1 No. steel post Considering 6.25 rft. of work a) Cost of materials: 2 x 6'-3"= Add wastage 5%= = = 2 x 1.5" x 1.5"= Add wastage 5%= = = b) Fittings, hardwares and consumables: i) Electrodes in/c electricity c) Cost of labour for making grill fencing i) Welder / fabricator ii) Welder helper iii) Ordinary labour d) e) f) 0.20 No. 0.20 No. 0.20 No. @ @ @ Tk. Tk. Tk. 160.00 120.00 100.00 each = Tk. each = Tk. each = Tk. = Tk. Sub-total = Tk. 10% = Tk. Total = Tk. Labour charge for fitting-fixing the grill fencing: i) Mason ii) Mason helper 0.20 No. 0.20 No. @ @ Tk. Tk. 150.00 120.00 each = Tk. each = Tk. Grand total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. 30.00 24.00 510.67 51.07 17.87 579.61 26.08 32.00 24.00 20.00 20.00 415.15 41.52 456.67 12.00 Nos. @ Tk. 4.00 each = Tk. 48.00 12.5 rft. 0.63 rft. 13.13 rft. 30.72 Ibs. 0.030 sft. 0.002 sft. 0.032 sft. 0.33 lbs. @ Tk. 10.85 Per Ib. = Tk. 3.58 @ Tk. 8.71 Per lb. = Tk. 267.57

i) 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs. per rft.

ii) 1.5" x 1/4" M.S. plate: @ 10.20 lbs. per sft.

Carrying of materials to work-shop and fabricated materials to site: Work-shop charges:

Contractor's profit Overhead expenses VAT

- 405 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

Grand total = Tk. Rate per rft. = Tk. Rate per rm. = Tk. Say, Tk. 318 .00 Per rm.

605.69 96.91 317.96

ANALYSIS FOR ITEM NO. 160 Barbed wire fencing (7'-0" height) with RCC pillars 8'-0" c/c. Considering 120' - 0" x 7' - 0"= 840 sft. of work a) 12 BWG barbed wire: @ 950 rft per cwt. Horizontal: 8 x 120'-0"= Diagonal: 15 x 2 x 10'-6"= = = b) c) G.I wire i) Silled labour ii) Head mason d) Local carriage, storage, sundries etc. 960 rft. 315 rft. 1275 rft. 1.34 cwt. 2.00 kg. 2.5 Nos. 1 No. @ @ @ @ Tk. 1,450.00 Tk. 50.00 Tk. Tk. 120.00 180.00 Per cwt. = Tk. Per kg. = Tk. each = Tk. each = Tk. L.S. Total 10.00% 3.50% = = = = 1,943.00 100.00 300.00 180.00 50.00 2,573.00 257.30 90.06 2,920.36 131.42 3,051.78 3.63 39.07

Labour for stretching, tightening and binding barbed wire in position

Tk. Tk. Contractor's profit Tk. Overhead expenses Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 39 .00 Per sqm.

ANALYSIS FOR ITEM NO. 161 Barbed wire fencing (4'-6" height) with 4" av. dia best quality local bullah post 6'-0" c/c. Considering 120' - 0" x 4' - 6"= 540 sft. of work

- 406 -

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

9 Nos. horizontal line of barbed wire with equal spacing & two nos of diagonal lines per bay. a) 12 BWG barbed wire: @ 950 rft per cwt. Horizontal: 9 x 120'-0"= Diagonal: 20 x 2 x 7'-6"= = = b) c) Cost of nails and staples: Cost of G.I. Wire 1080 rft. 300 rft. 1380 rft. 1.45 cwt. 2 kg. 2.25 kg. @ @ @ Tk. 1,450.00 Tk. Tk. 40.00 50.00 Per cwt. = Tk. Per kg = Tk. Per kg = Tk. 2,102.50 80.00 112.50

ii) Labour for streching, tightening and binding barbed wire in position a) Carpenter b) Skilled labour d) Local carriage, storage, sundries etc. Contractor's profit Overhead expenses VAT 1.50 Nos. 2.50 Nos. @ @ Tk. Tk. 160.00 120.00 each = Tk. each = Tk. L.S. = Tk. Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 69 .00 Per sqm. 240.00 300.00 75.00 2,910.00 291.00 101.85 3,302.85 148.63 3,451.48 6.39 68.78

ANALYSIS FOR ITEM NO. 162 Barbed wire fencing over brick wall/RCC member with 1.5" x 1.5" x 1/4" M.S. angle post 2'-0" straight + 1'-

6" inclined.
Considering 24'-0" x 3'-6"= 84 sft. of work A. Barbed wire works: 7 x 24'-0" + 49 x 4'-6"= = 2) Cost of 18 SWG G.I. wire 388.5 rft. 0.41 cwt. 1.00 kg
- 407 -

1) Cost of barbed wire: 12 BWG 2 ply 4 points; @ 950 rft. per cwt. @ @ Tk. 1,450.00 Tk. 50.00 Per cwt. = Tk. Per kg. = Tk. 594.50 50.00

Analysis of Rates of PWD Schedule (10th Edition), 16th October, 2002

3) Labour for streching, tightening and binding barbed wire in position a) Skilled labour a) Skilled labour 5) Local carriage and storage 6) T & P and sundries B. M.S. Angle works: 4 x (1'-0" + 2'-0" + 1'-6")= Add wastage 5%= = = 2) Fabrication cost of angles: i) Welder / fabricator ii) Welder helper iii) Mason for fxing in position iv) Mason helper 8) Local carriage and storage Contractor's profit Overhead expenses VAT 0.25 No. 0.25 No. 0.25 No. 0.25 No. @ @ @ @ Tk. Tk. Tk. Tk. 160.00 120.00 150.00 120.00 each = Tk. each = Tk. each = Tk. each = Tk. L.S. = Tk. Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft. = Tk. Rate per sqm. = Tk. Say, Tk. 234 .00 Per sqm. 40.00 30.00 37.50 30.00 20.00 1,537.24 153.72 53.80 1,744.76 78.51 1,823.27 21.71 233.69 18.00 rft. 0.90 rft. 18.90 rft. 44.23 lbs. @ Tk. 8.71 Per lb. = Tk. 385.24 1) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 lbs per rft. 1.50 Nos. 1.00 No. @ @ Tk. Tk. 120.00 120.00 each = Tk. each = Tk. L.S. = Tk. L.S. = Tk. 180.00 120.00 25.00 25.00 4) Labour charge for fitting with M.S. angle post

- 408 -

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

19. CEMENT PLASTER, POINTING WORK, WASHING WORK


Item No. 123(a-i) Description of items Minimum 12 mm thick cement plaster (1:4) with fresh cement (conforming to BDS 232) to wall both inner-and outer surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-incharge. Ground floor. Add for each additional floor up to 5
th th th

Unit

Unit Rate

(i) (ii) (iii) iv) (a-ii)

sqm floor. sqm sqm sqm

Tk. Tk. Tk. Tk.

98.00 4.26 6.38 8.51

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9 floor Minimum 12 mm thick cement plaster with neat cement finishing to plinth wall and upto 150 mm below ground level (1:4) with cement (conforming to BDS 232) up to 150 mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-incharge. Minimum 12 mm thick cement plaster with neat cement finishing to dado (1:4) with cement (conforming to BDS 232) up to 150 mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-charge. Ground floor Add for each additional floor up to 5 floor. Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor Minimum 12 mm thick cement plaster (1:6) with fresh cement (conforming to BDS 232) to wall both inner-and outer surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-incharge. Ground floor. Add for each additional floor up to 5
th th th th

sqm

Tk.

113.00

(a-iii)

(i) (ii) (iii) iv) (b).

sqm sqm sqm sqm

Tk. Tk. Tk. Tk.

122.00 4.26 6.38 8.51

(i) (ii) (iii) (iv) (c)

Sqm floor. sqm sqm sqm

Tk. Tk. Tk. Tk.

89.00 4.26 6.38 8.51

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9 floor Minimum 6 mm thick cement plaster (1:4) with fresh cement (conforming to BDS 232) to ceiling, R.C.C. columns, beams, surface of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c washing of sand cleaning the surface. scaffolding and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-incharge. Ground floor. Add for each additional floor up to 5th floor. (81)

(i) (ii) ahsan/aqa

sqm sqm

Tk. Tk.

80.00 4.26

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. (iii) (iv) (d)

Description of items Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor do-do cement plaster (1:3) in walls -do-doGround floor. Add for each additional floor up to 5
th th

Unit sqm sqm sqm

Unit Rate Tk. 6.38 Tk. Tk. Tk. Tk. Tk. 8.51 85.00 4.26 6.38 8.51

floor.

sqm sqm sqm

Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor 124 Flush pointing to brick wall with cement mortar (1:2) with cement having (conforming to BDS 232) in/c raking out the joints, and necessary scaffolding. curing at least for 7 days, cost of water , electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-charge. Ground floor. Add for each additional floor up to 5th floor. Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor Rule pointing to brick wall with cement mortar (1:2) with fresh cement (conforming to BDS 232) and raking out the joints, scaffolding, curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-charge. Ground floor. Add for each additional floor up to 5th floor. Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor Raised / tack pointing work to brick wall with cement mortar (1:2) with fresh cement (conforming to BDS 232) minimum 12 x 20 mm in size in/c. raking out the joints and necessary scaffolding, curing at least for 7 days, cleaning each and every brick, cutting the bricks with pumic stone where necessary etc. all complete in all floors, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-charge. Ground floor. Add for each additional floor up to 5th floor. Add for each additional floor above 5 floor and upto 9th floor Add for each additional floor above 9th floor Providing drip course/ nosing/ throating at the edge of sunshade or cornice with cement mortar (1:2) with fresh cement (conforming to BDS 232) in/c. scaffolding, curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-charge. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor above 5th floor and upto 9th floor Add for each additional floor above 9th floor
th

(i) (ii) (iii) (iv) 125

Sqm Sqm Sqm Sqm

Tk. Tk. Tk. Tk.

50.00 4.26 6.38 8.51

(i) (ii) (iii) (iv) 126

Sqm Sqm Sqm Sqm

Tk. Tk. Tk. Tk.

63.00 4.26 6.38 8.51

(i) (ii) (iii) (iv) 127

Sqm Sqm Sqm Sqm

Tk. Tk. Tk. Tk.

154.00 4.26 6.38 8.51

i) ii) iii) iv)

Rm Rm Rm Rm

Tk. Tk. Tk. Tk.

37.00 1.30 1.95 2.59

ahsan/aqa

(82)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 128

Description of items White washing by three coats, lime mixture prepared at least 12 hours before use, slacking stone lime, supply of gums, blue, stirring thoroughly, removing the floating materials from the mixer, surface cleaning to free from all foreign materials before application of each coat, applying one vertical & one horizontal wash for each coat & successive coat is to be applied after drying up of previous coat in/c hair brass, providing necessary scaffolding and cleaning plinth, floors, doors, windows, portions & ventilators by washing, rubbing, oiling if necessary after white wash for all floors in/c cost of water, electricity & other charges etc. complete in all respect as per direction of the engineer-in-charge. Colour wash with yellow orchred/any otherr colour pigment by two coats over a prime coat of white wash, lime mixture prepared atleast 12 hours before use, slacking stone lime, supply of gums, blue, stirring thoroughly, removing the floating materials from the mixer, surface cleaning to free from all foreign materials before application of each coat, applying one vertical & one horizontal wash for each coat & successive coat is to be applied after drying up of previous coat in/c hair brass, providing necessary scaffolding and cleaning plinth, floors, doors, windows, portions & ventilators by washing, rubbing, oiling if necessary after white wash for all floors in/c cost of water, electricity & other charges etc. complete in all respect as per direction of the engineer-in-charge.

Unit

Unit Rate

sqm 129

Tk.

6.35

sqm

Tk.

7.43

20. PAINTING, DISTEMPERING, POLISHING & VARNISHING


130 Cement Paint of approved quality and colour delivered from authorized local agent of the manufacturer in a sealed container, made from water based powder mixed with water (1:1), applying first coat, curing the same after six hours for 24 hours, second coat applied and curing the same for 7(seven) days etc, taking care and cleaning the surface fully from grease, oily substances, old paints, lime wash, fungus, algac etc., sand papering the surface before applying 1st and 2nd coat, complete in/c cost of electricity, water & other changes as per direction of the engineer-in-charge. sqm 131 Painting to door and window frames and shutters in two coats with approved best quality and colour of synthetic enamel paint delivered from authorized local agent of the manufacturer in a sealed container, having highly water resistant, high bondibilty, flexible, using specfic brand thinner applied by brass/roller/spray over a coat of priming elapsing time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and polishing with sand paper and necessary tools, scaffolding, testing charges etc. all complete in all floors. sqm Tk. 82.00 Tk. 57.00

ahsan/aqa

(83)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 132.

Description of items Approved best quality and colour synthetic polyvinyl distemper delivered from authorized local agent of the manufacturer in a sealed container, applying to wall & ceiling in 2 coats over a coat of brand specified primer or sealer elapsing specified time for drying/ recoating matt finish including cleaning and sand papering making the surface free from loose and flaky materials, dirt, grease, wax, polish, scraping all chalked & scaled materials, applying the paint by brush/rooller and necessary scaffolding etc. all complete in all floor as per direction of the engineer-incharge. Plastic emulsion paint of approved best quality and colour delivered from authorized local agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats over a coat of brand specified primer or sealer elapsing specified time for drying/recoating including cleaning drying, making free from dirt, grease, wax, removing all chalked & scaled materials, fungus, mending good the surface defects, sand paparing the surface and necessary scaffolding, spreading by brush/ roller/spray etc. all complete in all floor as per direction of the engineer-in-charge.

Unit

Unit Rate

sqm

Tk.

69.00

133.

sqm 134. Acrylic emulsion painting (silky finish) of approved best quality and colour delivered from authorized local agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats over a coat of brand specified primer or sealer including cleaning. drying, making free from loose and flaky materials, dirt, grease, wax, removing all chalked & scaled materials, fungus, elapsing specified time for drying, re-coating, flaking paints, mending good the surface defects, sand papering the surface, smoothing by putty and necessary scaffolding, testing charges, applied by brush/roller/spray etc. all complete in all floor as per direction of the engineer-in-charge. sqm 135. Textured painting of approved best quality and colour delivered from authorized local agent of the manufacturer in a sealed container, applying to wall and ceiling including cleaning, drying, making free from dirt, grease, wax, removing all chalked & scaled materials, fungus if required must be treated with fungicidal solution, flaking paints, mending good the surface defects, sand preparing the surface and necessary scaffolding, applied by brush/roller/spray etc. all complete in all floor as per direction of engineerin- charge. sqm. 136. Jensoline clorinated rubber painting of approved quality and colour delivered from authorized local agent of the manufacturer in a sealed container, applying to concrete surfaces and walls in three coats elapsing specified time for drying and re-coating including cleaning, drying, making free from dirt, grease, wax, removing all chalked & scaled materials, fungus (if required must be treated with fungicidal solution) flaking paints, washing the surface with soap water/caustic soda, mending good the surface defects, smoothening the surface by putty sand papering the surface and necessary scaffolding, applied by brush/roller/spray etc. all complete in all floor as per direction of the engineer-in-charge. sqm

Tk.

76.00

Tk.

80.00

Tk.

288.00

Tk.

122.00

ahsan/aqa

(84)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 137.

Description of items French polishing to door and window frames and shutters three coats over a coat of priming including putty, cleaning finishing and polishing with sand paper etc. all complete in all floor. Wood varnishing of approved quality and colour delivered from authorized local agent of the manufacturer in a sealed container using brand specified thinner to door and window frame and shutter in three coats, applied with brush including cleaning oil, grease, dirt, making dry, sand papering, if required washing with weak detergent solution, stripping out the colour straps, finisheing the surface, etc. all complete in all floors as per direction of the engineer-in-charge. Varnish (Yacht) Varnish (Egg shell) Varnish (Matt)

Unit

Unit Rate

sqm 138.

Tk.

75.00

(a) (b) (c)

sqm. sqm. sqm.

Tk. Tk. Tk.

68.00 72.00 65.00

ahsan/aqa

(85)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No.

Description of items

Unit

Unit Rate

21. DRAIN AND APRON


139. Constructing surface drain of 300 mm clear width and depth up to 300 mm in brick masonry with 125 mm thick check wall in cement mortar (1:6) over av. 75 mm thick cement concrete base (1:3:6) over one layer of brick flat soling. The surface having minimum 12mm thick cement plaster (1:3) and neat cement finishing with cement (conforming to BDS 232), curing at least for 7 days in/c excavationin all kinds of soil, back filling with fine sand (F.M. 0.8), consolidating and dressing, cost of water, electricity, other charges as per direction of the engineer-in-charge. rm 140. Constructing surface drain of 600 mm (Av) depth and 225 mm clear width at the bottom and 525 mm at the top having 125 mm thick cement concrete (1:2:4) curb up to 300 mm from the bottom over one layer of polythene on top brick flat soling and the side slopes of the remaing 300 mm height provided with 125mm thick lst class brick work in cement mortar (1:6) in/c minimum 12mm thick cement plaster(1:3) in/c neat cement finishing the surfaces and back of the drain up to 150 mm below ground level with fresh cement (conforming to BDS 232) curing at least for 7 days in/c excavation of all kinds of soil, back filling with fine sand (F.M. 0.8) consolidating and dressing, in/c cost of water, electricity, other charges as per direction of the engineer-in-charge. rm 141. Providing apron with 50 mm thick cement concrete (1:2:4) with cement (conforming to BDS 232), coarse sand and picked jhama chips in/c breaking chips and one layer brick flat soling at bottom with lst class or picked jhama bricks in/c cutting earth for preparation of bed and filling the interstices with local sand (F.M. 0.8) in/c finishing, dressing, curing at least for 7 days etc. all complete, in/c cost of water, electricity, other charges as per direction of the engineer-in-charge. Supplying, laying, fitting and best quality fixing 225 mm dia (internal) machine made R.C.C. pipe over 100 mm thick cement concrete (1:3:6) at base and sides in/c single brick flat soling and gasket with cement mortar (1:4) joints, cutting and filling trenches up to required depth in/c excavation of soil etc. all complete in all respects as per type plan and as per direction of the engineer-in-charge. (average depth of trench is 3'-6"). rm (b) -do- with 300 mm dia ( (internal) R.C.C. pipe. rm Tk. Tk. 792.00 1,103.00 Tk. 1,117.00 Tk. 541.00

sqm

Tk.

387.00

142.(a)

ahsan/aqa

(86)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No.

Description of items

Unit

Unit Rate

22. FALSE CEILING, WALL PANELING


143.(a) Supplying, fitting and fixing plain particle board ceiling of 12 mm thick with best quality and well seasoned Garjan wood frame of section 75 x 38 mm at 600 x 600 mm in grid suspended from ceiling /roof or beam by 12 SWG double ply G.I . wire fixed to the ceiling by rowel plug, screws, hooks, nails etc. maintaining straight lines and desired finished level at bottom face with vertical strut as required in/c cutting holes in slabs or beams by electric drill machine and mending good the damages, if any, during execution of the work in/c cost and carriage of all materials, accessories, labour for installation, eletricity charge, scaffolding, screws, nails etc. in/c. painting 2 coats over a coat of priming with best quality & approved colour synthetic enamel as per item no 131 of this schedule of etc. all complete as per drawing. design and direction of the engineer-in-charge (All sizes of wood are finished) Supplying, fitting and fixing plain particle board ceiling of 12 mm thick For auditorium and other type of tall structures beyond 4 m up to 8 m which do not cover the above item (Item No.143(a). Description of item is the same as in item No. 143(a) above. Supplying, fitting and fixing of 12 mm thick melamine board laminated by mechanical hot press with a milk white PVC membrance with aluminum frame suspended from ceiling. (a) Supplying fitting and fixing gypsum board ceiling of 12 mm thick board laminated by mechanical hot press with a milk white PVC membrane with aluminium T-bar frame in natural anodised finish at 600 x 600 mm in grid suspended from ceiling by 12 SWG double ply wire fixed to the ceiling by rowel plug. screws, hooks, nails etc. maintaining straight lines and desired finished level a bottom face with vertical wooden strut as required in/c making holes in slabs, or beams by electric drill machine and mending good the damages. if any, during execution of the work in/c cost of all materials, electricity .accessories, scaffoldings, labour for installation, screws, nails, etc. all complete as per drawing, design and direction of the engineer-in-charge. sqm (b) -do- with 12 mm thick veneered board ceiling 145. (a) Supplying, fitting and fixing 12 mm thick BT Veneered board in walling with best quality and well seasoned Garjan wood frame of section 75 x 38 mm at 600 x 600 mm in grid, fitted and fixed to wall by plugs, nails, screws etc. in/c treatment of inner surface with termide & damp proofing agent maintaining leveled and finished exposed faces in/c. making holes in wall and mending good the damages. If any, during execution of the work in/c. cost and carriage of all materials, electricity, accessories, labour for installation, scaffolding, screws, nails etc. in/c french polishing 3 coats over a coat of priming as per item no. 137 of the schedule etc. all complete as per design, approved sample and direction of the engineer-in-charge. sqm (b) -do- 12 mm thick particle board walling sqm Tk. Tk. 1,652.00 954.00 sqm Tk. Tk. 1,151.00 1,124.00

sqm

Tk.

1,129.00

(b)

sqm

Tk.

1,206.00

(c)

sqm

Tk.

752.00

144.

ahsan/aqa

(87)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No.

Description of items

Unit

Unit Rate

23. COLLAPSIBLE GATE, M.S. GATE, ROLLING SHUTTER ETC.


146(a) Manufacturing, supplying, fitting and fixing collapsible gate of any design & shape made of 3/4" x 3/8" x 1/8" channel placed @ 112 mm c/c vertically and connecting the same with each other by 20 x 3 mm M.S flat bar scissors 525 mm/ 600 mm long provided in 3 rows in/c cutting the different M.S. members to required sizes, fabricating, welding, riveting with required size rivets, providing requried size wheels, pulling handles on both sides, suitable locking arrangement, electrodes, greees and finally placing the same in position in between 2 (two) Nos. 50 x 50 x 6 mm M.S. Tee rail made by welding 2 Nos. 50 x 6 mm M.S. flat bar fitted and fixed at top and bottom with R.C.C. lintel/roof slab. floors and side wall with required Nos. 150 mm to 225 mm long 38 x 6 mm M.S. flat bar clamps one end welded with the gate member and the other end bifurcated and embedded in C.C. at the respective point in/c cutting holes and mending good the damages by pouring concrete (1:2:4) into the holes & finishing, etc complete, painting 2 (two) coats with approved best quality synthetic enamel paint over a coat of anticorrosive painting, both end carraige, in/c greesing, electodes, curing etc. complete as per drawing & designas per direction of the engineer-incharge. (excluding cost of paint) sqm 146 (b) 146 (c) 147.(a) - do - -do- collapsible gate made of 3/4" x 3/4" x 1/8" M.S. angle as vertical member and 3/4" x 1/8" F.I bar as scissors - do - -do- collapsible gate made of 1" x 1" x 1/8" M.S. angle as vertical member and 1" x 1/8" F.I bar as scissors Supplying, fitting, fixing, and installation of ordinary type M.S. gate (double leaf) of any design & shape with 38 x 38 x 6 mm M.S. Angle outer frame having 16 mm dia M.S. rod placed vertically @ 75 mm c/c. at bottom part and top part (arrows) and also placed horizontally at bottom for interconnection of 16 mm dia M.S. rod placed vertically as per design, the top part covered with 18 BWG M.S. sheet and fixed with 4 Nos. 38 x 6 mm F.I. bars placed diagonally and 4 Nos. 38 x 6 mm F.I. bars placed horizontally and vertically all passing through the centre, providing locking arrangements on 3 mm thick M.S. plate one for main gate and one for minimum 300 x 1025 mm pocket gate with 38 x 38 x 6 mm M.S. angle and 16 mm dia M.S. rod placed vertically @ 75 mm c/c, providing 38 x 38 x 6 mm M.S. angle clamps fitted and fixed with the outer frame of the main gate, the clamp being embedded in R.C.C. or R.C.C. core pillar with cement concrete (1:2:4) in masonry in/c cutting holes and mending good the damages, finishing, curing etc. in/c riveting, welding as and where necessary ,painting two, coats with approved quality of synthetic enamel paint over a coat of priming of anti-corrossive paint etc. all complete as per drawing, design and direction of the engineer-in-charge. (excluding cost of paint) sqm Tk. 2,017.00 sqm sqm Tk. Tk. Tk. 1,200.00 1,382.00 1,644.00

ahsan/aqa

(88)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 147.(b)

Description of items Supplying, fitting, fixing, and installation of ordinary type M.S. security gate of any design & shape with 50 x 50 x 6 mm M.S. angle outer frame and two 50 x 50 x 6 mm angle placed diagonally having 22 mm dia M.S. rod placed vertically @ 3.60 mm c/c. and also 38 x 6 mm F.I placed horizontally the bottom part covered with 3 mm thick m.s. sheet providing locking arrangements on 3 mm thick M.S. plate providing heavy type clamps fitted and fixed with the outer frame of the main gate, the clamp being embedded in R.C.C. or R.C. core pillar with cement concrete (1:2:4) in masonry in/c cutting holes and mending good the damages, finishing, curing etc. in/c, fabrication, riveting, welding as and where necessary, etc. all complete as per drawing, design and direction of the engineer-in-charge. (excluding cost of paint) Supplying, fitting, fixing and installation of ordinary type M.S. gate (double leaf)of any design & shape with 38 x 38 x 6 mm M.S. angle framing. the top and bottom parts provided with 25 x 6 mm F.I. bar placed vertically @ 150 mm c/c and the middle part is covered with 18 BWG M.S. sheet and fixed with 4 Nos 38 x 6 mm.F.I. bar placed diagonally and 4 Nos 38 x 6 mm F.I. bars placed horizontally and vertically,all passing throuh the centre as design in/c locking arrangement on 3 mm thick M.S.plate, providing 38 x 38 x 6 mm M.S. angle clamps fitting and fixed with the outer frame of the gate, the clamp being embedded in the R.C.C. or R.C.C. core pillar with cement concrete (1:2:4) in massonry in /c cutting holes and mending good the damages, finishing, curing in/c riveting, welding as and where necessary, painting 2 (two) coats of synthetic enamel paint over a coat of anti-corrossive paint etc.all complete as per drawing, design and direction of the engineer-in-charge. (excluding cost of paint)

Unit

Unit Rate

sqm 148.

Tk.

3,534.00

sqm 149. Supplying, fitting, fixing and installation ordinary type M.S. gate (double leaf) of any design & shape with 38 x 38 x 6 mm M.S.angle box (made by welding 2 Nos.38 x 38 x 6 mm angle) outer frame having 25 x 50 x 25 x 5 mm M.S. channel (made by welding 2 Nos. of angle) placed part diagonally after cutting and shaping as per requirement part horizontally @ 75 mm C/C the two part of each leaf being separated by a vertical member of 38 x 38 x 6 M .S. box and welded the each ends of diagonal and horizontal members properly with the box frame as per architectural drawing providing full locking arrangement on 3 mm thick M.S. plates providing 38 x 38 x 6 mm M.S. angle clamps, fitting fixing with the outer frame of the gate the clamp being embeded in R.C.C. pillars with cement concrete (1:2:4) in/c. cutting holes and mending good the damages, finishing, curingas and where necessary painting two coats with approved quality of synthetic enamel paint over a coat of priming of anticorrosive paint etc. all complete including making and providing 50 x 6 mm M.S. rail and 38 mm wheel for smooth movement of the gate etc. all complete as per drawing, design and direction of the engineer-in-charge. (excluding cost of paint) sqm

Tk.

1,780.00

Tk.

2,691.00

ahsan/aqa

(89)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 150.

Description of items Making, supplying, fitting and fixing G.I. pipe gate of any design & shape having 38 mm dia G.I. pipe outer frame and 19 mm dia. G.I. pipe vertical member placed @ 75 mm c/c by welding at top and bottom of G.I. pipe frame, cutting the pipes in proper shape and size in/c making semicircular band at the corners of the outer frame without damaging the pipe, covering 50% of the gate area with 18 BWG M.S. sheet, providing also two extra horizontal 38 mm dia G.I. pipes welded with vertical post, providing 6 Nos. huskle domney with R.C.C.or R.C.C core pillar with cement concrete (1:2:4) in masonry in/c cutting holes, mending the damages, making provision for minimum 0.61 m x 1.4 m pocket gate having its outer frame and inner vertical members made with 19 mm dia G.I. pipe in/c necessary locking arrangements. Painting the gate with 2 (two) coats of synthetic enamel apint over a coat of anti-corrosive priming, (Excluding the cost of paint) welding as and where necessary in/c necessary locking arrangement and providing 2 Nos. 16 mm M.S. socket bolts etc. all complete as per design and drawing.(excluding cost of paint) Supplying. fitting and fixing of rolling shutterof any design & shape made of 24 SWG G.P, sheet unit minimum 69 mm width having 10 mm & 12 mm dia Circular folding at ends ,rolled in machine, locked together properly to form rolling shutter, top of the shutter to be fitted w with circular spring box made of 22 BWG sheet, containing best quality spring made in China, nutted with 38 mm G.I. pipe at one end and the other end nutted to shutter in/c fitting the G.I. pipe again with 375 x 300 x 6 mm pankha at ends with side guide channel (side channel consist of 50 x 100 x 6 mm M.S. plate with 2 x 19 x 3 mm F.I. bar, middle channel consist of 2 x 150 mm x 6 mm M.S. plate with 2 x19 mm x 6 mm Fixed to wall or coloumn with clamps embeded in R.C.C. part by cement concrete (1:2:4) in/c cutting holes (minimumm 3 x 25 mm x6 mm) mending the damages, finishing, curing, bottom end of shutter fitted to folded G.P. sheet (min 125 mm width in two layers), which is again fitted to 25 x 25 x 3 mm angle, providing handle (with F.I. bar 25 x 6 mm riveted) and locking arrangement in both sides, painting two coats with approved colour and brand of synthetic enamel paint over a coat of priming etc. complete in all respect as per drawing design. Rolling shutter must be riveted at sides with G.P. sheet and patty) (excluding cost of paint)

Unit

Unit Rate

sqm 151.

Tk.

3,924.00

sqm

Tk.

1,744.00

ahsan/aqa

(90)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No.

Description of items

Unit

Unit Rate

24. STAIR RAILING & VERANDAH RAILING


152. Manufacturing, supplying, fitting and fixing stair railing of any standard height of any design & shape with square box (2 Nos.in each tread) made by thorough welding of 2 Nos. 19 x 19 x 3 mm M.S. angle to provide handrail, engraving each box 150 mm in the concrete by 50 x 50 x 6 mm anchor plate at base welding 38 mm x 6 mm F.I.bar inclined plain with the top of the box to fit in the grooved wooden rail by necessary screws in/c cutting grooves in concrete, mending good the damages with cement concrete (1:2:4), applying lst class polish to hand rail, 2 (two) coats of synthetic enamel paint of approved quality over a prime coats of synthetic enamel paint of approved quality over a prime coat etc. finished in all respect for all floors, Exposed area of railing will be considered for measurement. (excluding cost of hand-rail) sqm 153. Manufacturing, supplying, fitting and fixing stair railing of standard heightof any design & shape with square box (1 No. box in each tread) made by thorough welding of 2 Nos. 25 x 25 x 5 mm M.S. angle, engraving each box 150 mm in the concrete by 50 x 50 x 6 mm anchor plate at base welding 50 x 50 x 6 mm F.I. bar in inclined plain with the top of the box fit in the grooved wooden rail and 2 Nos. 225 x 25 mm finished section of wooden strip fitted and fixed at mid height of railing at both side of M.S.angle box in inclined plain parallet to the hand rail etc. fitted and fixed by necessary screws, nails. in/c cutting grooves in concrete mending good the damages with cement concrete (1:2:4) applying lst class french polish to wooden hand rail and inclined wooden strip and painting to F.I bar and square box with 2 (two) coats of synthetic enamel paint of approved quality and colour over a prime coat etc. complete in all respect for all floors (exposed area of railing will be considered for measurement.) (excluding cost of polishing and painting) Sqm 154. Supplying, fitting and fixing 12 mm dia G.I pipe stair railing of any standard height of any design & shape with 50 x 50 x 6 mm M.S. plate at the base f 12 mm dia G.I. Pipe and fitted andfixed by welding. Placing the pipes vertically @ 125 mm c/c (2 Nos. in each steps) 150 mm ecbeded into the R.C.C tread of stair case after cutting grooves and mending good the damages with C.C. & providing 38 x 6 mm F.I. bar on the top of G.I. pipe to provide wooden/G.I. pipe hand rail of any design in/c polishing painting etc. all complete. Exposed area of railing will be considered for measurement. (excluding cost of paint) With Hnadrail (150 x 62 mm) (finished) With Handrail (112 x 62 mm) sqm sqm Tk. Tk. 1,401.00 1,589.00 Tk. 2,217.00 Tk. 1,357.00

(a) (b)

ahsan/aqa

(91)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 155.(a)

Description of items Providing veranda railing with 38 mm dia G.I. Pipe hand rail of any design & shape with 12 mm dia G.I. Pipe post fixed vertically @ 125 mm c/c 75 mm of the bottom of the pipes to be embedded in flooor with 50 x 50 x 3 mm M.S. base plate welded at bottom, all comple including making necessary grooves in floor, wall, column, lintel etc. the post fixing in the groove with 1:2:4 cement concrete, manding good all damages, finishing, curing etc. as per plan & drawing and direction of the engineer-in-charge. (Exposed area of railing will considered towards measurement)

Unit

Unit Rate

sqm (b) -do- with 50 mm dia G.I. Pipe hand rail sqm

Tk. Tk.

1,665.00 1,863.00

25. GRILL FENCING, BARBED WIRE FENCING


156. Supplying, fitting and fixing steel grill fencing in bundary wall of any design & shape with 31 x 6 mm F.I. bar @ 150 mm c/c placed vertically after cutting as per required measurement. Welding the said F.I. bar with 2 Nos. horizontal 30 x 6 mm F.I. bar placed one at top and another at bottom in/c. embedding/fixing the horizontal F.I. bar in position in/c cutting grooves in wall upto 150 mm depth and mending good the damapes with C.C. (1:2:4) finished with two coats of painting with synthetic enamel paint over a coat of anti-corossive paint etc. complete as per drawing & design and as per direction of the engineer-in-charge. (excluding cost of painting) Supplying, fitting and fixing steel grill fencing of any design & shape made with 19 mm x 3 mm tube (angle box made with 2 Nos.19 x 19 x 3 mm angle in by continuous welding) placed vertically @ 150 mm c/c and welding the said vertical boxes with two Nos. horizontal 25 x 25 x 6 mm angle box made with 2 Nos. 25 x 25 x 6 mm angle by welding), placing one at bottom and another at top and again fitted and fixed by welding the said horizonatal tube box (with vertical 38 x 38 x 6 mm angle box post (made with 2 Nos. 38 x 38 x 6 mm angle by welding) provided 1800 mm c/c in/c embedding the tube box post in brick R.C.C. pillar or core wall upto 375 mm depth after cutting grooves in wall/pillar in/c. mending good the damages with C.C. (1:2:4) and finishing, curing, 3 coats of anti-corrosive paint etc. all complete as per design, drawing and diretion of the engineer-incharge. (excluding cost of paint) sqm 158 Manufacturing, supplying, fitting and fixing M.S. grill fencing as per desin with outer frames having 38 x 38 x 6 mm M.S. angle and inner members having 6 mm dia M.S. rod placed @ 110 mm c/c diagonally on both direction, welding each criss-cross end of rod with corners of outer frame including cutting rods and size angles to required shaps and size and setting the entire fence with the previously installed tube (angle box) post in/c thorough and full welding the frame with the angle box posts, painting 2 coats of synthetic enamel paint over a coat of anti-corrossive priming etc. all complete as per drawing and direction. (Excluding the cost of angle box post and its installation and excluding the cost of paint) sqm Tk. 793.00 Tk. 1,532.00

sqm

Tk.

655.00

157.

ahsan/aqa

(92)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 159

Description of items Manufacturing, supplying, fitting and fixing M.S. tube (angle box) post (bottom end bifurcated) made by thorough welding of two nos. 38 x 38 x 6 mm M.S. angle and vertically placing the post into C.C./R.C.C. foundation in/c cutting angle to required shape and size in/c covering the top of the post with 6 mm thick M.S. plate etc. all complete as per drawing (Excluding the cost of C.C./R.C.C. foundation)

Unit

Unit Rate

rm 160 Providing barbed wire fencing with R.C.C (1:2:4) pillars @ 2.43 mm c/c. and of section 100 mm x 100 mm at top and 150 mm x 150 mm at bottom of 2.13 m total height (1.37 m above G.L. and 0.76 m below G.L.) in/c 150 mm thick, 450 mm square spread footings (pillars reinforced with 4 nos. 10 mm dia main rod and 6 mm dia stirrups @ 150 mm c/c,footing reinforced with 5 nos. 10 mm dia rod both ways) supplying, fitting and fixing 8 lines of barbed wire horizontally (fixed with the post through 6 mm dia, rods embeded in to the post) and 2 lines diagonally from post to post with 12 BWG 2 ply barbed wire,with 4 points barbs @ at least 112 mm c/c in/c 6 mm thick (1:4) cement plaster upto 1500 mm length of the pillars etc. complete as per direction of the engineer-in-charge. (excluding cost of concrete, reinforcement and foundation which to be paid as per corresponding items in the schedule)

Tk.

318.00

sqm 161 Providing barbed wire fencing with average 100 mm dia best quality local bullah post of 1.98 m total height (1.37 m above G.L. and min. 0.60 m embeded in the ground) placed at 1800 mm c/c with 9 Nos. horizontal lines and 2 Nos. diagonal lines of 12 BWG 2 ply barbed wire with 4 points barbs @ at least 112 mm c/c in each way of 1.8 m in/c embeded the post tightly in ground and providing a cement concrete base of 200 x 200 x 300 mm around ballah at E.G.L, stretching the wires and fixing with the post with the help of minimum 62 mm long G.I. nails in/c supply of all materials etc. All complete as per direction of the engineer-in-charge. (Excluding the cost of ballah and its driving/fixing and concrete which to be paid as per corresponding items in the schedule) sqm 162 Supplying, fitting and fixing 12 BWG barbed wire (2 ply, 4 points) in fencing work @ 150 mm c/c in both horizontally and vertically, supported by 38 x 38 x 6 mm M.S. angle post (300 mm embeded in R.C.C. or in brick work with a cement concrete base of 75 x 75 x 300 mm) 600 mm vertical and 450 mm inclined or as per requirement @ 2.4 m c/c including straightening, binding the joints with 18 BWG wire making holes in the angle etc. in /c supplying of all necessary materials.complete in all respect as per direction of the engineer-in-charge (Excluding the cost of R.C.C/brick work/C.C. which to be paid as per corresponding items in the schedule) sqm

Tk.

39.00

Tk.

69.00

Tk.

234.00

ahsan/aqa

(93)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(94)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(95)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(96)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(97)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(98)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(99)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(100)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(101)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(102)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(103)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(104)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(105)

PWD Schedule of Rates, 16th October, 2002 (10th Edition)

ahsan/aqa

(106)

Vous aimerez peut-être aussi