Académique Documents
Professionnel Documents
Culture Documents
Flame Days 2013 seminar Ilkka Hannula VTT Technical Research Centre of Finland
08/04/2013
08/04/2013
08/04/2013
www.vtt.fi/inf/julkaisut/muut/2010/Hannula1.pdf
08/04/2013
www.vtt.fi/inf/julkaisut/muut/2011/Hannula301210.pdf
08/04/2013
08/04/2013
08/04/2013
08/04/2013
08/04/2013
10
With reformer, main components come very close to eq. and model results are usually satisfactory
08/04/2013
11
08/04/2013
12
Residual methane
08/04/2013
13
08/04/2013
14
Product gas
T = 850 C T = 550 C
Product gas
T = 850 C
08/04/2013
15
08/04/2013
16
08/04/2013
17
Feedstock input 300 MWth (50 wt%, LVH) to dryer for all simulated designs 4 end-product considered: methanol, DME, FT liquids and MTG 5 individual plant designs simulated 20 cases compared: Overall thermodynamic efficiency (on LHV basis) Economics (capital cost estimates & levelised production costs)
1 2 Currently proven Condensing CHP 550 C 550 C 5 bar 5 bar Vent Vent
4 5 Further R&D required CHP CHP CHP 850 C 850 C 850 C 5 bar 22 bar 22 bar Vent Vent CCS
08/04/2013
18
Feedstock input 300 MWth (50 wt%, LVH) to dryer for all simulated designs 4 end-product considered: methanol, DME, FT liquids and MTG 5 individual plant designs simulated 20 cases compared: Overall thermodynamic efficiency (on LHV basis) Economics (capital cost estimates & levelised production costs)
1 2 Currently proven Condensing CHP 550 C 550 C 5 bar 5 bar Vent Vent
4 5 Further R&D required CHP CHP CHP 850 C 850 C 850 C 5 bar 22 bar 22 bar Vent Vent CCS
08/04/2013
19
CASE Gasifier Pressure Temperature Heat loss Steam/O2 Carbon conversion Recycle gas / O2 Recycle gas flow S/O2 inlet temp Filter Temperature Reformer Outlet temperature Heat loss Steam/O2 Methane in (dry) Methane out (dry) Methane conversion S/O2 inlet temp N2 out (dry) C % mol% mol% % C mol% C bar C % % kg/s C
550
550
850
850
850
08/04/2013
20
CASE Gasifier Pressure Temperature Heat loss Steam/O2 Carbon conversion Recycle gas / O2 Recycle gas flow S/O2 inlet temp Filter Temperature Reformer Outlet temperature Heat loss Steam/O2 Methane in (dry) Methane out (dry) Methane conversion S/O2 inlet temp N2 out (dry) C % mol% mol% % C mol% C bar C % % kg/s C
550
550
850
850
850
For a plant having 300 MW biomass input (LHV, AR @ 50 wt% moisture) CH4 flow 3.8 MW 22.8 MW
08/04/2013
21
229 MW
250 MW
242 MW
08/04/2013
22
Fischer-Tropsch design
Synthesis Shell Middle Distillate Synthesis (Bintulu, Pearl) Cobalt-based (Co/Zr/SiO2) LTFT Very paraffinic syncryde, less alkenes and oxygenates than in any other large-scale industrial FT technology. 80 % per-pass conversion, ~ 0.90 Multitubular fixed-bed reactor at 200 C and 30 bar. Recovery & upgrade C5 recovered by condensation at 45 C and Psynth No cryogenic separation of C1-C2 Hydrocracker at 325 C and 40 bar with noble metal hydrocracking catalyst
Simplified layout of the FT synthesis, product recovery and refinery section, adapted SMDS design. From: Arno de Klerk (2011) Fischer-Tropsch refining, Wiley-VCH, 642pp, ISBN 9783527326051
08/04/2013
23
08/04/2013
24
08/04/2013
25
08/04/2013
26
- Detailed mass & energy balances used as a basis for equipment sizing - Chemical Engineers Plant Cost Index used to account inflation - Component costs scaled using individual exponents:
CAPITAL COSTS, M Auxiliary equipment Buildings Oxygen production Feedstock pretreatment Gasification island Gasification Hot-gas cleaning CO shift Syngas cooling Compression Acid gas removal Power island Fischer-Tropsch synthesis FT reactor HC recovery plant H2 production (PSA system) Wax hydrocracking FT recycle compressor TOTAL OVERNIGHT CAPITAL TOTAL CAPITAL INVESTMENT
5BAR/550C 5BAR/850C 22BAR/850C 97.0 18.8 47.2 31.1 150.9 51.1 38.7 6.2 10.2 8.9 35.9 27.1 77.0 41.2 8.1 1.4 25.7 0.5 352.1 369.7 93.6 18.8 43.8 31.1 151.4 51.1 37.9 6.6 10.2 8.9 36.8 23.9 80.9 43.4 8.6 1.5 26.9 0.5 349.9 367.4 93.6 18.8 43.7 31.1 149.3 51.1 39.5 7.1 10.6 5.7 35.3 30.0 80.1 43.0 8.5 1.4 26.7 0.6 353.0 370.7
08/04/2013
27
Investment cost factors Balance of Plant Indirect costs Contingency for standard components Contingency for less mature components Interest during construction, fraction of TPC Capital charges factor, (10%, 20a) O&M costs factor, fraction of TPC/a Public investment support, M
Prices Biomass, /MWh Electricity, /MWh District heat, /MWh
BOP instrumentation and controls, electrical connections, piping, insulation, and site preparation Indirect costs Engineering & head office costs 15 %, start-up costs 5 % and royalties & fees 2 % O&M Personnel costs 0.5 % Maintenance & insurances 2.5 % Catalysts & chemicals 1 %
30 % 22 % 20 % 30 % 5% 12 % 4% 0
17 50 30
08/04/2013
28
08/04/2013
29
08/04/2013
30
Gasoline @150$/bbl
Gasoline @100$/bbl
08/04/2013
31
VTT - 70 years of