Vous êtes sur la page 1sur 182

Company number Akara-001 Akara-002

tech/e Sec/table/fig dit locator Page E E 1.1, par 3 vii

Comment Spelling of Neil Wanamaker

Proposed resolution Correct

Response Accepted Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8

1 "..emphasize on " in 2 places Remove on. The major part of FC-BB-2 is the addition of the FC-BB-2_IP This is the major addition, not specification which makes use major part. Replace "IETF 1 of the IETF specification [16]. specification" with FCIP [16].

Akara-003

1.1, par 3

Accepted

Completed in Rev 5.8

Akara-004

1.2, par 1

1 "..support for E_Ports" The B_port model shows the switch (or BSW) outside the box, with the B_port being the boundary of this specification. The E_port model shows these inside, with the boundary being the E_Port. These should be consistent.

Replace by "..support for virtual E_Ports" or "support for VEports".

Rejected: The commented suggestion is good one but will create an uneveness in the naming of Reference Model. VE_Port and B-Port creates a confusin as to what part of a model dictates its name. We cannot use B_Access as it only applies to IP. In future, we may be able to call the models VE_Port and B_Access when BBW models are changed to show this.

Akara-005

Global

Global

Make boundary of this model be VE_Port, with E_Ports, switch elements, BSWs, etc. outside this specification. See Andiamo-001

Completed in Rev 5.8

Akara-006 Akara-007

E E

2.1 2.2

T1.105 and T1.105.02 have been revised (2001; prepublished). FC-BB is INCITS 342-2001. FC-SW-2 is INCITS 355-2001. FG reaffirmed 2001 (?). FC-GS-3 is INCITS 3484 2001. Correct 5 xxxxD should be filled in.

Accepted. BB, SW-2, GS-3 corrected.T1.105 and T1.105.02 references from 1995 have been used to make the standard. 2001 updates were not used and may actually [resent problems if the later one is used. Completed in Rev 5.8 Accepted Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page Table 17, Figure 11, Figure 12 50, 51,52

Comment Size of LLC/SNAP header is inconsistent.

Proposed resolution

Response

Status

Akara-008

Correct

Accepted

Completed in Rev 5.8

Akara-009

13.2.3.3.5, Figure 25

74, 75

It would appear that, with the exception of the LKA, ILSs are exchanged between (I.e., are initiated and terminated at) the attached E_Ports, not between the VE_Ports. These other ILSs are simply transported across the virtual ISL. Remove mention of other ILSs.

Rejected- ILSs are in fact exchanged between VE_Ports

Akara-010 Andiamo-001

T T

13.2.3.5.2.2 4.2, 4.4, 13.2.3.2.1

"If the network transit time is large enough to jeopardize meeting any Fibre Channel timeout requirements, the frame shall be discarded.". The FCIP entity cannot Timeout values should be agreed determine this by any means as part of routing setup during 76 specified in this standard. fabric initialization. 14-15 In these section there are a) complete the FSPF backbone and 72 several references to inter-AR definition in FC-SW-3; or b) connectivity, which requires include in FC-BB-2 the missing the usage of the FSPF pieces; or c) remove the inter-AR backbone protocol. But FSPF model from FC-BB-2. backbone is still not completely specified in FC-SW3. There are interoperability risks.

Accepted - Text indicating that timeout values will be adminstratively set. This should become a work item for FC-BB3 and FC-SW-4. See also McData-035. See also CNT-017 Completed in Rev 5.8

Accepted c). Removed all references to FSPF-Backbone, and AR Completed in Rev 5.8

Company number Andiamo-002

tech/e Sec/table/fig dit locator Page Comment Proposed resolution Response E several several The terminology used across Use a terminology consistent with the document is not consistent FC-FS. with FC-FS. It should be. Example: "FC Fabric Entity WWN" should be simply "Fabric_Name". WWPN should be N_Port_Name or B_Port_Name or what is required. Accepted E 13.2.3.4 75 The text says: "FCIP Wellknown Port 3225" It should be"FCIP Well-known TCP Port 3225".

Status

Completed in Rev 5.8

Andiamo-003

Accepted with correction: The correct term is actually FCIP Registered TCP Port Number 3225

Completed in Rev 5.8

Andiamo-004

13.2.3.3.5.1

75

The text says: "The Link Keep It should be"The Link Keep Alive Alive Switch Fabric ILS" SW_ILS". Accepted Completed in Rev 5.8 Completed in Rev 5.8 The text says: "A F Class frame" The text is ambiguous: "If the network transit time is large enough to jeopardize meeting any Fibre Channel timeout requirements" item a) says "FCsec frame authentication"; item b) says "IPsec TCP data authentication" The Requester Interconnect_Port_Name: definition says: "This field shall contain the name of the device that originated the EBP request." the term "name" is ambiguous The encoded value column is in binary It should be "A Class F frame" Accepted Give a more quantitative and measurable definition of "large enough", otherwise interoperability problems may occur. Accepted - See Akara -010 Change item a) in "FCsec frame authentication and confidentiality"; and item b) in "IPsec packet authentication and confidentiality". Accepted Clarify that this is a Port_Name. Completed in Rev 5.8

Andiamo-005 Andiamo-006

E T

13.2.3.5.2.2 13.2.3.5.2.2

76 76

Andiamo-007

13.2.3.5.4

77

Completed in Rev 5.8

Andiamo-008

13.3.3.2.5.1

81

Accepted: Changed to Port_Name. Please note Port_name refers to either an VE_Port or B_Access in this case. Completed in Rev 5.8 Express it in hex. Accepted Completed in Rev 5.8

Andiamo-009

table 23

82

Company number Andiamo-010

tech/e Sec/table/fig dit locator Page E 14.2.1 92

Comment Proposed resolution The Connection Usage Code Remove or resolve this text. paragraph contains the text "A TBD". What does it mean this paragraph? FC multicast/broadcast or IP multicast/broadcast ? What's wrong in supporting FC broadcast as defined in FCSW-3, being an FCIP link another kind of ISL link? The text says: "IPsec TCP data authentication" Clarify.

Response

Status

Accepted: See Brocade-127

Completed in Rev 5.8

Andiamo-011

16.6

101

Accepted. Add- This standard does not make use of IP broadcast/multicast. Completed in Rev 5.8 Change it in "IPsec packet authentication and confidentiality".

Andiamo-012

16.7

101

Accepted

Completed in Rev 5.8

Brocade-001 Brocade-002

E E

All Front Matter

All All

The frame type notation of FT0 and FT-1 are FC-PH notations. These have been redefined in FC-FS to be FT_0 and FT_1, respectively. NCITS needs to be changed to INCITS Change all instances of "National Committee for Information Technology" to "InterNational"

Change all references to FT-0 to FT_0 and FT-1 to FT_1. Accepted Change all instances of NCITS to INCITS Accepted Change all instances of "National Committee for Information Technology" to "InterNational" Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-003

Front Matter

All

Completed in Rev 5.8

Brocade-004

Front Matter

Bob Snively's contact information incorrect

Update to: Robert Snively (T11 Chairman) Brocade Communications Systems, Inc. 1745 Technology Drive San Jose, CA 95110 Phone: (408) 487-8135 Fax: 408-392-6655 E-Mail: rsnively@brocade.com Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution Update to: Steve Wilson (Working Group Chairman) Brocade Communications Systems, Inc. 1745 Technology Drive San Jose, CA 95110 Phone: (408) 487-8128 Fax: 408-392-6655 E-Mail: swilson@brocade.com Change to INCITS XXX-XXXX Change approved date to mm.dd.yy

Response

Status

Brocade-005 Brocade-006 Brocade-007

E E E

Front Matter Front Matter Front Matter

i iv iv

Steve Wilson's contact information incorrect Document number format incorrect Document not yet approved

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution Boilerplate text: "CAUTION: The developers of this standard have requested that holders of patents that may be required for the implementation of the standard, disclose such patents to the publisher. However, neither the developers nor the publisher have undertaken a patent search in order to identify which, if any, patents may apply to this standard. As of the date of publication of this standard, following calls for the identification of patents that may be required for the implementation of the standard, notice of one or more claims has been received. By publication of this standard, no position is taken with respect to the validity of this claim or of any rights in connection therewith. The known patent holder has, however, filed a statement of willingness to grant a license under these rights on reasonable and nondiscriminatory terms and conditions to applicants desiring to obtain such a license. Details may be obtained from the publisher.

Response

Status

Brocade-008 Brocade-009 Brocade-010

E E E

Patent Stmt Copyright Front Matter

v v v

Patent statement needs to be changed to the Have been announced/claimed format Copyright date listed as 199x Extraneous text "INSERT CODE HERE"

Accepted Change copyright date to 2002 Delete text Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-011

Forward

vi

Change to "(This Forward is not Text "(This Forward is not part part of American National of dpANS NCITS xxx-2001) Standard NCITS xxx-xxxx)" Paragraph 2 & bulleted list of Forward do not belong in forward. (Text "Finally, NCITS has approved. faa.dot.gov")

Accepted

Completed in Rev 5.8

Brocade-012

Forward

vi

Delete text

Accepted

Completed in Rev 5.8

Brocade-013 Brocade-014

E E

Forward Forward

vi vi

Change text to "This standard was developed by Task Group T11.3 of the InterNational Committee for Information Technology Standards (INCITS) during 2000-2002. The standards approval process Dates in paragraph 3 incorrect started in 2002. Last paragraph covered by Patent Statement Delete text

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-015 Brocade-016

E E

Forward Forward

vi vi

Missing paragraph Signature (Steve Wilson/Murali Rajagopal)

Add paragraph "This standard was processed and approved for submittal to ANSI by the InterNational Committee for Information Technology Standards (INCITS). Committee approval of the Standard does not necessarily imply that all committee members voted for approval. At the time it approved this standard, NCITS had the following members: (to be filled in by INCITS) Accepted Delete text Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-017

Forward

vi

Need to add T11 list of representatives

Add "Technical Committee T11 on Lower Level Interfaces, which Reviewed this standard, had the following members:", followed by current membership roster. Accepted Add introduction to document. This should contain an overview of what is contained in the document -- some versions contain clause by clause breakdown, as well as how the document fits into the T11 hierarchy.

Completed in Rev 5.8

Brocade-018

Introduction

vii

Introduction is missing

Accepted

Completed in Rev 5.8

Brocade-019

Page Hdr

1-

Header has improper format. Since Figure 1 is referenced by section 1.1, it should follow that section (or some where near the reference, but before the beginning of section 1.2, even if it means leaving some white space at the bottom of pg 1. Figures should appear near their reference in the text. Comma missing between 16 and Annex F in last line of table

Change to "INCITS T11, Project 1466-D Fibre Channel BB-2, Rev <rev>, <date>" Accepted

Completed in Rev 5.8

Brocade-020 Brocade-021

E E

1.1 1.2

1-2 1, 3

Move section 1.2 to start after figure 1. Move Figures 2 & 3 to closely follow their reference

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-022

Table 1

Add comma

Accepted

Completed in Rev 5.8

Brocade-023

2.1, 2.2

4, 5

FC-BB-2 references both FCPH documents ([4],[6],[7]) and the FC-FS specification [14]. Only one or the other should be referenced, since the two sets of documents contain Recommend that the FC-PH contradictory information. references be removed.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-024

2.1, 2.2

4, 5

FC-BB-2 References FC-SW [8], FC-SW-2 [10] and FC-SW3[12]. Since the documents may contain conflicting information, and since each is a full replacement for its predecessor, only FC-SW-3 Delete references to FC-SW and should be referenced. FC-SW-2 Accepted FC-BB-2 References both FCGS-3 and FC-GS-4. Since the documents may contain conflicting information, only one of these documents should be referenced. Delete references to FC-GS-3. Accepted Update reference [17] to version 4, when submitted Accepted Update reference [19] to IETF draft-ietf-ips-security-16.txt, version 16 Sept 2002 Accepted Definition indicates SR applies only to FC-BBW_ATM. Other portions of document indicate that it applies to both SONET and ATM. Need to make document consistent on this point. Note: This is the same definition in FC-BB version of document See comment

Completed in Rev 5.8

Brocade-025 Brocade-026 Brocade-027

E E E

2.1, 2.2 2.2 2.2

4, 5 5 5

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Brocade-028

3.1.11

Accepted- made SR and SFC apply to both ATM and SONET Accepted- Changed to prefixed since prepend is not a defined word in most dictonaries Accepted

Completed in Rev 5.8

Brocade-029 Brocade-030

E E

3.4.4 4.7a

9 17

appended is incorrect term. Switche(s) -- incorrect ()

Change to prepended. Change to Switch(es)

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-031

4.7a

17

This section indicates that class 2, 3, 4 and F Frames are to be exchanged between FCBBW/FC-BB-2_IP switches. This is a requirement of the FC-BB-2/FCIP protocols, but Class 4 support was not specified in the original FC-BB Update all references to Class 2, specification, though it was 3 & F support to include Class 4 also not prohibited. throughout the document. Accepted QoS Bandwidth guarantee considerations -- Listed as None. Shouldn't this be listed as no FC specific -- may choose to apply IP QoS standard functions for the IP backbone. See comment

Completed in Rev 5.8

Brocade-032

4.7c

17

Accepted - added a sentence from the FCIP draft in support of this.

Completed in Rev 5.8

Brocade-033

4.7e

18

This section indicates that SR is specific to FC-BBW_ATM and SFC is specific to FCBBW_SONET. This issue is Need to determine if SR is inconsistent thru-out the specific to ATM or not and make Accepted- made SR and SFC apply to document, and in BB as well. document consistent. both ATM and SONET A Simple flow control (SFC) Change to ...may optionally be can be optionally used. used. The first mention of class 1 not supported is in this section. Alluded to for first time in section 4.7a on pg 17. This should be made clearer. Recommend that in the introduction, explicitly mention that FC-BB-2 only supports classes 2, 3, 4 & F. Class 1 is not supported. (Resolve as part of Brocade-018)

Completed in Rev 5.8

Brocade-034

4.7e

18

Accepted

Completed in Rev 5.8

Brocade-035

4.8.1

18

Accepted - fixed the problem by adding a note in Clause 4 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Paragraph 2 indicates that SR protocol can be used with either ATM or SONET. Paragraph 3 indicates SFC can be used with either ATM or SONET. Yet 4.7e indicates that SR can only be used with ATM and SFC can only be used with SONET.

Proposed resolution

Response

Status

Brocade-036

4.9.1

18

The text needs to be fixed in one way or the other. (Brocade-028, Brocade-033 both indicate ATM specific but other sections of document indicate otherwise.) BB is not consistent on this point, so need to decide which is the appropriate way to go on this issue. Accepted: See Brocade-033

Completed in Rev 5.8

Brocade-037

4.9.1

18

Suggest new paragraph 2, inserted before current paragraph 2, stating "There are two flow control mechanisms defined for Paragraph 3, Sentence 1: the FC-BBW_ATM and FC"The Simple Flow Control BBW_SONET protocols. They (SFC) and mutually are the Selective Retransmission exclusive with the SR (SR) Protocol and the Simple protocol." Do not believe 'with' Flow Control (SFC) protocol. Accepted. The senetence has been is the proper term here. The two are mutually exclusive." deleted and the paragraph reworded. Paragraph 3, Sentence 2: Need to change word "can" to "may". [Note: If Brocade-037 is accepted, this sentence becomes sentence 1 of the paragraph (current sentence 1 deleted).] See comment Since Clause 6 is common to FC-BBW_ATM and FCBBW_SONET, and Clause 5 is specific to ATM, recommend reversing Clauses 5 & 6. See comment Paragraph 3. Indicates FCBBW_ATM encapsulates class 2, 3 & F frames.

Completed in Rev 5.8

Brocade-038

4.9.1

18

Accepted

Completed in Rev 5.8

Brocade-039

Clause 5,6,

20

Accepted - Made a separate clause for the common message formats, a separate clause for the SR Formats and palced the ATM caluse after the SR Procedures clause. Completed in Rev 5.8

Brocade-040

5.1

20

Need to add class 4 to the list.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Paragraph 5: P4 Indicates that SR is optional, and P5 indicates that SFC is also optional -- e.g. neither SFC or SR need to be used. But there is no way to indicate 'neither' in the BBW header. Paragraphs 8 & 9 -- Since LLC/SNAP comes before the BBW_Header, the order of these two paragraphs should be reversed.

Proposed resolution

Response

Status

Brocade-041

5.1

20

Update paragraph 5 to indicate that if neither SR or SFC is to be used, then still need to set BBW_Header to indicate SFC, but that value of PAUSE = 0 means no flow control. Accepted

Completed in Rev 5.8

Brocade-042

5.1

20

See comment

Accepted

Completed in Rev 5.8

Brocade-043

5.1

20

Assuming SFC is deemed applicable to ATM, the entire paragraph should be changed to read as follows: "When SR is Paragraph 8. "When SR is used, the 4 byte BBW_Header is used the message payload followed by the 4-byte consists of a 4 byte SR SR_Header, which are header. SFC Does not require prepended to the BBW Message a header." This statement is Payload. When SFC is used, the incorrect. When SR is used, SR header is not required, so the the 4 byte BBW_Header is 4-byte BBW_Header is followed by the 4-byte prepended directly to the BBW SR_Header, which are Message Payload." The first prepended to the BBW sentence of the paragraph should Message Payload. When SFC be eliminated completely ("A 4is used, the SR header is not byte BBW_Header is required, so the 4-byte appended..."). If SFC is deemed BBW_Header is prepended not applicable to ATM, then the directly to the BBW Message last sentence of the suggested Payload. text should also be eliminated. Accepted- paragraph rewritten Paragraph 9. The words 'appended at' needs to be changed to 'prepended to'.

Completed in Rev 5.8

Brocade-044

5.1

20

See comment

Accepted - replaced by 'prefixed'

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment First paragraph indicates FCBBW_ATM encapsulates class 2, 3 & F frames Bullet 1, Sentence 1: 'When flow control is not used, the BBW appends the two headers to the payload of the FC_BBW message.'

Proposed resolution

Response

Status

Brocade-045

5.2.3

21

Need to add class 4 to the list.

Accepted

Completed in Rev 5.8

Brocade-046

5.2.3

21

Change 'appends' to 'prepends'.

Accepted - paragraph rewritten

Completed in Rev 5.8

Brocade-047 Brocade-048

E E

5.2.3 5.2.3

21 21

Bullet 1: First sentence starts out as "When flow control is not used, the BBW appends", then second sentence indicates "BBW_Header specified the flow control type (SR or SFC). The BBW_Header PAUSE field carries a zero." This is contradictory. Bullet 2: When SFC is used, the BBW appends"

Change to "When flow control is not active, the BBW prepends""BBW_Header specified the flow control type of SFC, with a PAUSE field of zero. This means that no flow control is being requested. In addition, the SR_Header is not included as part of the BBW Accepted - paragraph rewritten message." Change 'appends' to 'prepends'. Change "PAUSE field." to "PAUSE field, and the SR_Header is not included as part of the BBW message." Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-049

5.2.3

21

Bullet 2: No mention of the SR_Header is made. Bullet 3: "When SR Protocol is used, the BBW appends"

Accepted

Completed in Rev 5.8

Brocade-050

5.2.3

21

Change 'appends' to 'prepends'.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-051

5.2.3

21

Bullet 3: "the two headers to the payload of the BBW message". Strictly speaking, according to table 9 (p. 27), these headers are prepended to the SR BBW Message. In fact, a third header, the SR_Header with format SR_I is inserted between the BBW Header and the BBW Message Payload. Clarify text. Sentences 'The SR Protocol makes the transport of FC Frames themselves are not flow controlled." This is description/selling of SR Protocol. It does not belong here. Delete text Change to The BBW Message consists of the SR_Header followed by the BBW Message Payload" or alternatively "The BBW Message consists of the SR_Header followed by the FC Frame"

Accepted

Completed in Rev 5.8

Brocade-052

5.2.3

21-22

Accepted

Completed in Rev 5.8

Brocade-053

5.2.3

22

Bullet 3, last sentence: "A 4byte SR_Header is appended at the beginning of each SRBBW message "

Accepted - paragraph rewritten

Completed in Rev 5.8

Brocade-054

5.2.4

22

Paragraph 3, last sentence: "Finally, a 5-byte ATM Cell Header is appended to each Change 'appended' to SAR PDU to form an ATM cell. 'prepended'. Paragraph 3, sentence 4 -Ambiguous sentence: "A minimum bandwidth allocation is recommended for each FCBBW_ATM VC that is used to avoid starvation

Accepted - used the word prefixed

Completed in Rev 5.8

Brocade-055

5.2.6

22

Change to: "A minimum bandwidth allocation is recommended for each FCBBW_ATM VC that is used, in order to avoid starvation

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Paragraph 4: Split into two sentences. Indicates that ATM guarantees in order delivery. The requirement that the FC frames must be shipped in order received should be listed in a separate sentence. Need consistency between the two bullets on what is happening at each end. The second bullet mentions stripping SOF/EOF. This is misleading -- not really stripping them, but instead decoding them & converting them back to ordered set format

Proposed resolution

Response

Status

Brocade-056

5.2.6

22

Terminate sentence after "ATM Virtual Connection (VC). Remove the word 'and', and capitalize 'Frames' to begin new sentence.

Accepted

Completed in Rev 5.8

Brocade-057

5.2.7

23

Change Bullet 2 to read: "Processing includes tasks such as removal of the LLC/SNAP, BBW_Header, SR_Header (if present) and decoding of the FC-BBW message." Describe the encoding/decoding process elsewhere.

Accepted - simplified the sentence.

Completed in Rev 5.8

Brocade-058

5.2.8

23

Change this to a reference -- SR Indicates that SR Flow control flow control is currently described Accepted - actually there is no need to is "(described in following in clause 7, which is not the place a reference here and removed the clause)" following clause. reference. Completed in Rev 5.8

Brocade-059

5.2.8

23

Assuming SFC is deemed applicable to FC-BB_ATM, need to add more text to describe SFC. For example, if a message with SFC flow control specified and PAUSE set is receive, and then a subsequent message is received with the PAUSE field set to 0, this indicates that the originator may resume sending traffic at normal rates. On the other hand, if a subsequent message is received with the PAUSE field set to a value, the time is reset to the new value. See comment

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-060

25

Add sentence to 6 indicating that this section applies only to FC-BBW_ATM and FCBBW_SONET. To make it clear to the reader that this section does not apply to FCBB-2_IP. May also want to direct reader to next section that applies to IP (e.g. clause 13) See comment Paragraph 1: '...(SNAP) and a 4-byte BBW_Header field." change 'and' to 'followed by' Add diagram showing the format of a BBW message following paragraph 1.

Accepted - added an Applicapabiliy sub caluse at the begin of each clause Completed in Rev 5.8 Accepted - this whole clause has been reorganized

Brocade-061

6.1

25

Completed in Rev 5.8

Brocade-062

6.1

25

See comment

Accepted

Completed in Rev 5.8

Brocade-063

6.1

25

Paragraph 2: " The encoding for LLC indicates ". This is not the only possible encoding Change to " The encoding for for LLC, only the one that BB-2 LLC of 0xAAAA03 required by is requiring. FC-BB-2 indicates" Move tables 3 & 4 to between paragraphs 3 & 4, so that they follow immediately after where they are referenced. See comment Paragraph 4: Move words 'See Table 6' to end of paragraph, since next sentence describe the contents of table 6. See comment Move tables 5 & 6 to follow paragraph 4, so that they immediately follow the text that references them. See comment

Accepted- paragraph rewritten

Completed in Rev 5.8

Brocade-064

6.1

25

Accepted - paragraph rewritten

Completed in Rev 5.8

Brocade-065

6.1

25

Accepted - paragraph rewritten

Completed in Rev 5.8

Brocade-066

6.1

25-26

Accepted - paragraph rewritten

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-067

6.1

25

Brocade-068

6.1

26

"If no flow control is desired, simply set the Flow Control Type to SFC and the PAUSE Add sentence after paragraph field to "0". Byte 3 of the BBW_Header should also be 4 or 5 to the effect that if no flow control is desired, simply set to "0", and the SR_Header must not be included in the use SFC with PAUSE value set to 0. BBW Message Payload." Table 5: PAUSE indicates that it is "Applicable to the SR Change to read "Applicable to the Protocol only" SFC Protocol only"

Accepted. Table 6 now clearly states the applicability. Added some of this text.

Completed in Rev 5.8

Accepted

Completed in Rev 5.8

Brocade-069

6.2

26

Section 6.2 indicates that it covers SFC Message formats. The numbers in the table support that. But the text prefacing table 7 does not indicate that this is specific to SFC, but uses a max size of 2148 for the BBW Message Payload. (consistent with SFC). Table 8 shows the structure of the BBW Message Payload with SFC, which is consistent with the section. But, the definition of the BBW Message Payload is never addressed for SR (clause 6.3, 7). Resolution for this issue is 1) Move table 7 to just after described in Brocade-069paragraph 1 of section 6.1 (see Brocade-072. Brocade-062).

Accepted

Completed in Rev 5.8

Brocade-070

6.2

26

See Brocade-069

2) Add new section before section 6.2 describing the BBW Message Payload, and show include table 8. May also want to add to this new section the Accepted - this whole clause has been optional SR_Header. reorganized

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-071

6.2

26

See Brocade-069

3) Add new section for no flow control, indicating that a BBW message with no flow control consists of a message which follows the formats of table 7 & 8, with no optional SR_Header, Flow Control set to SFC, PAUSE set to 0, and byte 3 of the Accepted in spirit - I have accomplished BBW_Header (do we have a this goal by approriate text in the name for this?) set to 0. rewritten clause Completed in Rev 5.8

Brocade-072

6.2

26

See Brocade-069

4) Change section 6.2 to describe the SFC message formats, indicating that the BBW message consists of message which follows formats of table 7 & 8, with no optional SR_Header, Flow control set to SFC, and PAUSE set to a value, as described in SFC section (which needs to be added). Byte 3 of the BBW_Header needs to be Accepted - clause has be rewritten and set to 0. should no longer be an issue Completed in Rev 5.8

Brocade-073 Brocade-074

E E

6.3.1 6.3.1

27 27

SR-BBW Message Payload is never defined. The SR_I Message format is defined, which I believe is one form of the SR-BBW message. (not SR-BBW Message Payload) See Brocade-069-Brocade-070 Paragraph 2: The SR_Header define Change "define" to "defines" Table 10: Should "MM:" be "MMMMM:" (to match table header) or "MMM MM" To mimic format?

Accepted - clause has be rewritten and should no longer be an issue Completed in Rev 5.8 Accepted Completed in Rev 5.8

Brocade-075

6.3.1

27

See comment

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Table 13: SR_I Description indicates that only class 2, 3 and F frames are supported. Table 13: A note should be added somewhere around Table 13, indicating that the Command/Response bit is indicated in Byte 3 of the BBW_Header. Paragraph 2 indicates that only class 2, 3 and F frames are supported

Proposed resolution

Response

Status

Brocade-076

6.3.1

28

Add Class 4.

Accepted

Completed in Rev 5.8

Brocade-077

6.3.1

28

See comment

Accepted

Completed in Rev 5.8

Brocade-078

6.3.2.1

30

Add Class 4.

Accepted

Completed in Rev 5.8

Brocade-079

6.3.2.1

30

Change Bullets 1 & 2 to something to the effect of replacing the SOF and EOF delimiters with the encoded forms; SOF at the head of the frame and EOF at the end of the frame, where they normally would be found. See comment Bullets 3, 4, 5: 'appending it'. Each of these headers are prepended to the SR-BBW Message Payload, in the order Change 'appending it' to stated. 'prepending it'.

Accepted

Completed in Rev 5.8

Brocade-080

6.3.2.1

30

Accepted - some of these bullets were delted because they were somewhat outside the scope of the SR_I Message Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-081

6.3.2.4

31-32

The description of Selective Reject does not seem to indicate the number of items in the payload. It furthermore does not indicate the maximum number of items that may be listed. While it is unlikely that 1074 N(R) items will be listed, causing the max payload size to be exceeded, a maximum number of items/max payload size should be indicated. See comment

Rejected- there is no maximum number for this specified in the SR protocol. Note that the max payload size of 2152 bytes is not applicable here and hence there is no restriction. (the author of this coment most likely mis took this for the SR_I payload limitations.

Brocade-082

6.3.5

33

Table 16: The first word indicates that it should include "Rejected BBW_Header Field Word 3". The BBW_Header is only 1 word long, unless you add the SR_Header, in which it is two words long. What is supposed to be inserted as the first word of the payload for SR_FRMR? See comment

Accepted- corrected to SR-Header and alsoa dded a Word Column to further make this a little clearer. Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-083

6.3.6.3

35

Clarification needed -- 1) "BBW_Header does not contain one of the defined encodings" What is meant by this? 2) "contains an address field other than the two Domain.Area.PortID of either FC-BBW" -- Where are these 'addresses' found in the message? This is the first mention in the document of a Domain.Area.PortID as related to a BBW Message. Unknown If SR is deemed to be common to both FCBBW_ATM and FCBBW_SONET (see Brocade033, Brocade-036), then this section should follow current section 6, before current section 5. (see Brocade 039)

Accepted

Completed in Rev 5.8

Brocade-084

Clause 7

37

See comment

Accepted

Completed in Rev 5.8

Brocade-085 Brocade-086

E E

7 7.1

37 37

Suggested text: "When SR flow control is the flow control of choice, but there are no SR messages to be sent, the Flow Control bit will be set to byte will Since SR is not for all be set to 0 for those messages. messages, some messages, Though this is depicted as will go out will a Flow Control meaning SFC flow control, when value set to SFC. Need to add used with a PAUSE value of 0, it description either to Clause 6 actually indicates 'no flow control Rejected - SR is sliding window protocol or clause 7 explaining this. required.' and will always be used once selected. Bullet 1: ...all class 2, 3 & F... Add Class 4. Accepted Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-087

7.2.1

38

Table 14 does not illustrate the different FC-BBW Message command and response field formats. It illustrates the SR_I message format. Think this is trying to reference some of the tables 9-13, and the SR_Header instead of the Change to "Section 6.3 describes Accepted : new correct sub clause will BBW_Header. the SR message formats." be referenced. Refers to an address field which includes whether a message is a command or a response. This is not true of BBW/SR. The indicator of command or response is noted in bit 0 of byte 3 of the BBW_Header. The note following this section also does not apply.

Completed in Rev 5.8

Brocade-088

7.2.2

38

Unknown

Accepted

Completed in Rev 5.8

Brocade-089

7.2.5.3

38

This section references a nonexistent section. Should reference section 6.3.6.3. Depending on resolution to comments against section 6.3.6.3 (See Brocade-083), this section may need to be updated/deleted. See comment The maximum CPSC-PDU size is specified in the first paragraph of text to be 2156. The table indicates that it may be a maximum of 2164. [Determined by summing 2152(max FC frame + SR Update text in paragraph 1 to Header)+4(BBW reference a max CPCS-PDU of Header)+8(LLC/SNAP)] 2164.

Accepted - added correct reference

Completed in Rev 5.8

Brocade-090

8.1

50

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-091

8.1

50

Why is note 2 important? If kept, should the note be expanded to indicate that the BBW Message Payload will always be a multiple of 4 bytes in size? See comment Note 3: "The maximum of 2148 bytes Change to "The maximum of 2148 bytes of BBW Message Payload

Accepted - made this part of the text under CPCS-PAD

Completed in Rev 5.8

Brocade-092

8.1

50

Accepted

Completed in Rev 5.8

Brocade-093

8.1

50-51

Last sentence describes figure11. If SFC is deemed to be SONET specific, this sentence and the figure need to be removed See comment Figure 12 is specific to the SR_I message. Does not show the mapping of the SR control messages. This is fine, but may want to make a clarification to this effect. Paragraph 3, sentence 3 -Ambiguous sentence: "A minimum bandwidth allocation is recommended for each VC that is used to avoid starvation Paragraph 2: "This service matches the requirements of FC Classes 2, 3 and F"

Rejected - SFC has been made common to both ATM/SONET

Brocade-094

8.1

52

See comment Change to: "A minimum bandwidth allocation is recommended for each that is used, in order to avoid starvation

Accepted -

Completed in Rev 5.8

Brocade-095

9.3

53

Accepted -

Completed in Rev 5.8

Brocade-096

9.4

54

Add Class 4.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-097

9.6

55

SFC is not mentioned in this section. If supported for FCBBW_ATM, then should be added to this section, indicating that SFC is for flow control only, does not have any retry/recovery mechanisms. If not supported in ATM, then need to remove references to SFC from the ATM sections. See comment Paragraph 5: byte-encoded Class 2, 3 or F Fibre Channel Frames Add Class 4.

Accepted - added a Note to indicate that SFC does not have errory recovery support. Also, modified the last paragraph to indicate the usefulness of the SFC/SR protocol and deleted any other secondary information. Completed in Rev 5.8

Brocade-098

10.1

56

Accepted

Completed in Rev 5.8

Brocade-099

10.1

56

Paragraph 6 states: "The SR protocol makes the transport of FC frames between two FCBBW_SONETs reliable." But, SONET, by definition is reliable, assuming that the SONET network is well engineered. Therefore, SR is not needed to make FCBBW_SONET reliable. Make SR applicable to ATM only. Paragraph 6 indicates that SR is optional, and Paragraph 7 indicates that SFC is also optional -- e.g. neither SFC or SR need to be used. But there is no way to indicate 'neither' in the BBW header. Paragraphs 10 & 11 -- Since LLC/SNAP comes before the BBW_Header, the order of these two paragraphs should be reversed.

Rejected - in light of the earlier comments to make SR applicable to both. However, will add the word "more" reliable so as not to diminish the already reliable nature of SONET

Brocade-100

10.1

56

Update paragraph 7 to indicate that if neither SR or SFC is to be used, then still need to set BBW_Header to indicate SFC, but that value of PAUSE = 0 Accepted- made SR and SFC apply to means no flow control. both ATM and SONET

Completed in Rev 5.8

Brocade-101

10.1

56

See comment

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-102

10.1

56

Assuming SR is deemed applicable to SONET, the entire paragraph should be changed to read as follows: "When SR is used, the 4 byte BBW_Header is Paragraph 10. "When SR is followed by the 4-byte used the message payload SR_Header, which are consists of a 4 byte SR prepended to the BBW Message header. SFC Does not require Payload. When SFC is used, the a header." This statement is SR header is not required, so the incorrect. When SR is used, 4-byte BBW_Header is the 4 byte BBW_Header is prepended directly to the BBW followed by the 4-byte Message Payload." The first SR_Header, which are sentence of the paragraph should prepended to the BBW be eliminated completely ("A 4Message Payload. When SFC byte BBW_Header is is used, the SR header is not appended..."). If SR is deemed required, so the 4-byte not applicable to SONET, then BBW_Header is prepended the first sentence of the Accepted- this whole sub clause has directly to the BBW Message suggested text should also be been rewritten to accommodate this Payload. eliminated. and similar comments. Paragraph 11. The words 'appended at' needs to be changed to 'prepended to'. Move Figure 15 to follow reference in section 10.2.1 First paragraph indicates FCBBW_SONET encapsulates class 2, 3 & F frames Bullet 1, Sentence 1: 'When flow control is not used, the BBW appends the two headers to the payload of the FC_BBW message.'

Completed in Rev 5.8

Brocade-103 Brocade-104

E E

10.1 10.2.1

56 57

See comment See comment

Accepted - consistently using the word prefixed - since prepend is not a proper dictonary word Completed in Rev 5.8 Accepted Completed in Rev 5.8

Brocade-105

10.2.3

58

Need to add class 4 to the list.

Accepted

Completed in Rev 5.8

Brocade-106

10.2.3

58

Change 'appends' to 'prepends'.

Accpeted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-107 Brocade-108

E E

10.2.3 10.2.3

58 58

Bullet 1: First sentence starts out as "When flow control is not used, the BBW appends", then second sentence indicates "BBW_Header specified the flow control type (SR or SFC). The BBW_Header PAUSE field carries a zero." This is contradictory. Bullet 2: When SFC is used, the BBW appends"

Change to "When flow control is not active, the BBW prepends""BBW_Header specified the flow control type of SFC, with a PAUSE field of zero. This means that no flow control is being requested. In addition, the SR_Header is not Accepted- this whole sub clause has included as part of the BBW been rewritten to accommodate this and similar comments. message." Accepted - this whole clause has been Change 'appends' to 'prepends'. reorganized Change "PAUSE field." to "PAUSE field, and the SR_Header is not included as part of the BBW message."

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-109

10.2.3

58

Bullet 2: No mention of the SR_Header is made. Bullet 3: "When SR Protocol is used, the BBW appends" Bullet 3: "the two headers to the payload of the BBW message". Strictly speaking, according to table 9 (p. 27), these headers are prepended to the SR BBW Message. In fact, a third header, the SR_Header with format SR_I is inserted between the BBW Header and the BBW Message Payload.

Accepted - this whole clause has been reorganized Accepted - using the word prefixed throughout

Completed in Rev 5.8

Brocade-110

10.2.3

58

Change 'appends' to 'prepends'.

Completed in Rev 5.8

Brocade-111

10.2.3

58

Assuming SR is deemed applicable to FC-BBW_SONET, Clarify text, otherwise delete paragraph.

Accepted - this whole clause has been reorganized

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-112 Brocade-113

E E

10.2.3 10.2.7

58 59

Sentences 'The SR Protocol makes the transport of FC Frames themselves are not flow controlled." This is selling/selling of SR Protocol. It does not belong here, even if SR is deemed applicable to FC-BBW_SONET. Delete text Bullet 2 begins "Processing Change to "Processing the FCthe SR_I message" BBW_SONET message ... Need consistency between the two bullets on what is happening at each end. The second bullet mentions stripping SOF/EOF. This is misleading -- not really stripping them, but instead decoding them & converting them back to ordered set format

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Brocade-114

10.2.7

59

Change Bullet 2 to read: "Processing includes tasks such as removal of the LLC/SNAP, BBW_Header, SR_Header (if present) and decoding of the FC-BBW message." Describe the encoding/decoding process elsewhere.

Accepted

Completed in Rev 5.8

Brocade-115

10.2.8

59

Need to add more text to describe SFC. For example, if a message with SFC flow control specified and PAUSE set is receive, and then a subsequent message is received with the PAUSE field set to 0, this indicates that the originator may resume sending traffic at normal rates. On the other hand, if a subsequent message is received with the PAUSE field set to a value, the time is reset to the new value. See comment If SR is deemed to be inapplicable to SONET, then need to delete this section

Accepted Rejected - SR is now made applicable to both ATM and SONET

Completed in Rev 5.8

Brocade-116

10.2.9

59

See comment

Company number

tech/e Sec/table/fig dit locator Page

Comment If SR is deemed to be inapplicable to SONET, then delete this figure, otherwise reference somewhere (11.1?) in text. First paragraph on pg 70: "The FC-BB-2_IP Protocol creates Encapsulated FC frames by appending "

Proposed resolution

Response

Status

Brocade-117

11.1

65

See comment

Accepted

Completed in Rev 5.8

Brocade-118

13.1

70

Change "appending" to "prepending"

Accepted - using the word prefixed throughout

Completed in Rev 5.8

Brocade-119

13.2.3.3.5

75

LKA clause cross reference is Correct cross reference, likely to non-existent clause. 13.3.3.2.5.2 SW-3 allocates a range of values for SW_ILSs to be defined by BB-2, but leaves it to BB-2 to define the specific encoded values for SW_ILSs defined by BB-2. BB-2 should add table showing the encoded values of SW_ILSs defined by BB-2 and insure that each SW_ILS has a defined encoded value.

Accepted

Completed in Rev 5.8

Brocade-120

13,15

75-94

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Brocade-121 Brocade-122

T E

13.2.3.3.5.1 13.2.3.4

75 75

The first sentence in 13.2.3.3.5.1 indicates that LKA is an SW_ILS. By definition, an SW_ILS has a frame type 1 (FT-1), with FC-4 Device Data format. VE_Port LKA in BB-2 has been defined as a FT-0, which is a Link Control. This Link Control is running as Class F. LKA as a link_control frame does not address the issue in a multiconnection FCIP Link, since Class F frames are likely restricted to a single connection in the link, and since there is no payload or reply frame, there is no way to convey information about the status of the other links. Thus, the LKA will be able to determine if a single connection (that which is running the class F frames) is up, but not if the other TCP connections is still up. via the FCIP Well-known Port 3225

Proposed resolution Change the current FC-BB-2 text so that the VE_Port LKA is not a Link Control frame but instead an ILS frame. Assign an SW_ILS encoded value for VE_Port LKA and add appropriate request and response format tables to FC-BB2. Change text to indicate that "VE_Port LKA should be transmitted every K_A_TOV when no data or Link_Control frames have been received on a given FCIP_LINK. It may also be transmitted any time no data or Link_Control frames have not been recieved on any single TCP connection in the FCIP_Link. As part of the payload on the transmit, the connection nonce for each TCP connection that is open on the FCIP_Link should be transmitted. The recipient closes any TCP connections that it has open, and that are not listed (establishment of new TCP connections are permitted). In addition, in the Accept, it sends a list of nonces it does not recognize. The recipient, on Accept, closes any TCP connections that it has open and is listed in the Accept payload (establishment of new TCP connections are permitted). If an Accept is not received, then the originator begins FCIP_Link exception handling, which may include recovery attempts or FCIP_Link termination (e.g. shut Change to "via the FCIP Wellknown TCP Port 3225

Response

Status

Accepted-Elizabeth's (02-647v4) LKA proposal will resolve all comments related to LKA Accepted- See Andiamo-003

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-123

13.2.3.5.4

77

Brocade-124

13.3.3.2.5.2

82

Delete reference to FCsec. This term is undefined and will not be used in FC-SP. See comment Accepted Change the current FC-BB-2 text so that the B_Access LKA is not a Link Control frame but instead an ILS frame. Assign an SW_ILS encoded value for B_Access LKA and add appropriate request and response format tables to FC-BB2. Change text to indicate that "B_Access LKA should be transmitted every K_A_TOV when no data or Link_Control frames have been received on a given FCIP_LINK. It may also be The first sentence in transmitted any time no data or 13.3.3.2.5.2 indicates that LKA Link_Control frames have not is an SW_ILS. By definition, been recieved on any single TCP an SW_ILS has a frame type 1 connection in the FCIP_Link. As (FT-1), with FC-4 Device Data part of the payload on the format. B_Access LKA in BB- transmit, the connection nonce 2 has been defined as a FT-0, for each TCP connection that is which is a Link Control. This open on the FCIP_Link should be Link Control is running as transmitted. Class F. LKA as a link_control The recipient closes any TCP frame does not address the connections that it has open, and issue in a multi-connection that are not listed (establishment FCIP Link, since Class F of new TCP connections are frames are likely restricted to a permitted). In addition, in the single connection in the link, Accept, it sends a list of nonces it and since there is no payload does not recognize. The or reply frame, there is no way recipient, on Accept, closes any to convey information about TCP connections that it has open the status of the other links. and is listed in the Accept Thus, the LKA will be able to payload (establishment of new determine if a single TCP connections are permitted). connection (that which is If an Accept is not received, then running the class F frames) is the originator begins FCIP_Link up, but not if the other TCP exception handling, which may connections is still up. include recovery attempts or Accepted - See Brocade-121

Completed in Rev 5.8

Completed in Rev 5.8

Company number Brocade-125

tech/e Sec/table/fig dit locator Page E 15.5.2 98

Comment Bullet 3: FC-FS is reference #14, not 6

Proposed resolution Correct cross reference to FCFS.

Response Accepted

Status Completed in Rev 5.8

Brocade-126

13.3.3.2.5.3

83-84

Transitions P4:P1, P4:P2 and P4:P3 are not defined, but are Add definitions for these state depicted in figure 28. transitions.

Accepted-

Completed in Rev 5.8

Brocade-127

14.2

92

Connection Usage Code: Indicates that the intended usage is still TBD. The description of the ASF SW_ILS is not clear that the ASF payload will be the echo of the FSF received on the previously authenticated connection, as required by FCIP 9.1.2.3. ASF Accept Payload -- why 8 bytes of reserved payload?

Change this paragraph to read "The Connection Usage Code field is to contain Fibre Channel defined information regarding the intended usage of the connection. The FCIP Entity uses the contents of the Connection Usage Flags and the Connection Usage Code fields to locate appropriate QoS settings in the in the shared database of TCP connection information and apply those settings to a newly formed connection. No values have been defined for this field at this time, so this field must be set to 0." Accepted - slight changes in wording. A diagram indicating the relationship between the FSF and the ASF should be added, and the text should be made more explicit to demonstrate this relationship. Accepted- see McDATA-041 Remove 8 bytes reserved payload.

Completed in Rev 5.8

Brocade-128

15.2.2.1

93-94

Completed in Rev 5.8

Brocade-129

15.2.2.1

94

Accepted

Draft Upadted

Brocade-130

A.2

103

The table of FC-BB-2 SOF OS codes needs to be updated to match the codes specified by the IPS FC Frame Encapsulation Document, section 5.3 See comment

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

Brocade-131

A.2

103

The table of FC-BB-2 EOF OS codes needs to be updated to match the codes specified by the IPS FC Frame Encapsulation Document, section 5.3 See comment Since both references in F.2 are references for BB-2 in general, the document references should be used instead of having a separate reference section in the annex. Bookmarks make navigation much much easier, annexes in the TOC would be nice, as would figure numbers in the LOF and table numbers in the LOT. Use FC-BB-2_ATM and FCBB-2_SONET rather than FCBBW_ATM and FCBBW_SONET as used in the rest of the document. Do I have standard compliant FC-BB-2_IP device if the external FC ports of my box are F_Ports instead of E_Ports? If SW-3 supercedes SW-2 why mention SW-2 at all? my box are F_Ports instead of E_Ports? Somewhere an "FC Fabric Entity" needs to be defined. Even if it simply references FCFG.

Accepted

Completed in Rev 5.8

Brocade-132

118120

Delete section F.2 and replace references in section F.1 with corresponding document reference numbers.

Rejected - was told during BB standardization by INCITS that this way the correct way. BB prior to version 4.7 orginally had one one set of references.

CNT-001

TOC/LOF/LO T

Accepted- will include in the next Rev

Completed in Rev 5.8

CNT-002

Figures 4-6

Accepted- I believe the comment meant to say just the opposite: use FCBBW_ATM and FC-BBW_SONET rather than FC-BB-2_ATM and FC-BB2_SONET Completed in Rev 5.8

CNT-003

General

Accepted- Yes- Fig. 23 and 25 updated to reflect this Completed in Rev 5.8

CNT-004

General

Accepted: For second part of the comment see Response to CNT-003

Completed in Rev 5.8

CNT-005

General

Accepted - term no longer used. See also Andiamo- 002

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

CNT-006 CNT-007

E E

1.1 2.3 and Annex F

Reads "FC Over TCP/IP Network mapping emphasizes on the IP Network", should remove the "on", or change "on the" to "an" and reads "The major part of FC-BB-2 is the addition", could read "The major difference between FCBB-2 and FC-BB is the addition" The current rev of the security draft is 16 Would seem less confusing to define FC-BBW_SONET as used throughout the document rather than FCBBW_SONET/SDH SR can be applied with FCBBW_SONET as well Says interaces, should be interfaces. Might want to add EBP and LKA. Might want to add B_Access End of second sentance should read "both of these models." In each clause, the last paragraph, why the caveat? Should explain exactly what is "the BSW function." Note that Class 4 is not always mentioned when the document is talking about the supported classes.

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

CNT-008 CNT-009 CNT-010 CNT-011 CNT-012

E T E E E

3.1.7 3.1.11 3.4.13 3.6.1.1 3.6.1.4

Accepted Accepted- corrected Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

CNT-013

4.1

Accepted

Completed in Rev 5.8

CNT-014 CNT-015

E E

4.2, 4.4 4.4

Accepted See Andiamo-001

Completed in Rev 5.8 Completed in Rev 5.8

CNT-016

4.7, bullet a

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The FC-BB-2 entity has no way of ensuring a frame will traverse the internet within any specified TOV. Computing IP Network transmit time is nontrivial. SR (as well as SFC) may be used with either FCBBW_ATM or FCBBW_SONET interfaces. ISL Flow Control Mode of R_RDY needn't be mandated. Initialization should be described for legacy FC-BB devices as well. Something along the lines of initializing the WAN side before beginning port state initialization on the FC side. Similar to FC-BB-2 devices. Need a space between "functions." and "This" Need a space between "payload." and "The" Document states that "The procedures to be followed on receipt of Set Mode (SR_SM command are specified in 7.2.5.6, Receiving an SR_SREJ response message." Should read "SR_SREJ message" The document talks about total path delay never exceeding R_A_TOV. That should be E_D_TOV.

Proposed resolution

Response

Status

CNT-017

4.7 bullet b

Accepted-First item will state that BB-2 will not admit stale frames into the FC network. Second item will be deleted. Completed in Rev 5.8

CNT-018

4.7 bullet e

Accepted

Completed in Rev 5.8

CNT-019

4.8.1 bullet 2

Accepted

Completed in Rev 5.8

CNT-020 CNT-021 CNT-022

E E E

4.8.2 6.3.1.3 6.3.2.1

Accepted Accepted Accepted

Draft Upadted Completed in Rev 5.8 Completed in Rev 5.8

CNT-023

6.3.2.4

Rejected- this is the sub clause title as written and also the protocl as defined by LAPB Accepted: Path Delay will never exceed 1/2 E_D_TOV.Also see McData035 Completed in Rev 5.8

CNT-024

9.2, 12.1

Company number

tech/e Sec/table/fig dit locator Page

Comment There is no value in mandating a flow control mode between an FC switch and FC-BB-2_IP device. Need a space between "connection." and "The" Its not clear what is needed to fully identify a FCIP Link Originator, Acceptor or an FCIP Link; i.e. all the items or one of the items listed Redundant information as draftietf-ips-fcencapsulation-08.txt states the same in greater detail. Redundant information as draftietf-ips-fcencapsulation-08.txt states the same in greater detail. R_RDY flow control is not the only flow control a B_Port need use. Redundant information as draftietf-ips-fcencapsulation-08.txt states the same in greater detail. And what is intended by "A TBD." Reads "and it associated virtual ISL," should read "its"

Proposed resolution

Response

Status

CNT-025 CNT-026

T E

13.1 13.1

Accepted - verbage indicating that E, VE, and B_Ports operate as defined in FC-SW-3 added in Clause 4. Accepted

Completed in Rev 5.8 Completed in Rev 5.8

CNT-027

13.2.3.3.4

Accepted

Completed in Rev 5.8

CNT-028

13.2.3.5.2.1

Rejected: This brief explanation is beneficial

CNT-029

13.2.3.5.2.2

Rejected: This brief explanation is beneficial

CNT-030

13.3.2

Accepted

Completed in Rev 5.8

CNT-031 CNT-032

E E

14.1.1 14.2.1

Accepted Accepted- see Brocade 127

Completed in Rev 5.8 Completed in Rev 5.8

CNT-033

15.2.2.1

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

CNT-034

15.2.2.3

Does FC-BB-2 care which order authentication is performed? It would make things a little more "backward compatible" if the B_Access authenticates with its peer then the individual switches and would agree with the steps outlined in Clause 15.3.1 Step 8 indicates that link cost determination is described in Clause 13.2.3.2.1 yet that clause doesn't indicate a recipe to determine link cost. 2 items appear to be striked out - is the intent to leave them in the document? This clause talks about switch requirements. How does a switch attached to a B_Port deside which Virtual ISL to use? ISL Flow Control Mode of R_RDY needn't be mandated. References the letter "a" in the text when describing the alpha symbol in Figure B.1 References the letter "b" in the text when describing the beta symbol in figure B.1

Rejected - Overtaken by events

CNT-035

15.3.1, step 8

Accepted: Editor to provide verbage. (e.g. link cost is implementation specific) Accepted: The struck items have been removed

Completed in Rev 5.8

CNT-036

15.3.4.1

Completed in Rev 5.8

CNT-037

15.3.4.2

Accepted - Clause removed. See ENDL177 Completed in Rev 5.8

CNT-038

15.4

Accepted

Completed in Rev 5.8

CNT-039

Annex B.2.1

Accepted- changed to alpha symbol

Completed in Rev 5.8

CNT-040

Annex B.2.2

Accepted- changed to beta symbol

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The phrase "but eliminates the effect of gaps." is inaccurate. 1point CDV is a measurement, a negative value correspond to gaps but cannot eliminate them. The last sentence reads poorly, "This service mostly closely..." rather than "This service most closely..."

Proposed resolution

Response

Status

CNT-041

Annex B.2.2

Accepted- new wording extracted verbatim from ATM Forum's Traffic Management Spec.

Completed in Rev 5.8

CNT-042

Annex B.7

Accepted

Completed in Rev 5.8

CNT-043 CNT-044 CNT-045

T E E

Annex D Annex F Annex F.2

First paragraph reads "parameters.Note", needs a space. The math in D.2 and D.3 are incorrect. They should read. D.2 W = ((155520000 * (10ms + 4ms))/ (8 * 2136 bytes)) = 127 D.3 T1 = ((((127 * (8 * 2136 bytes)) / 155520000) + 5ms) + 5ms) = 24ms + 1ms The table is labeled "D" should that not be "F". Why does an annex need special references?

Accepted Accepted Rejected- ISO Rules

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-001

Global

The ISO style guide for cross references within a standard specifies a format containing just the subclause number (i.e., '15.2.2' not 'Clause 15.2.2'). The sole exception is for clauses that do not include a period in the clause number (i.e., 'clause 5' not '5').

Some cross references already use this format. Global adoption of this practice now, will greatly simplify the transition to ISO standard later.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The the extent possible, this standard would be easier to read if all references took the form 'FCIP [16]' instead of 'IETF standard [16]' or '[16]'. If possible, every table that continues on two or more pages should have a title and column headers on every continuation page. Better still, the titles should indicate somehow that the table is continued. Only one of 'Switch Fabric ILS', 'ILS', or 'SW_ILS' should be used consistently. The last usage appears to be the most common. NCITS [s/b] INCITS National Committee for Information Technology Standards [s/b] InterNational Committee for Information Technology Standards Use either 'Phone: (xxx) xxxxxxx' or '(xxx) xxx-xxxx' not both. Given the notation used for FAX numbers, it would appear that 'Phone: (xxx) xxxxxxx' should be preferred. [two instances] Remove revision history before Public Review.

Proposed resolution

Response

Status

ENDL-002

Global

Accepted

Completed in Rev 5.8

ENDL-003

Global

Accepted

Completed in Rev 5.8

ENDL-004 ENDL-005

E E

Global Global

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-006

Global

Accepted

Completed in Rev 5.8

ENDL-007 ENDL-008

E E

i ii

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The dpANS sent to Public Review should not have change bars.

Proposed resolution

Response

Status

ENDL-009

viii

Accepted

Completed in Rev 5.8

ENDL-010

1.1, 1st p after dashed list, s 2 1

The FC over ATM and SONET Network mappings layer on the ATM and SONET backbone technologies, resulting in the FC-BBW_ATM and FC-BBW_SONET specifications that map directly to physical connections. The FC Over TCP/IP Network mapping layers on the IP Network, resulting in the FCBB _IP specification that maps to a logical connection.

Accepted

Completed in Rev 5.8

ENDL-011 ENDL-012 ENDL-013 ENDL-014 ENDL-015

E E E E E

1st p after dashed list, s 3&s4 1 Clause 2, p 1, s 1 4 3.1.4 3.1.12 3.2.1 6 6 6

[Delete] FC-BB-2 makes use of the previously defined FCBB standard [9] for the FCBBW_ATM and FC BBW_SONET specifications. which [s/b] that which [s/b] that which [s/b] that (two instances) can [s/b] may

The major part of FC-BB-2 is the addition of the FC-BB-2_IP specification which makes use of the IETF specification [16]. [Since FC-BB-2 contains all the text that was present in FC-BB, no discussion of the relationship between the two is necessary. Doubtless, the folks working on the GFP mapping would take umbrage at the description of FCBB-2_IP as the 'major' addition in FC-BB-2.] Accepted Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number ENDL-016 ENDL-017 ENDL-018

tech/e Sec/table/fig dit locator Page E E E 3.2.2 3.2.10 3.2.15 6 7 7

Comment which [s/b] that which [s/b] that which [s/b] that [Delete] Can be used interchangeably. [Contains no useful information.] which [s/b] that can [s/b] may [two instances] 3.2 contains a definition of ATM, 3.3 contains a definition of SONET, so it seems natural that 3.4 should contain definitions of FCIP and TCP/IP. [Do not italicize] Encapsulated FC Frame: which [s/b] that The FCIP Data Engine glossary entry appears to be in the wrong place. Between the 3.4.13 and 3.4.14 would be more appropriate. which [s/b] that

Proposed resolution

Response Accepted Accepted Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-019 ENDL-020 ENDL-021

E E E

3.2.18 3.3.9 3.3.10 s 2

7 9 9

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-022 ENDL-023 ENDL-024

E E E

3.4 3.4.4 3.4.7

9 9 10

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-025 ENDL-026

E E

3.4.7 3.4.13 3.5, 2nd & 3rd dashed entries, s 2 && p 9 & p 10, s 1 3.6.1.1 3.6.1.4

10 10

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-027 ENDL-028 ENDL-029

E E E

11 12 13

which [s/b] that [four instances] FCIP Add ', reference [16]' to end of acronym definition FCIP Add ', reference [16]' to end of acronym definition

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment add acronym IETF Internet Engineering Task Force (www.ietf.org) CSM should be the first acronym listed in this sub clause. Add an acronym entry for RFC. can [s/b] may which [s/b] that

Proposed resolution

Response

Status

ENDL-030

3.6.1.4

13

Accepted

Completed in Rev 5.8

ENDL-031 ENDL-032 ENDL-033 ENDL-034

E E E E

3.6.1.4

13

Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

3.6.1.4 13 4.7, 1st p on pg 18 4.8.1 18

ENDL-035 ENDL-036 ENDL-037

E E E

4.8.1, 2nd dashed entry, s1 18 4.9.1, p 2, s 4 18 4.9.1, p 3, s 2 18

which indicates [s/b] indicating which [s/b] that can [s/b] may

Accepted Accepted Accepted - this paragraph has been rewritten

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-038

4.9.1, 3rd & 8th p after fig 8, s 2 20 4.9.1, 4th p after fig 8, s 1 20 5.2.3, 1st p on pg, s 5 22 5.2.4, p 1, s 2 22 5.2.7, dashed list entries 23 5.2.10, p 1, s 1 23 6.3.1, 1st p after table 9, s1 27

can [s/b] may [two instances]

Accepted - one instance because of paragraph restructing (Believe the intended Clause was 5.1 not 4.9.1) Rejected - second instance - use of the word 'may' is stylistically akward Completed in Rev 5.8 Accepted- But I believe Clause 5.1 was intended Completed in Rev 5.8 Accepted- this paragraph has been written. Completed in Rev 5.8 Accepted Completed in Rev 5.8

ENDL-039 ENDL-040 ENDL-041

E E E

which [s/b] that which indicates [s/b] indicating can [s/b] may which [s/b] that [three instances] which [s/b] that

ENDL-042 ENDL-043

E E

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-044

which [s/b] that

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 6.3.1.1 & 6.3.1.2, p 1, s 2 29 6.3.1.5, p 1, s 2 29 6.3.1.7, p 1, s 2 30 6.3.3, p 1, s 1 32 6.3.5, p 1 & p 6, s 1 33 6.3.5, 1st p after dashed list, s 1 33 6.3.5, Table 16, bit 66 34 6.3.6, p 1, s 1 & s 2 && 6.3.6.2, p 2, s 1&s2 34 6.3.6.2 1st p on pg, s 1 && 6.3.6.2.2, p 2, s 1 && 6.3.6.3, p 1, s 1&s2 35 7.1, p 1, s 2 37 7.1, 1st p on pg, s 1 38 7.2.4.1, p 2, s 2 39 7.2.5, p 1, s 1 41 7.2.6.1, p 1, s 1 46 7.2.7.2, p 2, s 2 47

Comment

Proposed resolution

Response

Status

ENDL-045 ENDL-046 ENDL-047 ENDL-048 ENDL-049

E E E E E

which [s/b] that [two instances] can [s/b] may can [s/b] may which [s/b] that which [s/b] that [two instances]

Accepted Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-050 ENDL-051

E E

must [s/b] shall must [s/b] shall

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-052

which [s/b] that [four instances]

Accepted

Completed in Rev 5.8

ENDL-053 ENDL-054 ENDL-055 ENDL-056 ENDL-057 ENDL-058 ENDL-059

E E E E E E E

which [s/b] that [four instances] which [s/b] that which [s/b] that can [s/b] may which [s/b] that which [s/b] that can [s/b] is able to

Accepted Accepted Accepted Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number ENDL-060

tech/e Sec/table/fig dit locator Page 7.2.7.3, 3rd p E on pg, s 3 48 7.2.8.2, p 2, s 1 && p 4 s 1 48

Comment must [s/b] shall

Proposed resolution

Response Accepted

Status Completed in Rev 5.8

ENDL-061

must [s/b] shall [two instances] According to the ISO style guide notes are not allowed to contain requirements. Either remove the 'shall' from this note, or change the note to part of the body text.

Accepted

Completed in Rev 5.8

ENDL-062

7.2.8.2, p 3 (note), s 1 8.1, p 3, s 2 && p 5, s 3 && note 3 after table 17, s 2 9.3, p 1, s 1 9.4, p 2, s 1 9.6, p 1, s 3

48

Accepted

Completed in Rev 5.8

ENDL-063 ENDL-064 ENDL-065 ENDL-066

E E E E

50 53 54 55

can [s/b] may [three instances] can [s/b] may which [s/b] that which [s/b] that

Accepted Accepted Accepted Accepted Accepted- this paragraph has been rewritten.

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-067

10.1, 3rd p after fig 14, s 2 56 10.1, 4th p after fig 14, s 1 10.1, 1st p on pg, s 2 10.2.3, last p, s5 10.2.3, last p, s6

can [s/b] may

Completed in Rev 5.8

ENDL-068 ENDL-069 ENDL-070 ENDL-071

E E E E

56 57 58 58

which [s/b] that can [s/b] is able to be which [s/b] that which indicates [s/b] indicating

Accepted Accepted- substituted can with may Accepted - paragraph rewritten Accepted Accepted- substituted with may to be consistent with an earlier and similar comment from ENDL

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-072

10.2.4, p 1, s 2 58

can [s/b] is able to be

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 10.2.4, p 4, s 1 && last p on pg s 1 58 10.2.7, both dashed entries, s 1 59 10.2.10, p 1, s1 60 11.1, p 3, s 4 61 11.1, last p on pg, s 1 62 11.1, 1st p after dashed list, s 1 63 11.2, 1st p on pg, s 3 & s 4 67 11.2, 1st p on pg, s 3 67

Comment

Proposed resolution

Response

Status

ENDL-073

which [s/b] that [two instances]

Accepted

Completed in Rev 5.8

ENDL-074 ENDL-075 ENDL-076 ENDL-077

E E E E

which [s/b] that [two instances] which [s/b] that can [s/b] may must [s/b] shall [three instances]

Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-078

must [s/b] shall

Accepted

Completed in Rev 5.8

ENDL-079 ENDL-080

E E

must [s/b] shall [two instances] which [s/b] that All the other fonts used in this standard are san-serif. The font in this figure is a serif font. The smallest font size allowed in an ANSI standard is 9 pt. The following text is in a 7 pt font: '(Section, Line, Path)'. B-Port or E_Ports [s/b] B_Ports or E_Ports

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-081

11.2, Figure 20

67

Accepted

Completed in Rev 5.8

ENDL-082 ENDL-083

E E

11.2, Table 21

67

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

13.1, p 2, s 1 69 13.1, 3rd p after fig 22, s 1 69 13.1, 3rd p after fig 22, s 2 69

ENDL-084

which is [s/b] that are

Accepted

Completed in Rev 5.8

ENDL-085

can [s/b] may

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 13.1, 4th p after fig 22 (note), s 1 13.1, 4th p after fig 22 (note), s 1

Comment a FC-BB-2_IP [s/b] an FC-BB2_IP one FC-BB-2_IP [s/b] one FCBB-2_IP device The usage of bold text for 'Encapsulated FC Frames' makes no sense and should be removed. retaining their SOF/EOF identities. [s/b] retaining their SOF/EOF identities in the Encapsulated FC Frame. a similar way [s/b] the same way Control.The TCP [s/b] Control. The TCP All other instances of 'Encapsulated FC Frames' are italicized. Why not this one? which [s/b] that clauses [s/b] sub clauses [see 13.2.3.1] which [s/b] that The font size of 'For more details on ... SW-3 [12].' appears to be smaller than the rest of the paragraph. VE_Port' and 'FCIP_LEP' should not be bold, like the second occurrence of 'FCIP_LEP'. FC/FCIP Identifier' should not be bold.

Proposed resolution

Response

Status

ENDL-086

69

Accepted

Completed in Rev 5.8

ENDL-087

69

Accepted

Completed in Rev 5.8

ENDL-088

13.1, 1st p on pg, s 1 70

Accepted

Completed in Rev 5.8

ENDL-089 ENDL-090

E E

13.1, 1st p on pg, s 2 70 13.1, 2nd p on pg, s 2 70 13.1, 4th p on pg, s 1 & s2

Accepted Accepted Accepted - added some clarity to this sentence and previous sentence.

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-091

70

Completed in Rev 5.8

ENDL-092 ENDL-093

E E

13.1, 4th p on pg, s 3 70 13.2.1, p 1, s 1 70 13.2.1, 1st p after list, s 1 70 13.2.3.1, p 1, s1 70

Accepted- Italics removed in all cases Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-094 ENDL-095

E E

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-096

13.2.3.1, 1st list entry, s 2 72

Accepted

Completed in Rev 5.8

ENDL-097 ENDL-098

E E

13.2.3.3.2, p 1, s 2 73 13.2.3.3.2, p 5, s 1 73

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The following should be deleted: 'with the help of a Forwarding Table (see also Clause 13.2.3.2).' An FCIP Entity has no knowledge whatsoever about the Forwarding Table. main components [s/b] interface points If I understand the italics usage rules, in 'A FCIP Link Originator or FCIP Link Acceptor is fully identified by:' the following should be italicized 'FCIP Link Originator' and 'FCIP Link Acceptor' but 'fully identified' should not be italicized.

Proposed resolution

Response

Status

ENDL-099

13.2.3.3.3, p 1, s 1 73 13.2.3.3.3, 1st p on pg, s 1 74

Accepted

Completed in Rev 5.8

ENDL-100

Accepted

Completed in Rev 5.8

ENDL-101

13.2.3.3.4, 2nd p after dashed list, s 3 74 13.2.3.3.4, 1st p after 1st a,b,c list, s 1 74 13.2.3.3.4, 1st p after 1st a,b,c list, s 1 74

Accepted

Completed in Rev 5.8

ENDL-102

Do not italicize 'uniquely'. we only require [s/b] the following are required [at a minimum get rid of the 'we'] SW_ILS [s/b] SW_ILSs [three instances] [See 16.5 for the precedent for making acronyms plural in this way.] The smallest font point size allowed in an ANSI standard is 9 pt. The text 'Virtual ISL:Class...Class 2/3/4 Frame' is in an 8 pt font.

Accepted

Completed in Rev 5.8

ENDL-103

Accepted

Completed in Rev 5.8

ENDL-104

13.2.3.3.5, p 1, s 1 & s 2 74

Accepted

Completed in Rev 5.8

ENDL-105

13.2.3.3.5, Fig 25

75

Accepted

Completed in Rev 5.8

Company number ENDL-106 ENDL-107

tech/e Sec/table/fig dit locator Page 13.2.3.3.5.1, E p 2, s 2 75 13.2.3.4, p 1, E s2 75 13.2.3.5.2.1, p 1, s 3 76

Comment connection is down [s/b] connection is inoperative ISL/FCIP Link [s/b] Virtual ISL/FCIP Link the entering FC Frame [s/b] an entering Class F FC Frame [Add the following new sentence at the end of the paragraph] 'If no synchronized time stamp value is available to accompany an entering Class 2, 3, or 4 FC Frame, the frame should not be delivered to the FCIP_DE.

Proposed resolution

Response Accepted Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8

ENDL-108

Accepted

Completed in Rev 5.8

ENDL-109

13.2.3.5.2.1

76

Accepted

Completed in Rev 5.8

ENDL-110

13.2.3.5.4, 3rd p after a,b list 13.2.3.5.4, 3rd p after a,b list, s 3 13.3.1, p 1, s 1 13.3.1, p 2 (note), s 1 13.3.3.1, p 1, s 1

77

[Insert the following between the 1st and 2nd sentences] 'This mechanism works in concert with the FC-SP Virtual ISL authentication mechanism, transacting the Class F requests and responses over a previously authenticated TCP connection.' other FCIP security mechanisms [s/b] other FC-SP and FCIP security mechanisms which [s/b] that Delete the following: 'tends to be brief and' which [s/b] that 'B_Access' should not be bold. [see similar wording in 13.2.3.3.1.]

Accepted- See McData-041

Completed in Rev 5.8

ENDL-111 ENDL-112 ENDL-113 ENDL-114

T E E E

77 78 78 78

Accepted- See McData-041 Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-115

13.3.3.2.1, p 1, s 1 78

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 13.3.3.2.2, p 1, s 2 & s 3 & s4&s5 13.3.3.2.3, p 1, s 2 13.3.3.2.4, p 3, s 1 13.3.3.2.5, p 1, s 1

Comment

Proposed resolution

Response

Status

ENDL-116 ENDL-117 ENDL-118 ENDL-119

E E E E

78 79 80 80

B_Access [s/b] B_Access portal [four instances] B_Access [s/b] B_Access portal 'fully identified' should not be italicized. B_Access' [s/b] B_Access portals SW_ILS [s/b] SW_ILSs [two instances] [See 16.5 for the precedent for making acronyms plural in this way.] The smallest font point size allowed in an ANSI standard is 9 pt. The text 'B_Access Virtual ISL:Class...Class 2/3/4 Frame' is in an 8 pt font. B_Access [s/b] B_Access portal [two instances] EBP exchange parameters must be completed [s/b] EBP SW_ILS shall be completed ['EBP exchange parameters' is redundant phrasing and 'must' is a dirty word in standards.]

Accepted- one more instance also corrected Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-120

13.3.3.2.5, p 1, s 1 & s 2 80

Accepted

Completed in Rev 5.8

ENDL-121

13.3.3.2.5, Fig 27

80

Accepted

Completed in Rev 5.8

ENDL-122

13.3.3.2.5.1, p 1, s 1 80

Accepted

Completed in Rev 5.8

ENDL-123

13.3.3.2.5.1, p 1, s 2 80 13.3.3.2.5.1, 1st p after table 21, s 1 81 13.3.3.2.5.1, 5th p after table 21, s 1 81

Accepted

Completed in Rev 5.8

ENDL-124

name [s/b] world wide name

Accepted- but replaced it with Port_Name

Completed in Rev 5.8

ENDL-125

contains [s/b] shall contain

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Add a definition for the Responder Interconnect_Port_Name field.

Proposed resolution

Response

Status

ENDL-126

13.3.3.2.5.1 82 13.3.3.2.5.2, p 1, s 1 82 13.3.3.2.5.2, p 2, s 2 82

Accepted

Completed in Rev 5.8

ENDL-127

'LKA' should not be bold. connection is down [s/b] connection is inoperative [Insert the following between the subclause heading and fig 28] 'The B_Access initialization state machine is shown in Fig. 28.' Is this blank page necessary? which consists [s/b] consisting

Accepted

Completed in Rev 5.8

ENDL-128

Accepted

Completed in Rev 5.8

ENDL-129 ENDL-130 ENDL-131

E E E

13.3.3.2.5.3 83 13.4 86

Accepted Accepted - removed blank page Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

14.1, p 1, s 2 87

ENDL-132

14.1, Table 25

87

Table 25 should show that 4byte words are used in the FC frame encapsulation to contain the SOF and EOF representations. Essentially, 14.1.2 should be incorporated in table 25 with a note that the structure of the 4-byte SOF and EOF values can be found in [18]. [Move the note to the beginning of the subclause and change it to read] 'NOTE If there is any discrepancy between statements in this sub clause and FC Encapsulation [18] then FC Encapsulation prevails.'

Accepted

Completed in Rev 5.8

ENDL-133

14.1.1

87

Accepted- Note discarded but text retained. see also HP-045

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment for FCIP Protocol assigned by IETF [18] is value 1.[s/b] for the FCIP Protocol is value 1.[The FCIP Protocol# value is assigned by IANA not by IETF [18], but attempting to describe that here is not useful.]

Proposed resolution

Response

Status

ENDL-134

14.1.1, 2nd p after table 26, s 1

88

Accepted

Completed in Rev 5.8

ENDL-135

14.1.1, Table 27 and the p's that describe it 88

Since this standard concerns itself with only the FCIP encapsulation, there are no 'protocol specific' fields in the FCIP header. The contents of table 27 should be embedded in table 26 and the field descriptions should remove all mention of 'protocol specific'. Table 28 should be removed because the description is so inadequate as to be confusing. [Change the description of the Flags bits to] 'For FC-BB-2_IP Protocol the Flags bits shall be zero.' [Remove table 29 and the CRCV description.] 14.1.2 should be incorporated in table 25.

Accepted

Completed in Rev 5.8

ENDL-136

14.1.1, Table 28

89

Accepted

Completed in Rev 5.8

ENDL-137 ENDL-138

E E

14.1.1, 1st p after table 28, table 29, & CRCV description 89 14.1.2 90

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The note after table 30 is incorrect in that tables A.3 and A.4 define byte representations for SOF and EOF codes. No mention is made of how the 4-byte SOF/EOF codes used by FCIP are formed. Replace the note with a reference to [18]. 208 [s/b] 48 [Move the note to the beginning of the subclause and change it to read] 'NOTE If there is any discrepancy between statements in this sub clause and FCIP [16] then FCIP prevails.'

Proposed resolution

Response

Status

ENDL-139 ENDL-140

E E

14.1.2, Note 90 14.2, Table 31, row 2 90

Accepted. Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-141

14.2.1

90

Accepted- Note discarded but text retained. See HP-046

Completed in Rev 5.8

ENDL-142

14.2.1, 1st & 2nd p after table 32 91 14.2.1, 2nd p after table 32

Do not italicize 'generates'. [two instances] FSF [s/b] FCIP Special Frame [like the preceding paragraph]

Accepted

Completed in Rev 5.8

ENDL-143

91

Accepted

Completed in Rev 5.8

ENDL-144

14.2.1, Connection Usage Flags description 91

The bit names in the connection usage flags and the description of those bits should be reworded in terms of Class 2, Class 3, Class 4, and Class F. FCIP cannot use those terms because they cannot be defined in the IETF context. However, this standard already uses the terms liberally. So, use them here.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment [Change the description of the Connection Usage Code field to] 'The Connection Usage Code field shall contain zero.' Add a description of how the K_A_TOV field is used by VE_Port and by B_Access portals. The first row in Fig 30 gives the misimpression that FC Frames include a 4-byte encoded SOF and EOF. The fact that the SOF and EOF are 4-byte encoded should be moved to the second row of the table (i.e., to the FC Encapsulation row). it associated Virtual ISL [s/b] its associated Virtual ISL [replace] 'The FC Entity shall respond ... for the first TCP connection.'[with] If FC-SP authentication procedures are not being applied to the Virtual ISL, the FC Entity shall respond to the FCIP Entity indicating that the new TCP connection is authentic. added. [s/b] added using a TCP connection in the Virtual ISL that has already been authenticated.

Proposed resolution

Response

Status

ENDL-145

14.2.1, 2nd p on pg

92

Accepted: See Brocade-127

Completed in Rev 5.8

ENDL-146

14.2.1, 4th p on pg 92

Accepted - See Brocade -121

Completed in Rev 5.8

ENDL-147

14.3, Fig 30 92 15.2.2.1, p 1, s 1

Accepted

Completed in Rev 5.8

ENDL-148

93

Accepted

Completed in Rev 5.8

ENDL-149

15.2.2.1, starting at 1st p after 1st a,b,c list 93

Accepted

Completed in Rev 5.8

ENDL-150

15.2.2.1, 1st p on pg 94

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

ENDL-151

15.2.2.2, p 1, s 3

94

These two VE_Ports and their parent entities are authenticated using the mechanisms described in FCSP [15]. [s/b] For the first TCP connection in a Virtual ISL, these two VE_Ports and their parent entities are authenticated using the mechanisms described in FCSP [15]. Subsequent TCP connections in the Virtual ISL are authenticated using the mechanism described in 15.2.2.1. B_Access authentication starts with ... [s/b] For the first TCP connection in a B_Access Virtual_ISL B_Access authentication starts with ... Virtual_ISL [s/b] Virtual ISL

Accepted- superseded by Ralph's latest comments Completed in Rev 5.8

ENDL-152 ENDL-153

T E

15.2.2.3, p 2, s 1 15.2.2.3, p 2, s 2

95 95

Accepted- superseded by Ralph's latest comments Completed in Rev 5.8 Accepted Completed in Rev 5.8

ENDL-154 ENDL-155

T E

15.2.2.3 15.3.1, p 2 (note), s 1

95 95

[Insert the following as a new paragraph at the end of the subclause] 'Subsequent TCP connections in the B_Access Virtual ISL are authenticated using the mechanism described in 15.2.2.1.' LEPs [s/b] FCIP_LEPs [LEP is not a defined acronym] that are involved are operational [s/b] that are involved become operational

Accepted- superseded by Ralph's latest comments Completed in Rev 5.8 Accepted Completed in Rev 5.8

ENDL-156

15.3.1, p 4, s 1 95

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Use either 'Virtual ISL/FCIP Link' or '(Virtual ISL/FCIP) Link', preferably the former, but not both. can [s/b] may [or] can [s/b] is able to mechanisms [s/b] mechanisms and management controls

Proposed resolution

Response

Status

ENDL-157 ENDL-158

E E

15.3.1, p 4, s 1&s2 95 15.3.1, list entry 2, s 1 95 15.3.1, list entry 3, s 2

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-159

95

Accepted

Completed in Rev 5.8

ENDL-160 ENDL-161 ENDL-162 ENDL-163 ENDL-164

T E E E E

15.3.1, list entry 3, s 3 15.3.1, list entry 7, s 1 15.3.1, list entry 7, s 2 15.3.1, list entry 8, s 1 15.3.1, list entry 9, s 2

95 95 95 96 96

Authentication of connections other than the first is accomplished by authenticating each new TCP connection against a previously authenticated TCP connection using the mechanisms described in 15.2.2.1.[s/b] If the first TCP connection has been authenticated using the FC-SP mechanisms, the authentication of subsequent connections is accomplished by authenticating each new TCP connection against a previously authenticated TCP connection using the mechanisms described in 15.2.2.1. E-port or B-Port [s/b] E_port or B_Port E-Port [s/b] E_Port ISL [s/b] Virtual ISL for each ISL or Link [s/b] for each Virtual ISL or FCIP Link

Accepted- See McData-041 Accepted Accepted Rejected- sentence changed per Denver meeting Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 15.3.1, list entry 9, s 3 & s4 96 15.3.1, list entry 10, s 2 96

Comment for each connection [s/b] for each Virtual ISL or FCIP Link [two instances] See Annex F. [s/b] See FCIP [16].

Proposed resolution

Response

Status

ENDL-165

Accepted - small change made it Virtual ISL/FCIP Link Completed in Rev 5.8

ENDL-166

Accepted

Completed in Rev 5.8

ENDL-167 ENDL-168

E E

15.3.2, list entry 1 15.3.2, list entry 2, s 1

96 96

The sending FC Entity must deliver FC Frames to the correct FCIP Entity FCIP_LEP FCIP_DE (in the correct FC/FCIP Entity). [s/b] The sending FC Entity shall deliver FC Frames to the correct FCIP_LEP FCIP_DE in the correct FCIP Entity.[As written, the statement is redundant.] must [s/b] shall

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-169

15.3.2, list entry 2, s 2

96

[Delete] 'If a synchronized time value is not available, a value of zero shall accompany the FC Frame.' [The statement is not accurate and the reference to 13.2.3.4.2.1 in the previous sentence covers the issues.]

Accepted

Completed in Rev 5.8

ENDL-170

15.3.2, list entry 3, s 2

96

However, before forwarding ... for discarding the FC Frame. [s/b] However, before forwarding a FC Frame the FC Entity shall verify the end-toend transit time as described in 13.2.3.5.2.2. [The description of the transit checking rules should appear in only one place.]

Accepted

Completed in Rev 5.8

Company number ENDL-171

tech/e Sec/table/fig dit locator Page 15.3.4.1, p E 1, s 1 96

Comment a certain number [s/b] a number However, while assigning FC flows ... that FCIP_DE.[s/b] However, once a FC flow is assigned to a FCIP_DE within the Virtual ISL, all FC frames of that flow shall be sent on that same FCIP_DE. delete strikeout text These rules [s/b] This rule [Also, this sentence should not be in a new paragraph.] This paragraph should be a normal document paragraph not a numbered list entry paragraph. the FC Entity shall authenticate the source of the TCP connect request before use of the new TCP connection is allowed[s/b] the procedures described in 15.2.2.1 shall be followed Subclause 15.3.4.2 should be removed because it addresses a topic that belongs in the FCSW-n standard. [Add the following to the end of the note] 'If there is any discrepancy between statements in this sub clause and FCIP [16] then FCIP prevails.'

Proposed resolution

Response Accepted

Status Completed in Rev 5.8

ENDL-172 ENDL-173

E E

15.3.4.1, p 1, last s in p and list entry 1 96 15.3.4.1, 1,2,3 list 96 15.3.4.1, last p on pg 96

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-174

Accepted

Completed in Rev 5.8

ENDL-175

15.3.4.1, 1st p on pg 97

Accepted

Completed in Rev 5.8

ENDL-176

15.3.4.1, 1st p on pg 97

Accepted

Completed in Rev 5.8

ENDL-177

15.3.4.2

97

Accepted - Clause will be removed.

Completed in Rev 5.8

ENDL-178

15.5.1, p 3 (note)

97

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The number list paragraphs in this clause should be made regular text paragraphs (i.e., not numbered or lettered). The last paragraph of 15.5.2 (describing the use of the HLO SW_ILS) should be deleted or replaced with a discussion of the LKA SW_ILS. Add a new clause between 15.6.1.1 and 15.6.1.2. Title 'FCBB-2_IP Timers' In the new clause place a discussion of K_A_TOV. The font size and line spacing in this clause should be made to match that used throughout other parts of the standard. can [s/b] may can [s/b] are able to MUST [s/b] shall DOES NOT [s/b] shall not will receive [s/b] receives must [s/b] shall [two instances] [Delete] 'In both cases,' [It is not at all clear what cases comprise the 'both cases'.] Use either 'See Section' or just 'Section' but not both.

Proposed resolution

Response

Status

ENDL-179

15.5.2

98

Accepted

Completed in Rev 5.8

ENDL-180

15.5.2, p 6

98

Accepted-

Completed in Rev 5.8

ENDL-181

15.6.1

98

Accepted- Added text in Clasue 15.7.1 and LKA (see Brocade 121)

Completed in Rev 5.8

ENDL-182 ENDL-183 ENDL-184 ENDL-185 ENDL-186 ENDL-187 ENDL-188

E E E E E E E

15.6.1.2 16.2.3, p 1, s 1 16.2.3, p 2, s 3 16.2.3, p 2, s 4 16.3.1, p 1, s 4 16.3.5, p 1, s 1 16.3.5, p 1, s 2&s3

98 99 99 99 100 100 100

Accepted Accepted Accepted Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-189 ENDL-190

E E

16.3.5, p 2, s 1 100 16.3.5, dashed list 100

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 16.5, p 1, s 2 & s 3 && p 2, s1 101 16.5, p 1, s2 101

Comment DEs [s/b] FCIP_DEs [Three instances] [There is no defined acronym DE.] LEPs [s/b] FCIP_LEPs Virtual ISL[s/b] Virtual ISL as long as the first TCP connection is authenticated using the mechanisms described in 15.2.2 and FC-SP must [s/b] shall can [s/b] may [three instances] which [s/b] that

Proposed resolution

Response

Status

ENDL-191 ENDL-192

E E

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-193 ENDL-194 ENDL-195 ENDL-196

T E E E

16.7, p 2, s 1 101 A.1, p 5, s 2 102 B.1, p 5, s 1 &s5 104 B.1, p 5, s 7 104 B.2, 1st p after note, s 1

Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-197

105

must [s/b] needs to be

Accepted

Completed in Rev 5.8

ENDL-198 ENDL-199 ENDL-200

E E E

B.2, 1st p after note, s 4 105 B.2.1, p 3, s 2 105 B.2.2, p 1, s 2 105 B.2.2, 1st note on , s 1 106 B.3.3, 1st & 2nd p after dashed list, s 1 && 4th p after list, s 2 && B.4, 2nd note, s 1 108 B.4, p 5, s 1 108

can [s/b] may can [s/b] may [two instances] which [s/b] that which [s/b] that [and] can [s/b] may

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-201

Accepted

Completed in Rev 5.8

ENDL-202 ENDL-203

E E

can [s/b] may [four instances] must [s/b] are required to

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number ENDL-204

tech/e Sec/table/fig dit locator Page B.4.1, p 1, s E 1 108 B.4.2, p 1, s 4 && p 2, s 2 && p 3, last s && p 5 s 2 109 B.4.2, p 2, s 4 109 B.5, p 2, s 1 110 B.5, p 3, s 1 110 B.5, p 3, s 2 110 B.5, p 4, s 2 110 B.6, p 1, s 1 && p 2, s 3 && p 7, s 1 110 B.7, p 1, s 2 &s4 111 C.1, 2nd note, s 1 && C.1.1, p 3 (note), s 2 112 C.1.1, p 1, s 2 112 C.1.3.2, p 3, s2&s7 113 E.1, 1st p after Fig E.1, s3 116 E.1, last p on pg 116

Comment which [s/b] that

Proposed resolution

Response Accepted

Status Completed in Rev 5.8

ENDL-205 ENDL-206 ENDL-207 ENDL-208 ENDL-209 ENDL-210

E E E E E E

can [s/b] may [five instances] which [s/b] that can both support [s/b] both are capable of supporting can all support [s/b] all are capable of supporting can support [s/b] is capable of supporting must [s/b] are required to

Accepted Accepted Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-211 ENDL-212

E E

can [s/b] may [three instances] can [s/b] may [and] which [s/b] that

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

ENDL-213 ENDL-214 ENDL-215

E E E

which [s/b] that [two instances] can [s/b] may can [s/b] may [two instances]

Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

ENDL-216 ENDL-217

E E

must [s/b] shall can be processed [s/b] it is capable of processing

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

ENDL-218

F.1

118

Section F.1 should be removed. The reason the section exists is to include a table that does nothing more than duplicate information provided in FCIP. There is no new or useful information in section F.1. If section F.1 is not removed, the title of the table should be changed from 'D.1' to 'F.1' and the section references in the left column of the table should be changed from FCIP section references to FC-BB-2 section references. The references in this clause already appear in 2.2 and 2.3 respectively, and should not be repeated here. remove the word that from the phrase " indicates that the reword the phrase to now read clearance " "...indicates the clearance..." replace the word "has" with "had" reword phrase "...BBW_Header consist of 9..." so that it now reads:" .. Link which had been previously" to "...(No Suggestions) and consists of 9..."

Accepted - Annex Removed

Completed in Rev 5.8

ENDL-219

F.2 6.3.2.5 para 2, line 2

120

Accepted -See ENDL-218

Completed in Rev 5.8

HP-001

32

Accepted

Completed in Rev 5.8

HP-002

6.3.3, para 1, line 1 32 6.3.5, para 3, line 1

Accepted

Completed in Rev 5.8

HP-003

33

Accepted - corrected

Completed in Rev 5.8

HP-004

7.1, para 2, line 5 37

insert the word "the" at the end to read " and it only sees the of the line FC-BBW.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

HP-005

7.1 cont, para 5, line 2 &4 38

those parts of the paragraph should now read: " The SR protocol specifies the maximum number (k) of outstanding reword the first sentence to messages at any given time. K remove the reference to is a system parameter (32767) and place it at the end available. Typically, the value of of the last sentence in the k is expected to be far below the paragraph maximum number of 32767. Accepted the reference to tables 8-14 seems out of date when one looks at the tables change the phrase "upon receipt of the SR-SM command correctly" remove the word "below" at the end of the sentence. like the comment, remove the word "below" at the end of the sentence. In both cases the word appears at the end of a long clause title. replace the word "filed" with "field" to now read ".. Information field of this message.." perhaps an exact reference would be more appropriate such Accepted - the reference has been as tables 7, 8, 9, 13, 14, 15, and made to a caluse which covers these 16 tables. change the phrase "upon correctly receiving the SR-SM command, ..."

Completed in Rev 5.8

HP-006

7.2.1, para 1, line 1

38

Completed in Rev 5.8

HP-007

7.2.4.5 (cont), para 3 lines 1&2 39 word just before 7.2.4.4

Accepted

Completed in Rev 5.8

HP-008

40

Accepted

Completed in Rev 5.8

HP-009

7.2.4.4.2, para 2, line 5 40 7.2.5.2, para 1, line 3 42

Accepted

Completed in Rev 5.8

HP-010

Accepted

Completed in Rev 5.8

HP-011

7.2.5.6.1

43

there is an extra blank line between para 5 and 6 (counting para a), b) and c) as para 2, 3, and 4 respectively remove the extra line

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment re-word the first part of the first sentence: "If the Timer T1 runs out waiting for the acknowledgement from the remote FC-BBW for an SR_I message transmitted, the FCBBW " there appears to be a typo in the phrase " link is reset an if no outstanding" there appears to be some missing words in the phrase "latency delay components due Queuing time at the FCBBW"

Proposed resolution suggested rewording: "If the Timer T1 runs out while waiting for the acknowledgement from the remote FC-BBW of an SR_I message, transmitted, the FCBBW " it should read "" link is reset and if no outstanding"

Response

Status

HP-012

7.2.5.9, para 1, line 1 & 2 45 7.2.7.2, para 4, last line 47

Accepted- but changed to "If the Timer T1 runs out while waiting for the acknowledgement of an SR_I message from the remote FC-BBW, the FC-BBW " Completed in Rev 5.8

HP-013

Accepted

Completed in Rev 5.8

HP-014

9.2, para 1, lines 3&4

53

should read: "..the latency delays due to the queuing time at the FCBBW.." Accepted

Completed in Rev 5.8

HP-015

9.6, para 1, line 1

55

remove the word "media" from the phrase: "ATM networks are to read: "ATM networks are lossy lossy media and " and " Accepted suggest rewording the phrase "..requests the remote BBW to: "..requests the remote BBW from transmitting traffic.." stop transmitting traffic.." is there a missing letter in the phrase "...control and an error should read "...control and any recovery functions." error recovery functions." two sentence fragments ".using HDLC according to RFC 1662.The fields are transmitted from left to right" at the end of the line there is the phrase: "Unnumbered Frames in this use are" should it read ".using HDLC according to RFC 1662, the contents of the fields are transmitted from left to right"

Completed in Rev 5.8

HP-016

10.2.8, para 1, line 1

59

Accepted

Completed in Rev 5.8

HP-017

10.2.9, para 2, line 2 59

Accepted- made function singular since the plural is implied. Completed in Rev 5.8

HP-018

11.1, para 2, line 1&2 11.1(cont), control:, line 2

61

Accepted

Completed in Rev 5.8

HP-019

HP-020

several

should it read ".. "Unnumbered Frames in this use are" please convert all references to on pages 66 & 67, the x^43+1 x43 on this page to x^43 or scrambler is shown with a convert all other references to 66 & 67 superscript as x43 +1 use the superscript. 62

Accepted

Completed in Rev 5.8

Accepted

Completed in Rev 5.8

Company number HP-021

tech/e Sec/table/fig dit locator Page 12.1, para E 1, lines 3&4 68 12.2, para 1, note line 3 68

Comment see comment HP 14

Proposed resolution see comment HP 14

Response Accepted

Status Completed in Rev 5.8

HP-022

in the last line of the note there reword to "remains and is appears to be a word missing addressed "

Accepted

Completed in Rev 5.8

HP-023

13.1, para 3, lines 1-3

69

I believe that the real concern is that either all of the FCIP devices used to build a multiple AR SAN as written the text: "If Inter-AR must either all support Inter-AR E_port FC Switch connectivity connectivity or none of those architecture (Fig 6) is same FCIP devices can support supported, then every FC-BB- Inter-AR connectivity. I would 2_IP device is required to suggest the following re-wording: support the BSW function" If Inter-AR E_port FC Switch appears to imply that if any connectivity architecture (Fig 6) is vendor provides inter-AR supported by any FCIP in the connectivity support, then all SAN, then every FC-BB-2_IP vendors MUST also provide device in that SAN is required to that support. support the BSW function". Accepted: See Andiamo-001

Completed in Rev 5.8

HP-024 HP-025

E E

13.1-cont, para 4 lines 3&4, or 4&3 lines before 13.2 13.2.1, line 7

70 70

The word ONLY is the sentence implies too much uniqueness, and should be placed in context the word describes should not be plural correct

suggest rewording as follows: "The only delivery order guarantee provided by TCP, with respect to the FCIP protocol, is the correctly ordered delivery of Encapsulated FC frames within a single TCP connection." Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

HP-026

13.2.1, line 7

70

the text within clause 13 that describe the interfaces are subclauses, not clauses as in 14, revised text (including HP 25) 15, and 16 which describe should read: " The following subother parts of the FC-BB-2_IP clauses describe each of the protocol above interfaces" Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment Because Fig 23 includes the two network interfaces as well as the listed parts before this paragraph.

Proposed resolution

Response

Status

HP-027

13.2.3.1, para 1, line 2 70

reword the last sentence of the paragraph as follows: "In addition to the two network interfaces, it consists of the following major components" Accepted

Completed in Rev 5.8

HP-028

13.2.3.2, para 1, line 3 71

remove the word "and" and insert the word "the" in the phrase "the FC SE switches and route the data arriving" correct this is related to comment HP 23, and needs the same conditional requirement statement

Accepted

Completed in Rev 5.8

HP-029

13.2.3.2, para 1, last sentence

71

reword to "If the FCIP device is used in a multi-AR SAN, then the FC SE is required to support the BSW function of the Inter-AR architecture." Accepted: See Andiamo-001

Completed in Rev 5.8

HP-030

figure 23

71

the label "FCIP LINK" which identifies the links between the FCIP_LEP DE's and the TCP ports is misleading in that the FCIP LINK extends from the FCIP_LEP DE through the TCP ports, through the IP A better label is "One end of the stack and into the IP network. FCIP LINK" insert the word "is" into the phrase "...IP Routing and is between" at the end of the sentence there is the phrase "Clause 13.2.4"

Accepted Accepted - used the word "occur" instead of "is"

Completed in Rev 5.8

HP-031

13.2.3.2.1 para 1, line 1 72 13.2.3.2.2, last line

correct it should read "sub-Clause 13.2.4"

Completed in Rev 5.8

HP-032

72

Rejected: See ENDL- 001

Completed in Rev 5.8

HP-033

figure 24

73

The actual start point for the FCIP link is the bottom of the FCIP entity and not the bottom Accepted- actually removed this of the IP layer as shown (see correct by making the arrow pass because it did not add value to this also comment HP 30. through the TCP and IP layers. diagram.

Completed in Rev 5.8

HP-034

global

there are several references to search for and reword all 73 and clauses 13.2.3.x.x.x that references from clause 13.x.y.z.. others should be sub-clauses to sub-clause 13.x.y.z Rejected: See ENDL- 001

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

HP-035

13.2.3.3.4, bullet 2, FCIP Link 74

change to: "Conceptually, communication between two LEPs is similar to the at the end of the bullet, the last communication between two sentence should be reworded instances of a TCP application"

Accepted

Completed in Rev 5.8

HP-036

13.2.3.5.1

76

An additional sentence is needed to conform to the requirements of 16.3.5

append with the following: "The PMM is also the intended component for any miscellaneous housekeeping functions such as maintenance of event logs (see sub-clause 16.3.5)" Accepted

Completed in Rev 5.8

HP-037

13.2.3.5.4 (cont), para 2

77

near the end of the paragraph there is a reference to the FCIP RFC without the RFC and [16} tags. correct to read FCIP RFC [16] reword that sentence to: "An FC/FCIP entity pair has a potential security vulnerability where interactions may not be fully secured by either the FCSP or FCIP security features."

Accepted

Completed in Rev 5.8

HP-038

13.2.3.5.4 (cont), para 3

77

The first sentence now reads like the FC-SP or FCIP security features might attack the interaction of an FC/FCIP entity pair the last sentence states :"These ports interface with the CSM" but there is no mention of how that interface is performed.

Accepted - also had to slightly modified the following sentence to accommodate this change. Completed in Rev 5.8

HP-039

13.2.4 last sentence on page

77

add another phrase to the sentence so that it reads: "These ports interface with the CSM through an implementation defined interface." Accepted reword the last sentence of the paragraph as follows: "In addition to the two network interfaces, it consists of the following major components" Accepted correct it Accepted

Completed in Rev 5.8

HP-040 HP-041

E E

13.3.3.1, para 1, last sentence 13.3.3.2.1, line 1

78 78

see comment HP 27 unbold the term B_access

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

HP-042 HP-043

E E

13.2.3.3.1 and 13.3.3.2.1 figure 26

The same phrase is on both pages, that being: "The FC/FCIP Entity pair interface with the CSM and the PMM", but there is no indication of 72 & 78 how. 79 see comment HP 30

reword both to now say: "The FC/FCIP Entity pair communicate with the CSM and the PMM through an implementation defined interface." Accepted see comment HP 30 Accepted

Completed in Rev 5.8 Completed in Rev 5.8

HP-044

figure 29

85

In the figure the virtual ISL is shown as a heavy solid line and exists only between the VE_port and the FCIP LEP or the B_Access and the FCIP LEP. In truth the heavy line represents the last segment of the virtual ISL that exists between two VE_ports or two B_access. Similarly the FCIP link exists between two FCIP_LEP and not just between the TCP/IP stacks.

fix the legend as follows: rename the Virtual ISL to the First/Last segment of the Virtual ISL; rename the TCP can to the FCIP LINK; and rename the FCIP LINK to TCP Conn. An option would be to make the TCP portion of the FCIP link a dashed line, and so indicate in the legend Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

HP-045

14.1.1

87

Append the following text after the first sentence: "The information for this table and the field definitions has been extracted from the FC Encapsulation RFC [18]. Should there be a conflict between this table or the following field definitions and that of the RFC, then the RFC has precedence. The content of words one and if some text where inserted two in table 26 is defined by table after the heading describing 27 and the field definitions that the FC IP encapsulation RFC follow table 27. Similarly tables [18] then the first part of figure 28 and 29 provide specific details 26 would be pushed to the on the use of the FC next page making reading of encapsulation protocol flags" the figure on one page instead The note can then be deleted as Accepted- see ENDL- 133 forsome of of spanning two well. the text.

Completed in Rev 5.8

HP-046

14.2.1

90

see comment HP 45

Append the following text after the first sentence: "The information for this table and the field definitions has been extracted from the FCIP RFC [16]. Should there be a conflict between this table or the following field definitions and that of the RFC, then the RFC has precedence." The note can then Accepted- see ENDL- 141 for some of be deleted as well. the text.

Completed in Rev 5.8

HP-047

14.3

92

the title of the section should be renamed as there are multiple encapsulations within Rename to 14.3 TCP/IP this specification Encapsulation of an FC Frame

Accepted- with small change - TCP/IP Encapsulation [of an FC Frame is incorrect it should be Encapsulated FC Frame. Since this makes it rather repetious, I decided to keep it simple] Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

HP-048

15.2

93

append the following after the only sentence: "There are no specific procedures defined for continuing comment HP 36, a housekeeping functions such as brief statement is needed here maintenance of error or event as well logs"

Accepted

Completed in Rev 5.8

HP-049

15.3.1 step 7 95

there is no process for when the FC-BB-2_IP device is running in B-port mode

append the following to the end of the step: "When operating in BPort mode, it is expected that the external E-ports will exchange FSPF messages over the virtual ISL which result in the link becoming operational" Accepted

Completed in Rev 5.8

HP-050

15.3.1-(cont), step 8 96

sub-clause 13.2.3.2.1 does not contain any text on determining link cost, only an indirect reference to the FSPF Change the reference to using algorithms the procedures in FSPF there is no mention if the FSPF link cost is the same or different across multiple Virtual ISLs or FCIP links. They should be the same, given that they share a common IP infrastructure and link cost is determined by speed not distance

Accepted- Text to say link costs are implementation defined.

Completed in Rev 5.8

HP-051

15.3.1-(cont) step 9 96

append the following to the end of the step: "The establishment of additional ISLs or Links does not require the re-running of the FSPF cost algorithms as in step 8."

Rejected+G503-The FSPF behavior should be the same regardless as to whether the Fabric has FC-BB-2 links.

HP-052

15.3.3

96

there is no mention of the need for notification back to the FC fabric

append the following sentence to the end of the paragraph: "When the FCIP link is disconnected, notification of the disconnection shall be accomplished according to the procedures in 16.3.5" Accepted

Completed in Rev 5.8

HP-053

15.3.4.1 last word of para 1 96

the word is "rules" as it should not be plural as there is only one rule left after the edits drop the "s" in rules.

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page 15.3.4.1 first three words of para 2 96 15.3.4.1(cont), step 4 97

Comment

Proposed resolution

Response

Status

HP-054

the words "These rules are" should not be plural as there is only one rule left after the edits change to "This rule is" step/rule 4 at the top of the page appears to left over drop the step number and make it into a full paragraph

Accepted

Completed in Rev 5.8

HP-055

Accepted

Completed in Rev 5.8

HP-056

15.5.1, para 2

97

since the rules following the second paragraph are summarized from [16], a statement is needed that [16] overrides this specification (see comments HP 45 & 46) another case of clause x.y.z that should be a sub-clause

Rewrite the single sentence in the paragraph to: "Fibre Channel frame errors and the expected resolution of the errors are described in [16] and summarized below. Should there be a conflict between the summarization and [16], then the behavior in [16] shall take precedence" Accepted- see ENDL- 178

Completed in Rev 5.8

HP-057

16.1

99

correct it

Accepted

Completed in Rev 5.8

HP-058

16.2.2 16.3.1, para 1

99

rewrite the last sentence as follows:" then Encapsulated FC both the loss of TCP segments Frames will be discarded. Either and the discarding of FC case will cause the effective Accpeted- slight change - used shall frames will reduce throughput throughput to be reduced" instead of will. there is a reference to clause 15.6 item 4, that item does not exist correct pointer The second paragraph has the one sentence about the FC entity testing for failed TCP connections. There needs to be a corresponding action should a failed connection be identified

Completed in Rev 5.8

HP-059

100

Accepted

Completed in Rev 5.8

HP-060

16.3.1, para 2

100

d the following text after the one sentence: "Should such a test detect a failed TCP connection, the FC entity shall disconnect that connection following the procedures in sub-clause 15.3.3." Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment corrupted frames if detected by the sender should be discarded and not sent over the IP network. Corrupted frames detected by the receiver have already been sent over the IP network the word "Any" is capitalized and it should not be the word "requirements" should be singular and not plural

Proposed resolution

Response

Status

HP-061

16.3.4 para 1, line 2 100 3rd bullet from top B.2.1, para 3, line 1 B.3 2 line 107

reword to state: "Corrupted frames detected prior to transmission into the IP network, are discarded and not sent over the IP network" Accepted

Completed in Rev 5.8

HP-062

101

correct

Accepted

Completed in Rev 5.8

HP-063

105

correct it

Accepted

Completed in Rev 5.8

HP-064

the word "is" is missing between the words connection and established. insert it

Accepted

Completed in Rev 5.8

HP-065 HP-066

E E

F.1 line 1 and Note 118 Table D.1 118

both refer to data in [1] which should be [16]. In addition the note duplicates whats in the first sentence and should be eliminate the note and chage the eliminated reference from [1] to [16] Accepted: See ENDL-218 it should be table F.1 not D.1 change reference Accepted: See ENDL-218

Completed in Rev 5.8 Completed in Rev 5.8

HP-067

section F.2

120

not needed If no ACK is received within the E_D_TOV the VE_Port may retry LKA. If a VE_Port satisfied itself that the connection is down, the VE_Port shall restart FCIP Link Initialization (see [16]) Concern: Insufficient definition of "satisfied itself that the connection is down."

remove it and any refeerences to it as in F.1 line 1 (Comment HP 65) Accepted: See ENDL-218

Completed in Rev 5.8

INRANGE-001

Section 13.2.3.3.5.1 paragraph 2

Accepted - See Brocade-121

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

INRANGE-002

Section 13.2.3.5.2.2 paragraph 2:

If the network transit time is large enough to jeopardize meeting any Fibre Channel timeout requirements, the frame shall be discarded. Concern: The above language could lead to interoperability problems with different interpretations of maximum transit times given a single set of Fiber Channel Timeouts.

Accepted-See Akara -010

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

INRANGE-003

Section 13.3.3.5.2 paragraph 2 Section 13.3.3.5.3 figure 28

If no ACK is received within RTT_TOV (see B_Access Initialization State Machine) the B_Access may retry LKA. If a B_Access has satisfied itself that the connection is down, the B_Access shall transition to Exchange B_Port Parameters state. Concern:The RTT_TOV is calculated based on a single round-trip acknowledgement to an EBP during B_Port link initialization. The RTT_TOV is used during B_Port ISL operation to time-protect receipt of an ACK to to an LKA Switch Fabric ILS. There is insufficient detail in the draft to understand when a B_Access should consider a connection down, and a concern that it is based on a round-trip time that is measured only once on a link that may reasonably have a highly variable round-trip delay characteristic. State P5 not shown in diagram, but referenced in diagram and text.

Accepted-See Brocade 121 Accepted-P5 is removed and references to RTT removed.

Completed in Rev 5.8

INRANGE-004

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

INRANGE-005 McDATA-001 E

Section 4.7 section b 1.1

Latency delay guarantees and timeout value considerations: 1) FC-BB-2 shall ensure that the inherent latency between two FC-BB-2 devices is bounded and included well within the Fabric?s R_A_TOV?s value. FC-BB2_IP shall compute the IP Network transit time to comply with the above. Concern: The draft does not allow implementors in a multi-vendor configuration to determine the appropriate maximum transit times between FC-BB-2 devices in order to allow switches to deterministically guarantee E_D_TOV and R_A_TOV within the fabric. "FC Over TCP/IP" should be 1 "over" for consistency Uncapitlaize "Over" If the dashed lines in the figure are supposed to show the boundaries of FC-BB-2_IP, then it should not enclose Move the dashed line above the 2 FCIP(IETF). FCIP Enitity. 10 GFC did not map native FC over SONET. See Appendix A Remove the reference to this 2 of 10 GFC. mapping. "to support the Fibre Channel over TCP/IP" should be "to support Fibre Channel over 3 TCP/IP." FC-SP and FC-SW-3 should 12 be added.

Accepted: Section b addressed see CNT 17.See Akara - 010 Accepted

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-002

Figure 1

Accepted

Completed in Rev 5.8

McDATA-003

Note

Accepted

Completed in Rev 5.8

McDATA-004 McDATA-005

E E

third sentence top list

correct it. Add FC-SP and FC-SW-3.

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-006 McDATA-007

E E

4.7(a) 4.8.2

"Class 2, 3, 4, and Fshall be encapsulatedand transmitted..." implies that all classes must be supported. Class 4 is not widely 17 supported. Delete "Class 2, 3, 4 and F" Need a space or period after 18 "etc." add a space This sentence is incorrect "The procedures for Encapsulated FC Frame formatting, mapping and encapsulation are described in Clause 14 and the FC-BB-2_IP Protocol procedures are described in 69 Clause 15." "Functional Model" should not 70 be capitalized. FC-BB-2_IP Protocol 70 Interface" is wrong "E_Port FC Network Interface" is odd. Fibre Channel has a fabric, not a network. Does Network Interface have a special meaning that would require it to be captialized? This applies to the IP Network 70 Interface too. WWPN is not a defined term. WWPN should be Interconnect_Port_Name or 70 Port_Name. "Encapsulated FC Frames" 70 should not be bold. Should be "The procedures for formatting, mapping and encapsulating Encapsulated FC Frames are described in Clause 14. The FC-BB-2_IP Protocol procedures are described in Clause 15." The text should not be bold either. uncapitalize it Change to "FC-BB-2_IP Interface"

Accepted - text modifed per email Accepted

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-008 McDATA-009 McDATA-010

E E E 13.2.1 13.2.1

13.1

Accepted - slightly modified next sentence to match the tense in the previous sentences. Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

McDATA-011

13.2.1 and 13.2.3.1

Change to "E_Port interface" and "IP interface". "FC Network" should be replaced with "FC Fabric" throughout the document. AcceptedChange to Interconnect_Port_Name or Port_Name throughout the document.

Completed in Rev 5.8

McDATA-012

13.2.2

Accepted- changed to E_Port_Name

Completed in Rev 5.8

McDATA-013

first sentence

Unbold it and all other bold text in the document not in titles. Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment "All Encapsulated FC Frames are transparently transported (tunneled) over the IP network." is a misleading sentence because of the 70 implications of tunneled.

Proposed resolution

Response

Status

McDATA-014

last sentence of first pragraph

Remove "(tunneled)" from the sentence.

Accepted

Completed in Rev 5.8

McDATA-015

13.2.3.2

Remove the text regarding the function of the switching element. This clause states the function The switch is uniquely identified for the switching element, by the Switch_Name, not the FC 71 which is defined in FC-SW-3. SE. Accepted

Completed in Rev 5.8

McDATA-016

13.2.3.2

Change to "If the Inter-AR Last sentence of the first architecture is supported, the FC Accepted- References to FSPFparagraph is a false SE must support the BSW Backbone entities will be removed. See 71 requirement for BSW support. function." Andiamo-001 Completed in Rev 5.8

McDATA-017

13.2.3.2

"The FC-BB-2_IP Protocol forwards Encapsulated FC Frames across the IP Network. The forwarding function requires a knowledge of the FC routes and a Forwarding Table." is out of place. Isn't this section discussing the FC SE? What 71 is trying to be said?

Should it be"The IP Network Interface forwards Encapsulated FC Frames across the IP Network. The FC SE requires a knowledge of the FC routes and a Forwarding Table."? If this is not correct, FC-BB-2_IP Protocol needs to be defined. Accepted- this clause has been deleted. Completed in Rev 5.8

McDATA-018

Figure 23 and 25.

I thought we decided to change one of the E_Ports on the top to F_Port. We could Change one of the E_Ports on also remove the FC SW on the the top to F_Port and eliminate 71 right hand side of Fig 25. the middle FC SW from Fig 25. In the last sentence, it says "the selection of which FCIP_DE to use is decided by policies and not by FC Routing Change to "the selection of the or the VE_Port." Which FCIP_DE to use is decided by 72 policies? policies in the FCIP Entity".

Accepted

Completed in Rev 5.8

McDATA-019

13.2.3.2.1

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution Since it is "outside the scope" and it is implementation dependent, it might be better to remove description of "Forwarding Table" or change "IP addresses" to "TCP/IP Connections".

Response

Status

McDATA-020

13.2.3.2.3

Simple D_ID to IP addresses mapping is not sufficient. It needs to map to the TCP/IP 72 connection. The sentence "The term Virtual in VE_Port indicates the use of a non Fibre Channel link connecting the E_Ports" means connecting real E_Ports using non Fibre 73 Channel link.

Rejected- IP addresses are also used at the TCP layer which is passed as a psuedo header but snipped off at the IP layer

McDATA-021

13.2.3.3.2

Suggest changing "connecting the E_Ports" to "to provide E_Port capability between two FC-BB-2_IP devices." or change "E_Ports" to "VE_Ports". Accepted Accepted- added "The FC/FCIP Identifier uses the Name_Identifier format"

Completed in Rev 5.8

McDATA-022

13.2.3.3.2

FC/FCIP Identifier is an 8-byte Identifier, but there is no Suggest using WWN format for 73 description on its format. the 8-byte Identifier. Change: To uniquely identify a FCIP Link, we only require: "we" is used in the clause.The to: To uniquely identify a FCIP use of second person narrative Link, the following fields are 74 should be removed. required: " pair via one or more virtual constructs." The following text describes the virtual constructs. By this definition, always more than "one" virtual construct is involved (VISL Change " via one or more and FCIP Link) between two virtual constructs" to "via virtual 74 FC/FCIP Entity pairs. constructs". Should be VE_Port_Name and we should define the VE_Port_Name as the Port Name of the VE_Port.

Completed in Rev 5.8

McDATA-023

13.2.3.3.4

Accepted- except used the word items instead of fields as suggested to match the previous set. Completed in Rev 5.8

McDATA-024

13.2.3.3.4

Accepted

Completed in Rev 5.8

McDATA-025

b)

74 VE_Port WWPN is incorrect

Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-026

c)

74 Fabric Entity is not defined

Change Fabric Entity throughout the document to Interconnect device or add a definition to the definitions section describing Accepted- Fabric Entity replaced by Fabric Entity. Switch_Name wherever applicable

Completed in Rev 5.8

McDATA-027 McDATA-028

T T

13.2.3.3.4 a)

The identity of the FCIP Link is identified by the Fabric Entity WWN of the Originator and the Acceptor and the FC/FCIP Entity Identifier of the FCIP Link Originator. Why do we have the asymmetry? We should add the FCIP Link Acceptor to the identity of the FCIP Link. What is the purpose of allowing more than one FCIP Link between FC/FCIP Entities? We could only recall that it addressed the ships passing in the night problem. If this is the case, then we should say that the TCP request with the lowest FC/FCIP Identifier should originate the link and the other 74 request should be rejected. Fabric Entity WWN is incorrect 74 or undefined.

Change "Although, more than one FCIP Link may be formed between a pair of FC-BB2_IP devices, a typical configuration may only consist of a single FCIP Link." to "Although, more than one FCIP Link may be formed between a pair of FC-BB2_IP devices, only a single FCIP Link can be betwen any two FCIP Entities." Add an item d) that says : "d) The 8-byte FC/FCIP Entity Identifier of the FCIP Link Acceptor." Correct Figure 29 to exclude the possibility. This is explained on the last slide of 02555v0. Should be "Switch Name" throughout the document

Rejected-First Comment and change in Fig. 29 request. Accepted - to add VE Port or B Access as an additional identifier for FCIP link. Completed in Rev 5.8 Accepted Completed in Rev 5.8

McDATA-029

13.2.3.3.5.1

K_A_TOV default value and resolution are not specified. This should be less than E_D_TOV and have a default 75 value of 1 second.

Accepted - Default value is 1/2 E_D_TOV; Table 21, Table 22 , will be changed to include resolution (in millseconds). Also define resolution for Suggest adding a default value of E_D_TOV and R_A_TOV were 1 second and say the rsolution of appropriate. Default value defined in K_A_TOV is in milliseconds. LKA. See Brocade 121

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment The standard should specify when a VE_Port should declare the connection is 75 down. Why is K_A_TOV exchanged in EBP? FSF already 75 exchanges this value.

Proposed resolution We need to specify a dead interval for the VE_Ports. We suggest using the Dead_Interval specified in SW-2.

Response

Status

McDATA-030

13.2.3.3.5.1

Completed in Rev 5.8

McDATA-031

13.2.3.3.5.1

Remove K_A_TOV from EBP.

Reject - Possibly requred for other BB devices.

McDATA-032

13.2.3.5.2.2

Last two sentences have 76 grammar errors.

Change "Any frame other than a Class F" doesn't need "an" and "A Class F frame" instead of "an F Class frame". Accepted

Completed in Rev 5.8

McDATA-033

13.2.3.5.2

Add a note that says: "Note While it is strongly recommended that time services be synchronized throughout the While time synchronization fabric, some implementations between FC Entities is may choose not to use time recommended, there are services. Unsynchronized fabrics environments, like campuses, may receive frames that would that may not want to use time be discarded if time stamps were services since propagation used. Old frames could cause 76 delay is minimal. error recovery problems." Rejected

McDATA-034

13.2.3.5.2, last paragraph

"It is assumed" is an ambiguous sentence and the synchronization needs to be 76 clarified.

The text should say that "The administrator shall synchronize the time services on both sides of the FCIP link regardless of which time service is used. another time service can be used to synchronize each time service. The drift in time synchronization between the two FC Entities must Accepted - Entire paragraph will be be less than 1% of DLY_LIM." removed

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-035

13.2.3.5.2.2

The delay limit timeout value (DLY_LIM) should be defined for the transit time. If the network transit time exceeds DLY_LIM, then the frame should be discarded. A default value of DLY_LIM should be less than ED_TOV 76 and we propose 1 second. "Any Frame other than an Class F frame whose time stamp is zero shall be discarded." is too stringent. Some implementations may not want to discard these 76 frames.

Change text to: "If the network transit time exceeds DLY_LIM, the frame shall be discarded." The description of DLY_LIM was discussed extensively in FCIP and text could be obtained from there. Set the default value of DLY_LIM to 1 second and it shall be less than E_D_TOV.

Accepted - FTT-FCIP Transit Time will be ued to compare with 1/2 E_D_TOV. Text for FCIP Transit Time (FTT) is defined as the total transit time of an Encapuslated Fibre Channel frame in the IP network. The FCIP Transit Time is calculated by subtracting the time stamp value in the arriving Encapsulated FC Frame from the synchronized time in the FCIP Entity. Completed in Rev 5.8

McDATA-036

13.2.3.5.2.2

Delete the sentence or add "unless time services are not used."

Accepted-Editor will add the following sentence to 4.7b and in this sub calsue. "FC-BB-2 shall allow class F encapsulated frames to be transmitted with a zero timestamp value". Completed in Rev 5.8

McDATA-037

third paragraph

"However, no such authentication is defined for the second, third, etc. TCP connections, since to Fibre Channel they all appear to be part of an already authenticated Virtual ISL. The mechanism for authenticating the second, third, etc. TCP connections is described in Clause 15.2.2." These statements contradict each 77 other. Delete the first sentence. An FCIP Link should be able to have multiple IP addresses. Since the FCIP Link may have multiple TCP Ports, it should be able to have multiple IP addresses. This is supported in FCIP in clause 10.2 and 77 10.3.2.

Accepted - see McData 041

Completed in Rev 5.8

McDATA-038

13.2.4

Add the following text: "d) Multiple IP Addresses per FCIP Link - A single IP address per TCP Port."

Accepted

Completed in Rev 5.8

Company number McDATA-039

tech/e Sec/table/fig dit locator Page E b)

Comment IKE isn't an authentication 77 technique

Proposed resolution change "IKE authentication" to"IKE for key exchange"

Response Rejected

Status

McDATA-040

first a)

This standard will have to wait How can we reference FC-SP until FC-SP specifies more when it does not even have a information about Fibre Channel draft and it doesn't mention FC- level security before FC-BB-2 77 BB-2? can be approved.

Rejected- Reference to SP is OK

McDATA-041

first b)

Specify the difference between FC-SP TCP connection authentication discussed in This says that Security for 15.2.2.2 and 15.2.2.3 and FCIP TCP connections is defined in security discussed in 13.2.3.5.4. FCIP and then goes on to This may require changing figure define TCP connection 1 to show where FC-SP fits in authentication. The with the overall architecture. We boundaries between FCIP, FC- can't figure out the relationships SP and FC-BB-2 need to be between each standard and how defined in more detail. to implement an interoperable Particularly, how does FCIP product from how it is specified 77 relate to FC-BB-2? now. Accepted What is FC Route-to-IP Route mapping? Is this the FC address to VE_Port or B_Access routing? Are IP addresses involved. Domain 78 ID or Destination ID? Please explain. The Switch_Name is not Include a Switch_Name in the 79 included in the Figure. diagram.

Completed in Rev 5.8

McDATA-042 McDATA-043

E T

second to last bullet Figure 26

Accepted- deleted text Accepted

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-044

First bullet

"the selection of which State "policies in the FCIP Entity" FCIP_DE to use is decided by or some more information about 79 policies." What policies? what policy. Accepted- "described in 15.4.5" replace Fabric Entity WWN and B_Access WWPN to Switch_Name and Interconnect_Port_Name. Specify 1 second as the default time for K_A_TOV.

Completed in Rev 5.8

McDATA-045 McDATA-046

E T

a), b) 13.3.3.2.5.1

These use non-standard 80 names No time is specified for 81 K_A_TOV.

Accepted- changed to B_Access_Name and Fabric_Name Completed in Rev 5.8 Accepted - See Brocade -121 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-047

13.3.3.2.5.2

RTT_TOV is not defined. In E_Port case, E_D_TOV is 82 used. What is the difference? Can E_D_TOV be used instead. "If a B_Access has satisfied itself that the connection is down, the B_Access shall transition to Exchange B_Port Parameters State". If the whole FCIP Link is dead, the switch should start from FCIP 82 Link Initialization. Should be FC/FCIP_Entity_3 85 instead of FC/FCIP_Entity_2. 86 Delete blank page

Accepted - See Brocade -121

McDATA-048 McDATA-049 McDATA-050

T E E

13.3.3.2.5.2 c) blank page

Change "Exchange B_Port Accepted- This comment is covered by Parameters State" to "FCIP Link a common LKA description. See Initialization". Brocade -121 Completed in Rev 5.8 Change 2 to 3. Delete blank page Accepted Accepted Completed in Rev 5.8 Completed in Rev 5.8

McDATA-051

hex values

The document needs to follow the ANSI convention for specifying hex numbers which is: Numbers or upper case letters in quotes immediately proceeded by the word hex (e.g. hex FA23) are 90 hexadecimal values. Change all Hex value notations. Why do we specify FSF if we never call for its use? This is defined in FCIP. Why 90 duplicate it? The note says FC Entity 91 incorrectly.

Accepted

Completed in Rev 5.8

McDATA-052 McDATA-053

T E

14.2.1 Note

Delete 14.2.1 or explain how/where it is used and why it's Rejected- we need this because of here. security related. Change it to "FC Fabric Entity". Change to "If the FC Fabric Entity is a FC Switch or B_Port device, " Determine it. Rejected Rejected- the names in the table have been changed to state Fabric_Name which already covers the B_Access case. Accepted: See Brocade 127 Completed in Rev 5.8

McDATA-054 McDATA-055

T T

Source FC Fabric Entity A TBD

The Switch_Name applies to 91 B_Ports as well. 92 What goes here?

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-057

15.2.2.1

The "When the ASF SW_ILS" sentence/paragraph should be stated more clearly. We should not allow "another equivalent authentication method". If the authentication mechanism is not in FC-SP, then it should not be a valid authentication technique. The "for the first TCP connection" on the end of the sentence is 93 probably a mistake.

Change to "Additional TCP connections to exisiting FCIP Links shall be authenticated with either FC-SP mechanisms or the ASF SW_ILS." Accepted - see McData 058

Completed in Rev 5.8

McDATA-058

15.2.2.1

An overview section needs to specify that there are two (or even three with FCIP) levels of authentication in BB-2, Fibre channel and FCIP. FCIP refers to user-level security and this is not mentioned in BB-2. We mention TCP connection and Fibre Channel Level authentication. These terms need to be explained in 93 detail.

Explain how there is TCP connection authentication with IKE, TCP connection authentication between FC Entities before ELP and Fibre Channel level authentication between switches during Fabric initialization after ELP. Also state that there is no user-level authentication in FC-BB-2 - FCIP should probably change that terminology. Accepted - see McData 041

Completed in Rev 5.8

McDATA-059

15.2.2.1

Does the FC Entity respond with both the a) configuration information and b) success of failure of an ASF SW_ILS? If not, then it should be an "or" not an "and". What is the Change to "or" and describe the 93 configuration information? configuration information.

Accepted - superseded by ENDL-149

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-060

15.2.2.1 last paragraph

The last paragraph should be the start of a new clause to define the ASF SW_ILS. The ASF SW_ILS should be defined similar to other SW_ILSs in SW-2. For example, the description of the fields in the ASF Request should be referenced below the payload table. References to "new" TCP Connections should be changed to "additional". How does the FC entity verify that the information in the ASF payload identify a TCP connection initiated by that FC/FCIP Entity pair. What address is the ASF 93 frame sent to?

Create new clause for ASF. Describe payloads below the table. Replace "new" with "additional" and explain how this is different from Security for the TCP connections described in FCIP on page 77. Specify how the FC Entity verifies the information in the ASF and that the S_ID and D_ID of the ASF is the Fabric Controller of each FC Entity. Accepted Text should read "ASF should use a previously authenticated TCP Connection in the existing FCIP Link to authenticate the Connection Nonce sent in the additional TCP Connection setup process. Accepted

Completed in Rev 5.8

McDATA-061

15.2.2.1

This section needs to state that the ASF is sent over a previously authenticated TCP connection as FCIP does on page 34 of draft 12. This is 94 not apparent in BB-2.

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-062 McDATA-063

T E

15.2.2.2 and 15.2.2.3 6)

Require FC Entities to authenticate the first as well as additional TCP connections. Please refer to 02-555v0 for suggested text and a complete Authenticating B_Ports and explanation. BB-2 needs to state switches prohibits legacy what is being authenticated at devices from taking advantage each level - particularly the Name of FCIP. FCIP should be as used in authentications and that transparent as possible to the the authentication frames should switches that are using the be sent to the Fabric Controller. FCIP link. Requiring switches TCP authentication must be to authenticate each other is independent of Switch Accepted- superseded by Ralph's 94 not transparent. authentication. comments 95 Should we reference SW-3? This clause is for the link setup, but what is the procedure for establishing additional TCP connections? The dependence of the additional TCP connection authentications on the first authentication needs to be 95 specified. "modelled" should be "modeled" in American 96 English. "(in the correct FC/FCIP 96 Entity)" is redundant. Reference SW-3 if possible. Accepted

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-064

15.3.1

Add a new clause or extend this clause to show the procedure for establishing additional TCP connections. Explain the dependence of additional TCP connections on the first authenticated TCP connection. Accepted - see changes in Item 3)

Completed in Rev 5.8

McDATA-065 McDATA-066

E E

10) 15.3.2 1)

change it. Delete it. Insert a comma after FC Frame in "However, before forwarding the FC Frame, the" Remove crossed out text

Accepted Accepted- see ENDL- 167

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-067 McDATA-068

E E

3) Crossed out text

96 grammar problem Crossed out text should be 96 removed.

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-069

8)

8) references 13.2.3.2.1. 13.2.3.2.1 doesn't say anything about link cost. I don't see the need for 8). Isn't this standard SW-3 initialization? Are we proposing that link costs be 96 different? Delete 8). I don't see the reason to specify that each FC-BB-2_IP devices shall manage TCP operational parameters independently for each ISL. They should be able to manage them as a group. Management of the links does Change the "shall" to a "may" or 96 not need to be specified. delete the sentence. "FC-BB-2_IP shall use the standard FC RDY ISL flow control with Buffer-to-Buffer credit con-trol [14] across its FC Interfaces" is incorrect. R_RDY is a Primitive Signal and FC Interfaces is 97 undefined. 98 not [6] 98 grammar error 98 Text is in different font.

Accepted- sentence changed per Denver Interim meeting

Completed in Rev 5.8

McDATA-070

9)

Accepted - changed to May; 2 instances.

Completed in Rev 5.8

McDATA-071 McDATA-072 McDATA-073 McDATA-074

E E E E

15.4 1) 15.5.2 3) 15.6.1.1 15.6.1.2

It should be "FC-BB-2_IP shall use standard Buffer-to-Buffer flow control [14]." FC-FS is [14]. change "it's" to "its". correct font.

Accepted Accepted Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-075 McDATA-076

T E

15.5.2 16.3.1

"The F-BB-2_IP device may choose not to generate Fibre Channel's F_BSY or F_RJT frames or otherwise participate in FC frame recovery." is negligent. How can we let one device defile the sanctity of the fabric? If the FC-BB-2_IP device is going to participate in the fabric, then it needs to fully participate in the resolution of 98 problems and error recovery. (See 15.6 Item 4) doesn't 100 exist. "TCP Flow (and error) control has mechanisms to detect lost and corrupted data." is 100 incorrect. "The FC-BB-2_IP device FC 100 Interface" is incorrect. "VE_Port or B_Access shall immediately forward the RLIR to the FC Switch Entity" is incorrect. The RLIR should be forwarded to the Domain 100 Controller of the switch.

Delete the sentence or explain why these devices fall to the level of IP and don't have to report F_BSY and F_RJT. Accepted-sentence deleted Should be 15.5.2. Accepted- 15.6.2

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-077 McDATA-078

E E

16.3.3 16.3.4

Should be "TCP Flow control and error control has mechanisms to detect lost or corrupted TCP segments." Accepted Should be "The FC Interface of the FC-BB-2_IP device". Accepted

Completed in Rev 5.8 Completed in Rev 5.8

McDATA-079

16.3.5

Change to "VE_Port or B_Access shall immediately forward the RLIR to the Domain Controller of the Switch." Accepted

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-080

16.3.5

Change "Failure to setup TCP connection" to "Failure to setup additional TCP connections" Change "TCP connect request timeout or Duplicate connect RLIRs should only be request" to "Additional TCP generated when existing links connect request timeout" and have an incident. RLIRs "Duplicate additional TCP should not be generated when connect requests" Change to initializations fail. SA "Successful completion of FC parameter mismatch is an Entity request to close the last initialization event that should TCP connection" Remove "Any be removed. There should confidentiality violations" or move also not be multiple reasons it to the next line. Remove and 100 per bullet. "SA parameter mis-match". Accepted The second sentence says that an LKA shoul donly be sent when no data or Link_Control frames have been received. It would be easier to just send the LKA every K_A_TOV. This would free up processor resources to 75 do other jobs. Change" An LKA is transmitted" sentence to " An LKA is transmitted every K_A_TOV and may not be sent if Data or Link_Control frames have been received from the remote VE_Port during the prior K_A_TOV period." Accepted See Brocade 121

Completed in Rev 5.8

McDATA-081

13.2.3.3.5.1

Completed in Rev 5.8

McDATA-082

13.3.3.2.5.2

Second pragraph states: "If a B_Access has satisfied itself that the connection is down". Saying the is down implies the Change "connection" to "link" for Accepted in sub clause 13.3.3.2.5.2 . 82 TCP connection is down. this clause and 15.2.3.2.5.2. However, 15.2.3.2.5.2 is non-existent The payload for LKA is undefined. Why is everything but the payload defined twice Define the payload for LKA in for VE_Ports and B_Access? one place and apply it to the 82 What is the SW_ILS Code? VE_Ports and B_Access.

Completed in Rev 5.8

McDATA-083

13.3.3.2.5.2

Accepted Brocade 121

Completed in Rev 5.8

Company number

tech/e Sec/table/fig dit locator Page

Comment

Proposed resolution

Response

Status

McDATA-084

13.3.3.2.5.2

There is a corner case where a frame might not be sent for almost 2 x K_A_TOV. This happens if the K_A_TOV timer is triggered at the start of one timer and the next data frame is not received till the end of 82 the next K_A_TOV timer. What is the usefulness of the LKA frame if it was transmitted over a functioning TCP connection while another 82 connection has failed? Cover Project Number is incorrecrt Cover X3 is now called INCITS

For SANmark purposes, add "In the worst case scenario, no data or LKA will be transmitted for almost 2 x K_A_TOV. Accepted See Brocade 121

Completed in Rev 5.8

McDATA-085 Qlogic-000 QLogic-001

T E E

13.3.3.2.5.2 Top line Top line

QLogic-002 QLogic-003

E E

Title Points of Contact

Cover Cover

Old spelling INCITS Information for Craig Carlson is incorrect

Add "For LKA to monitor the health of a Link, LKA should be sent on every TCP connection for a given link. Accepted See Brocade 121 Change to 1466-D Accepted Change "dPANS X3.xxx-200x" to "dPANS INCITS xxx-200x" Accepted Change all "NCITS" to "INCITS" in document. Accepted Change to: Craig W. Carlson (T11.3 Chaiman) QLogic Corporation 6321 Bury Drive Eden Prairie, MN 55346 (952) 932-4064 Fax: (952) 932-4037 E-Mail: craig.carlson@qlogic.com Accepted Remove blank page. Accepted Change "dPANS X3.xxx-200x" to "dPANS INCITS xxx-200x", make this change through-out document. Accepted

Completed in Rev 5.8 Completed in Rev 5.8

Completed in Rev 5.8 Completed in Rev 5.8

Completed in Rev 5.8 Completed in Rev 5.8

QLogic-004 QLogic-005

E E

Blank page Top line

iii iv

Blank pages are not allowed. X3 is now called INCITS

Completed in Rev 5.8

Company number QLogic-006 QLogic-007 QLogic-008 QLogic-009 QLogic-010 QLogic-011 QLogic-012

tech/e Sec/table/fig dit locator Page E Copyright v E E E E E E Top line 4th paragraph 4th paragraph After note vi vi vi vi

Comment Copyright is for wrong millenium. Approval date is wrong. Says the standard was developed during 1996-n. Says the approval process started 1997 Need line break Says Steve wilson is chair of FC-BB Membership list is incorrect.

Proposed resolution Change to 2002. Change "INCITS xxx-2001" to "INCITS xxx-200x". Shouldn't this be 2002? Shouldn't this be 2002?

Response Accepted Accepted Accepted Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Add blank line. Accepted Change "FC-BB" to "FC-BB-2". Accepted See FC-GS-3 for format, see website for current membership list. Accepted Completed in Rev 5.8 Completed in Rev 5.8 Remove blank page. Accepted

2nd to last vi line Membership vii list Blank page Clause 1 xviii 1

QLogic-013 QLogic-014

E T

Blank pages are not allowed.

This chause should come after Mover after these sections to definitions and conventions "Clause 4". sections. Dashed lists are not to be used. Why are we say that things are defined in "FC-BB"? Used "alpha" list. See FC-MI-2 for example. Remove the text "FC-BB-2 makes use of the previously defined FC-BB" and state that it replaces it. Create annex for future work. Number all notes in document. See FC-MI or FC-GS-4 for example. Note should be fixed to reflect the real status of 10GFC.

Accepted Accepted

Completed in Rev 5.8 Completed in Rev 5.8

QLogic-015 QLogic-016

E T

clause 1.1 clause 1.1; 2nd paragraph Clause 1.2, note Clause 1.2, note Clause 1.2, note

1 1

QLogic-017 QLogic-018

T E

1 1

Future work should not be discussed in main text. Notes should be numbered

Accepted Accepted. However, no annex is necessary at this time

Completed in Rev 5.8 Completed in Rev 5.8

Accepted

Completed in Rev 5.8

QLogic-019

Note talks FC over SONET being defined in 10GFC, but I believe that SONET was removed from 10GFC. Hanging paragraph

Accepted Remove hanging paragraph. Accepted

Completed in Rev 5.8 Completed in Rev 5.8

QLogic-020 QLogic-021

T E

Clause 2 Clause 2.1

4 4

Has reference to both FC-SW Since FC-SW-2 replaces FCand FC-SW-2. SW, remove reference to FCSW.

Accepted

Completed in Rev 5.8

Company number QLogic-022 QLogic-023 QLogic-024 QLogic-025

tech/e Sec/table/fig dit locator Page T 3.2.1 6 T T T 3.2.18 3.3.10 3.5 6 9 11

Comment "Can" is not normative and leads to confusion. Cannot use "Can". Cannot use "Can".

Proposed resolution Replace with "may". Replace with "may".

Response Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

QLogic-026

3.5.1

11

Accepted Replace both cans in this definition with "may". Accepted Hanging paragraph Remove hanging paragraph, this should be done for all hanging paragraphs in document. Accepted Use ISO convention for Binary. ISO convention is 010101b. See FC-MI or FC-GS-4 for definitions. This needs to be fixed in remaineder of document. Accepted Use ISO convention for Hex. ISO convention is ABC123h. See FC-MI or FC-GS-4 for definitions. This needs to be fixed in remaineder of document. Accepted

Completed in Rev 5.8

Completed in Rev 5.8

QLogic-027

3.5.2

11

Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

QLogic-028 QLogic-029 QLogic-030 QLogic-031

T T T T 4.7 (e) 4.9.1, 3rd paragraph 5.1, 3rd paragraph after figure

13 18 18 20

Should add list of defined keywords. Cannot use "Can". Cannot use "Can". Cannot use "Can".

Add list from FC-GS-4. Accepted Replace with "may". Replace with "may". Replace with "may". Accepted - this paragraph has been rewritten Completed in Rev 5.8 Accepted Accepted- this paragraph has been rewritten.

QLogic-032

5.1, last 20 paragraph on page 5.1, last 21 paragraph in clause 5.2.4, first paragraph 6.1, 6th paragraph 22 25

Cannot use "Can".

Replace with "may". Accepted - this paragraph has been rewritten Completed in Rev 5.8

QLogic-033

"Will" is not normative and can Replace with "shall". lead to confusion. Accepted Cannot use "Can". Will not use "will". Replace with "may". Accepted Replace both "will"s in paragraph with "shall". Accepted Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

QLogic-034 QLogic-035

T T

Company number QLogic-036 QLogic-037 QLogic-038 QLogic-039 QLogic-040

tech/e Sec/table/fig dit locator Page T 6.3.1.5 29 T T T T 6.3.1.7 6.3.2.3 6.3.4.1 6.3.6.2.2 30 31 33 35

Comment Cannot use "Can". Cannot use "Can". Will not use "will". Many "will"s in this clause. Many "will"s in this clause.

Proposed resolution Replace with "may". Replace with "may".

Response Accepted Accepted

Status Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8 Completed in Rev 5.8

Replace with "shall". Accepted Replace with "shall". Accepted Replace with "shall". Rest of document should be checked as well and wills replaced with shalls where found. Accepted. Replace with "may". Rest of document should be checked as well and cans replaced with mays where found. Accepted Removed crossed out text. Accepted

Completed in Rev 5.8

QLogic-041

8.1, 3rd paragraph

50

Cannot use "Can".

Completed in Rev 5.8 Completed in Rev 5.8

QLogic-042

15.3.4.1

96

Crossed out text below (1).

eted in Rev 5.8

Vous aimerez peut-être aussi