Académique Documents
Professionnel Documents
Culture Documents
MImax
MImin
KP +
KI
s
verr
-
+
PLL
V
dc, pu
V
dc ref
KPDC +
KIDC
vdc err
+
ABS()
SIGN()
dc
min dc
max dc
s -
C
j0.5X
L
B
A
jX
L
~
jX
L
-j0.5X
L
I
~
-j0.5X
L
I
a
1
a
1
b
1
C
jX
L
jX
L
jX
L
jX
L
jX
L
jX
L
B
A
b
1
~
~
~
V
in
= 0
V
in
= -j0.5X
L
I
V
in
= -j0.5X
L
I
C.B. closed C.B. open
3
parameters are also given in the Appendix.
Fig. 4. Schematic diagram of single-phase SSSC implementation.
V. TIME DOMAIN SIMULATION RESULTS
A. Double Line-to-Ground Faults
Fig. 5 illustrates the load angle responses of generators G
2
,
G
3
and G
4
during successful reclosing of a 3-30 cycles double
line-to-ground fault (phases a1&b1) on line 7-8 for the cases
of triple-pole switching (TPS) and Selective-pole switching
(SPS) with adaptive short-time compensation. As it can be
seen from Fig. 5, the maximum generator swing angles in the
case of the adaptive short-time compensation are smaller than
those corresponding to triple-pole switching. This is due to
the fact that the adaptive short-time compensation restored the
pre-fault transmission system capacity just after fault clearing.
This resulted in lower acceleration of the generator rotors and
improved the system stability. As generators G
3
and G4 are
more close to fault than generator G
2
, the improvements in
their stability are more noticeable.
B. Line-to-Line and Single line-to-Ground Faults
Clearing line-to-line faults does not necessarily require that
both faulted phases be opened. The discussion section of [1]
reported that single pole switching of line-to-line faults was
applied and performed correctly on three - 230 kV circuits in
Quebec, Canada. In such a case, the equivalent circuit of the
transmission system during adaptive short-time compensation
of line-to-line and single line-to-ground faults is shown in Fig.
6, where the SSSC would be injecting only in one phase a
capacitive voltage to compensate one half of the inductive
reactance of one circuit of the transmission line.
Fig. 7 illustrates the load angle responses of generators G
2
,
G
3
and G
4
during successful reclosing of a 3-30 cycles line-to-
line fault (phases a1&b1) on line 7-8 for the cases of triple-
pole switching (TPS) and Selective-pole switching (SPS) with
adaptive short-time compensation. As it can be seen from Fig.
7, the maximum generator swing angles in the case of the
adaptive short-time compensation are also smaller than those
corresponding to triple-pole switching.
The load angle responses of generators G
2
, G
3
and G
4
during
successful reclosing of a 3-30 cycles single line-to-ground
fault (phase a1) on line 7-8 for the cases of single-pole
switching (SPS) and single-pole switching with adaptive
short-time compensation are shown in Fig. 8. Fig. 9 illustrates
generator G
3
field current response during the same single
line-to-ground fault of Fig. 8. The system unbalance during
the dead- time in the case of single-pole reclosing without
compensation is clearly noticeable in Fig. 9(a). Such
unbalance is eliminated by adaptive short-time compensation
as shown in Fig. 9(b). The improvement of the system stability
is very noticeable also in this case as shown in Fig. 8.
Fig. 5. Generator load angle responses during successful reclosing of a 3-30
cycles double line-to-ground fault on line 7-8.
Fig. 6. Equivalent circuit of the transmission system during adaptive short-
time compensation of line-to-line and single line-to-ground faults.
VI. CONCLUSION
The paper presented the potential use of an existing SSSC
in improving system stability during selective-pole switching
of parallel transmission lines. The effectiveness of the
proposed adaptive short time compensation scheme is
demonstrated through detailed digital computer simulations on
a benchmark test system. The results of the investigations
have shown that adaptive short-time compensation of
unsymmetrical faults tripped with selective-pole switching
enhances significantly the system stability. Furthermore, since
the pre-fault transmission system capacity is restored
immediately after fault clearing, reclosing of the tripped
conductors can be delayed (the dead-time can be increased) to
ensure a complete extinction of the secondary arc. This will
increase the potential of a successful reclosure and, therefore,
further improvement of the system stability.
v
1
v
2
V
dc
A
B
LC filter
PWM
Converter
DC
Capacitor
Controller
i
sys
Gate firing
C1 C2
+
-
signals
i
L
v
1
v
2
26
30
34
1 2 3 4
G
2
,
D
e
g
.
Time, Sec.
TPS
SPS & Compensation
-63
-45
-27
1 2 3 4
G
3
,
D
e
g
.
Time, Sec.
TPS
SPS & Compensation
-40
-25
-10
1 2 3 4
G
4
,
D
e
g
.
Time, Sec.
TPS
SPS & compensation
C
j0.5X
L
B
A
jX
L
~
-j0.5X
L
I
j0.5X
L
4
Fig. 7. Generator load angle responses during successful reclosing of a 3-30
cycles line-to-line fault on line 7-8.
Fig. 8. Generator load angle responses during successful reclosing of a 3-30
cycles single line-to-ground fault on line 7-8.
(a)
(b)
Fig. 9. Generator 3 field current response during successful reclosing of a 3-30
cycles single line-to-ground fault on line 7-8: (a) single-pole switching and
reclosing, (b) single-pole switching and adaptive short-time compensation.
APPENDIX I
TABLE I
PI CONTROLLER PARAMETERS FOR SSSC CASE STUDIES
Controller gains
KP = 2.5, KI = 100 KPDC = 0.5, KIDC = 50
TABLE II
SSSC PARAMETERS
Coupling transformers
3 x 42 MVA, 42 kV/6.6 kV (converter
side)
xt = 0.1 p.u. rt = 0.002 p.u.
Three-level PWM
L = 0.09 mH C = 0.09 mF
Converter type 14 kV
LC Filter 0.8 mF
DC side base voltage fc = 1980 Hz
DC capacitor 0.8 mF
Carrier signal frequency fc = 1980 Hz
26
30
34
1 2 3 4
G
2
,
D
e
g
.
Time, Sec.
TPS
SPS & Compensation
-65
-46
-27
1 2 3 4
G
3
,
D
e
g
.
Time, Sec.
TPS
SPS & Compensation
-40
-25
-10
1 2 3 4
G
4
,
D
e
g
.
Time, Sec.
TPS
SPS & Compensation
27
29
31
1 2 3 4
G
2
,
D
e
g
.
Time, Sec.
SPS
SPS & Compensation
-47
-41
-35
1 2 3 4
G
3
,
D
e
g
.
Time, Sec.
SPS
SPS & Compensation
-30
-25
-20
1 2 3 4
G
4
,
D
e
g
.
Time, Sec.
SPS
SPS & Compensation
1
2
3
1 1.5 2
I
f
3
,
P
u
Time, Sec.
1
2
3
1 1.5 2
I
f
3
,
P
u
Time, Sec.
5
APPENDIX II
IMPROVEMENT OF POWER SYSTEM STABILITY USING SINGLE-
POLE SWITCHING OF LINE-TO-LINE FAULTS ON SINGLE-
CIRCUITS TRANSMISSION LINES
This section demonstrates the improvement of power
system stability by using single-pole switching and reclosing
of line-to-line faults on single-circuit transmission lines. In
this context, the test benchmark is modified by assuming that
line 7-8 is a single-circuit transmission line as shown in Fig.
10.
Fig. 11 illustrates the load angle responses of generators G
2
,
G
3
and G
4
during successful reclosing of a 3-30 cycles line-to-
line fault (phases a1&b1) on line 7-8 for the cases of triple-
pole switching (TPS) and single-pole switching (SPS). Fig. 12
illustrates generator G
3
electrical power response during the
same fault of Fig. 11. As it can be seen from Fig. 11, the
maximum generator swing angles in the case of the single-
pole switching are much smaller than those corresponding to
triple-pole switching. Moreover, Fig. 12 shows that the low-
frequency oscillations in the electrical power of generator 3
are more damped in the case of single-pole switching than in
the case of triple-pole switching. This is a clear evidence of
the advantage of single-pole switching of line-to-line faults.
Fig.10. Modified test benchmark with L7-8 is a single-circuit transmission line.
REFERENCES
[1] E.W. Kimbark, "Selective-Pole Switching of Long Double-Circuit EHV
Lines," IEEE Transactions on Power Apparatus and Systems, Vol. PAS-
95, 1976, pp. 219-230.
[2] IEEE Discrete Supplementary Controls Working Group, Power System
Engineering Committee, Single-Pole Switching for Stability and
Reliability, IEEE Transactions on Power Systems, Vol. 1, 1986, pp. 25-
36.
[3] H.J. Haubrich, G. Hosemann and R. Thomas, "Single-Phase Auto-
Reclosing in EHV Systems," CIGRE, Report No. 31-09, Paris, 1974.
[4] A.J. Gonzalez, G.C. Kung, C. Raczkowski, C.W. Taylor and D. Thonn,
"Effects of Single- and Three-Pole Switching and High-Speed Reclosing
on Turbine-Generator Shafts and Blades," IEEE Transactions on Power
Apparatus and Systems, Vol. PAS-103, 1984, pp. 3218-3228.
[5] Yong Hua Song and Allan T Johns, Flexible AC Transmission Systems
(FACTS), The Institution of Electrical Engineers, Michael Faraday
House, 1999.
[6] Narain G. Hingorani and Laszlo Gyugyi, Understanding FACTS,
Concepts and Technology of Flexible AC Transmission Systems, IEEE
Press, 2000.
[7] S.O. Faried, An Adaptive Short Time Compensation Scheme for
Improving Power System Stability and Reducing Turbine-Generator
Shaft Torsional Torques, IEEE Transactions on Power Systems, Vol.
15, May 2000, pp. 785-790.
[8] S. Jiang, U. D. Annakkage, and A. M. Gole, A Platform for Validation
of FACTS Models, IEEE Transactions on Power Delivery, Vol. 21, No.
1, January 2006, pp. 484-491.
Fig. 11. Generator load angle responses during successful reclosing of a 3-30
cycles line-to-line fault on line 7-8 of Fig. 10.
(a)
(b)
Fig. 12. Generator 3 electric power response during successful reclosing of a
3-30 cycles line-to-line fault on line 7-8 of Fig. 10: (a) triple-pole switching,
(b) single-pole switching.
18
36
54
1 2 3 4
G
2
,
D
e
g
.
Time, Sec.
TPS
SPS
-530
-275
-20
1 2 3 4
G
3
,
D
e
g
.
Time, Sec.
TPS
SPS
-59
-17
25
1 2 3 4
G
4
,
D
e
g
.
Time, Sec.
TPS
SPS
-1.4
0.1
1.6
1 2 3
P
G
3
,
P
u
Time, Sec.
-1.4
0.1
1.6
1 2 3
P
G
3
,
P
u
Time, Sec.
L
7-8
Infinite
bus
3
10
6
8 7
9
11
4
5
2 1
G
1
G
3
G
2
G
4
12
6
Sherif Omar Faried was born in Cairo, Egypt. He
obtained B.Sc. and M.Sc. Degrees in Electrical
Engineering from Ain Shams University, Egypt and
M.Sc. and Ph.D. Degrees in Electrical Engineering
from the University of Saskatchewan, Canada where
he is presently a Professor of Electrical Engineering in
the Department of Electrical and Computer
Engineering. His research interest includes power
system dynamics, FACTS, reliability and power
quality. He is a Registered Professional Engineer in
the Province of Saskatchewan.
Nehad El-Sherif El-Kharbawe was born in
Cairo, Egypt, on October 17, 1978. He received the
B.Sc. and M.Sc. degrees in electrical engineering
from Ain Shams University, Cairo, in 2001 and
2005, respectively. He is currently pursuing the
Ph.D. degree at the University of Saskatchewan,
Saskatoon, SK, Canada.
Abdel-Aty (Aty) Edris was born in Cairo, Egypt.
He received his BS with honors from Cairo
University, the MS from Ain-Shams University,
Egypt, and the Ph.D. from Chalmers University of
Technology, Sweden. Dr. Edris spent 12 years with
ABB Company in Sweden and in the USA, in the
development and application of Reactive Power
Compensators and High Voltage DC Transmission
systems. From 1992 to 2008, Dr. Edris was with
EPRI as Manager of Flexible AC Transmission
System (FACTS) Technology and Senior Technology Manager of EPRI
Power Delivery and Markets. Dr. Edris is presently a Principal Consultant at
Siemens Energy Company.
Dr. Edris is a member of several IEEE and CIGRE Working Groups and
the recipient of the IEEE 2006 Award for Industry Leadership and Scientific
Contribution to FACTS Technology, pioneering transformation of electric
transmission system into flexible, controllable, yet secure system operated at
thermal capacity. Dr. Edris was, also, the recipient of the IEEE 2008
Outstanding Engineer Award of the IEEE Region 6 Central Area.