NEW CONSTRUCTION MOBILE TRAVELING CRANE INSPECTION CHECKLIST Item No. Owner Location Model Boom Length Safe Working Load Location Date of Inspection NO 1

Form. No. Page

: :

NS-CL-TC-001 1 of 6

: : : : : : : : Result Remarks

Desription CRANE DOCUMENT Review manufacturer data report. Verify As Built Drawing. Verify material certificate. Verify NDT report. Verify dimensional report. Review manufacturer manual & specification. Review Preventive Maintenance Program. Review load chart. PREPARATION Check if the power/engine has been switch off for first stage of inspection & position of the unit was clearly safe. Check if the equipment has been properly prepared and cleaned to allow visual inspection. Check if all access, ladder, walkway and platform have handrail and toe protection CARRIER Review material certificate. Review welding procedure and welding performance. Verify NDT report, procedure, personnel qualification and NDT equipment calibration.

PT NUSAKURA STANDARINDO
CRANE INSPECTION & CERTIFICATION
Dimensional check and compare to drawing and / or document. Check support structure & chassis to ensure that no deformation and corrosion. Check weldments in the support structure & chassis for no exists deformation and corrosion. Check crane support structure for loose bolts or completeness of bolt. Check fuel tank for no exists leakage, deformation and compliance with safety requirement. Check outrigger to ensure that no deformation and corrosion exists. 4 OUTRIGGER Review material certificate. Review welding procedure and welding performance. Verify NDT report, procedure, personnel qualification and NDT equipment calibration. Dimensional check and compare to drawing and / or document. Check outriger to ensure that no deformation and corrosion exists. BOOM Review material certificate. Review welding procedure and welding performance. Verify NDT report, procedure, personnel qualification and NDT equipment calibration. Dimensional check and compare to drawing and / or document. Dimensional check and compare to drawing and / or document. Check boom for bent chord members, missing or broken lacing and cracked welds on critical members. Check boom section end connection for cracked welds, deformation and corrosion. Check mast and retractable mast for crack weld, deformation and corrosion. Check sheave for wear, crack, rope path alignment and bearing condition.

Form. No. Page

: :

NS-CL-TC-001 2 of 6

PT NUSAKURA STANDARINDO
CRANE INSPECTION & CERTIFICATION
Check boom angle indicators over full range for accuracy. Check boom hoist limiter or shutoff and anti two block devices for proper operation. Check pendant line for evident deterioration, corrosion and damage. Check hydraulic cylinders for wear and deformation (for telescopic boom). Check condition of hoses & fitting for any leakage and deformation. (for telescopic boom) 6 DRUM Check drum diameter, pitch diameter of not less than 18 times the nominal rope diameter used. Ensure the flange have minimum of' 1/2" (13 mm) over the top layer of rope at all times. Ensure no less than 5 full wraps of rope remain on the drums in any operating condition. Check for cracked or worn. Ensure boom hoist pawl or check valve for hydraulic cylinder is installed. Verify certificate of conformance. PUMP & MOTOR Inspect for loose bolts or fasteners. Inspect for leaks at joints between sections. Inspect Shaft seal leaks. Check unusual noises or vibration. Inspect loss of operating speed. Check excessive heating of the fluid. Check loss of pressure. Verify certificate of conformance. WIRE ROPE Verify certificate of conformance. Check wire rope for evident deterioration, broken and damage, or improper reeving. Check end attachedment for loose, missing or corroded bolt, pins, keepers or cotter pins. Record actual diameter and part line number using wire rope inspection report sheet

Form. No. Page

: :

NS-CL-TC-001 3 of 6

PT NUSAKURA STANDARINDO
CRANE INSPECTION & CERTIFICATION
9 WEDGE TYPE SOCKETS Verify that the socket and wedge are the correct size for the rope in use. Check the socket eye & pin for roundness and wear A pin keeper should always used with the pin. Check socket and wedge for rough edges or burns. Ensure wire rope clips used in conjunction with wedge sockets attached only to the unloaded (dead end) of the rope. Ensure U-bolts clips installed with the U-bolt section on the dead or short end, and the saddle HOOK Check crane hooks for deformation. Check condition of hook latch. Check connection of rope end. Record hook serial number and hook capacity. SHEAVES Check sheave for wear, crack, rope path alignment and bearing condition. BRAKE & CLUTCHES Verify testing report. Check control mechanism of brakes and clutches for proper operations. Check for leakage and damage in air and hydraulic system. Verify condition of all braking systems. The brake should have adequate capacity to smoothly stop 110% of rated load from the maximum design speed in the lowering mode while lowering. PRIME MOVER Check all fluid levels of prime mover. Check control mechanisms including brake and clutches for proper operation. Check for hoist lubricant oil leakage. In hoist where a sight glass is provided, check the fluid level.

Form. No. Page

: :

NS-CL-TC-001 4 of 6

10

11

12

13

14

PT NUSAKURA STANDARINDO
CRANE INSPECTION & CERTIFICATION
Check for leakage or damage in the air and non mechanical systems. Check belts and chain for proper adjustment. Ensure engine exhausts equipped with a spark arresting. Check power plants for proper performance compliance with safety requirements. Ensure the correct load rating chart for the configuration in use is visible to the crane operator at the primary control station. Check all control mechanism for proper adjustment, excessive wear of component and contamination by foreign matter. Check electrical apparatus for proper function Check electrical apparatus for proper function 15 HYDRAULIC SYSTEM Check for evident of loose and missing bolts. Check for evident Leakage and damage of host. Check pump pressure and compare to the manufacturers specified pressure setting in each hydraulic circuit. SWING MECHANISM Visually check for cracking and deformation. Check for excessive wear of components and contamination by lubricants or other foreign matter. Check the parking Brake & shall be capable of remaining in the engaged position without the attention of the operator. When provided, check dynamic fraction brake condition and proper function. When provided , check swing lock condition and proper function. Visually check for cracking and deformation. Check for excessive wear of components and contamination by lubricants or other foreign matter. Check the parking Brake & shall be capable of remaining in the engaged position without the attention of the operator. When provided, check dynamic fraction brake condition and proper function.

Form. No. Page

: :

NS-CL-TC-001 5 of 6

16

PT NUSAKURA STANDARINDO
CRANE INSPECTION & CERTIFICATION
When provided , check swing lock condition and proper function. Visually check for cracking and deformation. 17 CONTROLS, CABS & MISCELLANEOUS EQUIPMENT Check the control operations and functions shall be clearly marked and easily visible. Control levers for boom hoist , load hoist , swing and boom telescope ( when applicable ) shall return automatically to their center (neutral) positions on release. Check the condition of door, window, platforms and walkways. Load charts should be provided inside of cabs. Function check of the boom hoist limiter and overload protective device and anti two block system. Ballast or counter weight when applicable, crane should not be operated without the appropriate Ballast or counter weight in place as specified by the crane manufacturer. Fire Extinguisher : A carbon dioxide, dry chemical or equivalent fire extinguisher of sufficient capacity shall be kept in the cab or vicinity of the crane

Form. No. Page

: :

NS-CL-TC-001 6 of 6

Overall Comment : .. Legend : : Accept X : Reject NA : Not Available Inspector