Vous êtes sur la page 1sur 19

ROAD METAL RATES

DIVISION: NH Division, PWD, BAREILLY


. At
Km. No. 1 Bareilly Bareilly Bareilly Bareilly Bareilly Bareilly Bareilly Quarry 2 NH CD PWD Bareilly Quarry Distence Rate from ( Rs) Quarry 3 5 to 540 600 600 600 470 500 380 98 98 98 98 98 98

office /
Cost of cartage without 6 649.75 649.75 649.75 649.75 649.75 649.75

km-250 of NH24
Cost of cartage excluding 7 590.68 590.68 590.68 590.68 Total (3+7) (Rs) 8 1130.68 1190.68 1190.68 1190.68 1060.68

CIRCLE : 28th .Circle, N.H. P.W.D. , Bareilly ( New N H No -30 ) BAREILLY


I.S. Transit Tax 9 Total of col. (8+9) 10 1130.68 1190.68 1190.68 1190.68 1060.68 1090.68 Trade Tax on col. 1111 G.Total of col 11+12 12 1130.68 1190.68 1190.68 1190.68 1060.68 1090.68 380.00 Remarks 13

Stone Ballast ( 22.4-53 mm)

Distance from Quarry


from to

Lal Kuan Lal Kuan Lal Kuan Lal Kuan Lal Kuan Lal Kuan Local

16mm-22.4mm/ 11.2mm/13.2mm/ 10-16mm 11.2-2.8 mm / 2.3-9.5 (6.7mm) Stone grit 5.6 mm and below

km93 of BB road to km03 of BB road = 90 km


Mini bye pass road = 05 " on NH24 road up to office
= 03 "

Total

= 98kms

Stone Dust
590.68

Cost Of Cartage kmo to up to km75 =571.00 km76 to 98 @4.25 = 97.75 Total = 668.75 deduct for loading 19.00 hence cartage = 649.75

Coarse Sand
590.68 1090.68 Fine Sand

1) Distances from quarry have been taken from the shortest route. 2) Quarry rates have been taken of the respective circle applicable. 3) Cartage rates has been taken approved by SE Lko. Circle in the RMR. 4) Quarry rates are for approved quarry and RMR rates are minimum . JUNIOR ENGINEER

EXECUTIVE ENGINEER

SUPERINTENDING ENGINEER

N.H. Construction Division P.W.D. Bareilly

N.H. Construction Division P.W.D. Bareilly

28th Circle N.H. P.W.D. Bareilly

Analysis Of Rates
S. No.
2.4 (vi)

Description
Scraping of Bricks Dismantled from Brick Work including Stacking. Unit = numbers Taking output = 1000 numbers In lime/Cement mortar a) Labour Mate Mazdoor b) c) Overhead charges @10% input on (a) Contractor's profit @10% input on (a+b)

Unit Quantity Rate Rs

Cost Rs

day day

0.140 3.500

130.00 125.00

18.20 437.50 45.57 50.13 551.40

Rate per1000 Nos = a+b+c Rate per No ( a+b+c)/1000 2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry Unit = sqm Taking output = 100 sqm a) Labour Mate Mazdoor for scarping and loading b) Machinery Tractor-trolley c) Overhead charges @10% input on (a+b) d) Contractor's profit @10% input on (a+b+c) say

0.60

day day hour

0.160 4.000 0.320

130.00 125.00 234.00

20.80 500.00 74.88 59.57 65.52 720.77 7.21 7.20

Cost for 100 sqm = a+b+c+d Rate per sqm = (a+b+c+d)/100 say 2.4 2.4 (ii) (ii) B Dismantling Brick / Tile work In cement mortar a) Labour Mate Mazdoor for dismantling, loading and unloading b) Machinery c) d) Tractor-trolley Overhead charges @10% input on (a+b) Contractor's profit @10% input on (a+b+c) day day 0.030 0.750 130.00 125.00

3.90 93.75

hour

0.270

234.00

63.18 16.08 17.69 194.60

Cost for 1.25 cum = a+b+c+d Rate per cum = (a+b+c+d)/ 1.25 say

155.68 155.70

Junior Engineer

Assistant Engineer

Analysis Of Rates Cement Mortar 1:3 (1 cement : 3 Coarse sand)


CL. No.
12.6

S. No.

Description

Unit Quantity Rate Rs

Cost Rs

Sub- Unit = 1 cum Ana Taking output = 1 cum a) Materials Cement Coarse Sand b) Labour Mate Mazdoor Total Material and Labour = (a+b)

tonne cum day day

0.51 1.05 0.04 0.90

5900.00 1090.68 130.00 125.00 say

3009.00 1145.22 5.20 112.50 4271.90

Brick masonry work in 1:3 in sub-structure complete


CL. No. S. No. Description Unit Quantity Rate Rs
Cost Rs 13.1 1300 & Brick masonry work in 1:3 in sub-structure complete excluding pointing and 2200 plastering, as per drawing and Technical Specifications Unit = cum Taking output = 1 cum a) Material Bricks Ist class(excluding 10% c.p.) Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) b) Labour Mate Mason Mazdoor Add for scaffolding @ 5 per cent of cost of material and labour

each cum

500.00 0.24

3.35 4271.90

1675.00 1025.26

day day day

0.06 0.80 0.80

130.00 260.00 125.00

7.80 208.00 100.00 150.80 3166.86 316.69 3483.54 348.35 3831.90 3831.90 3831.90

a+b c) Overhead charges @10% input on (a+b) a+b+c d) Contractor's profit @10% input on (a+b+c) a+b+c+d Rate per cum (a+b+c+d) say

Junior Engineer

Assistant Engineer

Analysis Of Rates PCC M 15 / Plain Cement Concrete in Open foundation


CL. No.
12.8

S. No.

Description

Unit Quantity Rate Rs

Cost Rs

1500,1 Plain M15 Cement Concrete in Open 700 & Foundation complete as per Drawing and 2100 Technical Specifications. PCC Grade M15 Unit = cum Taking output = 15 cum a) Material Cement Coarse sand 40 mm Aggregate 20 mm Aggregate 10 mm Aggregate b) Labour Mate Mason Mazdoor c) Machinery Concrete mixer (cap. 0.40/0.28 cum) Generator 63 KVA add35% Escallation charges Cost of Labour, Material & Machinery (a+b+c) d) Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour and machinery a+b+c+d e) Overhead charges @10% input on (a+b+c+d) a+b+c+d+e f) Contractor's profit @10% input on (a+b+c+d+e) Cost for 15 cum = a+b+c+d+e+f Rate per cum = (a+b+c+d+e+f)/15 say

tonne cum cum cum cum day day day hour hour

4.13 6.75 8.10 4.05 1.35 0.86 1.50 20.00 6.00 6.00

5900.00 1090.68 1130.68 1190.68 1190.68 130.00 260.00 125.00 150.00 320.00

24367.00 7362.10 9158.52 4822.26 1607.42 111.80 390.00 2500.00 900.00 1920.00 987.00 54126.11 2165.04

56291.15 5629.12 61920.27 6192.03 68112.29 4540.82 4540.80

Junior Engineer

Assistant Engineer

Analysis Of Rates
PCC 1:3:6 in Foundation
CL. No. 9.1 S. No. 408 Description Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. Unit Quantity Rate Rs Cost Rs

Unit = cum Taking output = 15 cum a) Labour Mate Mason Mazdoor b) Material 40mm Aggregate at site Coarse Sand at site Cement at site Cost of water c) Machinery Concrete mixer0.4/ 0.28 cum Generator set 33 KVA Water tanker6 KL capacity Add 35% Escallation charges d) Overhead charges @10% input on (a+b+c) e) Contractor's profit @10% input on (a+b+c+d) Cost for 15 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/15

day day day cum cum tonne KL hour hour hour

0.640 1.000 15.000 13.800 6.900 3.300 18.000 6.000 6.000 3.000

130.00 260.00 125.00 1130.68 1090.68 5900.00 50.00 150.00 240.00 200.00

83.20 260.00 1875.00 15603.41 7525.70 19470.00 900.00 900.00 1440.00 600.00 1029.00 4968.63 5465.49 60120.44 4008.03 4008.00

say

Junior Engineer

Assistant Engineer

Analysis Of Rates Analyised Basic Rates Of Materials


M.S. Sheet 1.6 mm thick as per mareket cost for local cartage loading/unloading Hence Rate per Sqm Providing & fixing M.S.Sheets on roof of A.E." s camp Office in side lab & A.O.office& store room no: 5 a) Labour for dismantling of old damaged M.S. Sheets, verga, & making base etc. for fitting of New M.S.Sheets includeing nuts & bolts ,black smith & all labour t&p etc. b) Material M.S. Sheet 1.6 mm thick c) Overhead charges @10% input on (a+b) a+b+c d) Contractor's profit @10% input on (a+b+c) a+b+c+d Rate per Sqm (a+b+c+d) Sqm no Sqm

( As per market rate)

1.00 1.00 1.00

690.00 10.00 3.00

690.00 10.00 3.00 703.00

Sqm

1.00

l.s

25.00

Sqm Sqm

1.00 1.00

l.s 538.00

50.00 538.00 61.30 674.30 67.43 741.73 741.70

Plastering with cement mortar (1:3) Cement : coarse sand


CL. S. No. No. 13.3 1300 & Unit = 10 sqm 2200 Description Unit Quantity Rate Rs Cost Rs

Taking output = 10 sqm a) Material Cement mortar 1:3 (Rate as in Item 12.6) b) Labour Mate Mason Mazdoor a+b Overhead charges @10% input on (a+b)

cum

0.144

4271.90

615.15

day day day

0.04 0.50 0.50

130.00 260.00 125.00

c)

5.20 130.00 62.50 812.85 81.29 894.14 89.41 983.55 98.36 98.40

a+b+c d) Contractor's profit @10% input on (a+b+c) Rate per 10 sqm (a+b+c+d) say

Junior Engineer

Assistant Engineer

Analysis Of Rates
Earth work in excavation of foundation of structures 3.13 304 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious Ordinary soil Unit = cum Taking output = 10 cum Manual Means (Depth upto 3 m) a) Labour Mate day 0.320 130.00 41.60 Mazdoor day 8.000 125.00 1000.00 b) Overhead charges @10% input on (a) 104.16

c)

Contractor's profit @10% input on (a+b)

114.58 1260.34 126.03 126.00

Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 say

Plastering with cement mortar (1:3) Cement : coarse sand


CL. S. No. No. 13.3 1300 & Unit = 10 sqm 2200 Description Unit Quantity Rate Rs Cost Rs

Taking output = 10 sqm a) Material Cement mortar 1:3 (Rate as in Item 12.6) b) Labour Mate Mason Mazdoor a+b Overhead charges @10% input on (a+b)

cum

0.144

4271.90

615.15

day day day

0.04 0.50 0.50

130.00 260.00 125.00

c)

5.20 130.00 62.50 812.85 81.29 894.14 89.41 983.55 98.36 98.40

a+b+c d) Contractor's profit @10% input on (a+b+c) Rate per 10 sqm (a+b+c+d) say

Junior Engineer

Assistant Engineer

Analyised Basis on Market Rates Of Materials


Fittings into Toilets/ bath for General office stoff a) Urinal sheets no 3 b) w.c. sheets no 2 c) wash basin no 2 d) Cystern system no 2 e) Tapes no 6 f)G.I.pipe ft 22 g) drainage pipe ft 20 h) other fitting job 1 i) labour charges job 1 j)pvc water tank 200 liter capcity job 2 Total Fittings into Toilets/ bath atteched with E.E.,S room/A.E.ist/A.E.iiird /A.O.room a) Urinal sheets no 1 b) w.c. sheets uropion type no 1 c) wash basin no 1 d) Cystern system no 1 e) Tapes no 3 f)G.I.pipe ft 15 g) drainage pipe ft 18 h) other fitting job 1 i) labour charges job 1 j)pvc water tank 200 liter capcity job 1 Total 850.00 850.00 1800.00 3000.00 350.00 80.00 25.00 1200.00 2500.00 3000.00 2550.00 1700.00 3600.00 6000.00 2100.00 1760.00 500.00 1200.00 2500.00 6000.00 27910.00

950.00 4250.00 1800.00 4000.00 350.00 80.00 25.00 1000.00 2500.00 3000.00

950.00 4250.00 1800.00 4000.00 1050.00 1200.00 450.00 1000.00 2500.00 3000.00 20200.00

Junior Engineer

Assistant Engineer

Analysis Of Rates
Providing and laying of floor tiles taking output = 4.00 sqft (0.372sqm) a) Cost of Tile b) cost of cement c) coarse sand d) labour for laying e) over heads charges/westages Total Hence Rate per sqm Providing and laying of wall tiles taking output = 10.50sqft(0.9765sqm) a) Cost of Tile b) cost of cement c) coarse sand d) labour for laying e) over heads charges/westages Total Hence Rate per sqm Supply & Fixing steel grills,sections in old taking area 1.00 sqm 1.00 sqm l/s @ 25kg per sqm Hence rate per sqm Supply & Fixing glass pannels in old taking area 1.00sqm (10.76 sqft ) market rate Rs 75 per sqft Hence rate per sqm

sqft kg kg ft job

4.00 6.00 20.00 4.00 1.00

84.00 6.00 1.20 22.00 20.00

(a+b+c+d+e)/.372

336.00 36.00 24.00 88.00 20.00 504.00 1354.80

sqft kg kg ft job

10.50 10.50 1.00 10.50 1.00

36.00 6.00 1.00 20.00 20.00

(a+b+c+d+e)/0.9765

378.00 63.00 1.00 210.00 20.00 672.00 688.20

kg

25.00

70.00

1750.00 1750.00

sqft

10.76

75.00

807.00 807.00

Detail of Measurements
Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly.
S. No. Item of work Details Unit No L Measurements B H Qty

1 Dismantling Brick / Tile work of old damaged

Toilets, Bath rooms ( to chnge techanical room /A.E. and disposal of dismamtled material up to lead partion wall between of 1000m. All labour T&p etc complete.

Cum

2.30

0.23

3.50

1.85

toilet& bath 1
Repair of A E iiird room L=2x (4.8+3.2)/2

2.45 8.00

0.23 0.35

3.50 0.35

1.97 0.98

parapet wall of roof at A.E iiird room parapet wall of roof at store room no 5 side wall Cum nos

Repair of store godwn room no 1 , L=2(L+B)=2x (5.45+4.65) H=(3.1+4.4)/2

20.20

0.35

0.4

2.83

1 684

5.50

0.35

3.75

Total Scraping of Bricks Dismantled from Brick Work 10% nos of including Stacking.( obtain from dismantled brick total bricks work.) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry ( damaged surface of old plaster )

7.22 14.85 684.00

in Item 1 E.E.,s room toilet A.E.Ist room toilet A.E.iiird room toilet in AE iiird room store g.room no 1

Sqm

2 2 2 2 2 2 2 2 2 1 1

3.60 4.40 2.80 2.00 2.50 1.70 2.80 2.20 4.80 3.20 4.40

3.00 3.00 2.40 2.40 2.40 2.40 2.40 2.40 0.60 0.60 2.00

21.60 26.40 13.44 9.60 12.00 8.16 13.44 10.56 5.76 1.92 8.80
131.68

Total Providing & fixing M.S.Sheets on roof including supply of all materials & labour for dismanteling of old damages etc and for new fittings,fixing etc complete In A.E." s camp Office in side lab In A.O. Room In store godown room no: 5 Total Earth Work in excavation in foundation in ordinary soil etc i/c all lead & lift, all labour T & P etc. Complete. For construction of new General Toilets & w.c for official use .

Sqm

Sqm

1 1 1 1

3.15 4.30 4.60 5.40

2.20 1.10 2.20 5.15

Sqm

6.93 4.73 10.12 27.81 49.59

constructio n of urinals & bath for office staff

Cum

2 2 1 1

5.35 2.45 2.35 2.55

0.75 0.75 0.75 0.75

0.75 0.75 0.75 0.75

Total

Cum

6.02 2.76 1.32 1.43 11.53

Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.( in foundation & flooring of urinals,toilets) constructio n of urinals & bath for office staff in flooring in flooring Cum Cum 2 2 1 1 1 2 5.35 2.45 2.35 2.55 4.80 2.10 0.75 0.75 0.75 0.75 2.40 1.50 0.15 0.15 0.15 0.15 0.15 0.15 1.20 0.55 0.26 0.29 1.73 0.95 4.98

Brick masonry work in 1:3 in substructure complete excluding pointing and plastering, as per drawing and Technical Specifications

parapet wall of roof at A.E.room constructio n of urinals & bath for office staff constructio n of urinals & bath for office staff parapet wall of roof at store room no 1

Cum Cum

1 2 2 1 1

8.00 5.35 2.45 2.35 2.55 5.35 2.45 2.35 2.55

0.35 0.50 0.50 0.50 0.50 0.23 0.23 0.23 0.23

0.35 0.75 0.75 0.75 0.75 3.00 3.00 3.00 3.00

0.98 4.01 1.84 0.88 0.96 7.38 3.38 1.62 1.76

B = (0 .69 + 0.30 ) /2 = 0.50

Cum

2 2 1 1

20.20

0.35

0.35

2.47

h= ( 3.45+4.75 )/2 =4.10 Total Plain M15 Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. In plinth of new urinals & toilets and its flooring.complete. constructio n of urinals & bath for office staff in flooring for J.E. ( T ) room Total in flooring

1 Cum

5.50

0.35

4.10

7.89 33.18

cum

2 2 1 1

5.35 2.45 2.35 2.55 5.35 2.55 3.30

0.30 0.30 0.30 0.30 2.45 2.35 2.40

0.02 0.02 0.02 0.02 0.05 0.05 0.05

0.06 0.03 0.01 0.02 1.31 0.30 0.40 2.13

cum

2 1 1

Cum

Plastering with cement mortar


(1:3) Cement : coarse sand over brick work and over old damaged dismantled portion & complete.

parapet wall of roof at A.E.room parapet wall of roof at store room no 5

Sqm

9.70

1.05

10.19

1 1 2 2 2 2 2 2 2

20.20 5.15 4.90 2.55 2.80 2.00 2.50 1.70 2.80

1.05 3.75 3.00 3.00 2.40 2.40 2.40

21.21 19.31

on new side wall in Item 1 Sqm E.E.,s room toilet A.E.Ist room toilet

29.40 15.30 13.44 9.60 12.00

A.E.iiird room toilet

2.40 2.40

8.16 13.44

2 with ateched E.E.,s room ,toilet


L=2(4.9+2.35)

2.20 7.25 2.35 2.45 4.34 4.30 3.80 4.50 4.40 2.20 2.10 2.10 2.10 2.10

2.40

10.56
30.45 19.74 20.58 18.23

2 4 4 2 2 2 2 1 3 Sqm

in side w.c in side w.c


L=2(2.12+2.22)

office H/C Total Providing & Repreparing falls ceelling at place of old damaged as under In A.E." s camp Office in side lab In A.O. Room Total providing and fixing urinals sheets,Tapes washbasin,water supply/drainage fittings W.C.fittings, cysterns fittings etc. complete . ( in combine bath & toilets ) with atached E.E.,s room with aatached A.E. ist room with attech A.E. iiird room with attech Accountant officer room Genaral w.c.,urinals for office stoff Providing and laying of floor tiles including supply of all materials such as tiles,cement,c.sand,labour etc&complete for E.E.,S room for A.E ist/ iind room for A.E. iiird room Toilet with attech A.E. ist room Toilet with attech A.E. iiird room Toilet with attech E.E.,s room Genaral w.c.,urinals for office stoff Total

in room A.E.iiird Misc.

0.60 0.60 2.10 1.80 1.65

5.16 4.56 18.90 7.92 10.89


299.04

10

Sqm

1 2 3

3.15 4.30 3.60

2.20 1.10 2.20

Sqm

6.93 9.46 23.76 40.15

11

job job job job job

1 1 1 1 1

1.00 1.00 1.00 1.00 1.00

12

Sqm Sqm

1 1 1 1 1 1 1 2

6.30 5.30 4.40 2.50 2.80 2.80 4.80 2.10

4.30 3.30 3.15 2.10 2.20 2.00 2.40 1.50

Sqm

27.09 17.49 13.86 5.25 6.16 5.60 11.52 6.30 93.27

13

Providing and laying of wall tiles in baths including supply of all materials such as tiles,cement,c.sand,labour etc&complete Toilet with attech E.E. ,s room with attech A.E. ist room with attech A.E. iiird room Genaral w.c.,urinals for office stoff

L+B L=(2.8+2.0)
L=2(2.5+1.7) L=2(2.8+2.2) L=2(4.9+2.35)

Sqm Sqm

in side w.c in side w.c


L=2(2.12+2.22)

2 2 2 2 4 4 2

4.80 4.20 5.00 7.25 2.35 2.45 4.34

2.10 2.10 2.10 2.10 2.10 2.10 2.10

14

Total Supply & Fixing steel grills,sections in old existing windows in rooms , & ventiletors into bathrooms. A.E. iiird room & camp room

Sqm

20.16 17.64 21.00 30.45 19.74 20.58 18.23 88.83

window V w

Sqm

15

Store room Total Supply & Fixing glass pannels in old windows replesed to damaged pannels Supply of wooden furniture as under& complete A - Tables of size - 6'x4' ft B - Chairs C - Chairs with cussion D- Benches Supply of Steel Almirah with Box cell 6 Nos each including fittings locks in each and complete. Supply of ceilling Fans & fittings complete Supplying & fittings of coolers Supply of computers with assesaries required for work official work. Supplying of computr Tables Apply priming coat over new steel and other metal surface after and including prepairing the surface throughly cleaning oil grease dirt etc and scoured with wire brushes, fine steel /wood scrappers sand papering and knoting including cost of all materials, labour abd t&p[ etc required for proper completion of work.

4 3 2 1

0.80 1.65 0.90 0.90

1.10 1.10 0.45 1.30

Sqm Sqm 2.00

3.52 5.45 0.81 1.17 10.95 2.00

16

Nos Nos Nos Nos

2 40 8 4

2 40 8 4

17

Nos Nos Nos Nos Nos

2 4 5 2 2

2 4 5 2 2

18 19 20 21 22

door door window window window

Sqm

8 7 4 7 2

1.00 0.75 1.65 0.80 0.90

2.00 2.00 2.00 2.00 1.25

23

Total Painting first coat over priming coat ( excluding cost of priming coat) painting with medium quality enemel paint on wooden/ steel door & windows and complete. In EE,room , AE ist, AE iiird rooms , camp rooms , AO room, and in their bath/ Toilets. Complete the work

Sqm

16.00 10.50 13.20 11.20 2.25 53.15

door door window window window

Sqm

8 7 4 7 2

1.00 0.75 1.65 0.80 0.90

2.00 2.00 2.00 2.00 1.25

24

Total Same as in item no 18 above but subseqent coat after first coat onasabove

Sqm Sqm same as above

16.00 10.50 13.20 11.20 2.25 53.15 53.15

24

25

One priming coat & one coat of dry distemper on new / old surface including supply of all materials , labour , t&p etc. complete. for E.E.,S room ceilling for A.E ist/ iind room ceilling for A.E. iiird room ceilling Toilet with attech A.E. ist room ceilling Toilet with attech A.E. iiird room ceilling Toilet with attech E.E.,s room ceilling Genaral w.c.,urinals for office stoff

Sqm

Sqm

ceilling ceilling Toilet with attech A.O.,s room ceilling J.E. ( T ) Room ceilling Total Same as above item no 20 but for each coat of distemper after the first coat & complete. Replece old damaged Electric wiring with New Fittings Electric wirings in Rooms & bath etc. Complete the work.

2 2 1 2 2 1 2 2 1 2 2 1 2 2 1 2 2 1 2 2 4 4 1 2 2 2 1 2 2 1

6.30 4.30 6.30 5.30 3.30 5.30 4.40 3.15 4.40 2.50 2.10 2.50 2.80 2.20 2.80 2.80 2.00 2.80 4.80 2.40 2.10 1.50 4.80 2.10 2.10 1.70 6.30 3.30 2.40 6.30

3.40 3.40 4.30 3.40 3.40 3.30 3.60 3.60 3.15 1.30 1.30 2.10 1.10 1.10 2.20 1.30 1.30 2.00 0.90 0.90 0.90 0.90 2.40 1.50 1.10 1.10 4.30 3.00 3.00 4.30

Sqm

42.84 29.24 27.09 36.04 22.44 17.49 31.68 22.68 13.86 6.50 5.46 5.25 6.16 4.84 6.16 7.28 5.20 5.60 8.64 4.32 7.56 5.40 11.52 6.30 4.62 3.74 27.09 19.80 14.40 27.09 409.20

26

Sqm same

as

above

409.20

27

job

1.00

Junior Engineer

Assistant Engineer

BILL OF QUANTITY Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly. S. No.
1

Item of work
Dismantling Brick / Tile work of old damaged Toilets, Bath rooms ( to chnge techanical room /A.E. and disposal of dismamtled material up to lead of 1000m. All labour T&p etc complete. Scraping of Bricks Dismantled from Brick Work including Stacking.( obtain from dismantled brick work.) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry ( damaged surface of old plaster )

Unit

Qty.

Rate

Per

Amount

Cum Nos

14.85 684.00

155.70 0.60

Cum Nos

2312.22 410.40

2 3

Sqm

131.68

7.20

Sqm

948.096

Providing and Fixing of M.S.Sheets on roof of AE iiird / AO/ Store godwn room including supplying of sheets nuts & bolts all materials , labour for fixing etc complete . Earth Work in excavation in foundation in ordinary soil etc i/c all lead & lift, all labour T & P etc. Complete. For construction of new General Toilets & w.c for official use . Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.( in foundation & flooring of urinals,toilets) Cum 4.98 4008.00 Cum 19956.83

Sqm

49.59

741.70

Sqm

36780.90

Cum

11.53

126.00

Cum

1452.94

Brick masonry work in 1:3 in substructure complete excluding pointing and plastering, as per drawing and Technical Specifications in construction of new urinals,Toilets, & side wall of store godown room no 1 & reconstruction of parapet wall of roofs by dismanteling of old damaged parapets complete the work. Plain M15 Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. In plinth of new urinals & toilets and its flooring.complete.

Cum

33.18

3831.90

Cum

127140.53

Cum 9

2.13

4540.80

Cum

9669.07

Plastering with cement mortar


(1:3) Cement : coarse sand over brick work and over old damaged dismantled portion & complete.

Sqm

299.04

98.40

Sqm

29425.09

10

Providing & Repreparing falls ceelling at place of old damaged as under ( as per market rates ) providing and fixing urinals sheets,Tapes washbasin,water supply/drainage fittings W.C.fittings, cysterns fittings etc. complete . ( in combine bath & toilets ) with atached E.E.,s room with aatached A.E. ist room with attech A.E. iiird room with attech Accountant officer room Genaral w.c.,urinals for office stoff Providing and laying of floor tiles including supply of all materials such as tiles,cement,c.sand,labour etc&complete Providing and laying of wall tiles in baths including supply of all materials such as tiles,cement,c.sand,labour etc&complete Supply & Fixing steel grills,sections in old existing windows in rooms , & ventiletors into bathrooms. Supply & Fixing glass pannels in old windows replesed to damaged pannels Supply of wooden furniture as under& complete A - Tables of size 6' x 4' ft B - Chairs C - Chairs D - Benches Supply of Steel Almirah with Box cell 6 Nos each including fittings locks in each and complete. Supply of ceilling Fans & fittings complete Supplying & fittings of coolers Supply of computers with assesaries required for work official work. Supplying of computr Tables Apply priming coat over new steel and other metal surface after and including prepairing the surface throughly cleaning oil grease dirt etc and scoured with wire brushes, fine steel / wood scrappers sand papering and knoting including cost of all materials, labour abd t&p[ etc required for proper completion of work. S.I. ( chapter 15 new item 1 )

Sqm

40.15

400.00

Sqm

16060.00

11

job job job job job

1.00 1.00 1.00 1.00 1.00

20200.00 20200.00 20200.00 20200.00 27910.00

Job Job Job Job Job

20200.00 20200.00 20200.00 20200.00 27910.00

12

Sqm

93.27

1354.80

Sqm

126362.20

13

Sqm

88.83

688.20

Sqm

61132.81

14

Sqm Sqm

10.95 2.00

1750.00 807.00

Sqm Sqm

19153.75 1614.00

15 16

Nos Nos Nos

2 40 8 4

11500.00 1600.00 3500.00 650.00

Nos Nos Nos Nos

23000.00 64000.00 28000.00 2600.00

17

Nos Nos Nos Nos Nos

2 4 5 2 2

18000.00 2000.00 9000.00 56000.00 3500.00

Nos Nos Nos Nos Nos

36000.00 8000.00 45000.00 112000.00 7000.00

18 19 20 21 22

Sqm

53.15

17.00

Sqm

903.55

23

Painting first coat over priming coat ( excluding cost of priming coat) painting with medium quality enemel paint on wooden/ steel door & windows and complete. In EE,room , AE ist, AE iiird rooms , camp rooms , AO room, and in their bath/ Toilets. Complete the work S.I. ( chapter 15 new item 2 ) Same as in item no 23 above but subseqent coat after first coat onasabove One priming coat & one coat of dry distemper on new / old surface including supply of all materials , labour , t&p etc. complete. ( S.I.no 681 ) Same as above item no 20 but for each coat of distemper after the first coat & complete. ( S.I. no 682 ) Replece old damaged Electric wiring with New Fittings Electric wirings in Rooms & bath etc. Complete the work.

Sqm

53.15

25.00

Sqm

1328.75

24

Sqm

53.15

20.00

Sqm

1063.00

25

Sqm

409.20

22.00

Sqm

9002.40

26

Sqm

409.20

11.00

Sqm

4501.20

27

job

1.00

35000.00

Job

35000.00

938527.73

Junior Engineer

Assistant Engineer

Ceritication of Rates
Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly. It is to certified that the rate of the following items of work i.e. for item No. 1 to 31 S. No. Item of work Unit Rate
1 2 3 4

Remarks

Dismantling of Brick work and disposal of dismantled material upto a lead of 1000m .
Scraping of Bricks Dismantled from Brick Work including Stacking. Scarping Plaster in Lime or Cement Mortar from Brick/ Stone Masonry

Cum

155.70 0.60 7.20

Earth work in excavation in foundation of structures as per drawing and technical specifications. Cum 126.00 Cement concrete with 4cm gauge approved stone ballast, approved coarse sand cement in the proportion of 6:3:1 icluding supply of the all material, labour and T & P etc. required for proper comletion of the work First Class Brick Work in 1:3 Cement and Coarse sand Plastering with cement mortar (1:3) Cement : coarse sand
PCC M 15 / Plain Cement Concrete in Open foundation

Cum Cum

4008.00 3831.90 98.40


4540.80

6 7 8 9 10 11 12 14 15 16

Sqm
Cum

Providing & fixing M.S.Sheets on roof Fittings into Toilets/ bath for General office stoff Fittings into Toilets/ bath atteched EE/AE room Providing and laying of floor tiles Providing and laying of wall tiles Providing and laying of wall tiles Supply & Fixing glass pannels in old

Sqm Nos Nos Sqm Sqm Sqm Sqm

741.70 27910.00 20200.00 1354.80 688.20 1750.00 807.00

It is also certified that I am component to approve the rates of all these items as per

Assistant engineer NH, PWD, Bareilly

Executive Engineer NH, PWD, Bareilly

Suprintending Engineer 28Th Circle, PWD, Bareilly

Summary of Cost
Name of work : Repair and Maintenance of Divisonal Office N.H.C.D.Pwd Bareilly
S.No. 1 Item of Work

( 2012 - 2013 )
Amount

Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly.


Total A

938527.73
938527.73 14077.92 9385.28 961990.92 961991.00

2 3

W.C. Establishment 1.5% on A Labour cess 1% on A Total

Say

Rs . 9.62 Lacs

Junior Engineer NH, PWD, Bareilly

Assistant Engineer NH, PWD, Bareilly

Executive Engineer NH, PWD, Bareilly

Suprintending Engineer 28th Circle NH, PWD, Bareilly

Vous aimerez peut-être aussi