Vous êtes sur la page 1sur 28

Combined Heat and Power (CHP)

Level 1 Feasibility Analysis

Prepared for
Company B
Anytown, USA
Company B Level 1 CHP Feasibility Study

Combined Heat and Power (CHP)


Level 1 Feasibility Analysis
Company B
Anytown, USA

1. Executive Summary

The EPA CHP Partnership has performed a Level 1 Preliminary Economic Analysis of
the installation of a combined heat and power (CHP) system at Company B’s facility in
Anytown, USA. 1 The purpose of this analysis is to determine whether CHP is technically
appropriate at this site and whether CHP would offer significant potential economic
benefit to Company B, in order for the company to make a decision about whether to
fund a more comprehensive study. We have analyzed the existing electrical and thermal
needs of the site, have gathered anecdotal data regarding the site operations and existing
equipment, and have spoken to site personnel about the current and planned utility plant
needs of the facility. Our results indicate that the site is potentially a good candidate for a
CHP project.

To run an economic analysis of a system with this level of data required the use of
assumptions and averages. This preliminary analysis should therefore be considered an
indicator of technical and economic potential only. The EPA CHP Partnership does not
design or install CHP systems and cannot guarantee the economic savings projected in
this analysis. Where assumptions have been made, we have attempted to be realistic or
conservative. These assumptions will be detailed in the following report and suggestions
will be provided as to the scope of engineering that would be part of a Level 2 Feasibility
Analysis if Company B chooses to proceed to the next step of project development.

The Company B facility in Anytown, USA, has approximately one million square feet of
conditioned space on the campus. Although the operation is single shift, the rigorously
controlled environment of this research facility requires 100% outside air for supply and
roughly 30 air changes per hour. These conditions impose significant chilled water and
hot water requirements for terminal reheat. Medium pressure steam (100 psig) is used
during the day for animal sanitation. The facility has a base electric load of 3500
kilowatts (kW). It is possible that the city of Anytown, USA, could build the facility,
generate power for their system, and sell steam to the Company B campus at a discount.

This analysis looks primarily at the marginal cost of generation (operating costs only—
including CHP system fuel, CHP maintenance costs, and a credit for CHP thermal
output) for the various options considered. It also looks at the impact of the difference in
gas transportation costs imposed by the city of Anytown, USA, and Utility B. The
analysis modeled four gas turbine CHP systems at two natural gas pricing levels—
1
The analysis was performed by Energy and Environmental Analysis, Inc,1655 N. Fort Myer Drive,
Arlington, VA, 22209. EEA is a technical subcontractor supporting the EPA CHP Partnership.

EPA CHP Partnership 1


Company B Level 1 CHP Feasibility Study

$8/million British thermal unit (MMBtu) and $11/MMBtu. The systems are sized to meet
the base thermal requirements of the facility so that 100% of the system’s thermal output
can be used on site. This approach to CHP system design is the most fuel efficient, most
environmentally beneficial, and usually provides the best return on investment. Two of
the systems evaluated produce power in excess of the facility’s base electrical needs. In a
Level 2 analysis, once detailed thermal profiles of the site have been developed, other
system sizes and configurations should be explored. Table 1 summarizes the options that
were studied and the resulting marginal cost of generation.

Table 1 – Summary of Results

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A* Turbine B* Turbine C* Turbine C*
Number of Turbines 1 1 1 2
Total Capacity (kW) 3,490 3,495 4,550 9,100
Turnkey Price $5,095,000 $6,750,000 $5,774,000 $9,624,000
Marginal Cost of
Generation at $8/MMBtu $0.0590/kWh $0.0538/kWh $0.0582/kWh $0.0632/kWh
Marginal Cost of
Generation at $11/MMBtu $0.0788/kWh $0.0718/kWh $0.0770/kWh $0.0839/kWh
* Turbines A, B, and C represent actual gas turbines. In a customized feasibility analysis, the EPA CHP
Partnership would identify the turbine model and manufacturer.

A number of conclusions can be drawn from the results presented:

• A CHP system appears to be a viable energy management option for Company B.


A Level 2 study should evaluate the impact of various ownership options for the
CHP system, including having the system completely owned and operated by
Company B or partnering with the city of Anytown, USA, to build the facility and
arrange to buy steam at a discount from the utility.
• If the power is to be used solely on site, either the Turbine A or the Turbine B gas
turbine systems appear to be viable candidates. The difference in the marginal
cost of generation was not sufficient to rule out either turbine, nor was the
difference in installed costs. Maintenance contract issues, as well as basic
maintainability of each machine, could make a difference in the economics and
should be evaluated in the Level 2 study.
• Supplementary firing to raise additional steam in the heat recovery steam
generator is important to the overall performance of the Turbine A or the Turbine
B system.
• If the facility is to be constructed and owned by the utility (or in partnership with
the utility), then the single Turbine C gas turbine system appears to be a viable
choice. Supplementary firing (even at the cost of installing emissions after

EPA CHP Partnership 2


Company B Level 1 CHP Feasibility Study

treatment 2 ) should be considered for this machine and investigated in the Level 2
study.
• The option with two Turbine C turbines did not perform as well as the other
options on a marginal cost of generation basis; this outcome is primarily because
the thermal output of this option could be greater than the needs of Company B.
• Although marginal cost was the primary measure of comparative performance in
this analysis and is most often the determining factor for dispatch decisions, it
should noted that other critical considerations are often included in investment
decisions. These considerations could include capital costs, emissions profile, and
other potential benefits to the site, such as enhanced power reliability.

2
Supplementary firing was not considered for either of the Turbine C options in this analysis because of
the impact on emissions. Turbine C can meet current Anytown, USA emissions standards without after
treatment. The addition of supplemental duct burners, however, might require the use of after treatment.

EPA CHP Partnership 3


Company B Level 1 CHP Feasibility Study

2. Preliminary Analysis Details and Assumptions

Facility Description

Company B’s campus in Anytown, USA, is engaged in research and development. The
facility is based in an area that has a moderate year-round climate. The 70-acre park-like
campus in Anytown, USA, is located within close proximity to several major academic
research institutions and numerous leading-edge companies in the region.

There are approximately one million square feet of conditioned space on the campus.
Although the operation is single shift, the rigorously controlled environment of this
research facility requires 100% outside air for supply and roughly 30 air changes per
hour. These conditions impose significant chilled water and hot water requirements for
terminal reheat. Medium pressure steam (100 psig) is used during the day for animal
sanitation.

Power Requirements – The facility’s electric and thermal loads were established by
evaluating 15-minute interval data for gas and electric meters in 2004. Based on this
analysis, the facility has a peak electric demand of approximately 8,000 kW, yearly
average demand of about 4,700 kW, and a base electric load of 3,500 kW. The base
power demand is primarily used to operate the air handlers that provide the 30 air
changes per hour. Figure 1 illustrates the facility’s average demand for 2004. From
Figure 1, it can be seen that the minimum average demand occurs in the month of March.
Figure 2 displays interval demand data for the month of March and indicates that the
minimum demand occurred on March 28, 2004. Figure 3 displays the interval demand
data for March 28. Figures 1, 2, and 3 confirm the 3500 kW base load power demand.

Figure 1 – Average Hourly Demand

6000

5000
4000
Average
3000
Demand (kW)
2000

1000

0
v
b

g
r

n
n

c
l

p
ar

t
ay

ju
ap

no
oc
fe

ju
ja

au

se

de
m

Month

EPA CHP Partnership 4


Company B Level 1 CHP Feasibility Study

Figure 2 – Interval Demand Data for the Month of March

9000
8000
7000
6000
5000
Demand (kW)
4000
3000
2000
1000
0
Local Time

12:00
2004-Mar-02
2004-Mar-03
2004-Mar-05
2004-Mar-06
2004-Mar-08
2004-Mar-09
2004-Mar-11
2004-Mar-12
2004-Mar-14
2004-Mar-15
2004-Mar-16
2004-Mar-18
2004-Mar-19
2004-Mar-21
2004-Mar-22
2004-Mar-24
2004-Mar-25
2004-Mar-27

2004-Mar-29
2004-Mar-31
Day of the Month

Figure 3 – Interval Demand Data for March 28, 2004

5500
5000
4500
De mand (kW) 4000
3500
3000
2500
1 2 :0 0

1 4 :2 4

1 6 :4 8

1 9 :1 2

2 1 :3 6
0 :0 0

2 :2 4

4 :4 8

7 :1 2

9 :3 6

0 :0 0
Tim e of Day

Thermal Requirements – Figure 4 demonstrates the facility’s current average hourly


demand for natural gas based on monthly natural gas bills.

EPA CHP Partnership 5


Company B Level 1 CHP Feasibility Study

Figure 4 – Average Hourly Natural Gas Consumption

35.00
30.00
25.00
Average Gas 20.00
Cosumption
(MMBtu/hr) 15.00
10.00
5.00
0.00

v
b

g
r
n

c
l

p
ar

t
ay

ju
ap

no
oc
fe
ja

ju

au

se

de
m

m Month

As described above, natural gas is currently used for hot water (primarily for terminal
reheat) and steam for process cleaning. The process steam is used during daily
operations. Hot water is used to heat supply air to ensure the buildings meet the design
point of 72°F (when necessary). Company B has made the corporate decision to replace
their centrifugal chillers with double effect absorption chillers. Based on weather data
and load data provided by Company B, Dr. John Smith of the city of Anytown, USA,
developed an estimate of the facility’s chilled water loads and the steam that would be
required by the double effect absorbers to meet the estimated chilled water load. This
analysis used the chilled water and steam estimates developed by Dr. Smith and overlaid
the steam requirement of the proposed chillers to the steam that is currently required to
supply the hot water and process steam needs for facility. The results (average hourly
aggregate steam requirements) are shown in Figure 5.

Figure 5 – Average Hourly Aggregate Steam Requirements

35,000
30,000
25,000
Steam 20,000 Absorber Requirement
Requirement
(MMBtu/hr) 15,000 Existing Thermal Load
10,000
5,000
-
v
n

p
ar

ay

Ju

No
Ja

Se
M

Month

EPA CHP Partnership 6


Company B Level 1 CHP Feasibility Study

Figure 5 shows that the steam requirement of the absorption chiller fills in demand during
the months when the facility’s hot water demand tapers off. This analysis indicates that
there will be a reliable steam demand of at least 17,000 to 20,000 lbs/hour year-round
once the absorption chillers are installed. Table 2 presents the total purchased power and
boiler fuel for the facility with current equipment (including existing electric chillers and
based on 2004 utility data) and for the situation where the existing electrical centrifugal
chillers are replaced by double effect absorption chillers. Annual purchased power is
reduced by approximately 5,730,000 kilowatt-hours (kWh); boiler fuel is increased by
109,500 MMBtu/yr.

Table 2 – Facility Purchased Power and Boiler Fuel Consumption

Current Equipment
(With Electric Chillers) With Absorption Chillers
Annual Purchased Power (kWh) 40,988,040 35,258,040
Annual Boiler Fuel (MMBtu) 165,892 275,391

Dr. Smith’s analysis calculated 24 hour daily averages for chiller operations, which was
considered sufficient for this level of analysis. However, it is our understanding that the
energy management system at the facility prevents chiller operation when the outside air
temperature is below 64°F. Bin temperature data for the area seems to indicate that this
operating regimen would result in virtually no chiller operation in the months of January,
February, November, and December. Chiller operation in the summer would vary from
12 to 16 hours per day. This information needs to be studied much more closely in any
Level 2 analysis to be certain that “needle peaks” for the steam consumption arising from
absorption chiller operations are not masked by averaging chiller operation data. Further
analysis also would help confirm the potential usefulness of chilled water storage to
reduce such steam demand peaks.

Combined Heat and Power Options

Several CHP options based on gas turbine generators were evaluated. Gas turbines have
long been used in CHP applications, and the steam that can be generated from hot turbine
exhaust matches the steam conditions (temperature and pressure) that the Company B
facility currently uses, along with the steam requirements of double effect absorption
chillers. As shown in Figure 6, a gas turbine would generate electric power at the facility.
This power could solely be used on site, or if Anytown’s electric utility chose to build the
plant, they could deliver the power to their grid. In the latter case, Company B would
purchase 100% of their power needs from the utility. Hot exhaust is then routed to the
heat recovery steam generator (HRSG). As will be discussed below, two analyzed options
incorporated the use of a duct burner in the turbine exhaust to provide additional steam
beyond what the unfired gas turbines could provide. (The turbine exhaust still has 15%
oxygen sufficient to support further combustion.)

EPA CHP Partnership 7


Company B Level 1 CHP Feasibility Study

Figure 6 – System Schematic

Steam from the HRSG would be provided to meet three primary thermal demands. The
first demand is heating the hot water that is required for domestic hot water needs and for
terminal reheat in the heating, ventilation, and air conditioning (HVAC) system.
Secondly, it might be useful to have a hot water storage tank 3 to provide the system with
a thermal flywheel as indicated in Figure 6. Lastly, steam would also be supplied to the
double effect absorption chillers and for the facility’s cleaning requirements.

Gas Turbine Options

Three different gas turbines have been considered in this Level 1 analysis. These are
Turbine A, Turbine B, and Turbine C. 4 Table 3 presents the key performance features for
each of these machines.

Table 3 – Candidate Gas Turbines

Turbine A Turbine B Turbine C

Net Generating Capacity (kW) each: 3,490 3,495 4,550


Heat Rate (Btu/kWh, HHV): 14,248 13,680 10,290
Electric Generating Efficiency 24.0% 24.9% 33.2%
(HHV):
Duct Firing Capability: Yes Yes No
Unfired Steam Production (lbs/hr): 19,600 20,000 14,100
Fired Steam Production (lbs/hr): 30,400 29,000 N/A

3
The cost of hot water storage was not included in this analysis
4
In a customized feasibility analysis, the EPA CHP Partnership would name actual equipment
manufacturers to form the basis of this analysis.

EPA CHP Partnership 8


Company B Level 1 CHP Feasibility Study

The four cases included in this analysis consist of the following:


• Option 1 – One Turbine A (Power used only on site)
• Option 2 – One Turbine B (Power used only on site)
• Option 3 – One Turbine C (100% of the power exported)
• Option 4 – Two Turbine Cs (100% of the power exported)

Table 4 summarizes the key parameters of each proposed CHP option. For the first two
options outlined in the table, an additional variation is considered—supplemental firing in
the HRSG. Supplementary firing will allow the first two options to raise additional steam.
Use of the supplemental burners can be modulated to match HRSG steam output to
hourly steam demand at the facility.

Table 4 –CHP Options

Option 1 Option 2 Option 3 Option 4


Gas Turbine: Turbine A Turbine B Turbine C Turbine C
Number of Turbines: 1 1 1 2
Total Capacity (kW): 3,490 3,495 4,550 9,100
Supplemental Firing Capability? Yes Yes No 5 No
Max Steam, unfired (lbs/hr) 19,600 20,000 14,100 28,200
Max Steam, fired (lbs/hr): 30,400 29,000 na na
Fuel Consumption, Unfired (MMBtu/hr) 49.7 47.8 46.8 93.6
Fuel Consumption, Fired (MMBtu/hr): 61.4 56.8 na na
Assumed Availability: 92% 92% 92% 92%

Screening Analysis

Electricity Production

As described above, the baseload electric demand of the plant was verified to be 3,500
kW. Annual plant operating hours are 8,760. The first two CHP options considered were
both assumed to provide 3,490 kW and 3,495 kW respectively. The third option
considered was 4,550 kW and the fourth option considered was 9,100 kW (twice the third
option). For the first two options, all power output could be used on site. For the last two
options, the gas turbines provide power output that exceeds the plant’s base load. For
conservatism, the analysis assumes an availability factor of 92% for the turbines,
representing 8,059 run hours per year. Typical gas turbine systems have actual
availabilities of 97 to 98%.

As described in Table 2, total plant power consumption is estimated to be 35,258,040


kWh/yr after conversion of the electric chillers to double effect absorption units; total
needed boiler fuel without CHP is estimated to be 275,390 MMBtu/yr. The total power

5
It is believed that if Turbine C is not supplementary fired, that selective catalytic reduction (SCR) would
not be required. However, adding a supplementary burner would change this. For Turbine A and Turbine
B, SCR would be required as a NOx control measure regardless if the turbines were supplementary fired or
not.

EPA CHP Partnership 9


Company B Level 1 CHP Feasibility Study

generated, CHP fuel consumed (including for the supplemental HRSG duct burner where
appropriate), and boiler fuel consumed for steam needs not met by the CHP system for
each of the options are shown in Table 5 and Table 6.

Table 5 – Annual CHP Energy Balance (Unfired HRSG Case)

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A Turbine B Turbine C Turbine C
Number of Turbines 1 1 1 2
Total Generation (kWh) 28,203,667 28,244,074 36,769,824 73,539,648
Purchased Power (kWh) 7,054,373 7,013,966 35,258,040 35,258,040
CHP Fuel Consumed (MMBtu) 401,724 386,267 378,237 756,473
Boiler Fuel Consumed (MMBtu) 73,624 70,257 127,908 26,673

Table 6 – Annual CHP Energy Balance (Fired HRSG Case)

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A Turbine B Turbine C Turbine C
Number of Turbines 1 1 1 2
Total Generation (kWh) 28,203,667 28,244,074 36,769,824 73,539,648
Purchased Power (kWh) 7,054,373 7,013,966 35,258,040 35,258,040
CHP Fuel Consumed (MMBtu) 440,037 419,937 378,237 756,473
Boiler Fuel Consumed (MMBtu) 22,031 24,311 127,908 26,673

Recommended Activities for Level 2: Assumptions on peak, average, and base electric
loads should be reviewed in detail and specific seasonal and/or daily variations should be
identified and included for system sizing and detailed economic calculations. A detailed
electric profile would enable an accurate analysis of savings and would ensure that the
system is sized correctly for the application. The load profile should also consider any
projected load growth at the facility. As described earlier, a much more thorough analysis
of the facility’s chilled water consumption should be included in a Level 2 analysis. This
information would help to confirm that the 3,500 kW baseload demand is unaffected by
the switch from electric chillers to absorption chillers and would also more accurately
estimate total annual power needs at the facility.

Thermal Energy Production

Options 1 and 2 (unfired simple cycle turbines) and Option 3 (single Turbine C) all
produce thermal energy at levels at or below the 17 to 20 MMBtu/hr minimal thermal
demands of the site (including absorption chiller requirements). Boiler fuel requirements,
as shown in Table 5, remain significant in these options—to meet steam needs when
hourly demand is beyond CHP system thermal capacities and when the systems are down
for maintenance. Additional boiler fuel consumption is much lower for Options 1 and 2
with supplemental duct firing (Table 6) because the HRSG can increase steam output to
meet higher peak hourly demands. The boiler fuel consumption in these two cases is
essentially for supplying steam when the CHP systems are down for maintenance.

EPA CHP Partnership 10


Company B Level 1 CHP Feasibility Study

Similarly, the boiler fuel consumption for Option 4 (the two Turbine Cs) is for meeting
steam demands when the turbines are down for maintenance. The tables do not show,
however, that the average steam output of Option 4 at 29.2 MMBtu/hr often exceeds
maximum hourly steam demands and is therefore underutilized.

Recommended Activities for Level 2: The Company B facility has fairly detailed 15-
minute interval data available with which to measure likely minimum and maximum
steam consumptions. Using monthly average data, while appropriate for this level of
analysis, might mask steam consumption minimums that would lead to the dumping of
thermal energy, which would hurt the project’s overall economics. The use of interval
data would prevent such an error. Interval data also should be used to confirm the
usefulness of hot water storage and if useful, the necessary capacity.

Similarly, a much more thorough analysis of the facility’s chilled water consumption
should be included in a Level 2 analysis. This analysis would help confirm minimum and
maximum steam requirements, as well as the potential usefulness of chilled water
storage.

Budget Installation Costs

Preliminary budgetary cost estimates were developed for each option and included the
following equipment: turbine/generator, HRSG, electrical switchgear and controls,
mechanical interconnection to the existing thermal system, and necessary emission
control system (SCR for Turbine A and Turbine B). 6 .Budgetary estimates for each of the
turbine systems were provided by the respective vendors. The Turbine A system and the
Turbine B system were both quoted with duct burners. A discount was estimated based
on in-house data for the lack of such a burner where appropriate for Options 1 and 2. The
budget costs are turnkey and include engineering, labor, and commissioning. Total
installed cost estimates for the six systems are detailed in Table 7 below.

Table 7 – Budgetary Cost Estimates

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A Turbine B Turbine C Turbine C
Turnkey Price w/Duct Burner $5,095,000 $6,750,000 $5,774,000 $9,624,000
Deduction for Duct Burner ($250,000) ($250,000) N/A N/A
Turnkey Price w/o DB $4,845,000 $6,500,000 N/A N/A
Price per kW (w/ DB) $1,460/kW $1,931/kW $1,269/kW $1,058/kW
Price per kW (w/o DB) $1,388/kW $1,860/kW N/A N/A
Incremental Maintenance $0.006/kWh $0.006/kWh $0.008/kWh $0.008/kWh

Recommended Activities for Level 2: Following the electrical and thermal energy
analysis and system size/application decision detailed in the previous sections, substantial
preliminary design engineering (30%) would enable an accurate installation cost to be

6
A fuel gas compressor is not required because there is a high pressure transmission line just across the
street from the plant.

EPA CHP Partnership 11


Company B Level 1 CHP Feasibility Study

determined for this system. Assumptions about the ability of existing plant systems to be
used for the CHP system need to be confirmed. The requirements and cost of connecting
with a nearby high pressure gas line would also have to be estimated. Installation cost
issues will have the single biggest impact on return on investment for the project.

Emissions

Current emissions standards in Anytown, USA, are expected to require SCR for the
Turbine A and the Turbine B systems. The Turbine C system, if installed without a duct
burner, might be permittable without SCR.

Recommended Activities for Level 2: This analysis did not consider existing emissions at
the Company B facility and how these emissions might impact compliance requirements
for the CHP system. The level 2 analysis should evaluate costs associated with initial and
ongoing environmental compliance and reporting. Once a decision to proceed with the
project has been made, the site should engage qualified environmental consultants to
manage environmental compliance, including confirmation of the anticipated
requirements for emission control and reporting processes, and securing of construction
permits.

Utility Interconnection

Options 1 and 2 would be designed to operate in parallel with the utility and will need to
meet Utility B’s interconnection and safety requirements. 7 It is anticipated that the power
export options (3 and 4) would have the active participation of the Anytown, USA, utility
in the design and implementation.

Recommended Activities for Level 2: Engage in preliminary discussions with Anytown,


USA,’s municipal utility regarding interconnection and capture all costs associated with
meeting interconnection requirements.

Maintenance

Based on our discussions with vendors, this analysis uses an incremental maintenance
cost for the CHP systems of $0.006/kWh for the Turbine A and Turbine B gas turbines
and $0.008/kWh for Turbine C.

7
“Parallel” with the utility means the on-site generation system is electrically interconnected with the
utility distribution system at a point of common coupling at the site (common busbar) and facility loads are
met with a combination of grid- and self-generated power. Interconnection requires various levels of
equipment safeguards to ensure power does not feed into the grid during grid outages. A parallel
configuration is in contrast to “grid isolated” operation, wherein the CHP system serves either the entire
facility or an isolated load with no interconnection with the utility’s distribution system. Grid isolated
systems typically require increased capacity to cover facility peak demands and redundancy for back-up
support.

EPA CHP Partnership 12


Company B Level 1 CHP Feasibility Study

Recommended Activities for Level 2: A detailed maintenance proposal from the vendor
of the equipment selected in the final design should be provided and associated costs
included in the final economic analysis.

Power Reliability –CHP System as Backup Power

The primary benefit of a CHP system is that it produces power for less money than
separate heat and power. An additional benefit can be the use of the onsite capacity to
provide backup generation in the event of a utility outage. In certain applications, the
value of this additional reliability can outweigh all other factors in the investment
decision.

In order to implement this capability, there are added costs to tie into the existing
electrical systems that are beyond the scope of this level of analysis. Those costs can
include engineering, controls, labor, and materials. The engineering required to analyze
the existing electrical system, determine critical loads, provide a design, and determine
cost to provide backup power from the system can be fairly costly.

The justification for this additional cost should be financial: it pays to do it if there is a
way to account for the benefits in the financial analysis. One simple method is to offset
the turnkey cost of a similarly sized backup generator against the incremental cost of the
CHP system. There are other ways to account for the reliability benefits using
assumptions of avoided catastrophic revenue losses due to utility blackouts. Regardless of
how the benefits are quantified, it is important to provide some estimate that captures
reliability benefits to balance the incremental costs associated with this added capability.

Recommended Activities for Level 2: If the facility is interested in pursuing running the
system in the event of a utility outage, the engineering firm hired to perform the Level 2
analysis should be very experienced in electrical design and use of CHP as a backup
system. Extensive review of the site’s existing electrical system and identification of
critical loads should be considered along with the system sizing criteria previously
discussed in order to come up with the optimal system to meet the facility’s needs.

Baseline Utility Costs

The objective of this analysis was to calculate the marginal cost of generation of the
various CHP options as a function of the fuel cost. Currently natural gas is transported to
the facility by the Anytown, USA,’s municipal utility. To calculate the appropriate cost of
fuel, the transportation rate of the utility must be added to an estimated natural gas
commodity cost. The commodity cost is estimated by adjusting the 18-month strip at
Henry Hub 8 by the approximate basis 9 between Henry Hub and the Anytown border. In
addition, for comparison, the cost of fuel was calculated as if the natural gas had been

8
This is a futures contract that would allow a company to buy a specified quantity of natural gas at a single
price for the period of 18 months.
9
The current difference in spot market prices of natural gas at Henry Hub and in Anytown, USA.

EPA CHP Partnership 13


Company B Level 1 CHP Feasibility Study

delivered by the utility at their electric generation transportation tariff. The cost of fuel is
summarized in Table 8.

Table 8 – Cost of Fuel ($/MMBtu)

Anytown, USA Utility

Henry Hub 18 Month Strip $11.53 11.53


Basis to State Border ($3.83) ($3.83)
Transportation Costs $3.20 $0.20
Totals $10.90 $7.90

Because this calculation is clearly speculative regarding the calculation of the commodity
costs, the costs used in the analysis were rounded to $11.00/MMBtu and $8.00/MMBtu.

Recommended Activities for Level 2: Gas utilities are often willing to negotiate favorable
gas rates for CHP sites based on their substantial, constant, year-round demand. A minor
reduction in gas rates can have a profound impact on return on investment. Inquiries
should be made into negotiated rates based on the projected volumes of gas consumption
with CHP.

3. Economic Analysis
The results of the economic screening for the CHP options without supplemental duct
burners are shown in Table 9 and graphically in Figure 7. The marginal cost of generation
was calculated for each CHP option. The marginal cost includes operating costs only—
including CHP system fuel, CHP maintenance costs, and any credit for CHP thermal
output for the various options considered.

Table 9 – Marginal Costs of Generation (without supplemental firing)

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A Turbine B Turbine C Turbine C
Number of Turbines 1 1 1 2
Total Capacity (kW) 3,490 3,495 4,550 9,100
Marginal Cost of Generation
at $8/MMBtu $0.0627/kWh $0.0573/kWh $0.0582/kWh $0.0632/kWh
Marginal Cost of Generation
at $11/MMBtu $0.0840/kWh $0.0765/kWh $0.0770/kWh $0.0839/kWh

EPA CHP Partnership 14


Company B Level 1 CHP Feasibility Study

Figure 7 – Marginal Costs of Generation (without supplemental firing)

$0.0900
$0.0800
$0.0700
$0.0600
Marginal Cost $0.0500
of Power
$0.0400 $8/MMBtu
($/kWh)
$0.0300 $11/MMBtu
$0.0200
$0.0100
$0.0000
Turbine A Turbine B Turbine C Two Turbine Cs

CHP Options

Table 10 and Figure 8 present the results for the CHP options with in inclusion of
supplemental HRSG duct firing for Options 1 and 2.

Table 10 – Marginal Cost of Generation (with supplemental firing)

Option 1 Option 2 Option 3 Option 4


Gas Turbine Turbine A Turbine B Turbine C Turbine C
Number of Turbines 1 1 1 2
Total Capacity (kW) 3,490 3,495 4,550 9,100
Marginal Cost of Generation
at $8/MMBtu $0.0590/kWh $0.0538/kWh $0.0582/kWh $0.0632/kWh
Marginal Cost of Generation
at $11/MMBtu $0.0788/kWh $0.0718/kWh $0.0770/kWh $0.0839/kWh

EPA CHP Partnership 15


Company B Level 1 CHP Feasibility Study

Figure 8 – Marginal Costs of Generation (with supplemental firing)

$0.0900
$0.0800
$0.0700
$0.0600
Marginal Cost $0.0500
of Power
($/kWh) $0.0400 $8/MMBtu
$0.0300 $11/MMBtu
$0.0200
$0.0100
$0.0000
Turbine A Turbine B Turbine C Two Turbine Cs

CHP Options

The best performing system, based on the marginal cost of generating, was the Turbine B
gas turbine with supplementary firing. The primary reason for this outcome was that
Turbine B is slightly more efficient than Turbine A and with supplementary firing, it
could meet more of the thermal energy requirement than the single Turbine C. The results
for the two Turbine C options varied. The single Turbine C had competitive marginal
generating costs with the unfired simple cycle turbines used in Options 1 and 2. While the
recuperated Turbine C produces much less usable thermal energy per kWh generated than
either of the simple cycle turbines, the higher electric generating efficiency of Turbine C
keeps marginal costs competitive. The greater thermal displacement of Options 1 and 2
when supplemental duct firing is added further lowers the marginal costs of these
options—duct firing results in a $0.003 to $0.005/kWh reduction in marginal generating
costs. The marginal costs of Option 4 (two Turbine Cs) are comparatively high due to the
fact that there are times when the combined thermal output of the two-turbine system is
above the thermal demands of the site and is essentially wasted.

The tables also illustrate that the $3/MMBtu difference in gas costs between the
$8/MMBtu case and $11/MMBtu case results in an almost $0.02/kWh increase in
marginal generating costs across the four options. Detailed summaries of the results are
included in the appendix.

EPA CHP Partnership 16


Company B Level 1 CHP Feasibility Study

4. Conclusions
This Level 1 analysis points to several conclusions:

• A CHP system appears to be a viable energy management option for Company B.


A Level 2 study should evaluate the impact of various ownership options for the
CHP system, including having the system completely owned and operated by
Company B or partnering with Anytown, USA, to build the facility and arrange to
buy steam at a discount from the utility.
• If the power is to be used solely on site, either the Turbine A or the Turbine B
systems appear to be viable candidates. The difference in the marginal cost of
generation was not sufficient to rule out either turbine, nor was the difference in
installed costs. Maintenance contract issues, as well as basic maintainability of
each machine, certainly could make a difference in the economics and should be
evaluated in the Level 2 study.
• Supplementary firing to raise additional steam in the heat recovery steam
generator is important to the overall performance of the Turbine A or the Turbine
B systems.
• If the facility is to be constructed and owned by the utility (or in partnership with
the utility), then the single Turbine C system appears to be a viable choice.
Supplementary firing (even at the cost of installing SCR 10 ) should be considered
for this machine and investigated in the Level 2 study.
• The option with two Turbine C turbines did not perform as well as the other
options on a marginal cost of generation basis; this outcome is primarily because
the thermal output of this option could be greater than the needs of Company B.
• Although marginal cost was the primary measure of comparative performance in
this analysis and is most often the determining factor for dispatch decisions, it
should noted that other critical considerations are often included in investment
decisions. These considerations could include capital costs, emissions profile, and
other potential benefits to the site, such as enhanced power reliability.

10
Supplementary firing was not considered for either of the Turbine C options in this analysis because of
the impact on emissions. Turbine C can meet current Anytown, USA emissions standards without
aftertreatment. The addition of supplemental duct burners may require use of SCR.

EPA CHP Partnership 17


Company B Level 1 CHP Feasibility Study

Appendix

EPA CHP Partnership 18


Company B Level 1 CHP Feasibility Study

Company B - $8.00/MMBtu Gas Price Case

Plant Consumption Details


Peak Demand (Annual peak), kW 8,000 Based on 2004 electricity usage
Average MW Demand, kW 4,679 Based on 2004 electricity usage
Average Thermal Heating Demand, MMBtu/hr 15.15 Based on 2004 natural gas usage
Average thermal Cooling Demand, MMBtu/hr 10.00 Estimated based on converting existing chiller load to double effect absorption
Operating Hours 8,760
Current Annual Power Consumption, kWh 40,988,040 Based on 2004 electricity usage
Base Case Annual Power Consumption, kWh 35,258,040 Based on converting existing chiller load to double effect absorption
Base Case Annual Thermal Consumption, MMBtu 220,313 Includes heating and cooling loads
Plant annual power to heat ratio 0.6
Estimated Boiler Heater Efficiency % 80%

Average Gas Cost $/MMBtu $8.00

CHP Options
Turbine A Turbine A Turbine B Turbine B One Two
Prime Mover w/duct firing w/o duct firing w/duct firing w/o duct firing Turbine C Turbine Cs
Turbine Capacity, kW 3,490 3,490 3,495 3,495 4,550 4,550
Number of Turbines 1 1 1 1 1 2
Duct Burner Capability? Yes Yes Yes Yes No No
CHP System Electric Capacity kW 3,490 3,490 3,495 3,495 4,550 9,100
Electrical Efficiency, HHV 24.0% 24.0% 24.9% 24.9% 33.2% 33.2%
MMBtu/hr Thermal Provided (unfired) 20.3 20.3 20.7 20.7 14.6 29.2
Power to Heat Ratio 0.6 0.6 0.6 0.6 1.1 1.1
System Availability, % 92% 92% 92% 92% 92% 92%
System Hours of Operation 8,059 8,059 8,059 8,059 8,059 8,059
Power Generated Annually, kWh 28,203,667 28,203,667 28,244,074 28,244,074 36,769,824 73,539,648
Thermal Generated Annually, MMBtu 202,688 164,050 202,688 167,282 117,987 235,973
CHP Thermal, MMBtu/yr 164,050 164,050 167,282 167,282 117,987 235,973
Duct Burner Thermal, MMBtu/yr 38,638 0 35,405 0 0 0

Capital Cost, $ $5,095,000 $4,845,000 $6,750,000 $6,500,000 $5,774,400 $9,624,000


Capital Costs, $/kW $1,460 $1,388 $1,931 $1,860 $1,269 $1,058
O&M Cost, $/kWh $0.0060 $0.0060 $0.0060 $0.0060 $0.0080 $0.0080

Turbine A Turbine A Turbine B Turbine B One Two


Economics Base System* w/duct firing w/o duct firing w/duct firing w/o duct firing Turbine C Turbine Cs

Energy Summary
Purchased Power, kWh 35,258,040 7,054,373 7,054,373 7,013,966 7,013,966 35,258,040 35,258,040
Generated Power, kWh 0 28,203,667 28,203,667 28,244,074 28,244,074 36,769,824 73,539,648
Boiler Steam, MMBtu/yr 220,313 17,625 58,899 17,625 56,205 102,326 21,338
CHP Thermal Used, MMBtu/yr 0 202,688 164,050 202,688 167,282 117,987 198,975
Boiler Fuel, MMBtu/yr 275,391 22,031 73,624 22,031 70,257 127,908 26,673
CHP Fuel, MMBtu/yr 0 440,037 401,724 421,853 386,267 378,237 756,473
(CHP system + duct burner)

Cost Summary
Boiler Fuel Savings n/a ($2,026,879) ($1,614,138) ($2,026,879) ($1,641,076) ($1,179,867) ($1,989,749)
CHP Fuel n/a $3,520,298 $3,213,791 $3,374,822 $3,090,139 $3,025,894 $6,051,787
CHP O&M n/a $169,222 $169,222 $169,464 $169,464 $294,159 $588,317
Total Costs n/a $1,662,641 $1,768,875 $1,517,407 $1,618,528 $2,140,185 $4,650,356
Cost per kWh Generated: n/a $0.0590 $0.0627 $0.0537 $0.0573 $0.0582 $0.0632

* Base System assumes


existing chiller load converted to
double effect absorption Cost per Generated kWh = total incremental cost of CHP (CHP fuel+CHP O$M-boiler savings) diveded by kWh generated

EPA CHP Partnership 19


Company B Level 1 CHP Feasibility Study

Company B - $11.00/MMBtu Gas Price Case

Plant Consumption Details


Peak Demand (Annual peak), kW 8,000 Based on 2004 electricity usage
Average MW Demand, kW 4,679 Based on 2004 electricity usage
Average Thermal Heating Demand, MMBtu/hr 15.15 Based on 2004 natural gas usage
Average thermal Cooling Demand, MMBtu/hr 10.00 Estimated based on converting existing chiller load to double effect absorption
Operating Hours 8,760
Current Annual Power Consumption, kWh 40,988,040 Based on 2004 electricity usage
Base Case Annual Power Consumption, kWh 35,258,040 Based on converting existing chiller load to double effect absorption
Base Case Annual Thermal Consumption, MMBtu 220,313 Includes heating and cooling loads
Plant annual power to heat ratio 0.6
Estimated Boiler Heater Efficiency % 80%

Average Gas Cost $/MMBtu $11.00

CHP Options A B C D E F
Turbine A Turbine A Turbine B Turbine B One Two
Prime Mover w/duct firing w/o duct firing w/duct firing w/o duct firing Turbine C Turbine Cs
Turbine Capacity, kW 3,490 3,490 3,495 3,495 4,550 4,550
Number of Turbines 1 1 1 1 1 2
Duct Burner Capability? Yes Yes Yes Yes No No
CHP System Electric Capacity kW 3,490 3,490 3,495 3,495 4,550 9,100
Electrical Efficiency, HHV 24.0% 24.0% 24.9% 24.9% 33.2% 33.2%
MMBtu/hr Thermal Provided (unfired) 20.3 20.3 20.7 20.7 14.6 29.2
Power to Heat Ratio 0.6 0.6 0.6 0.6 1.1 1.1
System Availability, % 92% 92% 92% 92% 92% 92%
System Hours of Operation 8,059 8,059 8,059 8,059 8,059 8,059
Power Generated Annually, kWh 28,203,667 28,203,667 28,244,074 28,244,074 36,769,824 73,539,648
Thermal Generated Annually, MMBtu 202,688 164,050 202,688 167,282 117,987 235,973
CHP Thermal, MMBtu/yr 164,050 164,050 167,282 167,282 117,987 235,973
Duct Burner Thermal, MMBtu/yr 38,638 0 35,405 0 0 0
5.095 6.75 9.624
Capital Cost, $ $5,095,000 $4,845,000 $6,750,000 $6,500,000 $5,774,400 $9,624,000
Capital Costs, $/kW $1,460 $1,388 $1,931 $1,860 $1,269 $1,058
O&M Cost, $/kWh $0.0060 $0.0060 $0.0060 $0.0060 $0.0080 $0.0080

Turbine A Turbine A Turbine B Turbine B One Two


Economics Base System* w/duct firing w/o duct firing w/duct firing w/o duct firing Turbine C Turbine Cs

Energy Summary
Purchased Power, kWh 35,258,040 7,054,373 7,054,373 7,013,966 7,013,966 35,258,040 35,258,040
Generated Power, kWh 0 28,203,667 28,203,667 28,244,074 28,244,074 36,769,824 73,539,648
Boiler Steam, MMBtu/yr 220,313 17,625 58,899 17,625 56,205 102,326 21,338
CHP Thermal Used, MMBtu/yr 0 202,688 164,050 202,688 167,282 117,987 198,975
Boiler Fuel, MMBtu/yr 275,391 22,031 73,624 22,031 70,257 127,908 26,673
CHP Fuel, MMBtu/yr 0 440,037 401,724 421,853 386,267 378,237 756,473
(CHP system + duct burner)

Cost Summary
Boiler Fuel Savings n/a ($2,786,958) ($2,219,440) ($2,786,958) ($2,256,479) ($1,622,317) ($2,735,905)
CHP Fuel n/a $4,840,410 $4,418,963 $4,640,380 $4,248,942 $4,160,604 $8,321,208
CHP O&M n/a $169,222 $169,222 $169,464 $169,464 $294,159 $588,317
Total Costs n/a $2,222,673 $2,368,745 $2,022,886 $2,161,927 $2,832,446 $6,173,620
Cost per kWh Generated*: n/a $0.0788 $0.0840 $0.0716 $0.0765 $0.0770 $0.0839

* Base System assumes


existing chiller load converted to
double effect absorption Cost per Generated kWh = total incremental cost of CHP (CHP fuel+CHP O$M-boiler savings) diveded by kWh generated

EPA CHP Partnership 20


Level 2 CHP Feasibility Studies

Overview and Checklist

The tool provides an introduction to the elements of a Level 2 CHP feasibility study. It also
includes a checklist that energy users who are considering implementing CHP at their facilities
can use to:

• Review the results of a completed Level 2 CHP feasibility study for completeness
• Help develop the scope for the procurement of a Level 2 study

The checklist is a comprehensive listing of the items and issues that are considered in Level 2
studies. Please note, however, that each item in the checklist may not apply to every project.

What Is a Level 2 Feasibility Study?

A Level 2 CHP feasibility study is a detailed analysis of the economic and technical viability of
installing a CHP system. Usually, a Level 2 study will consider the return on investment for
multiple CHP system sizes, prime movers, and heat applications. The Level 2 study normally
follows a Level 1 CHP feasibility analysis and is based on more detailed engineering and
operational data from the site.

The purposes of a Level 2 study are to:

• Replace the assumptions used in the Level 1 feasibility analysis with verified data to
identify optimal CHP system configuration and sizing, appropriate thermal applications,
and economic operating strategies.
• Estimate final CHP system pricing.
• Calculate return on investment.

The outcomes of a Level 2 study are:

• Pricing estimates for construction and operation and maintenance of the CHP system.
• Existing and projected utility rate analysis.
• Final project economics, including simple payback and life-cycle cost analysis of the
investment.

The goals of a Level 2 study are to:

• Ensure that the recommended CHP system meets the operational and economic goals of
the investor.
• Provide all the information needed to make a final investment decision.

Level 2 Feasibility Checklist 1


Who Can Conduct a Level 2 Feasibility Study?

Different types of companies, including engineering firms, independent consultants, project


developers, and equipment suppliers, can conduct Level 2 studies. Project developers and
equipment suppliers may do so for reduced costs if the end user agrees to move forward with
them on the project if the results of the feasibility study meet some mutually agreed upon
threshold. Alternatively, engineering firms or consultants can provide an independent third-party
analysis of the CHP opportunity at an end-user’s site.

Regardless of the type of organization selected for the Level 2 study, end users should look for
the following critical qualities and capabilities when selecting the company that will conduct the
analysis:
• Previous experience with CHP and with the type of application under study.
• Sufficient in-house resources covering a full range of expertise, including engineering,
finance, operation, and environmental permitting.
• A proven track record of successfully completed Level 2 studies.

A number of CHP Partners provide both the experience and resources required for a successful
Level 2 study. To review a list of CHP Partners, visit www.epa.gov/chp/chp_partners.htm.

Suggestions for Ensuring the Success of a Level 2 Feasibility Study

A number of best practices have emerged for conducting successful Level 2 CHP feasibility
studies. End users can use the best practices that follow as models as they undertake their own
studies.

• Before the Level 2 study begins, it is recommended that the end user work together with
the engineer, consultant, project developer, or other entity selected to perform the
analysis to develop a mutual understanding of all operational goals for the project,
including needs for control, monitoring and maintenance, and whether the system will be
designed to run in the event of a utility outage. The potential for future load growth, due
either to planned site expansion or new construction, should also be considered.
• Successful Level 2 feasibility studies generally involve multiple site visits and thorough
review of existing electrical, mechanical, and structural drawings.
• Accurate system pricing generally involves making upfront determinations about system
size and location, prime mover, thermal applications, and preliminary design drawings,
including flow diagrams, equipment specifications, monitoring and control specification,
piping and wiring, and tie-in to existing building systems.
• Level 2 studies may need to include a detailed thermal and electrical load profile to
determine final system sizing and operation. To the extent possible, hard data should be
used to develop these profiles, pulled from electric utility interval data, existing controls
systems and/or the installation of data-loggers at the site.

Level 2 Feasibility Checklist 2


CHECKLIST FOR LEVEL 2 FEASIBILITY STUDIES

1 EXECUTIVE SUMMARY
1.1 Clear delineation of the objective of the feasibility study.

1.2 Brief description of site, energy needs, and recommended CHP equipment

selection.

1.3 Overview of project concept and economics. Simple payback, net present value,

and/or discounted cash flow for various financial arrangements.

1.4 Recommendations and rationale.

2 DESCRIPTION OF EXISTING SITE PLAN AND EQUIPMENT


2.1 Description of existing site and major energy consuming equipment; identify

systems/equipment that could be replaced or impacted by the proposed CHP

system.

2.2 Plot plan of site and proposed location of CHP system.

2.3 Description and location of existing electric feeds, transformers, and meters

including critical parameters such as voltage.

2.4 Description and location of existing gas lines, meters, fuel storage, etc., including

critical parameters such as pressure and capacity.

2.5 Identification of any site/location constraints or restrictions (site access, adjacent

properties, noise/zoning limitations).

2.6 Site expansion plans, if applicable.

2.7 Emergency/back-up power requirements and existing generating equipment.

2.8 Review of any possible power and thermal energy sales arrangements.

3 SITE ENERGY REQUIREMENTS


3.1 Review of recent gas and electric bills.

3.2 Review of current and projected gas (or other fuel) and electric rates.

3.3 Development of average hourly use patterns for each type of energy (on a

seasonal basis if appropriate) with thermal energy uses segregated by type/quality

(e.g., temperature, pressure, form [steam, hot water, hot air]).

3.4 Tables and/or graphs showing daily and annual use profiles for each form of

energy (e.g., electric/steam/hot water/chilled water).

3.5 Breakdown of energy usage, by type of energy, for equipment that is to be

displaced by CHP.

3.6 Review of CHP analysis methodology.

3.6.1 Description of computer modeling methods used.

3.6.2 Displaced thermal loads estimates and methodology

Level 2 Feasibility Checklist 3


3.6.3 Displaced electrical requirement estimates and methodology.

4 CHP EQUIPMENT SELECTION


4.1 Rationale for equipment selection.

4.1.1 Thermal output

4.1.2 Capacity

4.1.3 Emissions

4.1.4 Site constraints

4.1.5 Other

4.2 Discussion of alternative CHP system configurations

4.3 A quantitative and qualitative comparison of prime movers evaluated, including

model, kW capacity, fuel consumption comparison, seasonal performance,

electric and thermal energy displaced, sound levels, emissions, maintenance

requirements, availability/reliability, net revenue, capital cost, simple pay back,

or other “profitability index” used by the client.

5 DESCRIPTION OF PREFERRED CHP SYSTEM


5.1 System description – prime mover, generator, heat recovery

5.2 Electric and total CHP efficiency, amount of site energy displaced

5.3 Schematic of system – detailed layout

5.4 Single line diagram of thermal system

5.5 Single line diagram of electrical system.

5.6 System tie-ins

5.7 Controls and monitoring

5.8 N
ecessary site modifications

6 SYSTEM OPERATION
6.1 Operating hours per year.

6.2 Recommended operating profile (e.g., thermally base loaded, electric load

following, peaking).

6.3 Stand-alone (islanding) and black start capability needed?

6.3.1 Is load shedding required? If so, how is it implemented? How is

crossover accomplished?

7 REGULATORY AND PERMITTING REQUIREMENTS OVERVIEW


7.1 Review and description of emissions requirements for permitting, including

source(s) of information.

7.2 Review and description of local siting and zoning requirements.

Level 2 Feasibility Checklist 4


8 TOTAL CHP SYSTEM COSTS
8.1 Total costs – Summary of all inclusive or turnkey costs.

8.1.1 Capital costs - equipment

8.1.2 Installations costs – engineering, construction, commissioning

8.2 Capital costs - line item breakdown of major equipment/component costs.

8.2.1 Prime mover

8.2.2 Fuel compressor (if needed)

8.2.3 Black start capability (if needed)

8.2.4 Generator

8.2.5 Heat recovery

8.2.6 Cooling tower or other heat dump

8.2.7 Site electric tie-in and grid interconnection (islanding requirements

included if needed)

8.2.8 Controls

8.2.9 Site thermal tie-in

8.2.10 Additional thermal utilization equipment (e.g., absorption chillers)

8.2.11 Other equipment/modifications

8.2.11.1 Sound attenuation

8.2.11.2 Stack

8.2.11.3 Inlet air handling

8.2.11.4 Vibration

8.2.12 Emission controls

8.3 Installation costs – line-item breakdown of engineering, permitting, construction,

and contingency costs

8.3.1 Site preparation

8.3.2 Buildings (if needed)

8.3.3 Materials

8.3.4 Engineering

8.3.5 Construction

8.3.6 Permitting fees

8.3.7 Contingency

9 Non-fuel O&M costs (fixed and variable) – details on maintenance costs for major
system components and site interfaces; information on costs of turnkey versus self-
maintenance, and major maintenance/overhaul items and schedule

9.1 Prime mover

9.2 Heat recovery equipment

9.3 Thermal utilization equipment

9.4 Emissions control

10 PROJECT SCHEDULING-BREAKDOWN OF EACH PHASE (should include major


subcategories or elements)

Level 2 Feasibility Checklist 5


10.1 Purchase of equipment.

10.2 Construction

10.3 Permitting

10.4 Commissioning

11 ASSUMPTIONS FOR CASH FLOW ANALYSIS


11.1 Financing options and assumptions

11.1.1 Debt/equity ratio

11.1.2 Discount rate

11.1.3 Interest rate/Cost of debt

11.1.4 Tax rate

11.2 Total installed costs

11.2.1 CHP equipment and installation from Section 8 above

11.2.2 Any capital credit for displaced equipment purchases

11.3 Operation and maintenance

11.3.1 Self maintained

11.3.2 Supplier/vendor maintenance contract

11.4 Fuel and electric rates

11.4.1 Based on detailed tariffs/rates

11.4.1.1 Electric – customer charge, demand charge, commodity

charge; peak, off-peak, shoulder

11.4.1.2 Gas – commodity, delivery

11.4.2 Provide fuel/electric escalation rates assumed for outyears.

11.4.3 Review any changes to tariffs due to CHP

11.4.3.1 Supplemental electric tariffs

11.4.3.2 Standby rates/exit fees

11.4.3.3 Gas incentive rates

11.5 Any additional costs or credits

11.5.1 Incentives

11.5.2 Value of reliability

11.5.2.1 Cost of facility outages and value of increased power

reliability

11.5.3 Other benefits that can be monetized or assigned value

11.5.3.1 Emission credits

11.5.3.2 Other

11.6 Sensitivity analysis – impact of varying:

11.6.1 Fuel costs

11.6.2 Electric rates

11.6.3 Incentives

Level 2 Feasibility Checklist 6


11.6.4 CHP system availability (impact of CHP outages)

12 DISCOUNTED CASH FLOW ANALYSIS FOR PREFERRED SYSTEM

13 APPENDICES
13.1 Engineering calculations

13.2 Copies of appropriate regulations

13.3 Vendor’s brochures

13.4 Other pertinent information

Level 2 Feasibility Checklist 7

Vous aimerez peut-être aussi