FLEXIHOPPER INSTALLATION CHECK LISTS COMMISSIONING RESULTS AND CERTIFICATE LINK FOLDER
LINK ID:
Relocation Of GT2096
SITE A ID : GT5229
Page No. 1
Not OK
POSITIONS CHECK
A 1 N T 2 3 4 5 O U 6 7 8 9 10 11 I 12 U 13 14 15 16
Installation done like shown in the documentation (pole, direction, polarisation) Alignment unit and antenna are installed properly and screws are tightened Waveguide is properly mounted (Separate antenna or HSB configuration) The serial number of the antenna is recorded OU is installed properly (screws are tightened, sealing is in right position, enough space left for deinstallation) OU is grounded OU is marked with a far end Site ID Labels are mounted the IU-OU cables (Cable numbers) Connectors at OU, IU and in BTS are tightened properly. OU connector is sealed. The serial number of the OU's are recorded IU is installed correctly (capacity, redundant unit, cabling and connectors) Q1 Bus System is implemented correctly, management bus cables are installed (not applicable for RRIC) All necessary 2 Mbit/s Cables are installed (not applicable for RRIC) Flex bus cable connected IU is labelled with far end Site ID Cables DDF are labelled (not applicable for RRIC) The serial numbers of the IU's are recorded
Remarks:
Serial Numbers
Name-:
Signature
Date :
Page No. 2
OK
3.
Not OK
POSITIONS CHECK
A N T
1 2 3 4 5
Installation done like shown in the documentation (pole, direction, polarisation) Alignment unit and antenna are installed properly and screws are tightened Waveguide is properly mounted (Separate antenna or HSB configuration) The serial number of the antenna is recorded OU is installed properly (screws are tightened, sealing is in right position, enough space left for deinstallation) OU is grounded OU is marked with a far end Site ID Labels are mounted the IU-OU cables (Cable numbers) Connectors at OU, IU and in BTS are tightened properly. OU connector is sealed. The serial number of the OU's are recorded IU is installed correctly (capacity, redundant unit, cabling and connectors) Q1 Bus System is implemented correctly, management bus cables are installed (not applicable for RRIC) All necessary 2 Mbit/s Cables are installed (not applicable for RRIC) Flex bus cable connected IU is labelled with far end Site ID Cables DDF are labelled (not applicable for RRIC) The serial numbers of the IU's are recorded
O U
6 7 8 9 10 11
I U
12 13 14 15 16
Serial Numbers
Primary terminal Secondary terminal (1+0) Antenna OU1: IU2: OU2: 0.6:
Company: TELEYSIA
Name:
Page No. 3
OK
Signature
Date:
Page No. 4