CMT3212 - MEASUREMENT OF CONSTRUCTION WORKS I MAIN EXAMINATION MARKING SCHEME DWG No.

QA-SE-FW2-01 - QA-SE-FW2-05 TAKE-OFF LIST 1) SITE PREPARATION Site clearance Over-site excavation Anti-termite treatment 2) EXCAVATION Foundation pits Excavating in rock Backfilling Making up levels Disposal of excavated materials 3) DISPOSAL OF WATER 4) PLANKING AND STRUTTING 5) HARDCORE FILLING 6) PLAIN & REINFORCED CONCRETE Column bases Columns Beams Surface bed 7) REINFORCEMENT Bar reinforcement Mesh reinforcement to surface bed 8) FORMWORK Formwork to foundations Formwork to columns Formwork to plinth beam 9) DPC Damp proof membrane Damp proof courses ME - 1 Re-bars Add Take-off list Organization TOTAL Marks Distribution Each item on list 2 Marks 44 Marks 6 Marks 6 Marks 4 Marks 60 Marks

SITE PREPARATION

22/

2.50 1.50 1.40

Length

40,000 350 40,350 20,000 450 20,450

Excavating pits to receive foundations commencing 115.50 from stripped level: not exceeding 1.5 m deep. & Return, fill and ram. & Extra over all excavations for excavating in rock X 10% 11.55 m3 & 'Gladiator 4TC' or other equal and approved chemical anti-termite treatment to subsoil and filling applied in accordance with the manufacturer's

Width

22/ 4/

40.35 20.45 1.50 1.03 1.48 0.06

825.16 33.99 0.36 859.51

Clear site of all bushes, shrubs, undergrowth and the like generally, including small trees, grub up roots and burn arisings on site. & Excavate oversite to remove vegetable soil average 200 mm and spread and level where directed on site. 2/8/ 3.50 0.30 0.15 4.60 0.30 0.15 5.30 0.30 0.15

EXCAVATION Depth of excavation 1,200 400 1,600 200 Ddt O'site exc 1,400 Trench excavation 5,000 1,500 Ddt bases 3,500 6,600 750 Ddt 2)1500 1,250 Ddt 2)2500 4,600 6,800 1,500 5,300

2/2/

0.83

Excavating trenches to receive foundations 2.52 commencing from stripped level: not exceeding 1.5 m deep. &

2/

0.48 Return, fill and ram. 3.83

& Extra over all excavations for excavating in rock X 10% .38 m3 & 'Gladiator 4TC' or other equal and approved chemical anti-termite treatment to subsoil and filling applied in accordance ME - 2

Ddt bases

DISPOSAL OF WATER

HARDCORE FILLING
40.35 20.45 Ddt 22/ 16/ 4/ 2/ 0.45 0.35 4.65 0.30 6.20 0.30 6.45 0.30

Item

Allow for keeping all excavations free from water (except spring and running water) by pumping, bailing or other means necessary. PLANKING & STRUTTING

825.16

150 mm thick hardcore filling to make up levels; deposit, spread and level and compact: 50 mm selected lake sand blinding. &

3.47 22.32 7.44 3.87 788.06

Item

Allow for provision and subsequent removal of planking and strutting to uphold and maintain all faces of excavations generally.

Gladiator 4TC' or other equal and approved chemical anti-termite treatment to subsoil and filling applied in accordance with the manufacturer's instructions. & Imported earth filling to make up levels not exceeding 300 mm deep average.

Length of beams

Ddt column

5,000 350 4,650 6,600 175 225 6,200 6,800 350 6,450

Ddt 2)350 Ddt 2)450

REINFORCED CONCRETE
Reinforced in-situ concrete grade 25 - 25N/mm2 / 20 mm aggregate;

Ddt column

22/

2.50 1.50 0.40

Column bases.
33.00

& Ddt Return fill and ram & Cart away

ME - 3

Ddt base Ddt slab

Depth 2,050 400 150 1,500

High yield tensile steel bar reinforcement to BS 4449 as described including cutting to lengths, bending, hoisting and fixing including all necessary tying wire and spacing
242/ 600/ 3.10 1.62 750.20 972.00 1722.20

22/

0.45 0.35 1.50

Columns
5.20

T8 x 0.395 kg/m

& Ddt Return fill and ram & Cart away


286/ 2.00

572.00

T12 x 0.888 kg/m

40.35 20.45

825.16

150 mm surface bed including tamping around fabric reinforcement & Mesh fabric reinforcement reference A193 weiging 3.02 kg/m2 including 200 mm end and side laps. & 1000 gauge polythene damp proof membrane; 300 mm laps.
198/ 220/ 6/4/ 3.00 2.23 5.45 594.00 490.60 130.80 1215.40

T16 x 1.579 kg/m

2/8/

4.65 0.30 0.60 13.39 6.20 0.30 0.60 6.80 0.30 0.60 4.46

Ground beams

2/4/ 4/ 4/ 3/4/ 4/ 2/4/ 4/ 2/4/

5.45 8.28 11.10 6.10 8.28 7.15 7.35 4.43

43.60 33.12 44.40 73.20 33.12 57.20 29.40 35.44 349.48

T20 x 2.466 kg/m = 861.82 Kg.

2/2/

2/

4/ 4/

12.00 1.00

48.00 4.00 52.00

T25 x 3.854 kg/m

2.45 20.30

ME - 4

Sawn formwork
22/2/ 22/2/ 2.50 0.40 1.50 0.40

Adjustment of backfill
115.50 3.83 119.33 Ddt

44.00 26.40 70.40

Vertical or battering sides of foundations.

Return, fill and ram selected excavated materials around foundations; deposit in 150 mm layers and compact to 98% MDD.

2/8/ 2/2/ 2/

4.65 0.60 6.20 0.60 6.80 0.60

44.64 14.88

Vertical or battering sides of ground beams

33.00 2/8/ 4.65 0.30 0.15 6.20 0.30 0.15 6.80 0.30 0.15 0.45 0.35 1.05

(Bases (Beams

3.35

2/2/ 8.16 67.68 2/

1.12

2/ 2/

40.35 20.45

80.70 40.90 121.60

Edges of surface bed 75 150 mm high

0.61

22/

(Columns
3.64 84.31

DAMP PROOF COURSE Hessian based bituminous felt damp proof course: horizontal; 200 mm wide: 150 mm laps, bedded and jointed in cement mortar (1:4).
2/ 2/ 40.00 20.00 80.00 40.00 120.00

119.33

84.31 35.02

Load, cart, deposit and spread surplus Excavatingd material approximately 10 km from site to a place approved by the local authority.

200 mm wide.

ME - 5

Reg. No.. UNIVERSITY OF RWANDA COLLEGE OF SCIENCE AND TECHNOLOGY Avenue de l'Arme, B.P. 3900 Kigali, Rwanda UNIVERSITY EXAMINATIONS ACADEMIC YEAR 2013/2014 SCHOOL OF ARCHITECTURE END OF SEMESTER MAIN EXAMINATION DEPARTMENT OF CONSTRUCTION MANAGEMENT YEAR: 2 SEMESTER: 1

CMT 3212: MEASUREMENT OF CONSTRUCTION WORKS I DATE: ____/____/_____ DURATION: 3 HRS MAXIMUM MARKS: 60 INSTRUCTIONS TO CANDIDATES AND INVIGILATORS 1. Drawings QA-SE-FW2-01, QA-SE-FW2-02, QA-SE-FW2-03, QA-SE-FW2-04, QASE-FW2-05 together with a Bar Bending Schedule are attached showing a foundation layout and details of a Substructure of a Finished Product Warehouse. 2. The paper contains ONE Question and carries a total of 60 marks. 3. Use the dimension sheets provided for the measurement of the works. 4. Measurement must be done in accordance with the Standard Method of Measurement of Building Works for East Africa latest edition. 5. Candidates are expected to complete the work in the time allocated on the question paper. Particular attention will be paid in allocating marks to logical sequence, principles, accuracy, clearly setting out, annotation of dimensions and general neatness. 6. Any information assumed in the measurement should be clearly stated. When adequate information may appear not to have been provided, make reasonable and realistic assumptions. 7. Do not forget to write your registration number. 8. Do not write any answer on this question paper. Q1 Study the drawings carefully and measure (taking-off and squaring) the Substructure of the building. 60 Marks

Page |1

BAR BENDING SCHEDULE DATE NOV 13 2007 SUBSTRUCTURE FINISHED PRODUCT WAREHOUSE MEMBER COLUMN BASES BAR MARK 01 02 COLUMNS 03 04 BEAMS 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 25a 26 TYPE & SIZE T16 T12 T16 T8 T8 T20 T16 T16 T16 T16 T16 T16 T20 T20 T20 T20 T20 T20 T20 T20 T20 T20 T20 T25 T25 T20 No OF MBRS 22 22 22 22 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 No IN EACH 9 13 10 11 600 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 TOTAL No 198 286 220 242 600 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 LENGTH OF EACH BAR 3,000 2,000 2,230 3,100 1,620 5,450 5,450 5,450 5,450 5,450 5,450 5,450 5,450 8,275 11,100 6,100 6,100 6,100 8,275 7,150 7,350 7,150 4,425 12,000 1,000 4,425

Mass / Linear Metre T8 0.395 T12 0.888 T14 1.209 T16 1.579 T20 2.466 T25 3.854

Bar Bending Schedule