Vous êtes sur la page 1sur 31

Substation Automation and Protection Training

RED670 Line Differential Protection IED Current functions

ABB AB, 2007 2008-01-30 1

Substation Automation and Protection Training

RED 670; Current functions


Instantaneous phase overcurrent, IOC max 2 instances Four step phase overcurrent, TOC, 1 instance Instantaneous residual current, IEF, 1 instance Four step residual overcurrent, TEF, max 1 instance

ABB AB, 2007 2008-01-30 2

Substation Automation and Protection Training

RED 670; Current functions

Breaker failure protection, BFP, max 2 instances Stub protection, STB, max 2 instances Thermal overload protection, THL, max 2 instances Pole Discordance, PD, max 2 instances

ABB AB, 2007 2008-01-30 3

Substation Automation and Protection Training

RED 670; Current functions


IOC, TOC, THL, BFP and PD are standard in the preconfigured variants:

A31 3ph 1 CB A32 1ph 1 CB B31 3ph 2 CB B32 1PH 2 CB

ABB AB, 2007 2008-01-30 4

Substation Automation and Protection Training

Instantaneous Phase Overcurrent function (PIOC, 51)


IF

Set as instantaneous protection where the fault current is limited to defined maximum values e.g. from a long power line or a transformer reactance. Low transient overreach to allow setting close to the maximum through fault current level High speed to give fast fault clearance at heavy fault currents Can give phase information and be used with Distance protection as fast optional function also giving single phase tripping Current can be summated from two (or more) current input sets.

3I>>

ABB AB, 2007

2008-01-30 5

Substation Automation and Protection Training

Instantaneous Phase Overcurrent function (PIOC, 51)

OpMode = 1out of 3 or 2 out of 3 IP>> = The setting threshold for the current function StVaMult = A multiplication factor for increase of IP>> by activating input ENMULT

ABB AB, 2007 2008-01-30 6

Substation Automation and Protection Training

PIOC,51; Calculation of settings

Select IP>> = max(IfB,IfA)


ABB AB, 2007

Consider also eventual transient overreach due to possible dc component of the fault current
2008-01-30 7 Substation Automation and Protection Training


ABB AB, 2007

PIOC,51; Calculation of settings


Consider also the effect of parallel line when applicable

2008-01-30 8

Substation Automation and Protection Training

PIOC, 51; Function block

ABB AB, 2007 2008-01-30 9

Substation Automation and Protection Training

Phase Overcurrent function (TOC, 51_67)


Four stage Phase overcurrent. Each stage can be set Directional or Non directional Each stage can be Definite- or Inverse time delayed.

IF

19 IEC/ANSI curves Logaritmic invers

Taylor made curve is available Each stage can be blocked from second harmonic inrush currents. With directional memory Current can be summated from two (or more) current input sets.

3I> 4

ABB AB, 2007 2008-01-30 10 Substation Automation and Protection Training

Phase Overcurrent function (PTOC, 51_67)


4 step over current element One element for each step

faultState I3P V3P

Direction Element

dirPhAFlt dirPhBFlt dirPhCFlt

faultState PICKUP

TRIP

I3P

Harmonic Restraint Element

harmRestrBlock

enableDir Mode Selection enableStep1-4 DirectionalMode1-4

ABB AB, 2007

en05000740_ansi.vsd

2008-01-30 11

Substation Automation and Protection Training

Phase Overcurrent function (PTOC, 51_67)


The filtering principal can be selected to Discrete Fourier Filtering (DFT) or true RMS (RMS) by the setting parameter MeasType DFT filer out the fundamental component which is most common in normal line protection applications RMS gives a current which includes harmonics, which is usefull in shunt capacitor applications

ABB AB, 2007 2008-01-30 12

Substation Automation and Protection Training

Phase Overcurrent function (PTOC, 51_67), - Application

IF

G 4

67/51 3I> G

ABB AB, 2007

Back-up selectivity with direction and different time grading in both directions

2008-01-30 13

Substation Automation and Protection Training

PTOC, 51_67; Direction



Reverse

The direction is determined by checking the angle of U and I Voltage is the angle reference Lagging current is plus angle With directional memory Direction can be set


Uref RCA

ROA

ROA

Off/Non-directional Forward/Reverse

Forward
Idir


en05000745.vsd

RCA ~ 10-40 ROA ~ 100-150

ABB AB, 2007 2008-01-30 14

Substation Automation and Protection Training

TOC, 51_67; Reset possibilities


Curve name Curve Index no.

Instantaneous

IEC Reset (constant time) ANSI Reset (Inverse time)

ABB AB, 2007 2008-01-30 15

Substation Automation and Protection Training

4-step Phase overcurrent protection (TOC)



jX

The direction is determined by checking the angle of U and I Voltage is the angle reference Lagging current is plus angle With directional memory


Forward operation Forward operation
110-150

10-40 R

Reverse operation

Reverse operation

ABB AB, 2007 2008-01-30 16

Substation Automation and Protection Training

TOC, 51_67; Polarizing voltages


Polarizing voltages at phase to phase fault IdirL1L2 = IL1 - IL2 UrefL1L2 = UL1 - UL2
UrefL2 L3 = UL2 - UL3 UrefL3 L1 = UL3 - UL1

IdirL2 L3 = IL2 - IL3 IdirL3 L1 = IL3 - IL1

Polarizing voltages at phase to earth fault UrefL1 = UL1


UrefL2 = UL2 UrefL3 = UL3

IdirL1 = IL1 IdirL2 = IL2 IdirL3 = IL3

ABB AB, 2007 2008-01-30 17

Substation Automation and Protection Training

TOC, 51_67; Function block inputs


TOC1OC4PTOC_51_67 I3P U3P BLOCK BLKTR BLKST1 BLKST2 BLKST3 BLKST4 ENMULT1 ENMULT2 ENMULT3 ENMULT4 TRIP TR1 TR2 TR3 TR4 TRL1 TRL2 TRL3 TR1L1 TR1L2 TR1L3 TR2L1 TR2L2 TR2L3 TR3L1 TR3L2 TR3L3 TR4L1 TR4L2 TR4L3 START ST1 ST2 ST3 ST4 STL1 STL2 STL3 ST1L1 ST1L2 ST1L3 ST2L1 ST2L2 ST2L3 ST3L1 ST3L2 ST3L3 ST4L1 ST4L2 ST4L3 2NDHARM DIRL1 DIRL2 DIRL3

When activated, the current multiplier InMult (n=1 for step1 etc) is in use for step1, Step2, step3 and step4 for increasing the operate level

ABB AB, 2007

VisioDocument
2008-01-30 18 Substation Automation and Protection Training

TOC, 51_67; Function block outputs


TOC1OC4PTOC_51_67 I3P U3P BLOCK BLKTR BLKST1 BLKST2 BLKST3 BLKST4 ENMULT1 ENMULT2 ENMULT3 ENMULT4 TRIP TR1 TR2 TR3 TR4 TRL1 TRL2 TRL3 TR1L1 TR1L2 TR1L3 TR2L1 TR2L2 TR2L3 TR3L1 TR3L2 TR3L3 TR4L1 TR4L2 TR4L3 START ST1 ST2 ST3 ST4 STL1 STL2 STL3 ST1L1 ST1L2 ST1L3 ST2L1 ST2L2 ST2L3 ST3L1 ST3L2 ST3L3 ST4L1 ST4L2 ST4L3 2NDHARM DIRL1 DIRL2 DIRL3

General TRIP TRIP step1, step2, step3 and step4 TRIP phase L1, L2, and L3 TRIP step1 phase L1, L2, L3 TRIP step2 phase L1, L2, L3 TRIP step3 phase L1, L2, L3 TRIP step4 phase L1, L2,L3 General start START step1, step2, step3 and step4 START L1, L2 and L3 START step1 phase L1, L2 and L3 START step2 phase L1, L2 and L3 START step3 phase L1, L2 and L3 START step4 phase L1,L2 and L3 Second harmonic block Direction phase L1, L2 and L3

ABB AB, 2007 2008-01-30 19

Substation Automation and Protection Training

TOC, 51_67; Setting calculation For directional underreaching step1


Select the max(IfB) Consider also eventual transient overreach due to possible dc component of the fault current The set value for the high set underreaching step can be derived as:

I1 > = 1.31 IfB


The value 1.31 includes a security margin of 10% for transient overreach and 20 % general security margin

ABB AB, 2007 2008-01-30 20

Substation Automation and Protection Training

TOC, 51_67; Setting parameters

ABB AB, 2007 2008-01-30 21

Substation Automation and Protection Training

TOC, 51_67; Setting parameters General setting parameters


Basic settings

Advanced settings StartPhSel = Number of phases needed for operation (1, 2 or 3 of 3) IminOpPhSel = Minimum current in % of Ibase for directionality Should be set lower than setting of the lowest step

ABB AB, 2007 2008-01-30 22

Substation Automation and Protection Training

TOC, 51_67; Setting parameters Basic setting parameters for step1

K1 = Time multiplier for inverse time characteristic t1Min = Minimum operate time for inverse time characteristic I1Mult = Current multiplication factor for step1, activates if input ENMULT1 is high
ABB AB, 2007

2008-01-30 23

Substation Automation and Protection Training

TOC, 51_67; Setting parameters Advanced setting parameters for step1

ResetTypeCrv1 = Reset curve type for step1 tReset1 = Reset time delay for IEC inverse curve for step1 tPCrv1, tACrv1, tBCrv1, tCCrv1, tPRCrv1, tTRCrv1, tCRCrv1 = Parameter P, A, B, C , PR, TR and CR for customer programmable inverse time curve for step1

ABB AB, 2007 2008-01-30 24

Substation Automation and Protection Training

PTOC, 51_67; Setting parameters


IBase: Base current in primary A.


Normally set to the primary current of the CT. Range 1-99999 Normally set to the primary voltage of the VT (PT). Range 0.05-2000

UBase: Base voltage in primary kV


AngleRCA: Protection characteristic angle set in degrees.


Default set to 55. Range 40-65

AngleROA: Angle to define the angle sector of the directional function


Default set to 80. Range 40-89

ABB AB, 2007 2008-01-30 25

Substation Automation and Protection Training

PTOC, 51_67; Setting parameters


IminOpPhSel: Minimum current for phase selection set in % of Ibase


should be less than the lowest step setting. Default setting is 7%.

StartPhSel: Number of phases, with high current, required for operation: 1 of 3, 2 of 3 or 3 of 3.


Default setting is 1 of 3. Default set to Non-Directional

DirMode1: Directional mode


2ndHarmStab: Operate level of 2nd harmonic current restrain set in % of the fundamental current, range is 5-100% I steps of 1%.

Default setting is 20%.

HarmRestrain: Off/On, enables blocking from harmonic restrain.

ABB AB, 2007 2008-01-30 26

Substation Automation and Protection Training

PTOC, 51_67; Setting parameters

ABB AB, 2007 2008-01-30 27

Substation Automation and Protection Training

Instantaneous Earth Overcurrent function (IEF)


Set as instantaneous protection where the fault current is limited to defined maximum values e.g. from a long power line or a transformer reactance. Low transient overreach to allow setting close to the maximum through fault current level High speed to give fast fault clearance at heavy fault currents Can give phase information and be used with Distance protection as fast optional function also giving single phase tripping Current can be summated from two (or more) current input sets. Residual connection or separate inputs can be used.

IF

Irsd or 3I0

IN>>
ABB AB, 2007

2008-01-30 28

Substation Automation and Protection Training

4-step Earth fault protection (TEF, 51N_67N) Application


Earth fault protection of feeders in effectively earthed distribution and sub transmission systems Back-up earth fault protection of transmission lines Sensitive earth fault protection of transmission lines Back-up earth fault protection of power transformers Earth fault protection of different kinds of equipment connected to the power system such as shunt capacitor banks, shunt reactors and others

ABB AB, 2007 2008-01-30 29

Substation Automation and Protection Training

4-step Earth fault protection (TEF)

Four stage Earth overcurrent. Each stage can be set Off, Nondirectional, Forward or Reverse Each stage can be Definite- or Inverse time delayed. Taylor made curve is available Each stage can be blocked from second harmonic inrush currents. Directional polarizing from calculated UL1+UL2+UL3 or by external Open delta to a separate Analogue input.

IF

UL1+UL2+UL3

IN> 4

ABB AB, 2007 2008-01-30 30 Substation Automation and Protection Training

4-step Earth fault protection (TEF, 51N_67N)


Directional element with communication and WEI

Operation based on I*cos Polarising -3U0 > 1.0 % CVT filter against 3rd harm Characteristic angle AngleRCA = -180--180 o (default -65 ) Current can be summated from two current sets and the measurement can be from separate IN input or internally calculated: 3I0 = IL1+IL2+IL3

Reverse operation

3Io

3Io(rev) = 0,6 x 3Io (forward)


AngleRCA

3Io
Forward operation
ABB AB, 2007

-Upol

2008-01-30 31

Substation Automation and Protection Training

TEF, 51N_67N; Polarizing alternatives


Voltages polarization (-3U0) Current polarization (IN*ZN) Dual polarization


Both voltage and current is allowed to polarize

ABB AB, 2007 2008-01-30 32

Substation Automation and Protection Training

Earth Overcurrent function (TEF) - Application

IF

G 4

IN>

67N/51N G


ABB AB, 2007

Back-up selectivity with two directions and different time grading in both directions

2008-01-30 33

Substation Automation and Protection Training

PEFM, 51N_67N; Functional overview


Directional Check Element signal to communication scheme

3U0 3I0

Direction Element

operatingCurrent earthFaultDirection angleValid

4 step over current element One element for each step

TRIP

enableDir

3I0

Harmonic Restraint Element

harmRestrBlock

start step 2, 3 and 4 Blocking at parallel transformers SwitchOnToFault CB pos or cmd TRIP

Mode Selection
ABB AB, 2007

enableDir enableStep1-4 DirectionalMode1-4

en05000741.vsd

2008-01-30 34

Substation Automation and Protection Training

TEF, 51N_67N; Analogue inputs


The function are connected to pre-processing block by the following signals


I3P, input for the function Operating Quantity U3P, input for the function Voltage Polarizing Quantity IP3P, input for the function Current Polarizing Quantity

The function uses Residual Current (i.e. 3Io) for its operating quantity

directly measured Internally calculated from three phase current input within IED 670 (when the fourth analog input into the pre-processing block connected to TEF function Analog Input I3Pis not connected to a dedicated CT input of IED 670 in SMT tool).

ABB AB, 2007 2008-01-30 35

Substation Automation and Protection Training

4-step earth fault protection (TEF) t Set to match the distance protection reach

Step 1-3:

Directional or Non- directional Definitive time Second harmonic restrained Directional or Non- directional Normal inverse Very Inverse Extremely inverse Logarithmic inverse Definitive time Second harmonic restrained -

Step 4:

1sec

min

20 ms

ABB AB, 2007

2008-01-30 36

Substation Automation and Protection Training

4-step earth fault protection (TEF)


t

Directional Non-directional Independent or dependent time delay Second harmonic restrained Settable minimum operate current and time delay

Independent Logarithmic inverse


t min I min

Normal inverse Very inverse Extremely inverse

ABB AB, 2007 2008-01-30 37

Substation Automation and Protection Training

4-step earth fault protection (TEF)

10

10

19 different IEC/ANSI Current dependent characteristic curves (New) Communication logic


t1 i t2 i t3 i t4 i t5 i t6 i 1

Blocking Permissive overreach (POR) Fault current reversal Weak-end infeed echo and trip

0.1 0.1 100 100

1 .10

1 .10 Sti

1 .10 100000

ABB AB, 2007 2008-01-30 38

Substation Automation and Protection Training

Inverse characteristic for time-current back-up


Required for Back-up functions TOC, TEF Diagram or characteristic showing the operating times and corresponding actuating quantities or fault positions for the selective protection relays in the network

Purpose Coordinate the relay settings so that Faulty equipment is tripped as fast as possible The least possible damage is obtained for the healthy equipment A Back-up protection is obtained if the primary protection fails to trip

Directional

ABB AB, 2007 2008-01-30 39

Substation Automation and Protection Training

Earth fault protection (TEF) Application problem


Energizing a transformer will always mean inrush currents. Inrush has a high neutral content in directly earthed systems A parallel transformer in service will also see the inrush. The inrush will increase successively 2nd harmonic will be in phase opposition and the total content will after a while be reduced to small values. BlkParTrans set to ON and IN over a set level (1-4) can be used to maintain the blocking even if the harmonic contents is reduced and gives an advantage at parallel transformers.
51N 51N

IN>
51N

IN> Close
51N

IN>

IN>

ABB AB, 2007 2008-01-30 40

Substation Automation and Protection Training

ABB AB, 2007 2008-01-30 41

Substation Automation and Protection Training

STUB protection (STB)


Instantaneous overcurrent protection of busbar connection (STUB) when a line disconnector is open Required in Multi-breaker arrangements with CVT (VT) on line side of DS Z< (21) function cannot measure when line disconnector is open and must be blocked.

Line discon.

open

&

Trip

I STUB >
ABB AB, 2007

2008-01-30 42

Substation Automation and Protection Training

Pole discordance protection (PD)


Pole discordance can occur at breaker closing or opening when single pole operating devices are used. - Higher than 300 kV - Single phase trip breakers Contact based supervision of the poles I2 criteria to verify can be added as additional criteria to increase security Can be blocked during 1-ph AR to allow shorter trip times. Note! Only remote b-u trip if local attempt does not remove asymmetry. Bus trip will mean a big disadvantage for service.

&

Trip t

1Ph AR in progr

Trip rem end

ABB AB, 2007 2008-01-30 43

Substation Automation and Protection Training

Breaker failure protection (BFP)


BFP is the Local back-up for breaker failures. The failures can be due to trip coil, breaker drive or breaking components failure. At an breaker failure the surrounding breakers are used to clear the fault. Due to the big impact a breaker failure trip will have on the power system service, the BFR function has very high requirements on security against unnecessary tripping. The BFR function is started at CB tripping and if current still flows within, about 150 ms the surrounding breakers are tripped.

Failing breaker


G

Back-up breakers
ABB AB, 2007

2008-01-30 44

Substation Automation and Protection Training

Breaker failure protection (BFP)


Some setting parameters
Current level Retrip of actual breaker Iset 0,1 2 * Ibase -No retrip -With current check -Without current check 1 out of 3 or 2 out of 4 t1 0.000 60.000 s t2 0.000 60.000 s t3 0.000 60.000 s tp 150 ms (settable)

BFP
I>

t1 t2

Current check mode Retrip delay, one per phase Back up trip delay, one timer per phase Back-up trip 2 Trip pulse

ABB AB, 2007 2008-01-30 45

Substation Automation and Protection Training

Breaker failure protection (BFP)


Pre-filter Post-filter 0.5 * Stab zone

Adaptive current detection ASD No false operation in case of saturated CT Maximum reset time approx 1/2 cycle to allow short back-up tripping times.

ASD output RMS output


ABB AB, 2007

2008-01-30 46

Substation Automation and Protection Training

Breaker failure protection (BFP)

Fault occurs Normal clearing time Current detector dropout Protection time - 30 ms Breaker interrupting time - 60 ms Back-up breaker Start BFP BFP timer t2 BFP Trip Breaker time Margin

Breaker failure total clearing time


ABB AB, 2007

2008-01-30 47

Substation Automation and Protection Training

Breaker failure protection (BFP)


Note! Multiple functions
CB1 Trip Busbar Trip CB3 Intertrip 1

Start L1 Start L2 Start L3

3I>BF

Z<

CB3 Start L1 Start L2 Start L3 CB2 Start from all protection relays tripping the Breaker. Also Bus and Breaker failure protection. Not manual opening of breaker!
ABB AB, 2007

3I>BF

Trip CB1 Trip CB2 Intertrip1 Intertrip2

3I>

2008-01-30 48

Substation Automation and Protection Training

Energizing Check (SYN)


UA A ILoad
Inductive and Capacitive charging of dead line

UB B

Uhigh
27 SC/VC


Ulow

The dead line and Live bus conditions are checked. Uhigh and Ulow are verified

ABB AB, 2007 2008-01-30 49

Substation Automation and Protection Training

Synchronism Check (SYN)


UA A ILoad B UB

UAL

Icap

25 SC/VC

d dU

Paralleling (synchronism conditions are checked


, f, U and Uhigh are within set values

ABB AB, 2007 2008-01-30 50

Substation Automation and Protection Training

Synchrocheck function (SYN)


U-Line U-Bus

Energizing check High voltage Low voltage Operate time

U> 50-120% of Ub U< 10- 80% of Ub 80 ms (typical)

SYNC

U-Bus Line reference voltage

Paralleling (Synchronism) Check Frequency difference f < 3-1000mHz Voltage difference U < 2 - 50 % of Ub Phase difference < 5 - 90o Operate time 80 ms (typical)
Accuracy of frequency measurement about 0,5 mHz!

BLOCK

Fuse fail

ABB AB, 2007 2008-01-30 51

Substation Automation and Protection Training

Synchrocheck (SYN) Function block


Block inputs DS Bus 1 at DB arrangement DS Bus 2 at DB arrangement DS Line at 1 1/2 arrangement DS alt Line at 1 1/2 arrangement Bus1 VT Fuse fail alt. OK Bus2 VT Fuse fail alt. OK Line 1 VT Fuse fail alt. OK Line 2 VT Fuse fail alt. OK Test mode inputs Fuse fail on sel fuse Information that the voltage is included in the synchrocheck Information that the conditions for voltage, diff voltage phase angle diff etc are fulfilled Conditions for AR Conditions for Man close Test conditions fulfilled

ABB AB, 2007 2008-01-30 52

Substation Automation and Protection Training

Synchrocheck (SYN) Voltage selection


1U 1U UB1 UB2 B1Q B2Q

SYN1
ULN1

3U

DB Volt sel

IED

1U UB1

1U UB2

SYN1
ULN1 LN1Q

SYN2

ABB AB, 2007

3U

No Volt sel
2008-01-30 53 Substation Automation and Protection Training

Synchrocheck (SYN) Voltage selection

IED 1

3U
UB2

1U

IED

ULN1 B1Q

1U
UB1

SYN1

SYN1

3U
LN1Q

IED 2

1U

SYN1

1U 1U

SYN2

IED 3

1U LN2Q B2Q

SYN1
3U 1U

1 U ULN2 UB2 1U

ABB AB, 2007

No Volt sel
2008-01-30 54 Substation Automation and Protection Training

1 CB Volt sel

Synchrocheck (SYN) Voltage selection

REC670

1U 3U

SYN1

SYN2

SYN3

3U 1U

ABB AB, 2007

No Volt sel
2008-01-30 55 Substation Automation and Protection Training

Auto Reclosing (AR) Single-/ Two-/ Three-phase reclosing programs


Program
1 2 3 phase 1/2/3 phase

1st attempt
3 phase 1 phase 2 phase 3 phase 1 phase 2 phase 1 phase 2 phase 1 phase 2 phase 3 phase 1 phase 2 phase 3 phase

2nd attempt
3 phase 3 phase 3 phase 3 phase 3 phase 3 phase 3 phase ---3 phase 3 phase ---3 phase -------

3rd and 4st attempt


3 phase 3 phase 3 phase 3 phase 3 phase 3 phase 3 phase ---3 phase 3 phase ---3 phase -------

3 4 5

1/2 phase (No 3 phase) 1/2 phase (No 3 phase) 1/2/3 phase

1/2/3 phase

ABB AB, 2007 2008-01-30 56

Substation Automation and Protection Training

Auto-Reclosing (AR) new in REx670 Start Quick AR without synchrocheck Skip a step and continue with next (at multiple shots)

Put AR on hold e.g. waiting for Thermal relays to reset to have less sag before reclosing

ABB AB, 2007 2008-01-30 57 Substation Automation and Protection Training

Content

ABB AB, 2007

Time Overvoltage protection function Time Undervoltage protection function Multipurpose general protection function Fuse failure supervision Instantaneous phase overcurrent Time delayed phase overcurrent Instantaneous earth overcurrent Time delayed earth overcurrent Stub protection Pole Discordance protection Breaker failure protection Synchrocheck function Auto Reclose function


2008-01-30 58

Frequency protection
Substation Automation and Protection Training

TOF/TUF/RVF(df/dt) Frequency Protection-Functionality


Detection of over- or underfrequency Six stages of each function Measures Ph-Ph or Positive sequence voltage Undervoltage (Dead) blocking level Trip signal each step fully individually:

Settable frequency and settable time delay

High accuracy, short measuring time Df/dt with positive or negative setting Accuracy 2 mHz for three phase Accuracy 50 mHz for single phase

ABB AB, 2007

Voltage dependent tripping time!


2008-01-30 59 Substation Automation and Protection Training

TOF/TUF Frequency Protection - Application


Load shedding system System restoration system Generation shedding Remedial Action schemes

ABB AB, 2007 2008-01-30 60

Substation Automation and Protection Training

Trip Circuit Supervision Application with 670 series


+ -

3s

Trip Circuit fail

Trip Circuit supervision can be arranged using Binary inputs or mA inputs. mA inputs shall be used if supervision is required from both sides i.e. at Lock-out tripping

ABB AB, 2007 2008-01-30 61

Substation Automation and Protection Training

Vous aimerez peut-être aussi