Académique Documents
Professionnel Documents
Culture Documents
Overall: Various reasons contributed to the delay in the completion of the Complex (anticipated completion date of July 2013) as well as the unanticipated cost overruns of approximately $1.7 million ($3 million additional contract costs less the expected $335,000 of architectural services and $995,000 of HVAC work.). The detection of asbestos in underground conduits was unforeseen. However, Internal Audit believes more comprehensive design plan reviews and increased and timely collaboration by OFG and its service providers with respect to construction expectations and costs could have reduced the number of delay days and cost overruns
Risk rating (include quantitative and qualitative reasons for a rating of Low, Medium or High for the following categories if applicable - financial, compliance, operational): Medium OFG has adopted procedures and practices (such as Architectural Design Programming) that they believe will assist them in better managing the construction schedule in addition to cost overruns. Auditees responses/corrective action plan: OFG concurs with and is adopting procedures and practices to address Internal Audits observations.