Plant Engineering Construction Pte Ltd

21, Shipyard Road, Singapore 628144


Tel: 6268 9788 Fax: 6268 9488
URL: http://www.peceng.com

DISTRIBUTION
INTERNAL

HEAD OFFICE
SITE OFFICE

INSTALLATION PROCEDURE FOR

EXTERNAL

CLIENT (FW)

TOWERS

END USER (EMAPPL)

TOTAL
PURPOSE

ExxonMobil Asia Pacific Pte. Ltd.


Foster Wheeler
Project Title : Singapore Hydrocarbon Expansion Project (S-HCF)
ISBL Mechanical Works, Piping Fabrication and
Installation
Contract No. : SC-12/13900/9
P.O. No.

M.R. No.

Equip. Title

PRELIMINARY
TENDER

APPROVAL
CONFIRMATION
CONSTRUCTION
AS-BUILT

Req. Item No. :

Equip. Item No. :

INFORMATION

Client Document No. :


FWIC Doc Type :

DSN :

FWIC Rev:

Supplier Doc No. :


Status Code:
By :

Dept:

Supplier Rev:
Date:

Comment Status Code:


1-Rejected; 2-Comments as Noted; 3-Minor Comments Acceptable;
4-No Comments; 5-Information Only

Total No. of Sheets


4 (Incl. cover sheet)

A
REV.
TITLE:

Issued For Approval


DESCRIPTION

Gin Ling
PREPD

Zhao JC
CHKD

Page

Page 1 of 4

Chan YB
APPD

17.01.08
19.09.07
DATE

INSTALLATION PROCEDURE( TOWERS )


PEC JOB NO.
00AP2000

0!

FW CONTRACT NO.
SC-12/13900/9

DOCUMENT NO.
ISBL-WP-MEC-30

REV. NO.
A

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
17 Jan 2008
Rev. No:

Installation Procedure for Towers

ISBL-WP-MEC-30
Page 2 of 4

CONTENTS

1.0

1.0

SCOPE

2.0

REFERENCES

3.0

LIFTING & LIFTING GEARS

4.0

INSTALLATION METHOD

5.0

ALIGNMENT

6.0

GROUTING

7.0

SAFETY

SCOPE

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
17 Jan 2008
Rev. No:

Installation Procedure for Towers

ISBL-WP-MEC-30

Page 3 of 4

1.1 This procedure outlines the requirements when handling and installation of tower and its
accessories. The items covered are as follows:

2.0

T-9601 Stripper Tower


T-9701 Stabilizer Tower
T-9801 Product Tower #1
T-9802 Product Tower #2

REFERENCES
2.1 Manufacturers drawings
2.2 Specification for grouting and workmanship 13900-43C8

3.0

LIFTING & LIFTING GEARS


Refer to lifting plan by FW.

4.0

INSTALLATION METHOD
4.1 Mark out locations where tower is to be installed and conduct necessary site measurements to
note if there is any deviations from equipment drawing.
4.2 Check the anchor bolts dimension, quantity, elevation and the orientation of the concrete
foundation against the tower skirt baseplate.
4.3 Install the soleplate padding level.
4.4 After lifting the towers into position, lock nuts of anchor bolt. Later, tightened it to the specified
torque value.
4.5 Conduct the following inspection before and after grouting: : a. Plumbness for the vertical shall be made by viewing from two direction 90 deg.
b. Levelness, orientation and interference

5.0

ALIGNMENT
Plumbness of the towers shall be checked not to exceed a certain tolerance value. Other information
refers to ITP.

6.0

GROUTING
Unless otherwise specified, grouting shall be carried out in accordance with the following:

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
17 Jan 2008
Rev. No:

Installation Procedure for Towers

ISBL-WP-MEC-30
Page 4 of 4

6.1 Foundation surface shall be cleaned thoroughly and be removed of any dirt or oily spots. Surface
of foundation shall be wetted thoroughly with fresh water prior to grouting.
6.2 Portland cement mortar may be used and mixing ratio with clean fine sand shall be
approximately 1: 2 in volume and ratio of water to cement shall be less than 40 % in volume.
6.3 Grouting on base plate shall be:
a. Space under the base plate shall be packed fully with non-shrink grout
b. All shims and wedges shall be fully cover with grout
c. After pouring, excess grout shall be trimmed and surface of mortar outside of the base plate
shall be finished smoothly.
7.0

SAFETY
Refer to the attached JRIS for the alignment work of Towers.