HYUNDAI E&C CO.

, LTD RAS LAFFAN C IWPP PROJECT

SITE INSPECTION & TEST PLAN


PIPING PULMBING WORKS

ITP NUMBER DATE ITEM/COMPONET PREPARED BY QCE

RLC-AH-QP-91-3001 JUNE 21, 2009 PLUMBING WORKS H. S. KIM

REVISION NO.

APPROVED BY QC MGR

B. H. LEE

- LEGEND H-HOLD(MANATORY HOLD POINT UNTIL INSPECTION COMPLETE) W-WITNESS INSPECTION POINT(PROCEED IF INSPECTION AUTHORITY NOT AVAILABLE) R-REVIEW(RECORD/REPORT REVIEW) S-SURVEILLANCE INSPECTION(RANDOM CHECK) - NOTE 1. ALL INTERNAL CONTROL DOCCUMENTS SHALL BE THE LATEST REVISION 2. CONSTRUCTION MATERIALS MUST BE APPROVED PRIOR TO START ANY WORKS 3. WHERE AN ACTIVITY IS NOT APPLICABLE THEN N/A SHALL BE INSERTED AGAINST THE APPROPRIATE OPERATION REMARK

RAS LAFFAN C IWPP / QATAR

DISCIPLINE :

HVAC

ITP No. Rev. No. Page Date

RLC-AH-QP-91-3001
A 1 OF 2 JUNE 21, 2009 REMARKS

WORK DESCRIPTION : PLUMBING WORKS APPLICABLE DOCUMENT REPORT FORM

SITE INSPECTION & TEST PLAN


No 1 DESCRIPTION OF INSPECTION TEST Material Receiving Inspection 2 Verify material type/size/quantity Physical Damage

PARTICIPATION BY S/C HDEC Owner

Material Spec. Packing List As per Design DWG.

PQM-06-06

Excavation of Trench Excavation Depth

RLC-AH-QP-913001-01

Bedding(Material & Thickness)

As per Design DWG.

RLC-AH-QP-913001-01

Plumbing Installation 1) Elevation of Pipe 2) Hanger and Support of Pipe in Accessible Area 3) Pipe Connection As per Design DWG. RLC-AH-QP-913001-01/03 H W S

Plumbing Fixture Installation Install proper fixture Check the location & elevation Method Statement RLC-AH-QS-94-001 Para. 9, 10 S : Surveillance R : Review RLC-AH-QP-913001-02 S/C : HDEC Subcontractor H H W As per Design DWG RLC-AH-QP-913001-01 H W S

Pressure Test Hydrostatic Test Water Pressure Test H : Hold W : Witness

Legend;

RAS LAFFAN C IWPP / QATAR

DISCIPLINE :

PIPING

ITP No. Rev. No. Page Date

RLC-AH-QP-91-3001
A 2 OF 2 JUNE 17, 2009 REMARKS

WORK DESCRIPTION : UNDERGROUND PIPING(HDPE) APPLICABLE DOCUMENT As per Design DWG. REPORT FORM RLC-AH-QP-913001-01

SITE INSPECTION & TEST PLAN


No 7 DESCRIPTION OF INSPECTION TEST Pipe Insulation (If applicable)

PARTICIPATION BY S/C H HDEC W Owner S

Backfilling Backfilling Material Backfilling H : Hold W : Witness S : Surveillance R : Review As per Design DWG. RLC-AH-QP-913001-01 S/C : HDEC Subcontractor H W R

Legend;

RAS LAFFAN C IWPP PROJECT


INSPECTION REPORT FOR PLUMBING WORKS
BUILDING : SYSTEM:
NO. 1 2 3 CHECK ITEM Material Verification Excavation of Trench Bedding(Material & Thickness) Plumbing Installation 1) Elevation of Pipe 4 2) Hanger and Support of Pipe in Accessible Area 3) 5 6 7 8 Pipe Connection

UNIT NO.: DWG. NO.:


RESULT REMARK

Piping Fixture Installation Pressure Test (Hydrostatic Test or Water Pressure Test) Insulation(if applicable) Backfilling

REMARKS :

SIGNATURE CHECKED BY SUBCON VERIFIED BY HDEC QC REVIEWED BY OWNER : : :

DATE

FORM NO. RLC-AH-QP-91-3001-01

RAS LAFFAN C IWPP PROJECT


PRESSURE TEST REPORT
PACKAGE NO. : SYSTEM : P & ID NO. :

DATE OF TEST : DESIGN PRESSURE / TEMP : REQUIRED TEST PRESSURE : ACTUAL TEST PRESSURE :

TYPE OF TEST :

HYDROSTATIC PNEUMATIC OTHERS


TEST MEDIUM / TEMP : PRESSURE GAUGE SERIAL NO.: PRESSURE HOLDING TIME : SKETCH OF TEST BOUNDARIES : MIN.,

START :

FINISH :

RESULT : REMARK :

ACCEPT

REJECT

SIGNATURE CHECKED BY SUBCON VERIFIED BY HDEC QC REVIEWED BY OWNER : : :

DATE

FORM NO. RLC-AH-QP-91-3001-02

RAS LAFFAN C IWPP PROJECT


GENERAL CHECK REPORT
Description EQPT Name TAG No. SKETCH : Unit No. DWG. No.

REMARK :

SIGNATURE CHECKED BY SUBCON VERIFIED BY HDEC QC REVIEWED BY OWNER : : :

DATE

FORM NO. RLC-AH-QP-91-3001-03