SNAGGING REPORT PROJECT: CONSTRUCTION OF RESIDENCE Location : Zicack Portsmouth Contractor: Martin Inspection: Date: February 17 2014 Inspected

By: Engineer

On completion of the snagged works, a final inspection should be conducted and checked either Yes or No that the works has been satisfactory completed. Location INTERNAL
Master Bedroom suite

Description
general cleaning and removal of fine debris around window sills missing sash windows insect screens laches to be installed complete paint marks at door edges to be removed and make good finish bathtub support at side wall was considered inadequate and needs to be reinforced grout residue left at the ceiling level to be removed and make good finish complete installation of hanging rods to walking closet

Yes

No

Common Bathroom

moulding strip should be installed at ceiling to conceal irregular grout finish. complete painting finish at door edges Remove stain on floor tiles

Bedroom 1

check and repair stiffness of vertical movement to single hung sash window. complete painting at edge of door remove painting stains on architrave trimming and make good finish door to receive one coat of paint remove paint marks on door knob and make good finish sash windows insect screens laches to be installed complete

Bedroom 2

Corridor

alignment of architrave trimming and door frame requires improvement

Living Room /Dining

repair required to cracks develop between joints of drywall at ceiling plug finish to screw heads at skirting board to be completed. make good wall surface at lamp holder and paint finish remove paint mark on lamp holder at ceiling level sash windows insect screens laches to be installed complete Install complete lower strike plate for dead bolt lock remove stain on floor tiles in dining room general cleaning to remove fine debris at windows

Kitchen

at fridge location the side cladding installed requires some bracing to improve stability complete and make good grout finish at window jamb make good finish to broken wall tile at switch.

EXTERNAL
Rainwater Downpipes rainwater pipe terminated at building foundation wall should be extended with bends away from the building into side drains downpipe connection at the northeast corner of the building should be made good for water discharge into pvc pipe Access ramp the access ramp slope of 1:2 is to seep; the accepted gradient is 1:10 or maximum 1:8 the ramp should be finished at grade level and not with a riser Plumbing pipe grey water pipes exposed at grade to be buried at least 12 below grade, or ground level be raised 12 with selected backfilled material

grey water pipes should have a minimum 2% fall

Make good to broken tile edge and complete joint with grout

Clean and remove all stain on wall tiles surface

remove paint marks; varnish and make good finish

Improve wall surface preparation at lamp and make good paint finish

Remove paint marks on lamp holder

Remove paint from upper strike plate

Install lower strike plate for dead bolt lock

Make good to ceramic tile surface at light switch

Make good finish to grout at window jamb

The slope to this ramp exceeds the minimum slope of 1:10

The exposed grey water pipes are required to be buried

Remove downpipe and make good connection to discharge water

Provide for rainwater downpipes to run away from buildings foundation to drain