Académique Documents
Professionnel Documents
Culture Documents
By: Engineer
On completion of the snagged works, a final inspection should be conducted and checked either Yes or No that the works has been satisfactory completed. Location INTERNAL
Master Bedroom suite
Description
general cleaning and removal of fine debris around window sills missing sash windows insect screens laches to be installed complete paint marks at door edges to be removed and make good finish bathtub support at side wall was considered inadequate and needs to be reinforced grout residue left at the ceiling level to be removed and make good finish complete installation of hanging rods to walking closet
Yes
No
Common Bathroom
moulding strip should be installed at ceiling to conceal irregular grout finish. complete painting finish at door edges Remove stain on floor tiles
Bedroom 1
check and repair stiffness of vertical movement to single hung sash window. complete painting at edge of door remove painting stains on architrave trimming and make good finish door to receive one coat of paint remove paint marks on door knob and make good finish sash windows insect screens laches to be installed complete
Bedroom 2
Corridor
repair required to cracks develop between joints of drywall at ceiling plug finish to screw heads at skirting board to be completed. make good wall surface at lamp holder and paint finish remove paint mark on lamp holder at ceiling level sash windows insect screens laches to be installed complete Install complete lower strike plate for dead bolt lock remove stain on floor tiles in dining room general cleaning to remove fine debris at windows
Kitchen
at fridge location the side cladding installed requires some bracing to improve stability complete and make good grout finish at window jamb make good finish to broken wall tile at switch.
EXTERNAL
Rainwater Downpipes rainwater pipe terminated at building foundation wall should be extended with bends away from the building into side drains downpipe connection at the northeast corner of the building should be made good for water discharge into pvc pipe Access ramp the access ramp slope of 1:2 is to seep; the accepted gradient is 1:10 or maximum 1:8 the ramp should be finished at grade level and not with a riser Plumbing pipe grey water pipes exposed at grade to be buried at least 12 below grade, or ground level be raised 12 with selected backfilled material
Make good to broken tile edge and complete joint with grout
Improve wall surface preparation at lamp and make good paint finish
Provide for rainwater downpipes to run away from buildings foundation to drain