Raipur – Bilaspur

RFP floated for appointment of Technical Consultant for the conducting feasibility –
cum – preliminary design for 4 – laning of Raipur – Bilaspur of NH-200

Salient Features

Project location: - Raipur to Bilaspur, State of Chhatisgarh

Project offer: - 4 – laning of the existing road

Length of project: - 117.00 km

Type of Project: - DBFOT (Design, build, finance, operate,


transfer)

EPC cost: – Rs. 672 Cr.

Total cost: – Rs. 840 Cr. Approx. (add 25% to the EPC cost,
includes contingencies, IDC, financing costs, pre-
construction expenses, etc.)

Schedule of selection process of the consultant: -

Event Description Estimated Date

Last date for receiving queries/ clarifications 26.10.2009

Pre – proposal qualification 03.11.2009

Authority response to queries 09.11.2009

Proposal due date or PDD 17.11.2009 at 1100 hrs

Opening of proposals 17.11.2009

Letter of Award (LOA) {within 15 days of PDD}

Signing of agreement within 10 days of LOA

Validity of applications 90 days of proposal due


date

Scope of services of consultant

1. Traffic surveys and demand assessment


2. Engineering surveys and investigations
3. Location and layout of toll plazas
4. Location and layout of truck laybyes
5. Location and layout of bus bays and bus shelters
6. Social impact assessment
7. Environment impact assessment
8. Preliminary designs of road, bridges, structures, etc.
9. Preparation of Land Plan Schedules and Utility Relocation Plans
10.Preparation of indicative BOQ and rough Cost Estimates
11.Preparation of Schedules A, B, C, D and H of the Concession Agreement.

Traffic surveys and demand assessment


S.N Description of Activity Number of Survey Stations
o.

1. Classified Traffic Volume One station close to the proposed location of each
Count Toll Plaza and one station for every 20 km of
Project Highway.

2. Intersection Volume All major intersections (All locations where the


Count Project Highway intersects or meets a
NH/SH/MDR).

3. Pedestrian/Cattle At all locations of settlements/habitations along


crossing traffic count the Project Highway

4. Axle Load Spectrum One station each close to the proposed location of
each Toll Plaza

Time schedule for important deliverables


Description of Deliverables Week No Payment

Inception Report 2 ---

Report on Alignment (including proposed geometric improvements) and first 8 15%


traffic survey

Report on Land Plan Schedules and Utility Relocation 12 10%

Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs) 13 10%

Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs) 14 10%

Draft Feasibility Report and Schedules to the Concession Agreement 16 25%

Final Feasibility Report 18 20%

Completion of Services including assistance during Bid Process 52 10%

Total 100%