Improving the Research Request Process In the Division of University advancement At the University of Miami

Rick Melnyck

Introduction The Division of University Advancement at the University of Miami is charged with the responsibility and authority to coordinate all fund-raising activities of the university. President Shalala and other central, medical and school-based development officers are responsible for qualifying, cultivating, soliciting and stewarding donors for the University of Miami. The Advancement Research Department identifies, analyzes, tracks and compiles biographical and financial information on potential donors for President Shalala and central, medical and school-based development officers. Define Phase Research Requests (1) Business Case What is the name of the process? The name of the process is Research Report Requests. What is the aim of the process? The aim of the process is to get the Development Officers, VPs, AVPs and President Shalala the right amount of information on a particular prospect at the right time while making more efficient use of the Research Departments time. Why do the project at all? The Research Requests project should be conducted to satisfy the needs of the Development Officers, VPs, AVPs and President Shalala in regards to information they need on potential donors. Why do the highest priority project now? There seems to be a crisis in the Research office as the Researchers feel that they are overworked and understaffed. Many of the Development Officers do not use the Research Department and a lot of their time that should be spent cultivating and soliciting donors is spent doing research. Also, the Research staff is spending 100% of their time doing research reports and do not have time to identify new donor prospects for the University. What are the consequences of not doing the highest priority project? The consequences of not doing the Research Requests project would be twofold. Firstly, the Researchers would continue to feel overwhelmed with the amount of work they receive which could lead to frustration and possibly turnover. The Development Officers will continue to spend part of their time doing research when their time could be better spent with donors. Finally, if the researchers do not have time to identify new prospects the donor pool may start to dry up for the Development Officers.

What business objectives are supported by the highest priority project? The Prospect Management Project is strongly related to the Increase the endowment, Improve the national ranking of the University, Improve student experiences and Improve interdisciplinary research presidential objectives. Problem Statement According to the Research staff, they are overworked and understaffed due to the fact that the report requestors are asking for types of profiles that are more than the requestor needs and are an inefficient use of the researchers time and energy. The Development Officers (DOs) feel that their needs are not being met and that the process is reactive. This means that many of them do their own research and completely bypass the Research department. The DOs are spending a lot of their time doing research when they should be out cultivating and soliciting potential prospects. In addition, the Research staff is spending all of their time doing research reports and does not have time to identify new prospects for the Development Officers. Goal Statement The goal for the Research Request project is to improve the process of efficiently delivering the right type of research request to the customer for what they need it for. Also the time of the researchers must not only be spent on doing research reports but more importantly on identifying new donor prospects. Project Objective To transform the current Research Request process into a proactive and efficient process. What are the process boundaries? The starting point for the project is when the Research Requestor makes an online Report Request. The stopping point for the project is when the Research profile is delivered to the Research Requestor. What are the benefits of the project? The soft benefits include eliminating complaints from the Research Department for being overworked. It will also include making more use of the researchers time so they can spend time in other areas such as prospect identification. There will also be soft benefits to the requestors of the research as they will receive better quality reports due to researchers not having to rush to meet deadlines. Another benefit will DOs spending less time doing research and more time cultivating and soliciting prospects.

Hard benefits Research department 40% misclassified research requests X 520 requests per year = 208 misclassified reports/year X 10 hrs average extra time spent due to misclassification of report = 2080 extra hours spent on misclassified reports X $25/hr researcher salary (including benefits) = $52,000 saved per year New prospects identified per month The researchers will have over 2000 more hours to work on prospect identification. Since the researchers will have more time they will be able to identify prospects for the DOs to cultivate and solicit, those fundraising dollars would be added to the hard benefits of this project. Development Officers The hard benefits for the Development Officers are a little tougher to calculate. However having a couple more hours per day to meet with prospects could result in many more donations than would have resulted had they been doing their own research. (2) SIPOC Analysis Suppliers Development Officers Vice-President for University Advancement President Shalala Associate VicePresidents Other Development Staff Inputs Name of Prospect Name of Report Requestor Type of Report Needed Date Report Requested Date Report Required Process See flowchart below Output Research Profile Type of Report Total Number of Pages Number of Reports Requested Customers Development Officers Vice-President for University Advancement President Shalala Associate VicePresidents Other Development Staff

Start

Report requestor fills out online report request Form

Research Director receives request

Request is assigned to researcher

Researcher completes report

No

Research Director Reviews report

Does report meet standards?

Yes

Researcher sends profile to requestor

End

(3) Analysis Data for Voice of the Customer Data Raw VoC Data Affinity Diagram Theme (Focus Point) DOs end up doing their own prospect research when there is a Research Department to do it. (Product related) Driving Issue CTQ

Not an efficient process Not a proactive process at all, it is completely reactive Not a good system I am on my own My assistant and I do all of our own research Research cannot manage the flow, they start doing a profile for her then get pulled away to do a profile for Sergio or President Shalala I do my own research I identify my own prospects, I might get one from research once in a blue moon I do research to find my prospects which takes away from the time I could be out there raising money I do most of my own prospect identification and it is labor intensive

Reactive process

Cycle time to complete report (number of days until report completed)

Ability to identify new prospects

# of new prospects identified by research per month

Project Objectives: To decrease cycle time to complete reports by 30% and to also increase the number of new prospects identified by the Research department from the current level of zero, both of these objectives should be realized by December 31, 2006. Measure Phase Research Requests Introduction The measure phase contains three steps: operationally defining each CTQ, conducting Gage Reproducibility and Repeatability (R&R) studies on each CTQ, and developing a baseline for each CTQ. (1) Operational Definitions From the define phase, it has been determined there is one CTQ, cycle time to complete the research report (the number of days it takes to take the request and deliver the completed report to the requestor). The CTQ will be operationally defined in terms of the following three parameters: 1. Criteria 2. Test 3. Decision

Operational Definition for CTQ: Cycle time to complete report (number of days until report finished) Criteria for the cycle time to complete report: Open the database and accumulate all of the different reports for each requestor for each year. Test: Find the date the report was completed and the date the report was requested Decision: Subtract the requested date from the completed date, determine the number of days.

(2) Establishing the Validity of the Measurement System for Each CTQ CTQ: Cycle time to complete report (number of days until report finished) There is no measurement error to speak of. For each report requested we simply look at the date completed and subtract the date requested from it to get the cycle time to complete the report.

(3) Establishing the Baseline Capabilities for CTQ A dot plot and descriptive statistics were completed to show the cycle times to complete all the requests from 2004 and 2005. On average it took 10.271 days to complete a report in 2004 and 2005.
Variable C2 Variable C2 N 962 N* 0 Mean 10.271 SE Mean 0.386 StDev 11.961 Minimum 0.000000000 Q1 4.000 Median 7.000 Q3 14.000

Maximum 168.000

Dotplot of Cycle Time to Complete Report (in days)

25

50

75 CTQ

100

125

150

175

Each symbol represents up to 9 observations.

An Individuals-Moving Range chart was completed to show a baseline for cycle time to complete the 962 research requests in 2004 and 2005. The y-x axis represents the length of time (in days) it took to turnaround a research request, each value on the x-y axis represents each of the 962 requests made in the two year span. The chart shows a wildly out of control process.

I-MR for Days to Complete


1

160

Individual Value

120 80 40 0 1

1 1 1 1 11 1 1 1 1 1 5 5 2 2 2 2 2 2 2 2 2 2 1 1 2 6 6 6 6 2 8 8 6 2 1 5 1 5 2 6 6 2 2 2 6 6 6 5 1 5 5 2 6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 6 6 6 2 2 2 1 5 5 2 2 2 2 2 2 2 2 2 2 26 2 6 2 2 6 6 6 2 6 1 8 8 6 6 6 6 2 22 2 2 2 2 2 2 2 2 6 8 6 6 6 2 2 1 1 1 11 51

1 1

1 1 6 6 6 6

11

1 1 6 6 6 2 2 1 8 5 8

6 6 2 6

2 2 2 2 2 2 6 26 2 6 2 26 6 6 66 6 6 2 2 2 6 2 6

2 64 6 6 6 2 6 6 2 4 6

8 6

2 2 2 2 2 2 2 2 6 6 6 66 6 2 2 6 6 6 2 2 2 2 26 2 2 2 2 2 2 8 8 6 6 66 6 6 6 6 6 6 2 2 6 6 2 2 6 2 6 6 2 6

96

192

288

384

480 Observation

576

672

768

86

160 120
1 1 1 1

1 1

Moving Range

80 40 0 1

1 1 1 1 1 1 1 1 11 1 1 1

1 1

1 1 1 1 11 1 1 2 2 2 2 2 22 2

1 1

1 2 2 2 222 2 2 2 2 2 2

1 1 2 2 2 2 2 2

1 1

1 1 2 2 2 2 22 2 2 2 2 2 2 2

1 1 1 1

1 1 1 1 11 1 1

1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

2 2

2 2 2 2 2 22 2 2 2

2 2 2 2 2

2 2 2 2 2 2 2 2 2 22 2

2 2

2 2 2 2

96

192

288

384

480 Observation

576

672

768

86

Process capability cannot be calculated for this process as it is out of control. Further, cycle time and priority are correlated.

Analyze Phase Research Requests Process map identifying and linking the Xs and Ys:
Start

Report requestor requests specific report from online report request Form

X1 = Number of reports requested from each requestor per year

Research Director receives request

Request is assigned to researcher

Researcher completes report

X2 = Type of report ordered (L1, L2, B, T) X3 = Priority (Due Date - Date Requested) X4 = Inappropriate profile requested

No

Research Director Reviews report

Does report meet standards?

Yes

Researcher sends profile to requestor

Y1 = Cycle time to complete research report

End

The sources of the Xs came from process knowledge gathered by interviewing the Research Director, the Research Analysts as well as the Development Officers (DOs).

Operational definitions of Xs Operational Definition for X1: Number of reports requested from each requestor per year Criteria for the number of research requests per year per requestor: Open the database and look at the table containing research requests for each year. Test: Check to see if each request has the following criteria: 1. The name of the requestor 2. The area of the requestor 3. The name of the prospect being profiled 4. The type of report requested 5. The data the report was requested 6. The requested completion date Decision: If all six criteria have been met then a research request has been submitted, if not all six criteria have been met then a research request has not been submitted. Add up the total number of research requests per year per requestor. Operational Definition for X2: Type of report ordered (L1, L2, B, T) Criteria for type of report requested: Open the database and pick a report request. Test: Check to see the type of report in each report request. Decision: The report will be one of the following: Level 1, Level 2, Blurb, Trustee or Special. Operational Definition for X3: Priority Criteria for priority of the report request: Open the database and pick a report request. Test: Find the value for the date the report request was submitted and the date the requestor wants the report completed by. Decision: Subtract the date the report request was submitted from the date the requestor wants the report completed by to get the priority for the report request in days, for example, a report is submitted on the 14th and is needed on the 17th, so, the priority is 3 days

Operational Definition for X4: Inappropriate report requested Criteria for priority of the report request: Open the database and pick a report request. Test: Find the value for the type of report requested and the step in the prospect management process. Decision: If the report is a Level 1 and the step in the prospect management process is either Cultivate or Solicit then the request is appropriate, if the report is a Level 1 and the step in the prospect management process is Qualify then the request is inappropriate. If the report is a Level 2 and the step in the prospect management process is Solicit then the request is appropriate, if the report is a Level 2 and the step in the prospect management process is Qualify or Cultivate then the request is inappropriate. Gage R&R Studies of Each X Gage R&R studies were not conducted on the Xs because their values come from a database and are inherently obvious. Therefore, the assumption is that all of the measurements for the Xs are acceptable.

Establish Baseline Process Capabilities for Xs Baseline Data for X1: Number of reports requested from each requestor per year The control charts for the number of reports ordered per requestor for 2004 and 2005 shows special causes of variation. After talking to people involved with the process it was determined for both years that those who were above the upper spec limits were either President Shalala, the Vice-President, AVPs and a couple people who simply did not understand how the process works and ordered reports for everything. Those who were under the lower spec limits were people who do their own research The years 2004 and 2005 are separated is because the turnover for the Development Officers is ridiculously high! It is more meaningful to separate because in some cases some of the schools and colleges have had 2 or 3 different Development Officers in that 2 year period. For example, the College of Arts and Sciences, Paul Mischler had the 2nd most requests in 2004, he left and Holly Davis took over and she had the 4th most requests in 2005, digging deeper we found they both misclassified A LOT. If I put the data together for 2004 and 2005 they may not stick out as much and I may have missed them. After looking at the Pareto charts it was determined that 6 requestors including President Shalala, the Vice-President, a couple Assistant Vice-Presidents and a couple of users who are uneducated about the process account for 60% of the reports ordered.
C Chart - Reports by Requestor - 2004
80 70 60
1 1

C Chart - Reports by Requestor - 2005


1

100

80

Sample Count

Sample Count

50 40
1 1

60
1 1 1 1

30 20 10 0 3 6
2 1 2 2 2 1 1 2 1 1 1

40

+3SL=23.29 +2SL=19.74 _ +1SL=16.18 C=12.63 -1SL=9.07 -2SL=5.52 -3SL=1.97 30 33

20

1 1 1

1 1

+3SL=25.3 +2SL=21.6 _ +1SL=17.8 C=14.1 -1SL=10.3 -2SL=6.6 -3SL=2.8


1 1

12

15

18 21 Sample

24

27

12

16

20 Sample

24

28

32

36

Pareto Chart - Requests by Requestor - 2004


500 100 400 80

Pareto Chart - Requests by Requestor - 2005


500 400
Percent

100 80 60 40 20 0
Percent

Count

Count

300 200 100 0

60 40 20 0

300 200 100 0

a r o s z f a n k s s z a s a n a s s o r n x r e n s r e o n r al le r i e l e of r o ni o e e g r r e in r e n e a o le id a e e s tr la e al c h s a Jon z a ian sha Nix lot od rvi c om r ie oge rr e oh ba we on S a alk em C shc r b am ar nllingHou as oo O th i A Br B e C D Sh Mis Ro Gon T al Be D. P r a S S e G No R He is C Ro Po A ngles W stl M e y r an D is i ar Ca an C a tee m Ch Am Ch ex om Di le us Al Na o r C T Count 75 52 48 36 32 29 19 19 15 11 1110 10 10 9 7 6 5 5 4 4 3 3 3 2 2 2 2 2 1 1 4 Percent 17 12 11 8 7 7 4 4 3 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 1 Cum % 17 29 40 4855 62 66 70 74 76 7981 83 85 87 89 90 9193 93 94 95 96 96 9797 98 98 99 99 99100
C1

C1

Count 10477 39 38 30 29 23 20 18 18 15151310 7 7 6 6 6 5 4 3 3 3 3 2 2 2 2 2 2 1 5 Percent 2015 8 7 6 6 4 4 3 3 3 3 3 2 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 1 Cum % 203542505561 65697376 7982848688 8990919393 9495959697 9797989898 9999100

ez la io is a es ez ff e rs n es ik es n er os ro er a ra ox nc er tz ck ke n a se ns ra er al ala ar av ieg on m no bi d ge ixo ic otn on uso ttn od st ng ain r e C la de ar Be Bla ool adz in ou r so ha th nz h os DNor J Go alia A r Ro . N erv Pl ng r g Ma S C a elli ob Her LeB Ra chw D r H Pa Bes O T e Ga A Fe a r a D R Go S R i De S S an r m x is C oms te Di a No Ale u N Tr

Baseline Data for X2: Type of report ordered (L1, L2, B, T) The Level 2 report was the most requested report in 2004 and 2005, with the Blurb being the second most requested and the Level 1 and Trustee report following. This is significant due to the fact that a Level 2 report takes much longer to complete than any of the other reports which in turn increases the overall cycle time.

Type of Report Requested - 2004 Type 1=Level 1/Basic 2=Level 2/In-depth BL=Blurb C=Trustee Candidate E=Executive Profile M=Memo S=Special Number 107 156 126 23 3 3 24

Type of Report Requested - 2005 Type 1=Level 1/Basic 2=Level 2/In-depth B=Bio Summary BL=Blurb C=Trustee Candidate E=Executive Profile M=Memo S=Special
100 80
500

Number 78 217 3 182 25 1 2 12


100 80 60 40 20

Pareto Chart - Types of Reports Ordered - 2004


500

Pareto Chart - Types of Reports Ordered - 2005

Number Ordered

400 300 200 100 Type of Report 0

Number Ordered

400 300 200 100 Type of Report

60 40 20

Percent

Le 2=

l ve

In 2/

th ep -d

b ic te i le ial as lur of ec ida /B Pr =B Sp nd e l1 a = BL v e S v ti eC Le cu te xe 1= us Tr =E E = C


126 28.5 63.8 107 24.2 88.0 24 5.4 93.4 23 5.2 98.6 3 0.7 99.3

r he Ot

l y e th rb ia si c ar at lu ep ec Ba id m -d =B Sp 1/ m nd BL /In el Su S= Ca 2 v o e l Le Bi te ve 1= us Le B= Tr 2= C=
Count Percent Cum % 217 41.7 41.7 182 35.0 76.7 78 15.0 91.7 25 4.8 96.5 12 2.3 98.8 3 0.6 99.4

er th

Count Percent Cum %

156 35.3 35.3

3 0.7 100.0

3 0.6 100.0

Baseline Data for X3: Priority (Due Date Date Requested) The average report was needed in 11.228 days in 2004 and 2005.

Variable C2 Variable C2

N 962

N* 0

Mean 11.228

SE Mean 0.397

StDev 12.308

Minimum 0.000000000

Q1 4.000

Median 8.000

Q3 15.000

Maximum 169.000

I-MR for Priority


1

160

Individual Value

120 80 40 0 1

1 1 1 1 1 11 1 1 1 1 1 6 2 5 1 2 2 6 2 2 2 2 5 1 5 5 2 2 2 8 2 2 2 2 1 5 2 2 2 2 2 2 2 2 6 2 2 2 2 2 2 2 2 2 2 2 2 26 1 1 5 5 6 6 1 8 8 6 6 6 66 1 1 1 1 1 51

1 1 1 1 1 1 1 11 1 1 51 2 6 6

5 5 5

11

1 1

1 81 5 8 5

2 6 6 2 6 6

2 2 2 2 2 2 2 22 2 2 2 6 6 6 8 2

26 2 2 6 2 26 2 2 6 2 6 6

2 2 2 22 2 22 2 2 2 6 6 6 6 6 6 2 2 2 2 2 22 6 6 6 6 2 2 8 8 6 2 24 6 6

2 2 2 2 2 22 2 2 6 2 2 2 2 2 2 2 2 2 6 6 6 66 6 6 6 6 2 2 2 2 2 8 8 6 6 66 6 6 2 2 2 2 2 2 2 2 2 6 6 6 6 6 6 2 2 6 6 6 6 2 2 6 26 6 6

+3SL=30.5 _ +2SL=24.1 +1SL=17.6 X=11.2 -1SL=4.8 -2SL=-1.6 -3SL=-8.0

96

192

288

384

480 Observation

576

672

768

864

960

160

1 1

Moving Range

120
1 1 1 1

80 40 0 1

1 1 1 1 1 2 2 2 2 2 2 2 1 1 1 1 1 2 2 2 22 2 2 2 2 2 2 2 2 2 2 1 1 1 11 1 11 11

1 1 1 1 1 1 1 1 11 2 2 2 2 2 2 2 2 2 2 2 2 2

1 1 1 1 11 1

1 2 2 2 2 2

1 2 2 2

1 11 1 1 1 1 1

1 1 1 1

1 1 1 1 2 2 2

22 2 2 2 2 2

2 2 2 22 2 2 2 2 2 2 2 2 2

2 2 2 2 2 2 2 2 2

2 2 2

2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

+3SL=23.6 __ +2SL=18.2 +1SL=12.7 MR=7.2 -1SL=1.8 -3SL=0 -2SL=0

96

192

288

384

480 Observation

576

672

768

864

960

Percent

Baseline Data for X4: Inappropriate report requested After speaking with some of the Research staff it was realized that some of the reports may have been misclassified, meaning that the report requested was not the report that was actually needed (see operational definition). After taking a stratified random sample of the 6 people who made the most requests (in both 2004 and 2005) it was found that there was a misclassification rate of 40% in each year. Misclassification of Report requests - 2004 Number Misclassified 6 13 5 4 3 9 40

Name Donna Shalala Mischler Rosario Jones Gonzalez Talianoff Total

# 75 52 48 36 32 29 272

% 27 20 17 13 12 11 100%

N=100 N1=27 N2=20 N3=17 N4=13 N5=12 N6=11

Number ok 21 7 12 9 9 2 60

Misclassification of Report requests - 2005 Number Misclassified 4 5 11 12 3 5 40

Name Gonzalez Shalala Rosario Davis Noriega Jones Total

# 104 77 39 38 30 29 317

% 33 24 12 12 10 9 100%

N=100 N1=33 N2=24 N3=12 N4=12 N5=10 N6=9

Number ok 29 19 1 0 7 4 60

Develop Hypotheses about the Relationships Between the High Risk Xs and the CTQs X1: Number of reports requested from each requestor per year The number of reports requested from each requestor per year seems to be a large contributing factor to cycle time to turnaround reports. Upon further investigation it seems that only 1 researcher is assigned to President Shalala, the VP and AVPs even though they account for 60% of the research requests. When a large amount of requests from them comes in all of the other researchers put their own projects on hold to work on these projects.
Pareto Chart - Requests by Requestor - 2004
500 100 400 80

Pareto Chart - Requests by Requestor - 2005


500 400
Percent

100 80 60 40 20 0
Percent

Count

Count

300 200 100 0

60 40 20 0

300 200 100 0

a r o s z f a n k s s z a s a n a s s o r n x r e n s r e o n r al le r i e l e of r o ni o e e g r r e in r e n e a o le id a e e s tr la e al c h s a Jon z a ian sha Nix lot od rvi c om r ie oge rr e oh ba we on S a alk em C shc r b am ar nllingHou as oo O th i A Br B e C D Sh Mis Ro Gon T al Be D. P r a S S e G No R He is C Ro Po A ngles W stl M e y r an D is i ar Ca an C a tee m Ch Am Ch ex o m Di le us Al Na o r C T Count 75 52 48 36 32 29 19 19 15 11 1110 10 10 9 7 6 5 5 4 4 3 3 3 2 2 2 2 2 1 1 4 Percent 17 12 11 8 7 7 4 4 3 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 1 Cum % 17 29 40 4855 62 66 70 74 76 7981 83 85 87 89 90 9193 93 94 95 96 96 9797 98 98 99 99 99100
C1

C1

Count 10477 39 38 30 29 23 20 18 18 15151310 7 7 6 6 6 5 4 3 3 3 3 2 2 2 2 2 2 1 5 Percent 2015 8 7 6 6 4 4 3 3 3 3 3 2 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 1 Cum % 203542505561 65697376 7982848688 8990919393 9495959697 9797989898 9999100

ez la io is a es ez ff e rs n es ik es n er os ro er a ra ox nc er tz ck ke n a se ns ra er al ala ar av ieg on m no bi d ge ixo ic otn on uso ttn od st ng ain r e C la de ar Be Bla ool adz in ou r so ha th nz h os DNor J Go alia A r Ro . N erv Pl ng r g Ma S C a elli ob Her LeB Ra chw D r H Pa Bes O T e Ga A Fe a r a D R Go S R i De S S an r m x is C oms te Di a No Ale u N Tr

X2: Type of report ordered (L1, L2, B, T) The dot plot for Cycle Time to Turnaround Reports (CTQ) by Types of Report Ordered indicates: 1. The cycle time for Blurb reports has the lowest variation which makes sense as they are the shortest and quickest report. 2. The cycle time to complete Level 2 reports has the largest variation as they involve much more work than the others. This means that more Level 1 and Level 2 reports that are ordered will drastically affect the cycle time to turnaround reports.
Dotplot for Cycle Time to Turnaround Reports Dotplot for CTQ by Types of Report Ordered

Level 1

Level 2

Blurb Trustee

25

50

75 CTQ

100

125

150

175

Other

25

50

75 CTQ

100

125

150

Each symbol represents up to 9 observations.

Each symbol represents up to 12 observations.

The reason for the outliers in the dotplots above is due to the reports requested not being needed right at the moment. The reports were requested well in advance of them being needed meaning the researcher worked on other reports that were a higher priority (needed sooner) and worked on the outlier reports right before their due date. X3: Priority (Due Date Date Requested) The dot plots for Cycle Time to Turnaround Reports (CTQ) and Priority to Receive Reports indicate: 1. The values of Cycle Time to Turnaround Reports seem to be close to those of Priority to Receive Reports, meaning that the priority to receive the reports is a contributing factor to cycle time to turnaround reports (CTQ)
Dotplot for Cycle Time to Turnaround Reports
Dotplot for Priority to Receive Reports

25

50

75 CTQ

100

125

150

175

25

50

75 CTQ

100

125

150

175

Each symbol represents up to 9 observations.

Each symbol represents up to 8 observations.

X4: Inappropriate report requested The dot plot and descriptive statistics for Cycle Time to Turnaround Reports (CTQ) by Misclassified Reports indicates: 1. The dotplot shows that misclassification of reports increases the time it takes to complete reports. The average of 11.48 days for misclassified reports in 2004 and 12.8 days in 2005 are both higher than for all of the requests (10.22) 2004
Variable C1 N 40 N* 0 Mean 11.48 SE Mean 2.62 StDev 16.55 Minimum 0.000000000 Q1 5.00 Median 7.00 Q3 13.75

Dotplot for Misclassifed Reports 2004 vs CTQ

14

28

42

56 CTQ

70

84

98

2005
Variable C1 N 40 N* 0 Mean 12.80 SE Mean 1.63 StDev 10.32 Minimum 1.00 Q1 5.00 Median 10.00 Q3 15.75 Maximum 44.00

Dotplot for Misclassifed Reports 2005 vs CTQ

12

18

24 CTQ

30

36

42

Hypotheses Regarding Relationships Among the Xs and CTQ The analyze phase resulted in the following hypothesis: Cycle time to turnaround report = f (X1: Number of reports ordered per requestor/year, X2: Type of report ordered, X3: Priority, X4: Inappropriate report requested) The reason for the extreme points in the CTQs and their relationships to the extreme points in the Xs is due to the correlation between cycle time and how quickly the report is needed (priority). If a report is not needed for 90 days, the researcher wont work on it until close to the date it is needed instead focusing on reports that are needed sooner, hence, the outliers in the CTQs.

X1: Number of reports requested from each requestor per year There is no optimum number of reports requested per year. It all depends on the number of prospects they are going to qualify, cultivate or solicit, which depends on a bunch of factors that are not measurable. X2: Type of report ordered (L1, L2, B, T) There is no optimum type of report ordered. Blurbs are the easiest and least time consuming then come Level 1 reports and finally Level 2s are the most time consuming. As you will see in my improve phase it all depends where the prospect is in the cultivation cycle as to the type of report ordered. X3: Priority (Due Date Date Requested) There is no optimum level for priority. If the DO needs the report in 2 weeks because they are meeting with a prospect then the priority is 14 days. X4: Inappropriate report requested The optimum level for inappropriate report requested is zero. The more misclassified reports you have the more time your researchers are wasting doing research that most likely will not be used. This is a pretty easy fix in the improve phase. A Design of Experiments is not needed in the Analyze phase due to the fact that we know the optimum level of factor levels due to process knowledge (see above). The problems with the Xs can be solved by modifying the procedures in the Advancement Research Office which will be detailed in the Improve phase.

Improve Phase Research Requests The Research Report Request process begins with the report requestor going online and filling in the form below.

Misclassification of Reports After speaking with some of the Research staff as well as some of the Directors of Development it was indicated that some of the reports may have been misclassified, meaning that the report requested was not the report that was actually needed. In the Analyze phase we took a stratified random sample of the 6 people who made the most requests (in both 2004 and 2005) it was found that there was a misclassification rate of 40% in each year. After some investigation it is clear that this problem is caused by the requestor filling out the online report request form above and asking for a report that they do not need. The requestor ends up getting more information than they will use and the research department spends valuable time doing research for nothing as well as many hours of overtime. The prospect management cycle consists of the following stages and the type of report needed at each stage in the process is indicated in parenthesis: 1. Identify the prospect no report is needed 2. Qualify the prospect blurb report is needed (can often be provided by DODs assistant) 3. Cultivate the prospect Level 1 report is needed 4. Solicit the prospect Level 2 report is needed 5. Steward the prospect no report is needed In order to solve this problem the online report request form above will be modified so that the report requestor does not ask for a specific report but instead states the stage of the prospect management cycle that they are in. The Director of Research will then determine upon receiving the request which report will be completed depending on the stage in the prospect management cycle the prospect is in. Reports do not meet standards Another problem with the process is the fact that the Research Director must send many reports back to the researchers before sending them to the requestors because the report does not meet quality standards. Many of the same mistakes are made over and over again and waste not only the Research Directors time but also the individual researchers time as well. To solve this problem we will create a quality checklist for the researchers to go over before they submit the report to the Research Director for review. In addition, they will submit their report to their peers for a peer review before sending it to the Research Director.

Research Report Quality Checklist Prior to beginning any research report, remember to always do the following: Check Assignment of Prospect Check Prospect Management Status/Cultivations Contact Requesting Officer to Discuss Specific Needs Type of Report Prospecting Blurb PM Status Qualify Components of Research Job Title Brief Business Description (Include spousal occupation only if relevant. i.e. Education Prospects) Home Market Value Estimated Gift Capacity UM Affiliations Current Contact Information

Note: A Prospecting Blurb should not exceed 3-4 sentences. Customize, within reason, for your particular DOD. While some prefer simple one liners, stating only Estimated Gift Capacity and Affiliation, others prefer all info. available for such a request. Miscellaneous Event Blurb * Usually reserved for Presidential and Provost related events. Job Title Brief Business Description Significant Directorships Significant Charitable/Civic Affiliations Spousal Information, if Attending UM Affiliations Summarized UM Giving Confirmation of Home Address/Contact Personal Information (Spouse, children, birthdate) Confirmation of Business Address/Contact Current Business Dealings/News Significant Directorships Significant Charitable/Civic Affiliations Basic On-Line News Search (up to 3 years) Basic Wealth Indicators (i.e. Home Value, Stockholdings, Salary, Business Revenue - if owner of company) UM Affiliations (if not previously delivered) UM Giving History (if any) Indepth Online News Search Extensive Wealth Profile (including family relations if applicable) Indepth Business Information/Career History Indepth Analysis of Past Charitable Giving Philanthropic Affiliations Updated UM Giving History

Basic - Level 1

Cultivate

In-depth - Level 2

Ready to Solicit

NOTE: By this point, the DOD should be very familiar with prospect. A level 1 profile is already on file and does not need to be repeated. If on a rare occasion they have no prior research, you would have to inlcude Level 1 information as well. Depending on the DOD and their preferences, you may also combine/update your Level 1 with the Level 2 for a final product. Some may prefer simply the taregted info. Memo Report Miscellaneous Targeted to a specific question that a DOD may need for a

cultivation meeting (i.e. Recent sale of a company, pending lawsuit, or simply a current address and phone number) Also remember to check the following: Spelling Grammar Style (AP) Peer Review

NOTE: During a Peer Review, the reviewer should always write their name at the top of the draft reviewed. Apart from the elements listed above, remember to look out for information that does not add up, or seems off the mark... This document is for internal use within the Research Department only.

Reports requested by requestor The final problem with the Research Report Request process has to do with the fact that only 1 out of 6 researchers is assigned to the President's Office, Vice-President's Office and Trustee Services even though over 60% of the research report requests come from those 3 areas. In order to solve this problem a computer based simulation of the process was created to optimize the workload of the Research Analysts. The ARENA Input Analyzer was used and it was determined that an Exponential distribution fit the interarrival time data the best. See below.

Inter-arrival Rate of Report Requests Distribution Summary Distribution: Expression: Square Error: Exponential -0.5 + EXPO(1.23) 0.021524 I used Input Analyzer to fit the

The 4 different types of reports each have their own processing times. processing times and they were as follows (in hours): Blurb Report POIS(4.81) Level 1 Report TRIA(16,30,42) Level 2 Report TRIA(36,48,60) Trustee Candidate Report TRIA(4,5.95,8.95)

A simulation model and experiment was created using the ARENA simulation software package without making any changes to the system (see below). The results were compared to the actual system performance to verify your model. The results obtained in Arena were very close to the actual system. Actual System 962 10.27 Simulation Model Average 898 9.25* 95% CI (866, 931) (8.52, 9.98)

# of reports in 2 years Cycle time (in days)

* Difference may be related to the fact that in the actual system there is a step where the reports are checked by the Research Director and sent back for revision if not up to specifications. This was omitted from the model due to the fact that there is currently no Research Director and a good estimate of the time and frequency of that part of the process could not be made.

[Simulation of current process]


A s s g i n Co m m Re q u e s t o r u n c i a t o i n

Com m uni c at o i n Type of Repor t


1 0 0 E s l e

Ds i p o s e A s s g i n Re q u e s t o r

E n g n i e e r n i g

Engi neer i ng

0T

r u e

F a s l e

Ds i p o s e

0
A s s g i n M Re q u e s t o r u s c i

M usi c

0T

r u e

F a s l e

A s s g i n Re q u e s t o r S t u d e n t A f f a r i s

St udent

Af f ai rs

0T

r u e

F a s l e

A s s g i n Re q u e s t o r B o a r d o f T r u s t e e s

Boar d of

0T Tr ust ees

r u e

F a s l e

Ds i p o s e

0
A s s g i n Re q u e s t o r J u d a c i

Judai c St udi es
6 7 E s l e

A s s g i n Re q u e s t o r Nu r s n i g

Nur si ng
7 1 1 E s l e

Re s e a r c h e r A s s g i n Re q u e s t o r A S
1 0 5 0 E s l e

# 1

Re c o r d

R SM AS 0

Re s e a r c h e r 1

RS M

A s s g i n Re q u e s t o r Co r p o r a t e

C or por at e and Foundat i on R el at i ons


6 3 8 E s l e

Re c o r d Re s e a r c h e r A s s g i n Re p o r t L e v e l T m i 2 e # 2

Re s e a r c h e r 2

A s s g i n

Re q u e s t o r

Ar chi t ect ur e
1 2 5 0 E s l e

Re c o r d Re s e a r c h e r A s s g i n Re p o r t L e v e l T m i 1 e # 3

Re s e a r c h e r 3

A r c h t i e c t u r e

0
Re c o r d A l

Co m S e n t

p e l t e d t o

Re p o r t

Re p o r t

A r r i v e s

A s s i g n T i m E n t e r n i g

Ar ea Request Fr om
E s l e

Com i ng
1 . 3 6 1 3 . 3 1 4 1 . 4 1 8 8 . 3 1 4 1 3 . 7 6 9 6 . 3 1 4 1 2 . 9 3 1 9 2 . 0 9 4 2 5 . 0 2 6 2 3 . 3 5 0 8

Re q u e s t o r

0
A s s g i n Re q u e s t o r

Educat o i n
1 0 2 9

A s s i g n Re p o r t

B l u r b T m i e

Send t o C or r ect R esear cher


Re q u e s t o r = = 1 9 Re q u e s t o r = = 1 8
E s l e

Re c o r d Re s e a r c h e r # 4

Re s e a r c h e r 4

E d u c a t i o n

E s l e

Re q u e s t o r = = 1 7 Re q u e s t o r = = 1 6 Re q u e s t o r = = 1 5 Re q u e s t o r = = 1 4

Ds i p o s e

5 . 1 3 0 9 1 . 6 7 5 4 3 . 2 4 6 1 . 8 3 7 7 3 . 1 4 1 4 3 . 8 7 4 3 9 . 7 3 8 2 1 5 . 9 1 6 2 3 6 . 5 4 4 5

0T
A s s g i n Re q u e s t o r L a w

u e

A s s g i n

T r u s t e e s T m i e

Law

Re p o r t

Re q u e s t o r = = 1 3 Re q u e s t o r = = 1 2 Re q u e s t o r = = 1 1 Re q u e s t o r = = 1 0 Ds i p o s e 6 Re q u e s t o r = = 9 Re q u e s t o r = = 8

Re c o r d Re s e a r c h e r # 5

Re s e a r c h e r 5

F a s l e

Re q u e s t o r = = 7 Re q u e s t o r = = 6 Re q u e s t o r = = 5 Re q u e s t o r = = 4 Re c o r d Re s e a r c h e r # 6 6 Re s e a r c h e r

A s s g i n

Re q u e s t o r

At hl et c i s
2 3 3 2 E s l e

A t h l e t i c s

Re q u e s t o r = = 3 Re q u e s t o r = = 2 Re q u e s t o r = = 1

0T
A s s g i n Re q u e s t o r L o we

u e

Lowe M useum

F a s l e

A s s g i n

Re q u e s t o r A u l m n i

Al um ni R el at o i ns
7 0 7 E s l e

A s s g i n

Re q u e s t o r

Li br ar i es

0T

u e

L b i r a r e i s

F a s l e

Ar t s and Sci ences


A s s g i n Re q u e s t o r A r t s a n d S c e i n c e s
3 5 4 5 E s l e

A s s i g n Re q u e s t o r P r e s d i e n t S h a a l a l

Pr esi dent

Shal al a
4 9 1 3 E s l e

A s s i g n

Re q u e s t o r V P

Vi c e Pr esi dent s O f f i ce
4 2 1 2 4 2 E s l e

The different scenarios and modifications of the system that were experimented with were the following: 1. Alternative #1 One additional Research Analyst was hired @ $40,000 per year and assigned to help Research Analyst #1 with the reports for President Shalala, VPs and the Board of Trustees. This was due to the fact that the queue and cycle times were the highest for that area. 2. Alternative #2 In this scenario Research Analyst #5 (the least busy) was re-assigned to help Research Analyst #1 with the reports for President Shalala, VPs and the Board of Trustees while his reports were re-assigned to Research Analyst #2 (he had the 2nd lowest utilization) 3. Alternative #3 All Research Analysts work from a single queue and the first available Research Analyst works on the next report in the queue. See the charts below for the results of the 95% confidence intervals of the following three performance measures after 15 replications of each alternative were run for 24 hours a day for 730 days (2 years): 1. Cycle time (in hours) 2. Average time report is in queue (in hours) 3. Utilization of Research Analysts.

Cycle Time (in hours) Comparison Between Current System and 3 Alternatives Current System Alternative #1 Alternative #2 Alternative #3
Avg Avg of all Researcher 1 Researcher 2 Researcher 3 Researcher 4 Researcher 5 Researcher 6 Researcher 1&7 Only 1 queue Researcher 1&5 65.99 89.44 24.32 42.15 27.87 41.57 37.56 Half width 5.81 10.04 2.37 1.24 1.01 1.73 2.06 95% CI (60.18,71.8) (79.4,99.48) (21.95,26.69) (40.91,43.39) (26.86,28.88) (39.84,43.3) (35.5,39.62) Avg 32.96 24.32 42.15 27.87 41.57 37.56 30.98 Half width .49 2.37 1.24 1.01 1.73 2.06 .86 95% CI (32.47,33.45) (21.95,26.69) (40.91,43.39) (26.86,28.88) (39.84,43.3) (35.5,39.62) (30.12,31.85) Avg 33.31 36.26 42.15 27.87 37.57 30.98 Half width .53 1.89 1.24 1.01 2.06 .86 95% CI (32.78,33.84) (34.37,38.15) (40.91,43.39) (26.86,28.88) (35.5,39.62) (30.12,31.85) Avg 27.12 27.12 Half width .30 .30 95% CI (26.82,27.42) (26.82,27.42) -

Average Time in Queue/Report (in Hours) Comparison Between Current System and 3 Alternatives Current System Alternative #1 Alternative #2 Alternative #3
Avg Researcher 1 Researcher 2 Researcher 3 Researcher 4 Researcher 5 Researcher 6 Researcher 1&7 Only 1 queue Researcher 1&5 65.43 1.80 6.62 3.99 3.42 6.49 Half width 10.15 1.05 .65 .75 1.29 1.62 95% CI (55.28, 75.58) (.75, 2.85) (5.97, 7.27) (3.24, 4.74) (2.13, 4.71) (4.87, 8.11) Avg 1.80 6.62 3.99 3.42 6.49 6.97 Half width 1.05 .65 .75 1.29 1.62 .83 95% CI (.75, 2.85) (5.97, 7.27) (3.24, 4.74) (2.13, 4.71) (4.87, 8.11) (6.14,7.8) Avg 5.96 6.62 3.99 6.49 6.97 Half width 1.62 .65 .75 1.62 .83 95% CI (4.34,7.58) (5.97, 7.27) (3.24, 4.74) (4.87, 8.11) (6.14,7.8) Avg .32 Half width .1 95% CI (.22,.42) -

Utilization of Research Analysts Time Comparison Between Current System and 3 Alternatives Current System Alternative #1 Alternative #2 Alternative #3
Avg Researcher 1 Researcher 2 Researcher 3 Researcher 4 Researcher 5 Researcher 6 Researcher 1&7 Only 1 queue Researcher 1&5 .6938 .06 .21 .12 .10 .19 Half width .02 .01 .02 .01 .01 .01 95% CI (.6738, .7138) (.05, .07) (.19, .23) (.11, .13) (.09, .11) (.18, .20) Avg .06 .21 .12 .10 .19 .35 Half width .01 .02 .01 .01 .01 .01 95% CI (.05, .07) (.19, .23) (.11, .13) (.09, .11) (.18, .20) (.34,.36) Avg .1631 .21 .12 .19 .35 Half width .01 .02 .01 .01 .01 95% CI (.1531,.1731) (.19, .23) (.11, .13) (.18, .20) (.34,.36) Avg .23 Half width .01 95% CI (.22,.24) -

The different performance measures for all three alternatives in relation to the current system came out statistically significant, as none of the 95% confidence intervals of their means overlapped with the 95% confidence interval of the mean of the current system.

In regards to cycle time (in hours), the most important metric the results can be summarized as follows: Current System (68.16, 79.84) 95% C.I. Alternative #1 (32.47,33.45) 95% C.I. Alternative #2 (32.78,33.84) 95% C.I. Alternative #3 (26.82,27.42) 95% C.I.

Average time in queue for Shalala/VP reports can be summarized as follows: nd (note: all of the average times in queue can be found in the 2 table above) Current System (55.28, 75.58) 95% C.I. Alternative #1 (6.14,7.8) 95% C.I. Alternative #2 (6.14,7.8) 95% C.I. Alternative #3 All in 1 queue (.22,.42) 95% C.I.
rd Clearly the 3 Alternative appears to be the best as the 95% C.I. for its mean is the lowest and does not overlap any of the others. However this alternative would require all Research Analysts to work on all of the reports and use 1 queue. This would not be feasible due to the fact that Development Officers are used to working with their own Research Analysts and have developed strong working relationships with them.

The results from Alternatives 1 and 2 appear to be fairly close and there is no statistical significance between them as the 95% C.I.s of their means overlap. Alternative #1 would require the Division of University Advancement to hire an additional Research Analyst at an annual salary of $40,000. The increase in performance does not appear to be enough to justify this expenditure. Therefore amongst Alternatives explored in this study Alternative #2 is the preferred solution.

Revised Flowchart of the Research Report Request Process


Start

Report requestor requests report online stating stage of Prospect Management cycle prospect is in

X1 = Number of reports requested from each requestor per year

Research Director receives request

Request is assigned to researcher depending area requestor is from

Researcher completes report

X2 = Type of report ordered (L1, L2, B, T) X3 = Priority (Due Date - Date Requested) X4 = Inappropriate profile requested

Researcher completes quality checklist and peer review and submits report to Research Director for review/approval
No

Research Director Reviews report

Does report meet standards?

Yes

Researcher sends profile to requestor

Y1 = Cycle time to complete research report

End

Pilot Test Results

Misclassified Reports August 1- October 3, 2006 Total number of reports requested Total number of reports misclasified % misclassified 100 14 14%

The changes which were implemented reduced the misclassification reports from 40% to 14%

Dotplot of Cycle Time to Complete Reports (in days)


Dotplot of Cycle Time to Complete Report (in days) - Pilot Test

9 12 timetocomplete

15

18

21

Descriptive Statistics: timetocomplete Variable timetocomplete Variable timetocomplete N 100 N* 0 Mean 7.340 Maximum 23.000 SE Mean 0.717 StDev 7.169 Minimum 0.000000000 Q1 1.000 Median 6.000

Q3 13.000

Prospects Identified by Research Department With the re-organization of researchers and the reduction in the misclassified reports the researchers have been able to use their time to identify new donor prospects for the university Since August 2006 over 400 new good prospects were identified, prior to this DMAIC project the researchers did not identify any new prospects due to the fact they were spending all of their time doing non-value added research reports. In addition, that number may grow much higher as there are a total of 84 prospects who have been identified but the researcher is waiting to hear back from the Development Officer as to whether they are good for that School/College or not.

Before/After I-MR Chart of Cycle Time (CTQ #1)

I-MR Chart of Cycle Time by Before/After


1 160 Individual Value 120 80 40 0 1 106 212 318 424 530 Observation 636 742 848 954 1060
1 1 1 1 1 1 1 1 11 1 11 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1

11 1 1 1 1 11

1 1

1 1

1 1 1

1 1 1 1 1 1 1 1 1 11 1 1

_ UCL=16.4 X=7.3 LCL=-1.8

1 160 Moving Range 120 80 40 0 1 106 212 318 424 530 Observation 636

1 1

1 1 1 1

1 1 1 1 1 11 11 1 1 1 1 1 1 11 11 1

1 1 1 1 1 1 1 1 1 1 1 1 1 1

1 1

11 11 1

1 1

1 1 1 1 1 1 11 1 1 1 1 1

11 1 1

1 1

__ UCL=11.2 MR=3.4 LCL=0 1060

742

848

954

I-MR Chart of Cycle Time (after)


1 1 1 11 1 111 1 1 1 1 11 1

20 Individual Value 15 10 5 0 1

UCL=16.45

_ X=7.34

LCL=-1.77 10 20 30 40 50 Observation 60 70 80 90 100

16 12 8 4 0 1

1 1 1 1 1

Moving Range

UCL=11.19

__ MR=3.42 LCL=0 10 20 30 40 50 Observation 60 70 80 90 100

Upon improving the process the mean cycle time went from 10.217 days with a standard deviation of 11.961 days before to a mean cycle time of 7.53 days and a standard deviation of 7.227 days after. By improving the process with the DMAIC project we were able to decrease mean cycle time substantially as well as reduce variation. Control Phase

The Control phase is comprised of 4 steps: 1. Standardization 2. Mistake-proofing 3. Documentation 4. Giving control of the process back to the process owner

(1) Standardization

Who is involved at the revised steps of the process? The Director of the Research department as well as all of the Research Analysts are involved in the revised steps of the process.

What should they be doing after standardization of the revised standard operating procedures? Upon receiving a research request they should do the following: 1. Look up the prospect in the system to make sure the report requestor specified the correct prospect management status on the online report request form. 2. If the prospect management status on the request form does NOT match the prospect management status in the system the research analyst should call the requestor and get them to update it in the system. 3. If there is anything on the request that is unclear the research analyst should call the requestor for clarification. 4. The Research Analyst should log the report request in the Project Log database and make sure to enter all of the normal information as well as the new fields which were added (prospect management cycle stage) 5. After completing the report the researcher should complete the Research Report Quality Checklist and have another Research Analyst perform a peer review to ensure quality. 6. After sending the report to the requestor the Research Analyst should close out the project in the Project Log database and make sure to enter in the completed date as well as the new fields which were added in this project (peer review completed (Y/N), checklist completed (Y/N) With the time saved from this project Research Analysts will have more time to identify new prospects for the Development Officers. It is important that these new prospects are tracked in order to: (a) give the Research Analysts the credit they deserve in regards to helping bring in new donations (b) help keep track of the hard benefits of this DMAIC project In order to be able to track these new prospects, Research Analysts will be asked to do the following: 1. Go into the new Prospect Identification database and set the Research Status on prospects they are researching as potential donors to the letter R, also enter the date, the research analysts name and the area the prospect is being identified for (School/College). 2. After identifying that prospect as a possible good donor their name is sent to their respective Development Officer. If the Development Officer confirms the prospect is a good one change the Research Status to I, if the prospect is not good for that School/College set the Research Status to NR, if the prospect is not a good prospect for UM at all set the Research Status to N.

Why should they follow the revised standard operating procedures? There are a few reasons they should follow the revised standard operating procedures: 1. To prevent misclassifications of report requests. 2. To ensure reports are sent out with the highest quality. 3. To allow proper tracking of newly identified prospects. 4. To ensure Development Officers are entering prospect management information into the system. 5. To ensure the Report Requestor gets exactly what they need. 6. To be able to ensure the Research Department gets the credit they deserve for helping bring in donations.

Where/when should they be doing the revised process procedures? The revised process procedures should be done throughout the Research Report Request Process. Documentation will be given to the Research staff to tell them exactly where/when they should be doing the revised process procedures.

How much will it cost to do the revised process procedures? There will be no cost to do the revised process, everything is being done in-house.

Is additional training needed to perform the revised process procedures? Yes, additional training will be conducted for the Research staff as well as those who submit Research Report Requests.

How often should the revised process procedures be monitored? The revised process procedures will be monitored monthly.

Who will monitor the revised process procedures? The Research Director as well all Research Analysts will be trained on monitoring the revised process procedures. The Research Analysts will be trained in order to help foster intrinsic motivation on their part so that they feel like they are part of the improvements that are taking place.

Who will make decisions on the future outputs of the revised process procedures? The Research Director will make decisions on the future outputs of the revised process procedures.

(2) Mistake-proofing Potential risk elements were identified that could be carried through the process by using failure mode effects analysis (FMEA). These risk elements are: 1. Requestor enters wrong Prospect Management status on Report Request form. 2. Research Analyst neglects to conduct peer review/use quality checklist. 3. Researcher neglects to change Research Status for newly identified prospects.

Failure Mode Effects Analysis (FMEA)


Risk Elements Requestor enters wrong PM status on request Failure Mode Possible misclass. of report Likelihood of Occurrence 9 Severity Likelihood of Detection 7 RPN Action Likelihood of Occurrence 7 Severity Likelihood of detection 7 RPN

441

Researcher neglects to conduct peer review/use checklist

Researcher neglects to change Research Status for newly identified prospects

Lower quality reports. More time by Director proofing reports Research does not get the credit it deserves for Prospect Ids

252

126

Look up prospect in system. Call requestor for clarification Create weekly exceptions reports for Director for monitoring purposes Create weekly exception reports for Director for monitoring purposes

196

72

70

Requestor enters wrong Prospect Management status on Report Request form. Upon receiving online report requests the Research Analyst will look up the prospect in the database to ensure that the correct Prospect Management status was entered. If they do not match the Research Analyst will call the Research Requestor for clarification.

Research Analyst neglects to conduct peer review/use quality checklist. Weekly exceptions reports will be created for the Director to monitor peer reviews and use of the quality checklist for reports rendered that week. Researcher neglects to change Research Status for newly identified prospects. Weekly exception reports will be created for newly identified prospects whose status is R (being reviewed) to remind them to call their Development Officers to see if the prospects they have identified are good or not.

(3) Documentation Training Documentation for Researchers and Requestors of Research The revised Research Request process is as follows: The report requestor will specify the current prospect management status (amongst other information) on the online report request in order to receive the correct report. Prospect Management Status Qualify Cultivate Solicit Type of Report Given Blurb Level 1 Level 2

It is very important that the Requestors of Research realize the importance of specifying the correct prospect management status on the online report request form in order that the Research Analyst performs the correct research. The Research Director or Senior Research Analyst will assign the incoming research requests to Research Analysts depending on who the requestor is. With the revised process there are currently 2 Research Analysts assigned to President Shalala and the Office of the Vice-President for University Development and 4 Research Analysts distributed evenly among the Schools and Colleges.

Research Requests Procedures Upon receiving the Research Request the Research Analyst should do the following: 7. Look up the prospect in the system to make sure the report requestor specified the correct prospect management status on the online report request form. 8. If the prospect management status on the request form does NOT match the prospect management status in the system the research analyst should call the requestor and get them to update it in the system. 9. If there is anything on the request that is unclear the research analyst should call the requestor for clarification. 10. The Research Analyst should log the report request in the Project Log database and make sure to enter all of the normal information as well as the new fields which were added (prospect management cycle stage) 11. After completing the report the researcher should complete the Research Report Quality Checklist and have another Research Analyst perform a peer review to ensure quality. 12. After sending the report to the requestor the Research Analyst should close out the project in the Project Log database and make sure to enter in the completed date as well as the new fields which were added in this project (peer review completed (Y/N), checklist completed (Y/N). Prospect Identification Procedures When working on prospect identification Research Analysts should do the following: 1. Go into the new Prospect Identification database and set the Research Status on prospects they are researching as potential donors to the letter R, also enter the date, the research analysts name and the area the prospect is being identified for (School/College). 2. After identifying that prospect as a possible good donor their name is sent to their respective Development Officer. If the Development Officer confirms the prospect is a good one change the Research Status to I, if the prospect is not good for that School/College set the Research Status to NR, if the prospect is not a good prospect for UM at all set the Research Status to N.

(4) Giving control of the process back to the process owner This concludes the project. This process will now be turned over to the process owner with control plans for future PDSA cycles.