Vous êtes sur la page 1sur 18

Table of Contents:

1. 2. 2.1. 2.2. 2.3. 3. 3.1. 3.2. 3.3. 4. 4.1. 4.2. 5. 6. 6.1. 6.2. 6.3. 7. 8. 8.1. 8.2. 8.3. 9. 9.1. 9.2. 9.3. 9.4. 9.5. 9.6. 9.7. 9.8. 9.9. 10.

Objective ........................................................................................................................................................... 4 General requirements ..................................................................................................................................... 4 Logic diagram of operations.............................................................................................................................. 4 Reference documents ....................................................................................................................................... 6 General requirements concerning works ......................................................................................................... 6 Basement level preparation ........................................................................................................................... 6 Basement level inspection for erection purposes ............................................................................................ 6 Concrete basement level preparation .............................................................................................................. 6 Metal basement level preparation .................................................................................................................... 7 Installation ........................................................................................................................................................ 7 General............................................................................................................................................................... 7 Installation tolerances ........................................................................................................................................ 7 Wedging ............................................................................................................................................................ 7 Alignment.......................................................................................................................................................... 8 Alignment chronology ........................................................................................................................................ 8 Execution of alignment ...................................................................................................................................... 8 Allowable alignment tolerances ........................................................................................................................ 8 Tightening of anchor pieces .......................................................................................................................... 9 Piping connection ......................................................................................................................................... 10 Erection of pipes .............................................................................................................................................. 10 Jointing ............................................................................................................................................................. 10 Connection of the main pipes ......................................................................................................................... 10 Inspections ..................................................................................................................................................... 11 Inspections of the basement level "for erection" ............................................................................................ 11 Equipment installation inspection ................................................................................................................... 11 Alignment checking before jointing of pipes................................................................................................... 12 Checking of main pipes jointing ...................................................................................................................... 12 Alignment checking after piping connection................................................................................................... 12 Alignment checking after final setting of pipe elastic supports...................................................................... 12 Checking of auxiliary mechanical equipment erection .................................................................................. 12 Checking of instrumentation and control installation ..................................................................................... 12 Miscellaneous .................................................................................................................................................. 12 Attachment 1: Alignment of rotating machines ........................................................................................ 12

10.1. Measuring instruments .................................................................................................................................... 12 10.2. Alignment procedures ..................................................................................................................................... 13 10.3. Marking of the reference points ...................................................................................................................... 13 10.4. Adjustment of the distance between shaft ends ............................................................................................ 14 10.5. Adjustment of parallelism ................................................................................................................................ 14 10.6. Adjustment of concentricity ............................................................................................................................. 16
Originator Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

2/18

T4-APD-B0-A-40104

11.

Attachment 2: Calculation of tolerances for semi-flexible coupling ..................................................... 18

11.1. Calculation of speed factor (Fv) values .......................................................................................................... 18

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

3/18

T4-APD-B0-A-40104

1. OBJECTIVE
The present document collects the general recommendations and/or requirements concerning the erection of rotating machines and particularly: motor-driven feedwater pumps miscellaneous motor-driven pumps

Given the wide range and diverse nature of the equipment concerned and especially the particular requirements relating to some major components (such as feedwater pumps) the present document can be amended or completed by specific rules mentioned in the Erection Instructions (EI) and/or Erection Quality Control Plan (EQ).

2. GENERAL REQUIREMENTS
2.1. Logic diagram of operations
The extent of the works and inspections to be performed for erection of rotating machines is shown by the following logic principle diagram:

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

4/18

T4-APD-B0-A-40104

Inspection of basement level for erection


Preparation of basement level

Placing of equipment Prealignment of the rotating machines not arranged on a common frame "Equipment location" inspection Alignment with anchor bolts tightened to their rated torque Grouting Alignment checking prior to pipe jointing Jointing of main piping

Checking of main piping jointing Main piping connections

Alignment checking after main piping connection Final adjustment of the elastic supports of the main piping Alignment checking after final adjustment of the elastic supports of main piping Installation of auxiliary mechanical equipment (coolers, pipes, ...) Miscellaneous mechanical equipment erection checking

X
Instrumentation and control equipment erection checking

Installation of instrumentation

and control equipment

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

5/18

T4-APD-B0-A-40104

2.2. Reference documents


The basic documents at the Erection Subcontractor's disposal are: The civil works conformance report relating to basement level. The tolerances allowed for civil works execution (Erection Standard: EG 101) The equipment manufacturing drawing. The general arrangement drawing (GA) or the piping arrangement drawing (PA). The list of equipment and accessories for the equipment concerned and the corresponding warehouse issue slip. The erection instruction (EI) with erection drawings and documents. The erection quality control plan (EQ).

2.3. General requirements concerning works


The access and erection areas must be kept tidy and clean. During erection, all necessary steps shall be taken to protect the surrounding equipment and the equipment waiting for erection.

3. BASEMENT LEVEL PREPARATION


3.1. Basement level inspection for erection purposes
The Erection Subcontractor performs the following operations: Materialization on the basement level: - of the theoretical equipment installation axes - of a reference level. Checking of: - location with regard to the theoretical axes - basement level geometry - surface conditions of basement level and anchor holes - location of anchor bars in anchor holes - visuel examination of foundations to search for apparent construction and erection defects and faults (cracks, deformations, assembly of metal foundations, ...).

Once these inspections have been performed, the Erection Subcontractor: gives his inspection report stamped "issued for erection" or transmits his observations with request for bringing the basement level to its final form (civil works basement or metal support) or proposes a new installation.

3.2. Concrete basement level preparation


Careful concrete surfacing at the shims Checking of dimensions, flatness and horizontality of the supports thus arranged.
Originator Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

6/18

T4-APD-B0-A-40104

3.3. Metal basement level preparation


Cleaning of basement levels Elimination of the defects caused by any possible damage (shocks for instance).

4. INSTALLATION
4.1. General
Rotating machines can be delivered: on rigid frames, mounted and set in workshop in separate elements with shaft line to be assembled on Site.

Refer to the relevant Erection Instruction (EI) for: location and orientation special instructions

Equipment must be installed with respect to the theoretical reference axes of the installation building or area.

4.2. Installation tolerances


Tolerances to be adopted unless stated otherwise in the Erection Instruction (EI) concerned: Installation with respect to the theoretical reference axes: - arrangement : 5 mm - level : 5 mm Verticality (perpendicularity deviation) = 0.3 mm per meter Horizontality = 0.3 mm per meter

5. WEDGING
Arranged on each side of each anchor bolt, and as close as possible to the anchor holes (or bolts in case of metal foundations) Wedging height on concrete foundations: above 30 mm Reduce to the minimum the number of wedges to be stacked while respecting the stipulated height The wedges shall be dimensioned (length x width) as specified on the documents attached to the construction package cleaned and burred. The temporary wedges (screws jacks for instance) provided to make final wedging easier, must imperatively be removed before the anchor bolts are tightened to their rated torque. The jacks-wedges definitely embedded in grouting mortar shall be blocked by tack-welds after the last alignment checking and before the grouting mortar is poured.

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

7/18

T4-APD-B0-A-40104

6. ALIGNMENT
6.1. Alignment chronology
Considering the type of the machine, all or some of the following alignments must be carried out. Prealignment: only for the machines not installed on a common frame. Alignment prior to pipe jointing: - before pouring the grouting and wedging mortars - after tightening of the anchor bolts to their rated torque. Alignment after pipe connection Alignment after final adjustment of the elastic supports of the main pipes.

6.2. Execution of alignment


Alignment comprises 3 types of operation: adjustment of the distance between shaft ends or coupling plates, axial positioning of axes, radial positioning of axes.

Appendix 1 details a method for aligning 2 axes. Alignment is performed with "cold machines" The cold position of shafts is defined in the relevant Erection Instructions (EI), when the shaft deformations and displacements affect the alignment. NOTE: For spring mounted foundations ; shaft alignment is not affected by loading and adjustment of spring supports. Nevertheless it is recommended that the couplings stay open during these operations for control measurement.

6.3. Allowable alignment tolerances


Unless stated otherwise in the Manufacturer's drawing or Erection Instructions (EI), the tolerances are as follows: Semi-flexible couplings with rubber inserts For the same coupling, the allowable tolerances vary with the rotation speed. The alignment is satisfactory if the 3 following conditions are met: Parallelism: maxi angle difference (EA) = 16 Fv Od/10000 Concentricity: maxi radius difference (ER) = 16 Fv Od/10000 Maxi (EA + ER) = 16 Fv Od/10000

Where Fv is the speed factor calculated by means of the abacus of Appendix 2, Od is the outside diameter of the half coupling. Rigid couplings
Originator Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

8/18

T4-APD-B0-A-40104

Parallelism

0.01 mm max. on a diameter of 100 mm (i.e 1/10000) 0.02 mm max.

Concentricity :

Flexible couplings Parallelism : 0.05 mm max on a diameter of 100 mm (i.e 5/10000) 0.20 mm

Concentricity :

Tooth couplings Parallelism - Max.: 0.025 mm for n = 1 800 rpm max. on a diameter of 100 mm (i.e 2.5/10000) - Min. : 0.015 mm for n > 1 800 rpm on a diameter of 100 mm (i.e 1.5/10000) where n = number of revolutions per minute. Concentricity (tolerance in event of misalignment): - Max.: 0.05 mm for n = 1 800 rpm max. - Min.: 0.03 mm for n > 1 800 rpm.

Clearance between the coupling hubs: 0.5 mm NOTE: Before measuring the clearance between hubs, make sure that: The possible axial rotor locking device has in fact been removed, The free rotor of an electric motor is in the correct position with a 0.3 mm tolerance.

7. TIGHTENING OF ANCHOR PIECES


Nuts: mounted lubricated Tightening torque to be adopted tolerances 5 % if the erection instruction (EI) or its appendices specify no special value. bolt mm Torque value m daN

14 3,5

16 5,5

18 7,5

20 10,5

22 14

24 18,5

27 27

30 33,5

33 50

36 64

Tighten all anchor bolts progressively.

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

9/18

T4-APD-B0-A-40104

8. PIPING CONNECTION
8.1. Erection of pipes
The pipes absolutely must be erected by starting from the fixed point of the piping so as to end in the machine pipe. In no case shall erection be started by fixing the piping onto the machine. When designing the piping execution and prefabrication, extra-lengths are to be provided so as to adjust the pipe sections arranged as close as possible to the machine in the 3 planes.

8.2. Jointing
Before beginning any jointing operation, check that the protecting covers have in fact been placed on the machine pipes to prevent any foreign matter from entering the machine. Jointing is satisfactory only if: All the welds on the piping jointed to the machine are made (up to the first fixed point support, at least) All hangers between the fixed point and the machine are free and set on "cold piping" position, in conformity with the instructions shown on the supports drawings The flange facings are parallel and centered, taking account of the tolerances given hereafter. The clearance between the flange facings complies with the type of connection to be made (flanges or welds)

Flange-type jointing During the checking of the jointing, the flange/pipe weld must be totally carried out and checked. Unless specified otherwise in the erection instruction (EI), the preliminary connection tolerances to be complied with are the following: - Parallelism : < 0.1 mm for pipe < 12" < 0.3 mm for pipe 12" < < 24" < 0.5 mm for pipe > 24" - Concentricity : The flange fixing bolts must be put into place manually without forcing and particularly without applying any load or thrust on the pipe whatsoever.

Weld-type The preliminary connection tolerances are those applying to butt-welding and specified in the Piping Welding Standards or in the relevant Erection Instructions (EI).

8.3. Connection of the main pipes


Before connection check that the piping preliminary connection complies with the instructions specified in item 82, To prevent any risk of electric striking between the various machine internals during the welding operations, make sure that: The grounding terminal is well connected to the general grounding circuit of the Power Plant The grounding connector is well fastened to the machine frame.

Welds are made in conformity with the Piping Welding Rules. The machine-to-pipe heterogeneous welding processes shall be specified in the Erection Instructions (EI).
Originator Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

10/18

T4-APD-B0-A-40104

For connections by welded joints: Realize only one joint at a time on the same shaft line Check the alignment before proceeding to any welded connection of main pipes Take all necessary arrangements to prevent any deformations of the machine, e.g. realize the weld according to the method of the "Quarters opposite" to 2 welders Make sure that the machine has not undergone any deformation during welding, so that the adequate measures can be taken as soon as a deformation is detected. The inspection points specific to the machine are defined in the erection instruction (EI).

The corrective actions selected shall receive the approval of the erection supervision department.

9. INSPECTIONS
The following list is not exhaustive. It defines the minimum inspection to be performed by the Erection Subcontractor. In addition to these inspections, the Erection Subcontractor must take all the necessary steps to ensure erection quality. The inspections specified hereafter shall be detailed in the Erection Quality Control Plan (EQ) which may be completed or amended by the Erection Instructions (EI).

9.1. Inspections of the basement level "for erection"


Visual examination to detect the visible defects Layout and materialization of the theoretical equipment axes Basement level altitude Horizontality of the basement upper part Dimensions of the basement(s) (geometry) Installation of the basement(s) with respect to the theoretical equipment axes Anchoring or fixing holes (number, location, dimensions, installation and location of the anchor bars) Chipping of the basement surface.

9.2. Equipment installation inspection


Surface conditions, dimensions, flatness, horizontality of base levels for metal wedges Position of the theoretical axes of the equipment or of a set of elements connected one to another Horizontality and verticality Orientation of equipment with respect to the reference axes of the building relative position of the machines preliminary alignment of the independant machines.

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

11/18

T4-APD-B0-A-40104

9.3. Alignment checking before jointing of pipes


Torque load of anchor bolts Alignment.

9.4. Checking of main pipes jointing


Erection of pipes up to the first fixed point with setting of supports Characteristics of each jointing and in particular: Parallelism of flanges Centering of the pipe on the nozzle Clearance between the sides to be assembled.

9.5. Alignment checking after piping connection


Checking of connecting welds on machines Alignment.

9.6. Alignment checking after final setting of pipe elastic supports


Filling of the pipes conveying water Complete thermal insulation of pipes Unlocking of elastic supports Alignment.

9.7. Checking of auxiliary mechanical equipment erection


Refer to the Erection Standards relative to the corresponding equipment (fabricated components, piping, ...).

9.8. Checking of instrumentation and control installation


Refer to the Construction Data Package for Instrumentation.

9.9. Miscellaneous
Protection of the equipment being erected and of the surrounding equipment as well. Inner and outer cleanliness of equipment after erection

10. ATTACHMENT 1: ALIGNMENT OF ROTATING MACHINES


10.1. Measuring instruments
Miscellaneous measuring instruments can be used for the alignment operations and, in particular:
Originator

For alignment truing (preliminary alignment): - fitter setting gauge


Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

12/18

T4-APD-B0-A-40104

set of adjusting shims

For alignment: - comparators - set of shims (normal or oblique)

These instruments are supplied by the Subcontractor charged with realizing or checking the alignment.

10.2.

Alignment procedures
Alignment is to be ensured by a qualified fitter perfectly familiarized with the usual procedures associated with this king of work. Alignment and prealignment include 3 checkings of: distance between both shaft ends parallelism concentricity

When defining the concentricity corrections, do not forget to take account of the possible shaft line shifting defined in an Appendix to the relevant Erection Instructions (EI). Before performing the various alignment measurements, make the machines provided with journal bearings rotate a few turns so as to get an oil film The various alignment measurements require the simultaneous rotation of both shafts as if they were connected.

10.3.

Marking of the reference points


4 fixed points to be marked on the body of one of the machines (12 o'clock, 3 o'clock, 6 o'clock and 9 o'clock) according to 2 perpendicular axes (one vertical axis and one horizontal axis - see fig. 1 hereafter). 2 diametrally opposed A and B generatrices to be marked on both half-coupling sleeves (see figure 1 hereafter).

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

13/18

T4-APD-B0-A-40104

FIGURE 1

10.4.

Adjustment of the distance between shaft ends


The distance between the coupling hubs must be adjusted according to the Manufacturer's drawing so as to respect the functional axial clearances. Distances shall be checked only after adjustment of the rotors within their respective axial clearances.

10.5.

Adjustment of parallelism
Use one or two comparators (normal mounting or mounting with return level). If the measurement cannot be made by means of a comparator, sets of shims may, exceptionally, be used. Make both machines rotate simultaneously and after each quarter-turn, read the "a" and "b" values at the vertical marks 12 o'clock and 6 o'clock or at the horizontal marks 3 o'clock and 9 o'clock. See figures 2, 3 and 4 hereafter, for information.

FIGURE 2

FIGURE 3

FIGURE 4

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

14/18

T4-APD-B0-A-40104

12 o'clock a b

Driven rotor

Driving rotor

Driven rotor

Driving rotor

9 o'clock

3 o'clock

6 o'clock

Calculate the average of the "a" and "b" values at the 12 o'clock, 3 o'clock, 6 o'clock and 9 o'clock points. See figure 5 hereafter, for information.

FIGURE 5

12 o'clock

a = 5.00 Average = 6.5 mm b = 8.00

9 o'clock a = 6.25 b = 7.25 Average = 6.75 mm

3 o'clock a = 6.75 b = 3.75 Average = 5.25 mm

6 o'clock

a = 7.00 Average = 6.5 mm b = 6.00

This example points out that the "a" and "b" measurements made at the same place are not identical. This is of minor importance for the measurement interpretation as an average of both these values is made. Interpret these averages. The difference between both averages of points facing one another (either vertically or horizontally) gives the parallelism differences. See figures 6 and 7 hereafter, for information.

FIGURE 6

FIGURE 7

12 o'clock

Difference : 0

9 o'clock Difference : + 0.5 mm

3 o'clock Difference : 0

6 o'clock

Difference : 0

In this example, it will be observed that:


Originator Alstom Identification number Rev. Date Lang. Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

15/18

T4-APD-B0-A-40104

Parallelism is correct in the vertical plane Parallelism is defective (0.5 mm clearance on 9 o'clock side) in the horizontal plane.

The parallelism differences must be less than those allowed for this machine. Otherwise, corrections shall be made util acceptable values are reached. In the example mentioned above, one of the machines is to be moved in the horizontal plane for: Decreasing the 0.5 mm measure at 9 o'clock Increasing the 0.5 mm measure at 3 o'clock.

10.6.

Adjustment of concentricity
The comparator is to be arranged on the generatrix marked A. Make the machines rotate simultaneously and after each quarter-turn, read the "c" value at the 12 o'clock and 6 o'clock vertical marks and at the 3 o'clock and 9 o'clock horizontal marks. See figures 8, 9 and 10 hereafter for information.

FIGURE 8

FIGURE 9

FIGURE 10
12 o'clock

9 o'clock

3 o'clock

6 o'clock

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

16/18

T4-APD-B0-A-40104

Interpret these measurements See figures 11, 12 and 13 hereafter, for information.

FIGURE 11 Measurement readings

FIGURE 12 Vertical distance and correction

12 o'clock

2c = 5.00 mm

12 o'clock

Distance : 0

9 o'clock 2c = 4.85 mm

3 o'clock 2c = 5.75 mm

Correction : 0.30 mim. towards 12 o'clock

6 o'clock

2c = 5.60 mm

6 o'clock

Distance : + 0.60 mm

FIGURE 13 Horizontal distance and correction

9 o'clock Distance : 0

3 o'clock Distance :- 0.9 0 mm

Correction : 0.45 mm towards 9 o'clock

The concentricity differences must be less than those allowed for this machine. Otherwise, corrections shall be made on the machine on comparator needle side until acceptable values are reached. In the example mentioned above, the rotor axis is to be moved even if the relevant Erection Instructions (EI) does not specify any shaft line difference between "cold" and "hot" positions. 0.30 mm (vertically) from 6 o'clock to 12 o'clock 0.45 mm (horizontally) from 3 o'clock to 9 o'clock.

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

17/18

T4-APD-B0-A-40104

11. ATTACHMENT 2: CALCULATION OF TOLERANCES FOR SEMI-FLEXIBLE COUPLING


11.1. Calculation of speed factor (Fv) values

Example: For a coupling with an outside diameter of 300 mm, with spacer, rotation speed of 3000 rpm: Fv = 0.53 whence the following alignment tolerances:

16x0 , 53x300 10000 : 0.25 mm at the outside diameter of the half couplings. EA max. =
ER max. = 0.25 mm (EA + ER) max. = 0.25 mm

Originator

Alstom Identification number

Rev.

Date

Lang.

Sheet

ALSTOM POWER SYSTEMS S.A..


ALSTOM 2013. All rights reserved.

TJN/40/M/----- -----/EG/013
Owners dwg number

A
Rev

04.04.2013

En

18/18

T4-APD-B0-A-40104

Vous aimerez peut-être aussi