ACTIVITY ATTRIBUTES

KEADUE WWTP UPGRADE WORKS

KMCF ENGINEERING DUBLIN ROAD ATHLONE

2014

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Date: Co. Roscommon Activity ID: 1.1 Activity: Tendering/ Publish WBS No: Project Details on E-Tenders Activity Description: This activity involves summiting project details online for relevant parties interested Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be basic computer skills for details on E-tenders. responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Expressions of Interest Type of Effort: This activity is a fixed duration activity which will have duration of 30 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Date: Co. Roscommon Activity ID: 1.2 Activity: Tendering/ WBS No: Expressions of Interest Activity Description: This activity involves detailing/document all parties interested in the project Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be basic computer skills. responsible for performing the work for this activity. Activity Predecessors: Publish Project Details on ETenders Activity Successors: Review Tender Pack Type of Effort: This activity is a fixed duration activity which will have duration of 23 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 1.3 Activity: Tendering/ Review WBS No: Tender Pack Activity Description: This activity involves reviewing all necessary components of tender pack Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be basic computer skills. responsible for performing the work for this activity. Activity Predecessors: Expressions of Interest Activity Successors: Preparation of BoQ Type of Effort: This activity is a fixed duration activity which will have duration of 7 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 1.4 Activity: Tendering/ WBS No: Preparation of BoQ Activity Description: This activity involves Preparing a bill of quantities for project Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be basic computer skills for Preparation of BoQ. responsible for performing the work for this activity. Activity Predecessors: Review Tender Pack Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 7 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.1 Activity: Feasibility/ WWTP WBS No: Selection Activity Description: This activity involves selecting an appropriate WWTP based on chosen P.E size and cost. Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be computer skills for WWTP Selection. responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Site Layouts Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.2 Activity: Feasibility/ Site WBS No: Layouts Activity Description: This activity involves preparing site layout drawings for project. Activity Responsibility: Resources and Skill Sets Required: This activity requires Contractor will be computer skills AutoCAD and software's for the decision on responsible for performing the Site layout. the work for this activity. Activity Predecessors: WWTP Selection Activity Successors: Permits Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.3 Activity: Feasibility/ Permits WBS No: Activity Description: This activity involves contacting relevant authorities to obtain necessary permits i.e. discharge permits etc Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Site Layouts Activity Successors: Contractor Submissions Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.4 Activity: Feasibility/ WBS No: Contractor Submissions Activity Description: This activity involves detailing all submissions received from the contractor. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Permits Activity Successors: Material Submissions Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.5 Activity: Feasibility/ Material WBS No: Submissions Activity Description: This activity involves detailing all relevant material submissions for the project. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Contractor Submissions Activity Successors: Plant Submissions Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.6 Activity: Feasibility/ Plant WBS No: Submissions Activity Description: This activity involves detailing all relevant plant submissions for the project. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Material Submissions Activity Successors: Health & Safety Audits Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.7 Activity: Feasibility/ Health WBS No: & Safety (H & S) Audits Activity Description: This activity involves preparing a health and safety audit for the continued development and implementation of H & S throughout the project Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Plant Submissions Activity Successors: Human resources Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.8 Activity: Feasibility/ Human WBS No: resources Activity Description: Human resources is required to distinguish roles and responsibilities for the project and to organize organizational charts and a staffing Management Plan Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Health & Safety (H & S)Audits Activity Successors: Procurement Completion Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.1.9 Activity: Feasibility/ WBS No: Procurement Completion Activity Description: This activity involves bringing the project procurement to a completion Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Human resources Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.1 Activity: Contact Suppliers/ WBS No: WWTP Supplier Activity Description: This activity involves ordering WWTP systems/materials Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Concrete Supplier Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.2 Activity: Contact Suppliers/ WBS No: Concrete Supplier Activity Description: This activity involves ordering concrete supplies. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: WWTP Supplier Activity Successors: Building Materials Supplier Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.3 Activity: Contact Suppliers/ WBS No: Building Materials Supplier Activity Description: This activity involves ordering building materials supplies Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Concrete Supplier Activity Successors: Plant Hire Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.4 Activity: Contact Suppliers/ WBS No: Plant Hire Activity Description: This activity involves hiring plant machinery for site Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Building Materials Supplier Activity Successors: Submit Tender Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.5 Activity: Contact Suppliers/ WBS No: Submit Tender Activity Description: This activity involves submitting for tendering Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Plant Hire Activity Successors: Tender Awarded Type of Effort: This activity is a fixed duration activity which will have duration of 0 day. Location of Activity: All work associated with this activity will occur at head office Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 2.2.6 Activity: Contact Suppliers/ WBS No: Tender Awarded Activity Description: This activity mean rewarding successful contractor with project Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Submit Tender Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 0 day. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 3.1 Activity: Preliminaries / WBS No: Insurance Activity Description: Insurance is the equitable transfer of the risk of a loss, from one entity to another in exchange for payment. It is a form of risk management primarily used to hedge against the risk of a contingent, uncertain loss. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Employers' Liability Insurance Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

10

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 3.2 Activity: Preliminaries / WBS No: Employers' Liability Insurance Activity Description: Coverage against common law liability of an employer for accidents to employees, as distinguished from liability imposed by a workers' compensation law. Activity Responsibility: Resources and Skill Sets Required:. Contractor has relevant Contractor will be skills set to complete this task responsible for performing the work for this activity. Activity Predecessors: Insurance Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days. Location of Activity: All work associated with this activity will occur at head office. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.1.1 Activity: Commencing on WBS No: Site / Site Office Activity Description: This activity involves setting up site office on site for duration of the project Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Commencing on site Activity Successors: Office Equipment Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

11

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.1.2 Activity: Commencing on WBS No: Site / Office Equipment Activity Description: This activity involves setting up all necessary office equipment for duration of project. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Site office Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.1 Activity: Mobilisation / WBS No: Traffic Management Activity Description: This activity involves setting up a traffic management plan to control and direct traffic in a safe manner during construction of the project. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Site Safety Induction Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

12

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.2 Activity: Mobilisation / Site WBS No: Safety Induction Activity Description: Site induction communicates essential information regarding the site, the working methods and health and safety management. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Traffic Management Activity Successors: Road Brushing Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.3 Activity: Mobilisation / Road WBS No: Brushing Activity Description: This activity involves removal of necessary brush from roadside ditches for the safety of the travelling public Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Site Safety Induction Activity Successors: Site Clearing Plant & Equipment Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

13

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.4 Activity: Mobilisation / Site WBS No: Clearing Plant & Equipment Activity Description: This activity involves hiring of necessary plant equipment for clearing of construction site Activity Responsibility: Resources and Skill Sets Required: This activity requires Site Relevant sub-contractor will experience for Clearing Plant & Equipment. be responsible for performing the work for this activity. Activity Predecessors: Road Brushing Activity Successors: Excavation Equipment Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.5 Activity: Mobilisation / WBS No: Excavation Equipment Activity Description: This activity involves hiring of necessary excavation equipment for clearing of construction site Activity Responsibility: Resources and Skill Sets Required: This activity requires Site Relevant sub-contractor will experience for Excavation Equipment. be responsible for performing the work for this activity. Activity Predecessors: Site Clearing Plant & Equipment Activity Successors: Paving Equipment Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

14

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.2.6 Activity: Mobilisation / WBS No: Paving Equipment Activity Description: Activity Responsibility: Resources and Skill Sets Required: This activity requires Site Relevant sub-contractor will experience for Paving Equipment. be responsible for performing the work for this activity. Activity Predecessors: Excavation Equipment Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.3.1 Activity: Temporary Works / WBS No: Site Security Fencing Activity Description: This activity involves setting up of fencing around the site for public safety. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Car Parking Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

15

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.3.2 Activity: Temporary Works / WBS No: Car Parking Activity Description: This activity involves construction of temporary car park for onsite for duration of project. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Site Security Fencing Activity Successors: Site Entrance / Access Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints: :

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.3.3 Activity: Temporary Works / WBS No: Site Entrance and Access Activity Description: This activity involves providing site entrance/access for to construction site. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Car Parking Activity Successors: Temporary Site Services Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

16

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.3.4 Activity: Temporary Works / WBS No: Temporary Site Services Activity Description: This activity involves setting site up temporary site services for duration of project i.e. plumbing and electrics. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Site Entrance / Access Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.1 Activity: Ground Works/ Site WBS No: Clearing Activity Description: This activity involves clearing the site and getting it ready for construction. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Strip Top Soil Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

17

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.2 Activity: Ground Works/ WBS No: Strip Top Soil Activity Description: This activity involves the stripping back of top soil. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Site Clearing Activity Successors: Top Soil Storage Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.3 Activity: Ground Works/ Top WBS No: Soil Storage Activity Description: This activity involves the storing of the top soil removed. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Strip Top Soil Activity Successors: Trial Holes Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

18

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.4 Activity: Ground Works/ WBS No: Trial Holes Activity Description: This activity involves trial holes been dug to determine the geology and water table of the site. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Top Soil Storage Activity Successors: Set Out Site Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.5 Activity: Ground Works/ Set WBS No: Out Site Activity Description: This activity involves setting out the site is to stake out reference points and markers that will guide the construction of new structures such as roads or buildings. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Trial Holes Activity Successors: Place Access Road Sub-Base Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

19

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.4.6 Activity: Ground Works/ WBS No: Place Access Road Sub-Base Activity Description: This activity involves laying the sub base and providing and access road to the site. Activity Responsibility: Resources and Skill Sets Required:. Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Set Out Site Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.1 Activity: Control Room/ WBS No: Setting Out Activity Description: This activity involves setting out the site to stake out reference points and markers that will guide the construction of the Control room. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Activity Successors: Excavate for Foundations and Services Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

20

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.2 Activity: Control Room/ WBS No: Excavate for Foundations and Services Activity Description: This activity involves excavating for foundations/ services for the control room. Activity Responsibility: Resources and Skill Sets Required:. Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Setting Out Activity Successors: Pour Foundations Type of Effort: This activity is a fixed duration activity which will have duration of 2 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.3 Activity: Control Room/ Pour WBS No: Foundations Activity Description: The activity involves the pouring of concrete for the foundations. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Excavate for Foundations / Services Activity Successors: Block Work Type of Effort: This activity is a fixed duration activity which will have duration of 1 day. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

21

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.4 Activity: Control Room/ WBS No: Block Work Activity Description: This activity involves the laying of blocks by a competent builder. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Pour Foundations Activity Successors: Roof Type of Effort: This activity is a fixed duration activity which will have duration of 4 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.5 Activity: Control Room/ Roof WBS No: Activity Description: This activity involves the building of the roof by a competent carpenter. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Block Work Activity Successors: Finishing Type of Effort: This activity is a fixed duration activity which will have duration of 4 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

22

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.6 Activity: Control Room/ WBS No: Finishing Activity Description: This activity involves the finishing of the control room. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Roof Activity Successors: Wiring Type of Effort: Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.7 Activity: Control Room/ WBS No: Wiring Activity Description: This activity involves the wiring of the control room by a competent electrician. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Finishing Activity Successors: Control Panels (ICS) Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

23

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.8 Activity: Control Room/ WBS No: Control Panels (ICS) Activity Description: This activity involves the installing of control panels for the WWTP. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Wiring Activity Successors: ReFurbish Type of Effort: This activity is a fixed duration activity which will have duration of 7 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.9 Activity: Control Room/ ReWBS No: Furbish Activity Description: This activity involves the refurbishing of the control room. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Control Panels (ICS) Activity Successors: Windows Type of Effort: Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

24

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.10 Activity: Control Room/ WBS No: Windows Activity Description: This activity involves the placing/fitting of the windows. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Re-Furbish Activity Successors: Painting Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

Activity Attributes Project: Upgrade Works to WWTP at Keadue, Co. Date: Roscommon Activity ID: 4.5.11 Activity: Control Room/ WBS No: Painting Activity Description: This activity involves the painting of the control room. Activity Responsibility: Resources and Skill Sets Required: Contractor has relevant Relevant sub-contractor will skills set to complete this task be responsible for performing the work for this activity. Activity Predecessors: Windows Activity Successors: Type of Effort: This activity is a fixed duration activity which will have duration of 3 days. Location of Activity: All work associated with this activity will occur at WWTP at Keadue. Activity Assumptions: Activity Constraints:

25

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.1 Activity: Excavate for SubWBS No: base Activity Description: This activity involves the excavating of the sub base Activity Responsibility: Sub Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Place Hardcore Sub-base Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.2 Activity: Place Hardcore Sub- WBS No: base Activity Description: This activity involves the placing of the hardcore base Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate for Sub-base Activity Successors: Erect Formwork Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

26

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.3 Activity: Erect Formwork WBS No: Activity Description: This activity involves the erecting of the formwork Activity Responsibility: Sub Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Place Hardcore Sub-base Activity Successors: Place Reinforcement Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.4 Activity: Place WBS No: Reinforcement Activity Description: This activity involves the placing of the steel reinforcement Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Erect Formwork Activity Successors: Pour Concrete Sub-Base Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

27

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.5 Activity: Pour Concrete Sub- WBS No: Base Activity Description: This activity involves the pouring of the concrete Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Place Reinforcement Activity Successors: Strike Formwork Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.6 Activity: Strike Formwork WBS No: Activity Description: His activity involves the striking of the formwork Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Pour Concrete Sub-Base Activity Successors: Install BMS units Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day week. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

28

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.7 Activity: Install BMS units WBS No: Activity Description: This activity involves the installing of the new package WWTP Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Strike Formwork Activity Successors: Connect new infrastructure Type of Effort: This activity is a fixed duration activity which will occur over a period of three days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.8 Activity: Connect new WBS No: infrastructure Activity Description: This activity involves the connecting of all pipes into the package WWTP Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Install BMS units Activity Successors: Commission Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

29

Activity Attributes Project: Keadue upgrade works/ Package system Date: Activity ID: 4.6.6.9 Activity: Commission WBS No: Activity Description: This activity involves the commissioning of the new package WWTP Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Connect new infrastructure Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of two day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Reinstatement Date: Activity ID: 4.6.7.1 Activity: Placing Concrete WBS No: Kerbs Activity Description: This activity involves the placing of the concrete kerbs around the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Pedestrian Paths Type of Effort: This activity is a fixed duration activity which will occur over a period of two days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

30

Activity Attributes Project: Keadue upgrade works/ Reinstatement Date: Activity ID: 4.6.7.2 Activity: Pedestrian Paths WBS No: Activity Description: This activity involves the placing /laying out of pedestrian foot paths Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Placing Concrete Kerbs Activity Successors: Replacing Top Soil Type of Effort: This activity is a fixed duration activity which will occur over a period of three days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Reinstatement Activity ID: 4.6.7.3 Activity: Replacing Top Soil

Date: WBS No:

Activity Description: This activity involves the replacing of the top soil around the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Pedestrian Paths Activity Successors: Seeding Type of Effort: This activity is a fixed duration activity which will occur over a period of two days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

31

Activity Attributes Project: Keadue upgrade works/ Reinstatement Date: Activity ID: 4.6.7.4 Activity: Seeding WBS No: Activity Description: This activity involves the reseeding of trees and plants around the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Replacing Top Soil Activity Successors: Bitumen layer to Road Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Reinstatement Date: Activity ID: 4.6.7.5 Activity: Bitumen layer to WBS No: Road Activity Description: This activity involves the laying of the bitumen layer for the road Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Seeding Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

32

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.1 Activity: Set Out Proposed WBS No: Pipe Network Activity Description: This activity involves the setting out of the proposed pipe network Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Excavate for, and Construct Manhole 1 Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.2 Activity: Excavate for, and WBS No: Construct Manhole 1 Activity Description: This activity involves the constructing for a new manhole (MH1) Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Set Out Proposed Pipe Network Activity Successors: Excavate & Lay Sewer Pipe A - B Type of Effort: This activity is a fixed duration activity which will occur over a period of two days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

33

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.3 Activity: Excavate & Lay WBS No: Sewer Pipe A - B Activity Description: This activity involves the excavating and the laying of pipe work from A -B Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate for, and Construct Manhole 1 Activity Successors: Excavate for, and Construct Manhole 2 Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.4 Activity: Excavate for, and WBS No: Construct Manhole 2 Activity Description: This activity involves the constructing for a new manhole (MH2) Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate & Lay Sewer Pipe A -B Activity Successors: Excavate & Lay Sewer Pipe B - C Type of Effort: This activity is a fixed duration activity which will occur over a period of two days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

34

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.5 Activity: Excavate & Lay WBS No: Sewer Pipe B - C Activity Description: This activity involves the excavating and the laying of pipe work from B -C Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate for, and Construct Manhole 2 Activity Successors: Excavate for, and Construct Manhole 3 Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.6 Activity: Excavate for, and WBS No: Construct Manhole 3 Activity Description: This activity involves the constructing for a new manhole (MH3) Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate & Lay Sewer Pipe B -C Activity Successors: Excavate & Lay Sewer Pipe C - D Type of Effort: This activity is a fixed duration activity which will occur over a period of two days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

35

Activity Attributes Project: Keadue upgrade works/ Sewer Connection Date: Activity ID: 4.7.7 Activity: Excavate & Lay WBS No: Sewer Pipe C - D Activity Description: This activity involves the excavating and the laying of pipe work from C -D Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate for, and Construct Manhole 3 Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.1 Activity: Excavate for SubWBS No: base Activity Description: This activity involves the excavating of the sub base Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Place Hardcore Sub-base Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

36

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.2 Activity: Place Hardcore Sub- WBS No: base Activity Description: This activity involves the placing of the hard core sub base Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Excavate for Sub-base Activity Successors: Erect Formwork Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.3 Activity: Erect Formwork WBS No: Activity Description: This activity involves the erecting of the formwork Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Place Hardcore Sub-base Activity Successors: Place Reinforcement Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

37

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.4 Activity: Place WBS No: Reinforcement Activity Description: This activity involves the placing of the steel reinforcement Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Erect Formwork Activity Successors: Pour Concrete Sub-Base Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.5 Activity: Pour Concrete Sub- WBS No: Base Activity Description: This activity involves the pouring of the concrete sub base Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Place Reinforcement Activity Successors: Strike Formwork Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

38

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.6 Activity: Strike Formwork WBS No: Activity Description: This activity involves the striking of the formwork Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Pour Concrete Sub-Base Activity Successors: Backfill Surrounds Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.7 Activity: Backfill Surrounds WBS No: Activity Description: This activity involves the backfilling in the surrounds of the pump chamber Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Strike Formwork Activity Successors: Install Pump Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

39

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.8 Activity: Install Pump WBS No: Activity Description: This activity involves the installing of the pump Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Backfill Surrounds Activity Successors: Commission Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Pump Chamber Date: Activity ID: 4.8.9 Activity: Commission WBS No: Activity Description: This activity involves the commissioning of the pump house Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Install Pump Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

40

Activity Attributes Project: Keadue upgrade works/ Demolition Works Date: Activity ID: 4.9.1 Activity: Demolish Existing WBS No: Activity Description: This activity involves the demolishing of the existing WWTP Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Remove from Site Type of Effort: This activity is a fixed duration activity which will occur over a period of five days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Demolition Works Date: Activity ID: 4.9.2 Activity: Remove from Site WBS No: Activity Description: This activity involves the removing of the old WWTP off site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Demolish Existing Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of five days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

41

Activity Attributes Project: Keadue upgrade works/ Site Finishing Date: Activity ID: 4.10.1 Activity: landscaping WBS No: Activity Description: This activity involves the landscaping of the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Planting Type of Effort: This activity is a fixed duration activity which will occur over a period of three days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Site Finishing Date: Activity ID: 4.10.2 Activity: Planting WBS No: Activity Description: This activity involves the planting of new plants on the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: landscaping Activity Successors: Fencing Type of Effort: This activity is a fixed duration activity which will occur over a period of three days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

42

Activity Attributes Project: Keadue upgrade works/ Site Finishing Date: Activity ID: 4.10.3 Activity: Fencing WBS No: Activity Description: This activity involves the fencing around the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Planting Activity Successors: Painting Type of Effort: This activity is a fixed duration activity which will occur over a period of five days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Site Finishing Date: Activity ID: 4.10.4 Activity: Painting WBS No: Activity Description: This activity involves the painting of facilities around the site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Fencing Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

43

Activity Attributes Project: Keadue upgrade works/ Testing Date: Activity ID: 5.1 Activity: Air Testing Sewer WBS No: Network Activity Description: This activity involves the testing of the sewer network to ensure all connections pipes are working Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Testing BMS Unit Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Testing Date: Activity ID: 5.2 Activity: Testing BMS Unit WBS No: Activity Description: This activity involves the testing of the Package BMS system to insure its working Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Air Testing Sewer Network Activity Successors: Testing Pump Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

44

Activity Attributes Project: Keadue upgrade works/ Testing Date: Activity ID: 5.3 Activity: Testing Pump WBS No: Activity Description: This activity involves the testing of the pumps to insure there in working order Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Testing BMS Unit Activity Successors: Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Completion Date: Activity ID: 6.1 Activity: Final Inspection WBS No: Activity Description: This activity involves the final inspection of all work carried out onsite Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Activity Successors: Condition Survey of Roads and Paths Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

45

Activity Attributes Project: Keadue upgrade works/ Completion Date: Activity ID: 6.2 Activity: WBS No: Condition Survey of Roads and Paths Activity Description: This activity involves a survey of all roads and paths to insure there up to required standard Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Final Inspection Activity Successors: CCTV Survey of Pipe work Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Completion Activity ID: 6.3 Activity: CCTV Survey of Pipe work

Date: WBS No:

Activity Description: This activity involves the testing of the pipe work to insure there in working order Activity Responsibility: Sub Resources and Skill Sets Required:. Contractor has Contractor relevant skills set to complete this task Activity Predecessors: Condition Survey of Roads and Paths Activity Successors: Demobilisation of Site Type of Effort: This activity is a fixed duration activity which will occur over a period of one day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

46

Activity Attributes Project: Keadue upgrade works/ Completion Activity ID: 6.4 Activity: Demobilisation of Site

Date: WBS No:

Activity Description: This activity involves the removing of site offices and plant machinery off site Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: CCTV Survey of Pipe work Activity Successors: As Constructed Drawings Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

Activity Attributes Project: Keadue upgrade works/ Completion Activity ID: 6.5 Activity: As Constructed Drawings

Date: WBS No:

Activity Description: This activity involves insuring site is of drawings specified Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: Demobilisation of Site Activity Successors: Safety File Handover Type of Effort: This activity is a fixed duration activity which will occur over a period of three days. Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints:

47

Activity Attributes Project: Keadue upgrade works/ Completion Activity ID: 6.6 Activity: Safety File Handover

Date: WBS No:

Activity Description: This activity involves the handing over of all files Activity Responsibility: Sub - Resources and Skill Sets Required:. Contractor has relevant Contractor skills set to complete this task Activity Predecessors: As Constructed Drawings Activity Successors: Type of Effort: Location of Activity: Keadue Co Roscommon Activity Assumptions: Activity Constraints: