PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 1 of 40
Approval:
Director / Date:
Segment Head HCM & OD:
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 2 of 40
TABLE OF CONTENTS
DESCRIPTION PAGE
DISTRIBUTION LIST 03
MANAGEMENT RESPONSIBILITY 11
RESOURCE MANAGEMENT 17
PRODUCT REALIZATION 21
CHANGE RECORD 34
FORMATS Appendix-06 40
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 3 of 40
DISTRIBUTION LIST
1. Master File / MR
2. HR
The copy of manual issued to Auditors will be stamped as “CONTROLLED”, while copy
can be issued to other external parties stamped as “UNCONTROLLED”.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 4 of 40
The manual describes the quality management system ISO 9001:2008 as adopted by
Professional Employers Private Limited. The operational activities of Professional
Employers (Private) Ltd. are HUMAN RESOURCE OUTSOURCING, HR MANAGEMENT
CONSULTANT & VERIFICATION SERVICES. It is intended to demonstrate PROFESSIONAL
EMPLOYERS PRIVATE LIMITED ability to provide consistent quality services that meet
customer and applicable regulatory requirements.
The system requirements of this manual are aimed at achieving customer satisfaction by
consistently providing conforming product and meeting or exceeding customer and
applicable regulatory requirements through application of the system, continual
improvement and the prevention of nonconformity.
This manual covers the quality-related activities of the Professional Employers Private
Limited Karachi & Lahore Office while finance department is not in the scope.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 5 of 40
Each page of the Manual is given a revision number. Changes are made by taking out
a new revision of the concerned revised page Changes will be indicated by italic text.
Review and approval of changes will be evident in change record sheet in the end of
the manual. Each revised page shall have a new revision number. The MR is responsible
for distributing all new revisions after their approval and retrieving the old revisions as per
document control procedure defined in the manual.
This document is not to be duplicated. Any one desirous of having a copy for
informational purposes should contact the MR, who shall issue an UNCONTROLLED copy.
The controlled copies are stamped ”CONTROLLED DOCUMENT” in green color on each
page while uncontrolled copies are stamped “UNCONTROLLED DOCUMENT” in green.
Uncontrolled copies shall not be updated.
While this manual could be revised any time a need so arises, a planned review shall be
carried out once every year by MR.
Compliance with the requirements of this quality manual and its referenced documents
is mandatory on everyone with in the scope of this quality management system.
Company does not perform and process as out source process and whole activity
performed by the company itself.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 6 of 40
QUALITY MANAGEMENT
SYSTEM
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 7 of 40
Following are the documents and their numbering scheme used at Professional
Employers Private Limited.
1.0 NUMBERING SCHEME
2.1 After the preparation and numbering of documents, these are reviewed and
approved by the competent authorities. The following personnel are reviewing
and approving authorities related to various quality system documents:
S/No
Document Prepared by Approval by
.
1. Quality Manual MR Director or MR
3.1 All QMS documents (except forms) will be controlled by stamping “CONTROLLED
DOCUMENT” in green. Only two hard copies will be taken print out one Master for
MR and one for HR, all the documents would be uploaded on Companies
Website for all the users for reference. Although print, save and copy commands
not provided to the users for better control.
3.2 Documents of external origin will be identified by their original name. Their
distribution is to be controlled in the same manner as the controlled documents
of PROFESSIONAL EMPLOYERS PRIVATE LIMITED. All documents of external origin
shall be listed on External Document List.
3.2 MR is also responsible to keep the external origin documents current by
periodically contacting the relevant issuing body.
3.3 Computer data is stored in hard disk and a back up is maintained. Only
authorized persons have access to the files, which are protected with password.
3.4 Controlled documents shall not be photo copied by recipients’ .Any one
requiring an extra copy or any information must obtain the same from MR, who
will issue an uncontrolled copy for such purposes. This will be stamped in green
as” UNCONTROLLED DOCUMENT”. Forms may be photocopied. One set of current
forms format is maintained by MR.
4.0 REVIEW AND APPROVAL OF DOCUMENTS
4.1 MR reviews and Director approves Quality Policy, Quality Objectives, Quality
manual and quality objectives’ planning. Job descriptions are reviewed by HOD
and approved by MR/Director.
4.2 Person reviewing and approving documents shall ensure that the documents
meet the requirements of quality management system.
5.1 MR ensures that all points of use have the relevant version of the applicable
documents.
5.2 If kept at a central location, obtain signatures for having read the document.
5.3 If issued to an individual, obtain signatures for having received the document.
Use form Master and Distribution list for both mechanism.
5.4 MR has one set of complete QMS documents. All forms will be placed with MR, in
PROFESSIONAL EMPLOYERS PRIVATE LIMITED, for easy accessibility to everyone.
Photocopies of formats are allowed for routine use.
5.5 DMR will assist MR from Lahore office in controlling of documents but Master list
will be maintained in Karachi Office by MR.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 9 of 40
6.1 Changes in any of the QMS documents will take place as follows:
a) MR or any person acting within the scope of QMS can suggest changes in
documents on Document Change Request QR-4.2-01.
b) Suggestions will be reviewed & approved by the concerned authorized
person.
c) Once approved MR will implement the changes in documents and upload
the same on Website.
d) Changes in the documents (except forms) will be identified by writing in
italic text.
e) Changes in the form formats will be identified by giving them a new revision
number
f) All documents after being changed will have a new revision number with
revised date.
7.0 MINOR AMENDMENT
8.1 MR is responsible for ensuring prompt removal of all obsolete documents from all
points of use and prior to issuing of new document or revisions destroying them
except one copy, which is kept for historical record. Such copies shall be
stamped in blue as “HISTORICAL DOCUMENT”.
9.0 SUPPORTING DOCUMENTS:
S/N
Document Number Retainer Retention time
o
1. Document change request QR-4.2-01 MR 3 Year
Document Master and
2. QR-4.2-02 MR 3 Year
Distribution List
External Document Master
3. QR-4.2-03 MR 3 Year
List
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 10 of 40
1.0 Every procedure contain master list of all quality records under title of supporting
documents. This List of Quality Records describes:
o Document title and number.
o Retainer
o Retention period
2.0 Records are indexed and grouped to facilitate their retrieval. Binders, drawers,
cabinets, computer disks and tapes, etc., containing records are clearly labeled
with identification of their content.
3.0 Records are normally stored in the same department where records are
generated.
4.0 Records are stored in dry and clean locations so that Records are protected
from moisture, excessive dust and physical damages.
5.0 Records and other quality documents may not be stored in private desk drawers
or other obscure locations that are not generally known.
6.0 All received faxes are photocopied first then retained in record.
7.0 A retention period for each type of record is established.
Nil
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 11 of 40
MANAGEMENT
RESPONSIBILITY
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 12 of 40
• CEO
• Director
• CFO
• MR / Manager Compliance
• Head of Relationship
• Head IS & Service Delivery
• HR & Admin Manager
Quality Policy
Quality Objectives
Procedure for Management Review Meeting
SUPPORTING DOCUMENTS:
Quality Objective
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 14 of 40
Functions and their interrelationships within the organization including responsibilities and
authorities are defined and communicated in order to facilitate effective quality
management. The departmental organizational chart describes the hierarchical
structure of PROFESSIONAL EMPLOYERS PRIVATE LIMITED and Job descriptions of
individuals describe the responsibilities and authorities of the company personnel. The
Quality System Procedures, Flow Charts also describe the responsibilities and Authorities
of personnel in relation to various quality system requirements.
SUPPORTING DOCUMENTATION.
Director has nominated a Management Representative (MR) & DMR and defined
responsibility and authority for the Quality Management System, which includes:
PROFESSIONAL EMPLOYERS PRIVATE LIMITED has established and maintains system and
operation level procedures, which also describe the internal communication between
various levels and functions of the organization regarding the quality management
system and its effectiveness. In addition to theses procedures following ways are used for
internal communication like
• Memos
• Intercom
• Email
5.6 Management Review
5.6.1 General
1.0 The Management Review meetings are conducted at least once in 6 months.
Unscheduled meetings may be called at any time on the direction of Director.
Participants of the Management Review meeting
2.0 MR circulates the notice of meeting to all participants at least one day before
the meeting date. This notice also includes the name and designation of
participants and agenda of the meeting.
Meeting Agenda
4.0 Director chairs the meeting in his absence MR will chair the MRM. The agenda
items are discussed one by one and MR presents the status of IQA results, results
of corrective actions, customer complaints/ feedback etc.
4.1 Lahore office DMR conducts the Partial MRM and discusses the applicable
agenda points in Lahore and will send their MRM Minutes to Karachi office for
discussion.
5.0 MRM members discuss the issues, decides actions, identify designations
responsible for actions and target dates for completion of actions.
6.0 MR records the minutes of the meeting. Minutes identify the agenda point,
discussion for each agenda, actions decided, designation responsible and
target dates.
7.0 The minutes of the meeting, after approval from the Director, MR keeps in record.
RESOURCE
MANAGEMENT
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 18 of 40
Providing /
Training Need Evaluation of
Level Orientation Arrange
identification Training
Training
Sr. Manager or Director / Director / Director / Director /
Manager Sr. Managers Sr. Managers Sr. Managers Sr. Managers
Sr. Manager / Sr. Manager / Sr. Manager / Sr. Manager /
Assist & Staff
Managers Managers Managers Managers
2.0 New employees are hired using the minimum qualification & Experience
requirement for that level as defined in job descriptions.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 19 of 40
3.0 In case where employee(s) meets the defined and approved hiring criteria of
Professional Employers Private Limited then he / she can be employed and
provide orientation / training and during probationary period closely
monitored.
4.0 For employees of the level of peon / office boy the hiring criteria are not
applicable.
5.0 Director prepared the orientation program whenever any new Sr. Manager or
manager is inducted.
6.0 The orientation program is prepared keeping in view the job responsibilities of
the designation.
7.0 The orientation program for managers contains at least the following topics.
9.0 The designations outline in above table identifies the training needs of their
direct reports using the following criteria where applicable.
o Change in company’s policy and procedure
o Induction of new process of new equipment
o Change in working instruction
o Frequency non-conformities related to an individual.
o Management Training
o Technical trainings
o ISO awareness
An individual need can also identify the training for himself.
10.0 The dept. Head / in-charges assess the validity of training needs. And if find
necessary arranges the training for that individual.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 20 of 40
CONDUCTING TRAINING
11.0 The designation outline in the above table can arrange the internal or external
training of their direct reports depending upon the type of training.
12.0 For external training the institution be selected based on its reputation and
after selection external training plan is prepared by MR and gets approved by
Director.
13.0 For internal training the trainer are selected based on their experience,
Qualification and performance.
VERIFICATION OF TRAINING
14.0 The department Head / In-charges or trainers himself verifies the effectiveness
of training by using any of the following method.
o Oral
o Demonstration
o Written
o Practical
15.0 If the performance of that individual indicates re-training or for their training the
training duration is extended.
16.0 The effectiveness of training is again verified after the re-training.
SUPPORTING DOCUMENTS:
Maintenance of Equipment
SERVICE
Realization
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 22 of 40
9 Customers’ feedback
9 Data analysis
9 Nonconformance reports &
9 Internal quality audit results.
SUPPORTING DOCUMENTS:
The company receives inquiries from customers through letter, fax, email, personal
visits, etc. the inquiries are received by Relationship department:
Director / Head of Relationship Department Reviews the contract / order before the
acceptance of order.
In case the customer desires to change any requirement after the order has been
confirmed, Director or Relationship Department reviews the nature and impact of
change desired. Depending on the nature and scale of change, the amendments
and the changes are approved by Director.
Legal and regulatory requirements, if any, which apply to company’s services, are
identified and a list is maintained by MR.
These results are presented as input in the management review and analyzed for
improvements.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 24 of 40
Customer Communication:
- Service Specifications
- Order or contract requirements`
- Customer feedback (including customer complaints)
- Phone / Fax
- Letter
- Email
- Personal Visits
Customer Complaints:
- Non-conforming Services
- Late Response
- Any other Problem
Only serious complaints are compiled and analyzed by MR, and actions are taken for
improvements.
SUPPORTING DOCUMENTS:
Responsibilities:
Company Purchases:
The aim of evaluation is to ensure that the supplier has the capability to supply
products and services that fully meet the requirements of the company.
Existing Suppliers:
Company’s existing suppliers, who have been dealing with company for more than
six months, are evaluated on the basis of their previous performance history. MR or
Admin Manager is responsible for evaluation of existing suppliers. The results of
evaluation are recorded on the Supplier Evaluation Form.
The Supplier Evaluation forms are reviewed and approved by MR. After approval, the
suppliers are registered in the list of approved suppliers by MR. Evaluation record and
list of approved suppliers are maintained by MR or Admin Manager.
New Suppliers:
- Market Reputation
- Experience and reference of other clients
- Credit facilities
- Price
At the arrival of materials, it is sent to the Receiving Area. The Admin Department
verifies the quantity of material against the Delivery Challan and records it in Stock
Register.
In case the material is rejected, Admin Department segregates the material in the
Receiving section and identifies as REJECTION. Admin Department prepares the
Corrective and Preventive Action Request and contacts the concerned supplier to
discuss the nature of nonconformity material, the nonconforming material is either:
The spot purchasing is made by the Admin Department from the market, No report is
made.
Purchasing Date:
SUPPORTING DOCUMENTS:
Every employee has the unique employee code and a separate file.
Customer Property:
Relationship department is responsible for handling the customer property (if any).
If customer property etc. are damaged or otherwise found to be unsuitable, not clear or
conflicting, this shall be reported by Director on Corrective and Preventive Action Request
and a record is maintained.
SUPPORTING DOCUMENTS:
PEOPLE does not use any measuring and monitoring devices in the company, this clause
is excluded and not applicable in the system.
8.1 GENERAL
This includes the determination of the need for and use of applicable statistical
techniques.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 28 of 40
FREQUENCY OF AUDIT
o Internal quality audit of all division / department shall be carried out at least once
per year. Director can increase the audit frequency depends upon the status and
importance of the activities to be audited.
o AUDITORS TRAINING
MR will arrange a training program with the help of consultant in which selected
individuals will be trained as an internal auditor. The MR department will also keep
and maintain the training records of each individual as per procedure.
Company may appoint consultant to audit as per plan, then any consultant can do
audit on the behalf of company he prepares audit report by using same format,
which are attached with this procedure.
o AUDIT PLAN
MR circulates reminder notice QR-8.2.1-05 for internal quality audit to all concerned
before audit day.
Auditors use Quality manual, procedures, work instruction, records & other related
documents as audit checklist.
Auditors conducts internal audit as per schedule, records the observation sheet QR-
8.2.1-02 and decides for conformance / non-conformance.
Against each non-conformance the auditor shall issue a non-conformance report
QR-8.2.1-03
After completion of audit, auditors shall prepare audit report QR-8.2.1-04 describing
the general findings of the audit. Auditors shall submit the audit report including non-
conformance reports, to the auditee for corrective action and to MR for record.
o CORRECTIVE ACTION
Department heads shall suggest corrective / preventive actions against each
nonconformance and also give target date of completion. After completing the
form, concerned department head shall send the report to MR.
After the target date, MR shall send the auditors to check weather non-
conformance has been removed or not. If non-conformance is removed, auditor
shall close the report otherwise decides a new target date.
MR shall discuss the results of internal auditing in MR meeting in accordance with
Management review meeting procedure.
SUPPORTING DOCUMENTS:
S/N
Document Number Retainer Retention time
o
1. Audit Schedule QR-8.2.2-01 MR 3 Year
2. Non-conformity Report QR-8.2.2-03 MR 3 Year
3. Audit Report QR-8.2.2-04 MR 3 Year
4. Audit notification QR-8.2.2-02 MR 3 Year
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 31 of 40
o PROFESSIONAL EMPLOYERS PRIVATE LIMITED measures not just its services, but
also its QMS processes in order to demonstrate the continuing suitability of
these processes to achieve planned results and for continual improvement.
Internal Quality Audits and Statistical data analyses are the methods used for
monitoring and measurement of QMS processes.
o The results of process measurements, arising from above methodologies, are
fed to management for review by Management Representative
o The review will be conducted to do correction and take corrective actions for
the conformity of the process and services.
8.3 & 8.5 Control of Nonconforming Services and Corrective & Preventive
Actions
Identification and control of nonconformance
To ensure the identification and control over non-conforming services so as to
prevent its unintended use or delivery, PROFESSIONAL EMPLOYERS PRIVATE LIMITED
ensures the following controls at these stages:
Identification of nonconforming candidate:
o The CVs of candidates stored in Database, before the hiring of any individual
and before placing them with the customer various check are performed as per
Hiring Process Flow.
Corrective actions
Corrective actions may be requested in one of the following Cases:
a) A non-conformance detected during Professional Employers Private Limited
in-process inspections.
b) A non-conformance reported by customer.
c) A non-conformance identified during internal quality audit.
d) A non-conformance identified during review of analyzed data.
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 32 of 40
SUPPORTING DOCUMENTS:
S/N
Document Number Retainer Retention time
o
1. Corrective and Preventive Action QR-8.3-01 MR 3 Year
2. CPA log sheet QR-8.3-02 MR 3 Year
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 33 of 40
The company collects and analyzes appropriate data to evaluate the suitability and
effectiveness of the quality management system and to identify areas for continual
improvement. This includes data generated by measuring and monitoring activities
and other relevant sources. Decisions based on facts are based on effective and
efficient use of appropriate statistical techniques.
Responsibility Presentation
S/No. Source of data Frequency Record #
Collection Analysis method
Services Confirmation & Customer Satisfaction
Head of
Customer
1. Relationship MR Quarterly Bar Chart QR-8.4-01
Feedback
Management
Head of
Customer
2. Relationship MR Quarterly Bar Chart QR-8.4-02
Complaint
Management
Supplier Performance
Supplier
3. DMR MR Yearly Bar Chart QR-8.4-03
Evaluation Form
QMS performance
Change Record
Appendix-01
(Organization
Chart)
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 36 of 40
Appendix-02
(Job descriptions)
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 37 of 40
Appendix-03
(Quality Policy)
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 38 of 40
Appendix-04
(Quality Objective)
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 39 of 40
Appendix-05
(PROCESS FLOW
CHARTS)
Document Revision #
PEOPLE-QM-01 01
QUALITY MANAGEMENT SYSTEM MANUAL Issue Date Page #
25-08-2009 Page 40 of 40
Appendix-06
(Forms)