Vous êtes sur la page 1sur 11

B3

Instrumentation requiring frequent access, such as local controllers, shall


be located no more than 1.5 meters above grade or permanent platform.
Instruments requiring limited access, such as temperature transmitters,
shall be no more than 3 meters above grade or permanent platform, and be
accessible by ladder or mobile platform.
SAES-J -400,
Sec.4.3.2
B2
All temperature instruments, connections, and primary elements shall be
located to provide safe access for installation and maintenance.
SAES-J -400,
Sec.4.3.1
B1
All temperature sensing elements shall be installed in thermowells.
Exceptions: Sensors for bearing, motor winding, furnace, skin or surface
temperature measurement, ambient air, electronic equipment cabinets.
(However, a mechanical protection sleeve shall be considered for the
sensors in the area where there is possibility of damage such as pump
bearings.).
SAES-J -400,
Sec.5.1
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
PROJ ECT TITLE
FAIL N/A
PLANT NO.
A Certification
RE-TEST
DATE
ITEM
No.
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SATR-J-6407 1-Oct-05 INST
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
TRAVEL TIME
SAUDI ARAMCO USE ONLY
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
Schedule Q,
Att. IV, Sec.6.1.
A1
Specific tools and equipment shall be identified to make and perform tests
in the field with instructions for their use, calibration, and storage.
Schedule Q,
Att. IV, Sec.6.1.
A2
The CONTRACTOR shall identify, maintain, control, adjust, and calibrate all
tools, gauges, instruments and other measuring and testing devices used
for controlling quality.
A3
Calibration shall be performed at established periods as specified in
the most stringent of SAUDI ARAMCO standards, other applicable
standards, or manufacturer recommendations; if no standards apply,
the calibration cycle shall not exceed six months.
Schedule Q,
Att. IV, Sec.6.1.
A4
CONTRACTOR shall provide backup equipment when the primary
equipment is being calibrated or tested.
Schedule Q,
Att. IV, Sec.6.1.
B Installation Inspection
A5
CONTRACTOR personnel performing test and calibrations shall be trained
per applicable international or manufacturer requirements.
Schedule Q,
Att. IV, Sec.6.2
Page 1 of 11
B14
Thermowell Vibration and Stress
Natural frequency and wake frequency calculations shall be performed
on each thermowell application, per ASME PTC 19.3.
If the calculated wake frequency is equal to or greater than 80% of the
thermo well's natural frequency, the next shorter standard size well shall
be specified until the calculated wake frequency falls below 80% of the
natural frequency. Standard U-lengths should be chosen whenever
possible.
SAES-J -400,
Sec.5.3.1.
B13
For process vessels and columns, the maximum insertion length shall be
600 mm (24 inches).
Exception:
For Catalyst Bed and other similar temperature profile measurements,
extended thermowells are allowed. Extended thermowells shall be in a
vertical orientation if feasible or supported such that vibration/gravity/
flow effects shall not cause fatigue or deformation failure of the
thermowell.
SAES-J -400,
Sec.5.2.9
B12
Initial insertion length "U" for flanged thermowells in process piping shall
be per Process Industry Practice PCFTE000 Temperature Measurement
Fabrication Details, Drawing PCFTE102.
Commentary Note: The final selection may be shorter based on wake
frequency calculations as detailed in Paragraph thermowell vibration and
stress. Attachment 2 & 5
SAES-J -400,
Sec.5.2.8.2
B11
Insertion Length
Initial insertion length "U" for threaded thermowells in process piping
shall be per Standard Drawing AB-036019. Attachment 2 of 4
SAES-J -400,
Sec.5.2.8.1
Standard thermowell bore selection for Threaded and Flanged
thermowells is 0.260 inch. The thermowell bore may be increased to
0.385 inch where required (e.g. filled systems). For the flanged
thermowell the tip diameter shall then be increased to 0.75 inc
SAES-J -400,
Sec.5.2.7
B9
Fabrication of Resistance Thermal Device / Thermo couple PCFTE 201
is to be as per attachment 4 and 5.
SAES-J -400,
Sec.5.2.6
B10
B8
Threaded thermowells shall be constructed and installed in accordance
with Standard Drawing AB-036019.(Attachment 3 of 4)
Commentary Note: Threaded thermowells with -inch MNPT process
connections shall be used only when required to replace existing -inch
thermowells.
SAES-J -400,
Sec.5.2.5
B7
Thermowells shall be 316 stainless steel unless alternative metallurgy is
specified or dictated by process conditions. Alternative metallurgy shall
be approved by the Materials Engineering Unit of CSD
SAES-J -400,
Sec.5.2.4
B6 Thermowells shall be tapered and machined from barstock material.
SAES-J -400,
Sec.5.2.3
SAES-J -400,
Sec.5.2.2
B4
When process temperatures are less than 535C and pressure-
temperature design conditions do not require an ANSI Class 900 or
higher flange, threaded or flanged thermowells may be used. If process
temperatures exceed 535C or the pressure-temperature design
conditions require an ANSI Class 900 or greater flange, flanged
thermowells shall be used.
SAES-J -400,
Sec.5.2.1
B5
Weld-in thermowells shall only be used when ASME or Saudi Aramco
standards or specifications require welded connections.
PASS FAIL N/A RE-TEST DATE
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
SATR-J-6407 1-Oct-05 INST
Page 2 of 11
PASS FAIL N/A RE-TEST DATE
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
SATR-J-6407 1-Oct-05 INST
B16
Maximum process pressure and static stress calculations shall be
performed on each thermowell application, per ASME PTC 19.3.
Commentary Note: Pressure and static stress effects may combine with
wake frequency vibration to cause failure of thermowells.
SAES-J -400,
Sec.5.3.3
B15
For Flanged Thermowells, where the calculated U-length ends up being
too short for good heat transfer, modifications to the thermowell design
may be made such as:
a) A thermowell collar or special flange weldolet may be used to tightly
hold the thermowell to the flange near the pipe wall, thus effectively
reducing the calculation U-length, or;
b) External dimensions such as root and tip diameter may be increased
to lower the wake frequency and increase the resonant frequency.
SAES-J -400,
Sec.5.3.2
C1
D
C Calibration Record / Test Equipment model :
C Calibration Inspection
C1 Dimensions as per data sheet.
Schedule Q,
Att. IV, Sec.6.1.
C2 Tag number correct
Schedule Q,
Att. IV, Sec.6.1.
C3
Checking thermocouples or secondary standards should be
homogeneous and uncontaminated. Any new thermocouple may be
used, but it should be checked against a primary standard and tagged
with its deviation from the standard curve. If a user does not have the
equipment and
technique for doing this, calibrated and tagged thermocouples are
available. The National Bureau of Standards or other standardizing
laboratories will furnish a report on the temperature-EMF characteristics
of a submitted thermocouple..[ ISA-MC96.1-1982, Appendix D- Sec
D3.4, Thermocouples- checking procedures]
SAES-J -400,
Sec. 3.2
C4
D.3.5 The accuracy of a checking thermocouple or secondary standard
will become questionable after use. Noble metal thermocouples may
normally be relied upon for a considerable period of use, provided that
the checking temperatures have not been avoided. Base metal
thermocouples used for checking purposes should be checked
frequently. NOTE: Base metal couples should not be used for checking
purposes below 480C (900F), if they are exposed between checks at
temperatures above 760C (1400F).[ ISA-MC96.1-1982, Appendix D-
Sec D3.4, Thermocouples- checking procedures]
SAES-J -400,
Sec. 3.2
Test Equipments Serial number:
a) Smart Field Communicator (SFC)
b) Millivolt generator
c) Digital Multimeter
d) Supply Unit
e) 250 Ohms Resistor
General Test Routines
Page 3 of 11
PASS FAIL N/A RE-TEST DATE
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
SATR-J-6407 1-Oct-05 INST
E1
F
F1
Test Procedures E
(a) Check Temperature transmitter against Data sheet.
(b) Connect as per attached hook-up drawing.
(c) Ensure that all polarities are correct and all connections are tight. Connect SFC, red wire to positive, black to negative.
(d) Switch on power supply and SFC unit.
(e) When the SFC is communicating , check that the ID of the transmitter is correct .
(f) If the output of the Transmitter is analog format proceed with calibration.
(g) If the output of the transmitter is digital format, change the format to analog using the SFC and as per the operations manual.
(h) When the output has been changed to analog proceed with calibration.
(i) Using T/C Tables, inject 0% input with millivolt generator and note that the output should be 4 mA, on the Multimeter.
(j) Inject 25,50,75,& 100 % of the range to the Transmitter and note that the output should
be 8mA,12mA,16mA and 20mA respectively.
(k) Then proceed in the reverse direction from 100% to 0%.
(l) If the error is greater than the allowable tolerance, inject 0% to the input of the transmitter and using the SFC and the operations
manual,adjust transmitter until output reads 4 mA
(m) Inject then 100% input and adjust accordingly the output should equal to 20 mA or 100%.
(n) Repeat steps (l) and (m) until accuracy is with in required tolerances.
(o) When accuracy is with in required tolerances repeat steps (i),(j) (k) and record the reading on the calibration certificte.
(p) For those transmitters are digital formatted, change back from analog to digital format using the SFC with reference to operators manual.
(q) After the calibration is completed turn off power supply.
(r) Disconnect all wiring and replace cover tightly.
(s) Then place calibration Tag, which shall be a blue colour on transmitter
(t) Sign off calibration sheet
(u) Instrument calibrations will be repeated where necessary during pre-commissioning or at any other stage where deficiencies are to be
rectified.
Test Variables
D1
1. Instruments shall be calibrated in a clean , dry, and air conditioned test and calibration workshop.
2. Test Instruments for Calibration shall be split in to two categories- Primary & secondary.
3. Primary instruments shall be high precision instruments and have valid calibration certificates traceable to a National Standards
laboratory.
4. The instruments shall be Calibrated every 6 months and the certificate retained in the workshop available for the Clients Inspection.
5.Primary instruments shall remain in the calibration workshop and shall not be removed to site.
6.Secondary instruments of lesser precision shall be calibrated by the Primary Instruments and shall be used for calibration works both with
in
the workshop and in the field.
7. Prior to calibration, the instruments shall be inspected to ensure that there is no physical damage. The instrument shall be identified by
Tag
No. and checked against data sheet, manufacturer, correct model, range, span and connection size .
8. All instruments must have a Calibration Certificate which is held in a file in the Instrumentation Work shop and is available for inspection o
request.
9. Field Instruments when not held in the Calibration workshop must be signed out /signed in on a Daily basis. This task to be done using a Lo
book system. The Log book to be made available for inspection on request.
10.All instruments used for Testing on project,on Arrival in to the Instrument Work shop must be logged in to a controlled log book of
instruments to be used on project. The Log book to be made available for inspection on request.
11.Instruments used daily for Testing on site to be entered on a daily log sheet .One copy to be kept in the Instrumentation work shop and on
copy to be placed in the instrumentation R.F.I box.
G - Tabulate the pass/fail criteria here (include range, limits, and units of measurement)
Manufacture's Test Variables if any to be highlighted including the
following:
F1 The temperature indicators / thermometers, 0% equal to the ambient
temperature of the room.
F2.The manufacturers instructions regarding adjustment, preservations,
accuracy to be adhered to.
Page 4 of 11
PASS FAIL N/A RE-TEST DATE
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
SATR-J-6407 1-Oct-05 INST
After successful completion of each calibration, the instrument shall be marked with a colored label bearing date of the calibration and the initials of
the witnessing party The color code shall be as follows:
Blue- Pre Calibration Tested.
Yellow - Installed & Pressure Tested.
Green- cables or tubing tested.
Red- Loop Check completed.
Ambient:
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), J uly 1993
5. ASME PTC 19.3 -1974, Part 3, Temperature Measurement- Instruments and Apparatus, Supplement to ASME Performance test codes
I. CONCLUSIONS
Notes: a. Indicate in 1 report all instruments of a skid tested and passed .
b. Rejected items should be listed in another report, unless they were corrected
within the calibration period.
c. Instruments repaired shall be indicated "Repaired and Accepted" in the test report.
4. ISA-MC96.1-1982 Temperature Measurement Thermo couples
3. SAES-J -400, Temperature, 31 May, 2004
50%
Insulation Resistance
25%
0%
75%
H. RESULTS
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA PASS FAIL N/A RE-INSP DATE
Input % Simulated Input Out Put Error
100%
75%
25%
0%
Hystersis at 110%
Specific gravity setting (For liquid interface level measurement)
Resistance
REMARKS:
REFERENCE DOCUMENTS:
2. Schedule Q -- Quality Requirements (Pro Forma Contract), November 2003
Page 5 of 11
PASS FAIL N/A RE-TEST DATE
ITEM
No.
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO TEST REPORT
SATR NUMBER DATE APPROVED QR NUMBER
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
SATR-J-6407 1-Oct-05 INST
2. Models used are just sample info. The product has to be approved by CSD and proponent.
Contractor / Third-Party Saudi Aramco
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
Technician Performing Test* PMT Representative
Attachment 2 Threaded thermowells -Standard Drawing AB-036019
Thermowell Mounted Head- PCFTE000-Drawing PCFTE202
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
5. Remarks: -1. Table G to be modified based on usage.
PID Representative QC Inspector
QC Record Reviewed Work Verified
Name, Title, Department,
Company, Initials and
Date:
Test Performed Successfully and Results are Acceptable:
Name, Initials and Date:
T&I Witnessed
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the
f
indicates compliance with appropriate standards or performance in a specified manner.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
6. SAMA RC 21-4-1966 Scientific Apparatus Makers Association, Temperature- Resistance Values for Resistance Thermometer elements for
Platinum, Nickel and Copper.
ATTACHMENTS:
Attachment 1- Ambient air quality
Attachment 3 Fabrication of Resistance Thermal Device / Thermo couple PCFTE 201
Attachment 4 Fabrication detail for Resistance Thermal Device / Thermocouple with Thermowell Mounted Head- PCFTE000-Drawing PCFTE202
Page 6 of 11
SAUDI ARAMCO ID/PID - 4/14/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
SATR-J-6407 1-Oct-05
Attachment 1Ambient air quality
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
INST
Page 7 of 11
SATR-J-6407 1-Oct-05
Attachment 2 Threaded thermowells -Standard Drawing AB-036019
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
INST
SAUDI ARAMCO ID/PID - 4/14/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
Page 8 of 11
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
INST
SAUDI ARAMCO ID/PID - 4/14/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
SATR-J-6407 1-Oct-05
Attachment 3 Fabrication of ResistanceThermal Device / Thermo couple PCFTE 201
Page 9 of 11
SAUDI ARAMCO ID/PID - 4/14/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
SATR-J-6407 1-Oct-05
Attachment 4 Fabrication detail for Resistance Thermal Device / Thermocouple with
Thermowell Mounted Head- PCFTE000-Drawing PCFTE202
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
INST
Page 10 of 11
Temperature -Transmitter RTD type-Functional Check /
Testing, and Certification
INST
SAUDI ARAMCO ID/PID - 4/14/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
SATR-J-6407 1-Oct-05
Thermowell Mounted Head- PCFTE000-Drawing PCFTE202
Page 11 of 11

Vous aimerez peut-être aussi