Académique Documents
Professionnel Documents
Culture Documents
3.) Solution
Given,
Demand D= 4,860 bags/yr.
Setup cost S = $10
Holding cost H = $75 then,
2DS 2(4,860 )10
a. Economic Order Quantity Q 36 bags
H 75
b. Average number= Q/2 = 36/2 = 18 bags
D 4,860 bags
c. Number of orders per year= 135 orders
Q 36 bags / orders
D
d. total cost, TC Q / 2 * H *S
Q
36 4,860
(75) (10 ) 1,350 1,350 $2,700
2 36
2(4,860 )(11)
e. Using S = $11, Q = 37 .757
75
37 .757 4,860
TC (75) (11) 1,415 .89 1,415 .90 $2,831 .79
2 37 .757
The total annual cost is Increase by [$2,831.79 – $2,700] = $131.79
6. Solution
Total Annual demand = 800*12 per year = 9600 per year
Purchase cost = $10 per crate per year
H = holding cost = (0.35)*Purchase Cost = $3.5 per crate per year
S = setup cost = $28 per order
As per EOQ model,
2DS 2(9600)28
EOQ = Q 392 bags
H 3.5
D
TC = TC Q / 2 * H * S (392/2)*3.5 + (9600/392)*28 = $1372
Q
As per Non-EOQ model,
Average inventory per month = 800/2 = 400
Total Cost = 400*3.5 + 12*28 = 1400 + 336 = $1736
2
The firm will save annually ($1736-$1372) $ 364 in ordering and carrying cost by using the
EOQ
9.) Solution
Given,
Production capacity p = 5,000 hotdogs/day
Usage or supply u = 250 hotdogs/day
Factor operate, n= 300 days per year
Setup cost, S = $66
Holding cost, H = $.45/hotdog per yr.
Annual demand D= 250*300= 75,000 hotdogs/yr.
2 DS p 2(75,000)66 5,000
a .Optimum output, Q0 4,812.27 or equal to 4,812
H p u .45 4,750
b. Number of runs per year = D/Q0 = 75,000/4,812 = 15.59, or about 16 runs/yr.
c. Run length: Qo/p = 4,812/5,000 = .96 days, or approximately 1 day
20. Solution
Given lead time demand, D= 600 pounds
Standard deviation of lead time σlt= 52 pounds
Safety stock = 4%
Service level = 96%
At 96 % level, Z value = 1.75
a.) Safety stock= Z-value * standard deviation = 1.75*52 = 91 pounds.
b.) ROP = Average demand during lead time + safety stock = 600+91= 691 pounds.
c.) with no safety stock the risk is 50%
3
2. AOA Diagram
Lib
Out
Ch 0.6 2.0
0.4 Sub
Write Ck
End
Start 0.2
3.0 0.5
Inst
Sh
0.8
2.0
Sel
1.0
4
3. AON Diagram.
CH Lib Out
W Ck Sub End
ST
Sh
Sel Ins
t
3.
4.) There are three parallel activities that need to be done simultaneously. If there is delay either
one of the activity it delays the project. So the Parallel paths, probabilistic activity durations may
be main reason for the project to take longer than the expected duration.
5
7. Solution:
Given data:
Time in days
a) Presdence diagram
C 5
E
2
A
F G End
D 3 6 8
Start
1
B I
H
4 7
6
The critical path is : D-F-G and expected duration of project is 21.5 days
A 6 4/36
B 8.5 9/36
C 8.17 25/36
D 12 36/36
E 6.33 16/36
F 6 4/36
G 3.5 25/36
H 4.17 1/36
I 6.83 9/36
4 25 16 45
For path A-C-E, σ = √36 + 36 + 36 = √36 = 1.118
36 4 25 65
For path D-F-G, σ = √36 + 36 + 36 = √36 = 1.344
9 1 9 19
For path B-H-I, σ = √36 + 36 + 36 = √36 = 0.726
7
be completed as they have less time to complete. The path that has the longest expected duration
be completed as they have less time to complete. The path that has the longest expected duration
10. Solution
Given data:
Activity Estimated time (weeks) Standard deviation (wks)
1-2 4 0.70
2-4 6 0.90
1-3 3 0.62
3-4 9 1.90
Precedence diagram:
2
1 4
b.) According to the question there will be fine of $5,000 per week if the project is late. The
schedule time is 11 weeks but estimated time is 12 weeks. We need to find the probability at
least there will fine of $5,000. That mean the project must be late 1 weeks for this condition.
Therefore, we need to find the probability at more than 12 weeks
Specified time−path mean
As we know z=
Path standard deviation
12−10
Now for path 1-2-4: z= = 1.75, at that point from the Z- table (Given at Appendix
1.14
B in book) the probability is 0.9599
12−12
For path 1-3-4: z = = 0, at that point from Z- table the probability is 0.5
2
As By considering the time that critical path activities are completed, other activities already will
be completed as they have less time to complete. The path that has the longest expected duration