Académique Documents
Professionnel Documents
Culture Documents
0 Table of content
0 Table of content ............................................................................................................
.........................2
0.1 Abbreviations .....................................................................................................................
............3
0.2 Map ...........................................................................................................................
.....................4
1 Introduction ...........................................................................................................................................
.4
2 Rationale .................................................................................................................................
...............5
2.1 Roads in Vanuatu ........................................................................................................
..................5
2.2 MCC MCA ..................................................................................................................................
...6
3 PWD maintenance training project ....................................................................................
...................7
3.1 Financing agreement. .....................................................................................................................
7
3.1.1 Financing agreement summary ................................................................
............................7
3.2 Global work plan introduction ...........................................................................
...........................8
4 Logical Framework - Revised in June 2005 ..................................................................
.......................9
5 Budget balance November 2006 .................................................................................
........................11
6 Heavy equipment ...................................................................................................................
..............11
6.1 Supplies by CIPAC ...................................................................................................
..................11
6.2 Supplies by JOHS ........................................................................................................
...............11
6.3 Laboratory supplies ..............................................................................................
.......................12
6.4 Others suppliers : ..........................................................................................................
...............12
7 Training contract ...........................................................................................................................
.......13
8 Annual programs and cost estimates .....................................................................................
..............14
8.1 Programme Estimate 1 ....................................................................................
............................14
8.2 Programme Estimate 2 ....................................................................................
............................14
8.3 Programme Estimate 3 ....................................................................................
............................15
8.3.1 Cost estimate .................................................................................................................
.......15
8.3.2 Activities ...........................................................................................................
...................15
9 Technical Assistance ...................................................................................................................
.........16
9.1 At PWD main office Port Vila ...........................................................................................
........16
9.2 VSO volunteers. ......................................................................................................................
.....16
10 Site visit to Malekula ...................................................................................................................
......16
11 Site visit to Tanna ...................................................................................................
...........................17
12 Findings .....................................................................................................................
........................17
12.1 Purchase of heavy equipment .. ...........................................................................................
......17
12.2 Maintenance issues .......................................................................................................
.............18
12.3 Network ...........................................................................................................
..........................19
13 Proposals .....................................................................................................................................
.......19
13.1 Setting up routine maintenance at division level .....................................................................19
13.2 Training ............................................................................................................................
..........20
14 MIPU & PWD institutions .............................................................................................
...................20
14.1 Ministry of Infrastructures and Public Utilities MIPU .............................................................20
14.2 PWD ........................................................................................................................................
...21
14.2.1 Roles and responsibilities ...................................................................................
...............21
15 Current states of indicators ..........................................................................................................
......21
15.1 Travel times to key facilities reduced. ....................................................................................
..21
15.2 Improved year round access to key facilities. ..........................................................................22
15.3 Complaints register .............................................................................................................
......22
15.4 Database that establishes priority maintenance plans for roads ...............................................22
15.5 Annual Work program and Budget for PWD ...............................................................
............22
15.6 Maintenance schedules for all equipment ....................................................................
.............22
2
0.1 Abbreviations
EC
European Commission
EDF
EU
European Union
GPS
HDM
IRI
LFM
MCA
MCC
NAO
PE
Programme Estimate
PMU
POPACA
PWD
QA
Quality Assurance
REDI
TA
Technical Assistant
TAG
TOR
Terms of Reference
TYPSA
VA
Vanuatu
VOC
VSO
Table 1: Abbreviations
0.2 Map
1 Introduction
The project aims at building the capacity of the Public Works Department, especially in two of the
main outer islands (Malekula and Tanna), to maintain properly transport infrastructure. It comprises
the provision of equipment, training, and demonstration works.
2 Rationale
2.1 Roads in Vanuatu 1
Roads are the primary and preferred mode of transport to access basic facilities (including health
and education), and for providing transport routes to markets for cash crops and small rural
enterprises.
Figures provided by the department of Public works would suggest that the road network underwent
little growth during period 1989 - 1997. Nonetheless, the road network did increase as several donor
funded road projects have been undertaken during the period. Some roads have been built without
any adequate study of the likely benefits or without any economic justification. In 2006, the network
may be classified in three categories : national, provincial and municipal roads.
According to PWD report dated March 2006, the total network length is about 2024 Km but the same
report also draws the attention to a few discrepancies between different sources of information.
Province
National
Provincial
Municipal
Total
Shefa
324
22
364
Sanma
486
130
2.6
618
Malampa
347
46
393
Tafea
205
6.8
212
Penama
361
51
412
Torba
42
42
1766
255
2.6
2024
Total
been formulated:
classification
Definition
Administrator
National
Road which form a link in the national arterial network and falls under the following PWD
:
- road which traverse the national land or goes around it and links the national
capital or provincial capital with other important villages
- roads which links an international port , national port, international airfield,
national airfield or places of national interest to another national road
- roads which links a place requiring development from stand point of the national
development ar land-use plans.
provincial
Roads which forms the local arterial network and falls under the following:
- road which links two or more villages to reach a national road
- roads which links a village with another village, local port or another place of
interest
Provincial
Government
municipal
Municipal
council
Date
5/11/2003
31/12/2003
Project estimate 1
Period
2004 - 2006
01/01/04 30/6/05
01/07/05 - 31/12/05
Project estimate 2
20/01/2006
01/01/06 - 31/12/06
Project estimate 3
07/07/2006
01/01/07 - 31/12/07
Progress report 1
01/01/2004 - 30/09/2005
Progress report 2
01/07/2006 - 30/09/2006
Infrastructure Development Project (OIIDP) under which essential transport infrastructure will be
rehabilitated or upgraded.
Rural Economic Development Initiative (REDI) projects were initiated in the provinces of Malampa
and Tafea to promote economic growth within the framework of the Comprehensive reform Program.
For the POP project and the REDI programmes, transportation is a major constraint to their
implementation and operation. The proposed project will also complement OIIDP and improve the
PWD capacity to properly maintain the transport infrastructure
Overall objective : "Improved rural economy and life by ensuring that basic transportation facilities
are kept operational, thus providing access to essential services, and facilitating shipment of
agricultural products."
Project purpose : "Improved access to markets and shipping services, and to social services delivery
points"
Results:
PWD's maintenance units strengthened two provinces (Malampa and Tafea) through the supply of
essential equipment, training and demonstration works.
Cost estimate :
Procurement of equipment
1 050 000
520 000
Demonstration works
380 000
Audit
15 000
Evaluation
30 000
Total
1 995 000
most of the equipment is old and very expensive if not impossible to repair
funding is insufficient
conditions in these areas will be improved thus allowing the beneficiaries a better access to markets
and social facilities (schools, hospitals).
Because of limited availability of PWD equipment, the project includes acquisition of some heavy
equipment necessary for the training sessions.
According to the "Global work plan", project philosophy is : "the effectiveness of road maintenance
depends largely on the operator's knowledge of road maintenance techniques, and their capacity to
carry out appropriate maintenance operations."
Project purpose
Overall objective
Project Description
To contribute to
improved access to
important social ,
economic and market
services in Vanuatu
Improved capacity in
PWD to deliver its core
maintenance function
Results
1. Financial Management
& Planning Skills
improved.
Source of verification
National statistics
Current Status
Equipment
Logbooks
available and in
use
Establishment of
complaint register
in progress
Work programme
for 2006
completed.
National Budget
Annual work
programme 2006
for PWD was
established in
October 2005
Check logbooks
Periodically
All equipment in
operation has
logbooks, but
recording needs
more attention
Check maintenance
Schedules
Check monthly reports
of provincial offices
Maintenance
schedules 20%
available
Breakdown rates
reduced from 11%
to 9%
Project Description
Rsulta
3. Quality Control
systems and skills
improved to
international standards
Source of verification
Annual report
Current Status
Road maintenance
rate increased to
63%
Annual reports
11 more
technicians trained
in QA
Activities
Project Description
Project documentation
Purchase of equipments
Purchase of consultancy
services
Recruitment of two
volunteers
Training
Establishment of work
programmes
Demonstration works
Community works
Monitoring by Project
Implementation Unit
(PIU)
Project Evaluation
Central Laboratory
PWD updated by
October 2005
Number of
test/year increased
Cost Estimates ()
Current Status
Purchase of Equipment
1,050,000
Training, expert
services, and
operational costs
520,000
483.117,97
Demonstration works
380,000
Evaluation
30,000
Audit
15,000
---------------Total
1,995,000
964.968,37
316.940,99
0
5.000
1.769.967,33
10
Budget
Budgeted in the FA
Commitments
1st Work Programme
Intraco
Johs. Gram-Hanssen
TYPSA
VSO
CIPAC
BMS (Audit)
TA to PWD (DHV)
PE 2006 (Rider 1)
Audit 2006
PE 2007
AT 2006-07
Audit 2007
Evaluation
Total committed
Balance
1
2
3
4
5
6
7
8
9
10
11
12
Total ()
1 995 000
VUV
EURO
43 000 000
320 747,98
4 800 000
34 444,14
343 179,00
13 444 815
95 924,35
18 198 392
130 000,00
46 842 470
345 000,00
350 000
3 000,00
59 985,00
32 225 000
231 834,53
3 483,00
33 000 000
237 410,07
157 500
3 500,00
15 000,00
1 987 829,07
7 170,93
EURO
VUV
953 733,12
6 Heavy equipment
Equipment has been delivered in August 2005:
Particulars
Value
Bulldozer
22 T 191 HP
Grader
13 T 140 HP
47 000 000 VT
Particulars
Dynapac CA 262D
Value
2 * 72 250
155190
Particulars
JCB 3CX 8 T
Value
60 200
11
Type
Particulars
Loader
JCB 436ZX 15 T
Value
109 600
187 989
QTY
21 pcs
21 pcs
27 pcs
27 pcs
29 pcs
1
1
1
1
2
10
3
1
40
1
1
1
1
4
1
1
15
8
2
15
20
1
1
4
MAKE
tool mac
tool mac
tool mac
tool mac
tool mac
bosch
lufkin
lufkin
sip
chubb
toolex
MODEL
pws 7 100
20x
20x
charge star 30
d-hundle
204/02
tl 75
CAPACITY
1 5/8" - 3 1/8"
(20-320)mm
(22" - 50 ) mm
1/2" - 2"
4mm-12mm
720 watt
objective
objective
24v(22a max)
6"
1.5kg
( 1,725
carmin
-
can210 (12fc)
-
750a
atlas copco
atlas copco
husqvana
xas 36
tex 22 ps
h 365
15.3kw @
200 (littres)
7bar (max)
1.5kw
spitwater
-
11 140 wp
-
5 cu ft
12
DESCRIPTION
1" spanner sockets set
1/2" drive socket set
3/4" drive socket set
3/4" drive socket set
3/8" drive socket set
angle grinder
automatic level c/w
battery charger
bench vice with anvil
cyclone shovels
fire extinguisher
gas welding kit high pressure
gps
heavy duty booster cable
light duty booster cable
measuring wheel
metallic cupboard
mobile compressor
pick up truck
pneumatic jack hummer
power saw
tourgue wrengers
water cleaner
wheelbarrow
QTY
21 pcs
21 pcs
27 pcs
27 pcs
29 pcs
1
1
1
2
10
3
1
1
1
1
1
1
1
1
1
1
MAKE
tool mac
tool mac
tool mac
tool mac
tool mac
bosch
lufkin
sip
chubb
toolex
carmin
bizhub
atlas copco
mitsubishi
atlas copco
husqvana
MODEL
pws 7 100
20x
charge star 30
d-hundle
204/02
tl 75
can210 (12fc)
xa537
k77t jensl
tex 22 ps
h 365
1
4
spitwater
-
11 140 wp
-
CAPACITY
1 5/8" - 3 1/8"
(20-320)mm
(22" - 50 ) mm
1/2" - 2"
4mm-12mm
720 watt
objective
24v(22a max)
6"
( 1,725 2,500) kpa
750a
100a
15.3kw @
3200cc
7bar (max)
1.5kw
5 cu ft
7 Training contract
On December 15th , 2004, contract # Serve/9-002/004/IC was signed with Technica Proyectos SA
TYPSA to conduct trainings in road maintenance.
Training sessions were organised by TYPSA company, and held from end August to early December
2005.
Final report is available.
Lists of trainees first week
Name
Position
Name
Position
Jimmy Johnson
Malekula manager
August Nalan
Operator
Fred Cudeous
Tanna manager
Sandy Reny
Qualify operator
Simeon Stanley
Santo manager
James Samuel
Grader operator
Alosio Sawan
Ambae manager
Richard Iao
Bulldozer operator
Bob Meltek
Bulldozer operator
Toares Augustin
Grader operator
Georges Mouris
Foreman
Position
Joseph Banyus
Operator
Jean Jacques
Jean Anthony
Operator
13
Atis Tessi
David Kai
Qualify operator
Brian Matamlele
Philip Mourison
Operator
Titus Tari
Edward Pakao
Anthony Yosef
Laboratory surveyor
Joe Antas
Laboratory
Viva Bani
Foreman
2 pilot and demonstration sites for road maintenance techniques : 25 km in Malampa province and
22 km in Tafea province.
Rider 22/08/2006 budget adapted to removeprocurement of one vehicle, tune DSA , accommodation
and contingencies.
demonstration works : site selection and planning has been made by Malekula and Tanna Works
Divisions.
quality assurance training : mainly with PWD soil laboratory facilities in Port Vila
Caption
Budget
100000
Procurements
5 050 000
120000
- equipment
4 550 000
121000
- spare parts
4 050 000
122000
500 000
130000
500 000
200000
9 400 000
210000
- In country training
9 400 000
300000
Demonstration works
15 735 000
310000
- Malampa
7 300 000
320000
- Tafea
8 425 000
400000
Operating costs
625 000
Total
30 800 000
8.3.2 Activities
Financial Management and Panning skills improved
Database that establishes priority maintenance plans for the main maintenance activities in
Vanuatu will be further improved, allowing a more realistic planning programme for the future.
Fleet management : logbook monitoring system in full operation, maintenance schedule for all
PWD equipment, reducing the breakdown ratesfrom 9% to 3 %
15
Road maintenance : in order to keep the Vanuatu road network in a goosd condition, the road
senior foremen and the road foremen from all the six provinces and the two municipalities will
attend further training / demonstration sessions to enhance their skills in proper road maintenance
techniques
Quality control
The eleven QA technicians trained during PE1 and PE2 operational period will be further trained
to reach acceptable level to be able to determine the good materials during the maintenance
activities.
9 Technical Assistance
9.1 At PWD main office Port Vila
John Andriamanantoa
John Pello
23/04/2005 - 31/08/2006
Luc Grandjean
13/11/2006 - 13/11/2007
30/05/2005 30 /05/2007
Lawrence Kithome
17/10/2005 - 16/10/2007
Individual training needs will be assessed during next visit, after discussion with PWD chief of
operation, who is the hierarchical chiefof division's staff.
On the way back, stop over at Santo, meeting with PW division Staff, PW division workshop and
visit of water works under progress ( 240 M" new reservoir build) and water facilities ( pumping
station)
Second site visit to Malekula scheduled for 12 to 15/12/2006
demonstration sites seem very well selected, works are more rehabilitation than maintenance
design and implementation of works are not properly done : too basic survey, no sketches /
drawings, no real cost estimate
routine (preventive) maintenance has to be put in place, starting with site inspections, surveys, ...
equipment downsize for routine maintenance, better matched to needs would be advisable and
come in support to community works.
one 4 wheel excavator with rock breaking hammer would be an asset, sandblast equipment and
adequate coating is needed for bridges structures.
province, with community works, has developed a rather large feeder road network without
having any idea of its extension and maintenance needs, nor having budget for same.
employment and job creation will become a matter of concern of young people on Tanna. Some
policy decision could take place and an action plan could be proposed.
12 Findings
12.1 Purchase of heavy equipment ..
According to monitoring report dated 04/09/06 - 22/09/06: "Estimate (PE) No.1 included [...] the
procurement of heavy machinery (probably more suited to major road building rather than
maintenance) ".
Available equipment is not adequate for routine maintenance and equipment of small labourers teams:
not enough hand tools : shovels, hoes, picks, axes, hammers, mining rod, ...
versatile agricultural tractors with tipping trailers, slashers, front loader, ... could also be
advisable.
no excavator available
a D8 size bulldozer 2 cannot be fully employed on Tanna for years : it would be advisable to plan
activities there (road opening / rehabilitation on section C and D, stockpiling huge quantities of
coral stone, ...) and then transferring to another island, with a planned program of work.
loader granted to Malekula is inefficient if served by only two old and small tipping trucks
Intervention
type
recurrent
maintenance
Periodic
maintenance
Rebuild
18
as they become likely, to mitigate the impact or the probability of occurence. Example: to clear a
landslide is curative. To plant the slope to stabilise it is preventive.
A well designed preventive maintenancepolicy allows savings and delivers a better level of service
than the restorative maintenance policy (even fast and effective).
Routine maintenance and periodic maintenance include a majority of preventive maintenance tasks
and some restorative maintenance activities.
Recurrent maintenance : light maintenance operations, to be carried out throughout the year in
order to prolong as much as possible, and at the lowest cost, the lifespan of a road. In particular :
pothole patching ,
Periodic maintenance : routine maintenance, to be carried out periodically to preserve the structure of
the roadway while renewing its surfacing: new dressing of the surface on the surfaced roads (every 8
to 12 years, according to the traffic), or heavy reshaping with recharging on the unsealed roads (every
4 to 6 years according to the traffic). The routine maintenance renovates the surfacing, without
renovating the structure of the roadway.
Rehabilitation or rebuilding: Heavy interventions intended to reconstitute the structure of a very
degraded road. Rehabilitation and rebuilding do not belong to the framework of maintenance; they are
in fact new investments to restore an infrastructure already paid for.
More details on maintenance in annex.
12.3 Network
Networks are in the range of 200 300 km on each island. The networks are neither well known, and
from first sight nor is maintained.
Substantial investments is lacking to allow normal use of 2x4 vehicles on the whole extent of the
network.
Target could be the normal use of a 2x4 pick-up on the network all year round : this would mean that
transport costs of goods and persons will be brought down to more acceptable levels : 4X4 vehicles
are more expensive to purchase and more costly to run, in fuel and spare parts.
13 Proposals
13.1 Setting up routine maintenance at division level
Being at the third and last year of the project, with a programme estimate already approved there is
little room to introduce new features. Nevertheless, in line with the planned activities and normal
duties of PWD staff at divisions level, some new orientations can be introduced and training towards
effective maintenance, as described above and in annex, could be completed.
3 Cantonnage: (French word). It is a manner of organizing all the small maintenance tasks, those which a person alone
can achieve with simple (hand) basic tools, like mowing, bush clearing, clearing out the ditches, culverts, bridges,
Each road-mender is in charge of X km of road which would keep him occupied all year round, with some control
and backup. Cantonnage can be carried out as well under force account (rgie) or under works contract.
19
During this last year of the project, key figures and productivity rates in different conditions could be
established, in order to be able in the near future to estimate the cost of the maintenance tasks.
Works and strategy could be seen as pilot activities for next maintenance projects country wide
(including MCA project) or for PWD budget's improvements.
After meeting and possibly Steering committee approval, available funds planned under PE3 could
be used to direct procurements towards smaller equipment ,to be used with labour team on preventive
maintenance.
13.2 Training
Training that has been carried out up date was found to be too academic by technicians.
Other training material, for labour based activities, will be made available to PWD and Works
divisions and trainings sessions will be organised with the help of the 2 VSO volunteers.
These trainings should also be offered to provincial staff, as provinces have the ownership of the
"feeder roads" network and are facing same maintenance problems.
On a day to day basis, individual needs will be identified. Without being exhaustive, the assessment
has not yet been made, some ideas could be :
etc.
Technical documentation has also to be made available at division's level, either on printed hard
copies or on CDROM.
20
14.2 PWD
The Public Works Department (PWD) is in charge of roads, buildings, water, solid waste collection
for public buildings and comprises 3 sections and 6 divisions.
Sections are :
Projects : in charge of investment budget lines
Operations : managing the recurrent budget
Finances
Sections are hosted in the main office located in Port Vila, first floor.
The Operation section is relayed at provincial level by Divisions : Shefa, Sanma, Malampa, Tafea,
Penama, Torba
Operation section
operate and maintain water supply system in urban areas of Lugainville, Norsup, Lakatoro and
Isangel
assist other government departments with management of maintenance of their facilities ans staff
housing
collect revenue for provision of water supply and electricity, and vehicles inspections
Project section
21
Monitoring this indicator could be made by a bi-annual survey amongst the taxi drivers, for example.
On a standardised form.
Starting point:
description / toponomy
Ending point :
description / toponomy
Distance :
Km
Classification:
National /provincial/ Municipal
Tanna province has already expressed a need to revise the classification and include more roads in
the national level.
classification
Definition
Administrator
National
Road which form a link in the national arterial network and falls under the following PWD
:
- road which traverse the national land or goes around it and links the national
capital or provincial capital with other important villages
- roads which links an international port , national port, international airfield,
national airfield or places of national interest to another national road
- roads which links a place requiring development from stand point of the national
development ar land-use plans.
provincial
Roads which forms the local arterial network and falls under the following:
- road which links two or more villages to reach a national road
- roads which links a village with another village, local port or another place of
interest
Provincial
Government
municipal
Municipal
council
23
16 Annexes
16.1 Annex : road maintenance definitions and practices
16.1.1 Common definition
A common understanding of road maintenance requires the understanding of the term "maintenance".
The basic objective of road maintenance is implicit in the word itself. It is done to ensure that the road
that has been constructed, or improved, is maintained in its original condition. It is accepted that over
the lifespan of the road, it will deteriorate due to factors with which maintenance activities cannot
deal. Nevertheless, maintenance is intended to begin on the first day after the road improvement
works have been completed.
In practice the effect of regular and timely maintenance is to increase the life of the road by putting
off the date at which it needs to be reconstructed.This has several benefits, the prominent one being
that maintenance stretches the period over which the benefits from the investment made are available
and therefore provide a higher rate of return on the initial investment. In addition, it puts off the date
when large investments have to be made to reconstruct the road. As the yearly cost of maintaining a
road is a small fraction of the investment cost, usually some 2-3%, the economic logic for effective
preventative maintenance is undeniable. It can indeed be argued that the construction of roads, whilst
consuming large amounts of money, is of limited importance if there is no effective maintenance
system.
For reasons that are difficult to assess, however, road maintenance is often viewed as an activity that
is carried out only when the road is damaged. As no one would apply this approach to his house or
even his own health, it is strange that it seems to be a pervasive attitude in the road sector.
The situation is particularly critical with unsealed roads. Here the main enemy of the road is water.
The whole concept of rural road building is to get the water as quickly and efficiently as possible
away from the road structure. This means that the camber of the surface, the slope of the shoulders,
the side drains and cross drainagestructures need not only be constructed effectively but also need to
be kept in a condition that will permit the free run off of the water. This means that the road once
constructed has to be looked after on a regular basis. This is why routine maintenance is so important
and is the core of an effective maintenance system. The term Recurrent maintenance is sometimes
used to cover certain activities (such as light grading) which are carried out during the year over and
above the activities of routine maintenance. Periodic maintenance is an activity that is undertaken
every 3- 5 years and is concerned with rectifying defects which are outside the scope of routine
maintenance. Routine maintenance however remains the key activity. It is the least costly but provides
the greatest benefits.
Maintenance, being a recurrent activity, should be financed from the recurrent budget. The funds
allocated to it should relate to a maintenance plan which defines those roads requiring maintenance
and, using standard figures for routine, recurrent and periodic maintenance, produces a recurrent cost
for the network.
Unfortunately, as in many other countries, road maintenance is not viewed as a recurrent activity. It is
viewed as a set of projects to be carried out on roads which, because of lack of maintenance, have
deteriorated to a state where they need improvement.
The present description of road maintenance in the budget reflects the curative rather than the
preventive approach to maintenance.
There is, therefore a major effort required not only to develop an effective and realistic rural road
24
maintenance system but also to create a maintenance culture along the lines described above.
non-pavement related; required continually on all roads in maintainable condition 4 (good and
fair) during the year irrespective of traffic volume or engineering characteristics.
Activities include: grass cutting, bush cutting, drain clearing, ditch cleaning, culvert
cleaning, road sign cleaning, repairs of minor damage to side slopes, levelling of
shoulders and verges.
pavement related; required at intervals during the year with a frequency depending on
condition of the pavement and traffic volume/composition.
Activities include: for paved roads, repairing pot-holes, patching, for unpaved roads,
repairing pot-holes,
Activities include:
for paved roads, edge repairs, crack sealing, line marking,
for unpaved roads, grading or dragging.
In an effective system routine maintenance would be the core activity and emergency maintenance
would consume only a small portion of the budget.
This is not the current situation in Vanuatu.
In an effective system, the order of priority of maintenance activities would be as follows:
1. Routine drainage works including clearing of ditches, clearing of culverts, clearing of
bridges, clearing of river channels, repairs of erosion damage, repairs to scour checks and
other minor drainage structures, repairs of culverts and other large structures, repairs of
embankment slopes, etc.,
2. Routine pavement works including filling of potholes, repairs to shoulders, etc.,
4 maintenance cannot be carried out on too badly damaged sections
25
a detailed condition inventory of all the roads in the Province, with classification according to the
Road Act;
an assessment of the cost of putting the core network into a maintainable condition;
26
16.2 Annex : list of all PWD equipment with condition (May 2006)
Beyond repair and very old equipment are still on the inventory due to public management rule of depreciation.
Management
No.
TND7
Bull Dozer
Excellent
Cost of Service to
Location
date
o
Tanna
SCD2
Bull Dozer
18
breakdown
03/2006 to date
Santo
MCD6
Bull Dozer
18
Breakdown
24/02/2006
Malekula
TCD9
Bull Dozer
18
breakdown
2004 to date
Sola
MHD5
Bull Dozer
19
Breakdown
19.05.05 to date
500 000
Malekula
SHD3
Bull Dozer
19
breakdown
Santo
MHD4
Bull Dozer
19
Beyond repair
since 2000
Malekula
PCD8
Bull Dozer
22
breakdown
Since 1998
Ambae
TCD6
Bull Dozer
22
Breakdown
2004 to date
6 000
Vila
SICT20G453
Cargo Truck
Good
51 780
Santo
SICT19G452
Cargo Truck
breakdown
Dec05 to date
Efate
SNCT21G360
Crane Truck
breakdown
Jan06 to date
Efate
SCCT22G598
Crane Truck
breakdown
Beyond repair
Santo
MJB4
Malekula
TWB5
Good
dec 05 to date
200 000
Tanna
STB2
Good
Efate
SJB3
breakdown
N0v.05 to date06
35 975
Santo
SKB1
Operational
8wks
Efate
PJB8
breakdown
Jan06 to date
Ambae
MJB4
20
Fair
Malekula
TJB6
20
Beyond repair
Tanna
Sold by tender
Type
Age
Period of
Breakdown
Condition
0,09 Excellent
Comment
Ripper bolts
waiting parts
Waiting spare parts
currently repairing the equipment
Reassembling engine
waiting to run test engine
Tender process
waiting for parts
Waiting repair
Palikolo road works
Waiting spare parts
Still waiting for Parts & Funds
Tender process
Shutdown not in use
Parts wait shipment Vila /Tanna
Collecting rubbish (municipal)
Waiting for parts
Under repair
MNHG7
Motor Grader
Excellent
Malekula
On Road works
SKG2
Motor Grader
Good
N-Epi
SMG4
Motor Grader
Fair
29 630
Santo
SKG1
Motor Grader
Good
Efate
PCG9
Motor Grader
Good
Ambae
TMG8
Motor Grader
10
Good
20 000
Tanna
SAG3
Motor Grader
17
Good
Efate
MAG6
Motor Grader
18
Good
315 000
Malekula
PAG10
Motor Grader
20
breakdown
Since 2005
Ambae
TAG11
Motor Grader
20
Beyond repair
Ambae
SCG5
31
Good
100 642
Santo
ATP1G652
Motor Grader
Pickup Truck
0,01 Excellent
Vila
STP19G638
Pickup Truck
0,02 excellent
Santo
ATP2G627
Pickup Truck
0,05 Excellent
Ambae
ATP2G761
Pickup Truck
0,05 Excellent
H.Office
MMIP24G596
Pickup Truck
Excellent
27
Malekula
TMIP28G597
Pickup Truck
excellent
Tanna
TTP27G577
Pickup Truck
excellent
Tanna
STP10G458
Pickup Truck
Good
South Epi
SHP18G459
Pickup Truck
breakdown
30/04/06 to date
Santo
TTP26G435
Pickup Truck
Fair
63 000
STP14G249
Pickup Truck
Good
11200
Santo
STP16G357
Pickup Truck
breakdown
24/04/06 to date
Santo
SMIP8G390
Pickup Truck
Good
Efate
TTP32G395
Pickup Truck
Ok
Sola
STP15G355
Pickup Truck
Breakdown
113 950
Santo
working
Road works west Ambae, weld hyd
pipe
Green hill road Clearance road verges
Waiting gear box & to be transferred
road works with out brakes
Waiting motor seal
Under write off process
Fanafo road works
Admin project unit
Carrying out Administrative work
Admin duties
Admin duties
Project s Admins
Admin activities
Admin activities
Mobil unit road activities
Waiting tender board of survey
Road works green hill
UBS works
Under repair wait parts
Housing operation / Mobil unit
Administration activities
Waiting parts
SNP9G359
Pickup Truck
Good
Efate
Administration duties
MTP23G389
Pickup Truck
Good
15 000
Malekula
MTP22G388
Pickup Truck
Good
12 000
Malekula
Road works
Workshop activities
STP17G539
Pickup Truck
fair
Santo
TTP25G472
Pickup Truck
Good
16 000
Tanna
STP7G258
Pickup Truck
operation
Efate
MTP22G472
Pickup Truck
Good
Malekula
STC13G9
Pickup Truck
breakdown
Santo
PTP30G485
Pickup Truck
Good
Ambae
PMIP29G315
Pickup Truck
Beyond repair
Ambae
AMAP3G486
Pickup Truck
Good
Efate
STC12G147
Pickup Truck
Beyond repair
Santo
ATP4G530
Pickup Truck
breakdown
Efate
STP6G233
Pickup Truck
Good
N-Epi
STP11G655
Pickup Truck
10
Beyond repair
Santo
TDP31G116
Pickup Truck
13
Beyond repair
Gaua
MTP20G653
Pickup Truck
13
breakdown
28.3.06
95 000
Malekula
SDP5G164
Pickup Truck
13
Good
Efate
SMBST28G
Septic Truck
breakdown
Santo
SNT8G361
Tipper Truck
Good
Efate
PMT15G252
Tipper Truck
Breakdown
09-mars-06
Ambae
SIT7G380
Tipper Truck
10
Good
158 940
Santo
SHT5G543
Tipper Truck
10
Good
28 000
Torba
SIT6G379
Tipper Truck
10
Good
86 460
Santo
SHT3G540
Tipper Truck
10
Good
Santo
SHT4G813
Tipper Truck
10
Good
70 000
Efate
TKT18G682
Tipper Truck
10
Fair
2005 to date
Torba
Being repaired
PHT14G543
Tipper Truck
11
Good
Ambae
MBT9TG605
Tipper Truck
11
Fair
Malekula
Transfer to Santo
water truck no driver
MTT18G205
Tipper Truck
11
Ok
23 000
Malekula
MTT8G206
Tipper Truck
11
Good
18 000
Malekula
TTT12G552
Tipper Truck
12
Good
10 000
Tanna
TTT13G715
Tipper Truck
12
Good
28 322
Tanna
TTT11G550
Tipper Truck
12
Good
Tanna
SHT4G540
Tipper Truck
12
breakdown
4/4/06to
Santo
PHT9G538
Tipper Truck
12
Fair
TTT10G519
Tipper Truck
12
Good
382 000
Tanna
PMT16G253
Tipper Truck
15
Good
Ambae
PMT17G254
Tipper Truck
22
Good
Ambae
PHTL10
Track Loader
20
Beyond repair
Ambae
SFT4
Tractor
20
Beyond repair
Santo
SFT2
Tractor Septic
20
Breakdown
Efate
SFT1
Tractor Slasher
20
Good
Efate
TFT6
Tractor Slasher
20
breakdown
2003 to date
Tanna
MFT5
Tractor Slasher
20
Good
400 000
Malekula
SFT3
Tractor Slasher
20
fair
2 000
Santo
MDR4
Vibrating Roller
Excellent
Malekula
TDR5
Vibrating Roller
Excellent
Tanna
SAR1
Vibrating Roller
Breakdown
7mths
Efate
PAR6
Vibrating Roller
Ok
5hrs
Pentecost
mars-03
Vibrating Roller
Fair
200 000
Santo
works
SAR2
Vibrating Roller
breakdown
25 260
Santo
SIWT24G451
Water Truck
Good
160 180
Santo
SNWT23G362
Water Truck
Good
Efate
MJL6
Wheel Loader
Excellent
Malekula
STL3
Wheel Loader
Fair
285 850
Santo
TJL7
Wheel Loader
Beyond repair
6hrs
2million
Tanna
PJL9
Wheel Loader
Ok
Ambae
SKL1
Wheel Loader
17
Good
N-Epi
PDL8
Wheel Loader
18
Good
Ambae
SCL4
Wheel Loader
18
Fair
11 520
Santo
TAL11
Wheel Loader
22
Breakdown
2004 to date
Torba
SCL2
Wheel Loader
34
Beyond repair
13yrs
Efate
MCL5
Wheel Loader
34
Fair
Torba
Transmission problem
Distribution of water waiting road
works
CBD road cleaning
Loading quarry
Sara Road works
Being burnt
Road works west Ambae
With road works
Waiting plate, welding Rod
Road works
To fit hydraulic
To re-assemble parts
Santo to shipped to Banks
16.3.1 in English
Final report. Technical Assistance to the PWD Vanuatu. DHC consultants. 14 pages +
annexes.
Mukesh Gupta. Discussion Paper. Road Rehabilitation & Maintenance Strategy in Solomon
Islands. ILO. 9 pages.
Maintenance of minor roads using the lengthman contractor system. fifth international
conference on low Volume roads, Raleigh North Carolina, 19-23 May 1991. Republished by
world Bank 03/1997. 6 pages
Technical manual. Labour based road construction methods. Johannessen. 1997. 91 Pages.
Tor Hernes. Ghana Feeder Roads Improvement and Maintenance by Contract. Summary of
Training Needs Survey and Proposal for the Training at Wiawso of Contractors and DFR
Staff. ILO, 1987. 26 pages.
A Tractor and Labour based Routine Maintenance System for Unpaved Rural Roads. DDF &
Intech Associates. 06/2003. 17 pages.
32
16.3.2 in French:
Approche Micro. L'entretien par les communes. http://www.madagascarcontacts.com/himoroutes. Ministre des Travaux Publics de Madagascar. NORAD OIT.
Louis Fernique. Financement de l'entretien routier et gestion des fonds d'entretien routier.
Expos. ENPC, 06/2004. 19 pages.
5 TRL Limited (Transport Research Laboratory) UK TRL is an independent, internationally recognised centre of
excellence in surface transport issues. For more than 60 years TRL has worked closely with customers in the public,
private and independent sectors of the UK and world-wide. http://www.trl.co.uk
33