(Assessment for ground improvement Works at Carbon Capture and
Storage (CCS) project at ICAD-1, Abu Dhabi
(Main Contractor: Dodsal)
Client: MASDAR & ADNOC
Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 1
Contents 1. General ................................................................................................................................ 2 2. Site Location & Brief ............................................................................................................ 2 3. Scope of Work: .................................................................................................................... 2 3.1. Ground Improvement .......................................................................................................... 2 4. Bill of Quantities .................................................................................................................. 4 5. Soil Investigation Report ..................................................................................................... 6 6. Commercial Payment Terms ............................................................................................... 7 7. Duration of the Project ........................................................................................................ 7 8. Submission Procedure ......................................................................................................... 7 9. Responsibility Matrix for ground improvement: ................................................................. 8
Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 2
1. General
We have prepared an assessment for the Ground Improvement works by using Stone Columns based on the Enquiries we have received from M/s Dodsal, Abu Dhabi.
Total Area of Ground Improvement 24,700 Sq.m
2. Site Location & Brief
The site is located in ICAD-1, Abu Dhabi.
3. Scope of Work:
3.1. Ground Improvement
Main Contractor requested to submit our offer based on two Options, Option-1 by using stone columns and Option-2 by dynamic replacement.
Emirates Steel Factory ESNAD Ground Improvement Area Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 3
The total area is around 24,700 sq.m. The allowable bearing pressure required is 200Kpa for Plot Area- 130m x 190m
190.0m 130.0m 190.0m Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 4
4. Bill of Quantities
The bill of Quantities provide for the both Options are as follows: OPTION-1- By using Stone Columns
Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 5
OPTION-2- By using Dynamic Replacement
Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
Rev 0, Dated 27-05-2014 Page 6
5. Soil Investigation Report
In this area there are 6 bores holes conducted to a maximum depth of 20m and some trial pits. As per the soil investigation report, the following is the summary for general information, for detailed information one has to go through the Soil report.
Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal
In general the top strata is Silty Sand with traces of clay upto 9.0m and very dense Silty sand from 9 to 11.0m and Mudstone starts from 11.0m, with UCS varies from 0.25MPa to 3.15MPa.
6. Commercial Payment Terms
1. 5% Advance Payment 2. Performance guarantee 10%, validity until Jan 31 st 2019. 3. 10% Rention shall be released after receipt of completion certificate.
7. Duration of the Project
Total duration is 45days for construction of Stone Columns.
8. Submission Procedure
1. Technical Bid- 3 sets
2. Unpriced Commercial Bid- 1 set
3. Priced Commercial Bid- 1 set Al Dhafra Pipe Line and Contracting WLL Project: Ground Improvement works Client: Dodsal