Sno.

Item Attribute Guideline Observation ACTIVITY PERFORMED REQUIREMENTS


CHECK
1
FREE
MOUNTING
POLE
Free mounting pole
present
3 mtrs length mounting pole
If No proceed to 2
Mounting Pole 1
Mounting Pole 2
Mounting Pole 3
2
MOUNTING
POLE
Space availability
assessment
Airtel preferred height for free
mounting pole is 18 to 25 Mtrs
3G antenna will be always below
1800 Mhz antenna
3 GANTRY
Gantry support
available
Cubes available to support the Gantry
be made available
20 cm cubes to give a height to the
gantry
Space availability for
Gantry
Check plinth availability for 3G
equipment (2.5 mtrs X 3.5 mtrs X 0.3
mtrs)
Space should be unobstructured
Should be closer to the equipments
ATTACH PIC
4 CANOPY
Space Availability for
Canopy
Gantry Space should have enough
clearing for canopy (3 mtrs
approximately)
5 DCDB Mark space for DCDB To be mounted on side of the PLINTH ATTACH PIC
6 DG DG capacity Record DG capacity
7
POWER
PLANT/IPMS
Rectifier Modules
Number of Rectifier modules
Make and Model
Free 63 AMPS DC breaker availability
8 EARTHING OGB to be identified
Check availability of Grounding bar
for Equipment Grounding
Length of Grounding
Cable
From grounding bar to the DCDB and
to the BTS equipment
Mention height at
which they are
Comprehensive SOW and Checklist for 3G upgrade_Airtel
Signature and Date of person
doing TSS
Name of the Company
PLEASE SUBMIT A SITE LAYOUT : Dimensions and position of GANTRY, DCDB and PLINTH
Sno. Item Attribute Guidelines Observation ACTIVITY PERFORMED REQUIREMENTS
CHECK
1 TSS SURVEY
Assess the space
availability
Refer the TSS survey to assess space availability to fix
mounting poll
2
MOUNTING
POLE
Installation of
mounting polls with
brackets as per TSS
survey
Check for verticality
Poles are properly mounted and fitted firmly on the body of
the tower
They should be at the same height AS FAR AS POSSIBLE
ATTACH PIC
3 PLINTH Making the PLINTH Refer TSS report to assess space availability
Excavate Excavate 2.55 X 3.55 X 0.3 Mtrs Deep ATTACH PIC
Rebar
Bend the Y-10 Rebar to conform to 200 mm spacing as per
rebar schedule in attached design document. Position and
Click photo
ATTACH PIC
Form Work
Do form work accoring to the excavated space.
Properly nailed and firm. Form work wood used should be
thick enough (ATLEAST 3/4 INCH) to hold the concrete
being poured and avoid any disforming in plinth.
Form work to include two sleepers over plinth dimensions
3.5 X 0.35 X 0.5 Mtrs with distance between them 0.3 mtrs
ATTACH PIC
Concrete Mixing
Mix concrete in the ratio of 1:2:4 (Cement, Sand and
Granite)
Cubes Making for
Gantry Support
Make three cubes with the mixed concrete of dimension 20
X 20 X 20 cms
ATTACH PIC
PVC pipe in Plinth Insert PVC pipe 100mm diameter (Justina to Get Clarity)
Concrete Pouring
Pour concrete in the Form Work. Level it well for clean and
firm plinth. Leave it for curing
ATTACH PIC
Canopy Installation Drill and Bolted secured firmly on the plinth ATTACH PIC
4 GANTRY Positioning of Gantry
Refer TSS report to assess space availability
Place the three concrete blocks equidistant to support the
gantry
Install the Gantry. Should be secure and firm
Grounding the Gantry
Put the bus bar tighten on the gantry to loop the 70 mm
earthing cable. Ground the gantry using a 70 mm earthing
(Green and Yellow) cable to the nearest grounding bar.
Ensure feeder cables are properly laid and secured in the
Gantry. Gantry should be well covered.
INCLUDE TIN SHEET TO SUPPORT THE CABLE at the "L"Joint
by placing it underneath
ATTACH PIC
5 DCDB
Positioning and
Installation
Refer TSS to assess space for DCDB
Fix Bolt on side wall of the plinth
Install one 63 Amps and 4 - 32 Amps breakers inside DCDB.
Secure by nuts and bolts
Ground the body of DCDB with 16 mm earthing cable to
nearest grounding bar
Bring DC power cable from existing DCDB through flexible
PVC conduit and terminate it to New DCDB 63 amps
breaker.
From 63 amps loop to power up remaining 4 - 32 amps
breakers
Check MCBs functioning via multimeter
Poles, Gantry, Canopies, to be purchased by Vendors from Suppliers standardised by Telenoetica
Comprehensive SOW and Checklist for 3G upgrade_Airtel
PLEASE SUBMIT A SITE LAYOUT : Dimensions and position of GANTRY, DCDB and PLINTH
Name of the Company
Signature and Date
of person doing TSS