Académique Documents
Professionnel Documents
Culture Documents
s
A
p
p
r
o
v
a
l
L
o
a
n
A
p
p
r
o
v
a
l
ractor
Project Supplier Sub
Contractor
Payment
Loan Repayment
Fig. 6. Contractors pre-nance (CPF) scheme.
628 M.P. Abednego, S.O. Ogunlana / International Journal of Project Management 24 (2006) 622634
company because it enables them to put the right person on
the right place and doing the right work.
Due to the companys reputation as an experienced and
procient tollway developer and operator, and also its sta-
tus as a state-owned enterprise, the nancial institutions
had no diculties trusting them and making a demanding
commitment. This condition became the nancial strength
for PT. Jasa Marga, thus increasing its nancial capabili-
ties. Therefore, PT. Jasa Marga is considered to have the
required capabilities and is more than willing to accept pro-
ject risks and will do their best to prevent or minimise the
consequences as long as the project is considered to be
nancially benecial.
4.2.3. Risk allocation strategy
According to Ward et al. [14], Edwards [15], and Flana-
gan and Norman [16], several conditions must be satised
to determine whether project risks have been properly allo-
cated or not. These conditions are:
Risk should be allocated to the party with the best capa-
bility to control the events that might trigger its
occurrence.
Risks must be properly identied, understood and eval-
uated by all parties.
A party must have the technical/managerial capability
to manage the risks.
A party must have the nancial ability to sustain the
consequences of the risk or to prevent the risk from
occurring.
A party must be willing to accept the risk.
However, these conditions are basically criteria that
must be evaluated against each party before allocating a
project risk to a particular party. In other words, it only
helps to determine where the risk should be allocated. On
the other hand, risk allocation strategy is more than just
deciding which party should accept the risk. It should go
beyond that. Proper risk allocation should also be able to
acknowledge the most appropriate time to allocate the risk
and provide an alternative solution. Therefore, besides just
determining which party (who) has the best capabilities to
accept the risk (what), the when and how factors should also
be considered to ensure proper risk allocation (Fig. 7).
Based on this perception, a risk allocation table is formed
using those four main factors to assess the actual risk allo-
cation strategy performed by the owner of this project as
well as providing the possible alternative risk allocation
strategy (Table 1).
Results from the risk allocation strategy assessment ver-
ied several issues. First, it provides evidence of the own-
ers actual capabilities to accept and control certain types
of risks. However, most of the time those risks were allo-
cated to another party. For example, the delay in the pro-
ject construction initiation was actually caused by the
inadequate results produced from the feasibility study as
well as lack of information from the owner regarding the
projects preparedness. This condition could have been pre-
vented if the project owner performs better planning and
applies information transparency during the project prepa-
ration stage. Instead, several modications in the construc-
tion methods were carried out and adjustments were made
during the construction stage, thus shifting the risk from
the project owner, who actually has the best capability to
control the risk in the rst place, to the contractor. More-
over, the implemented risk allocation strategy dealt with
the consequences of the risk by problem-solving approach
during the construction stage instead by preventive
approach during the preparation stage.
Another example concerns contractors incompetence.
The inability of a contractor to perform their share of duty
and responsibility in this particular project caused the
owner to select and assign an additional contractor to assist
contractors who under-performed. Again, the owner failed
to notice that this could have been prevented if they had
developed and implemented a better system for selecting
contractors as well as committing more time for the selec-
tion process to get the most qualied contractors.
However, all of the implemented risk allocation strate-
gies were not inappropriate. Since the owner acknowledged
the time limitation to complete the project and to prevent
or minimise the possibility of project delay due to the
unavailability of primary/main construction materials,
they developed a strategy during the preparation stage by
forming a special agreement with the suppliers of these
materials. The application of the CPF system can be con-
sidered as the best risk allocation strategy in this project.
The consequences of limited capital for the project were
overcome by developing a system which transfers the
responsibility to nance the project from the owner to
the contractors. The cash-ow and liquidity problems that
could have been experienced by the owner during the con-
struction stage were also prevented by the system because
Proper
Risk
Allocation
WHAT WHO
WHEN HOW
Risks to be
allocated
Willingness &
ability of a party
to accept risks
The right time
to allocate the
risk
Best strategy to
prevent/minimize
consequences
Fig. 7. Concept of proper risk allocation.
M.P. Abednego, S.O. Ogunlana / International Journal of Project Management 24 (2006) 622634 629
Table 1
Owners risk allocation strategy in the second stage Cipularang tollway project
Actual Risk (What) Suggestion
How When Who Category Detail Consequences Who When How
Application of value
engineering
Construction stage Contractors Construction
risks
Use of
preliminary
design to
develop the
detail design in
design-and-
build system
Additional design
work
Project owner
and design
consultants
Preparation
stage
Improve
coordination
between consultants
and owner
Practice longer
working hours
Additional design
and construction
cost
Multiple design
inspection and
evaluation
Practice 7 days/week
working days
Construction failure
Provide sucient
time allocation for
project design
Increased operation
and maintenance
cost
Conduct a more
thorough and
detailed feasibility
study
Project completion
delay
Application of value
engineering
Management of
constructions
primary/main
material
(reinforced steel
and concrete
girder)
Preparation stage Project owner and
contractors
Construction
risks
Delayed project
construction
initiation
Increase project cost Project owner Preparation
stage
Provide better
information
regarding project
preparedness
On-site construction
method
improvization
Construction stage Changes in project
planning
Conduct a more
thorough and
detailed feasibility
study
Practice longer
working hours
Changes in
construction
methods
Provide sucient
time allocation for
project planning
Practice 7 days/week
working days
Project completion
delay
Provide more
accurate project
estimation
Application of value
engineering
Construction stage Contractors Construction
risks
Unpredicted
project site
condition
Increase project cost Project owner Preparation
stage
Conduct a more
thorough and
detailed feasibility
study
On-site construction
method
improvization
Additional
construction work
Provide more
accurate project
estimation
Practice longer
working hours
Changes in
construction
methods
Practice 7 days/week
working days
Design modication
6
3
0
M
.
P
.
A
b
e
d
n
e
g
o
,
S
.
O
.
O
g
u
n
l
a
n
a
/
I
n
t
e
r
n
a
t
i
o
n
a
l
J
o
u
r
n
a
l
o
f
P
r
o
j
e
c
t
M
a
n
a
g
e
m
e
n
t
2
4
(
2
0
0
6
)
6
2
2
6
3
4
Assign additional
contractor to
assist the
contractors with
poor performance
Construction stage Project owner and
contractors
Construction
risks
Contractors
failure
Increase project cost Project owner Preparation
stage
Improve the system
and process of
selecting a
contractor
Time wasted to
search for additional
contractor and
selection process
Structural failure
Increase probability
of quality problems
Additional/extra
maintenance work
One year maintenance
period
Contractors Operation and
maintenance
risks
Construction
quality
Increase
maintenance cost
Project owner Preparation
stage
Provide sucient
time allocation for
project design
Reduce income/
prot
Consultants Construction
stage
Provide sucient
time allocation for
project planning
Proper project
control and
monitoring
Modify trac
management
within the city
Operation stage Regional government of
Bandung
Operation and
maintenance
risks
Insucient road
network
Trac jam in the
city of Bandung
Regional
government of
Bandung
Preparation
stage
Better coordination
with the central
government
Construction of an
overpass
Construction stage Complement the
regional
infrastructure
development plan
with the national
plan
Claim submission Construction stage and
operation and
maintenance stage
contractors Legal and
contractual risks
Inconsistent
contract
document
Disputes between
parties
Project owner Preparation
stage
Development of a
more balanced and
undiscriminating
contract document
Payment delay for
contractors
Transparency during
the discussion of
contract document
Project completion
delay
Increase project cost
Application of
contractor pre-
nance (CPF
system as a
nancial strategy]
Preparation stage Contractors and
nancial institutions
Financial risks Limited capital Project cancellation Contractors and
nancial
institutions
Preparation
stage
Application of
contractor pre-
nance (CPF system
as a nancial
strategy]
Project completion
delay
Cash-ow and
liquidity problems
(continued on next page)
M
.
P
.
A
b
e
d
n
e
g
o
,
S
.
O
.
O
g
u
n
l
a
n
a
/
I
n
t
e
r
n
a
t
i
o
n
a
l
J
o
u
r
n
a
l
o
f
P
r
o
j
e
c
t
M
a
n
a
g
e
m
e
n
t
2
4
(
2
0
0
6
)
6
2
2
6
3
4
6
3
1
the loan was made directly by the nancial institutions to
the contractors. Contractors were paid based on their work
progress achievement, and these loan debts would only be
acknowledged and eventually paid-back by the owner after
the project is completed and handed over to the owner.
Furthermore, the advantages obtained through the appli-
cation of CPF scheme are identied as follows:
It does not burden the project owners cash ow for the
whole construction phase.
The loan debt made by the contractor will only be
acknowledged by the project owner upon project
completion.
Financial guarantee from nancial institutions in terms
of interest rate.
All project costs and expenses are very well controlled
and monitored.
Reduce the probability of projects cost misuse by the
contractor.
Reduce time required to process payment
administration.
Provide nancial guarantee for contractors, thus
increasing productivity.
The loan interest will be calculated as soon as the project
begins, thus beneting the nancial institution.
Provide more time for project owner to plan and
develop loan repayment strategy towards nancial
institutions.
Based on the assessment of the acquired information, it
can be conrmed that even though the project owner has in
this case the best capabilities to accept and control the
risks, they failed to notice this condition most of the time,
thus resulting in an improper risk allocation time (when)
and target (who). Such action would then also inuence
the type of risk allocation strategy that will be implemented
(how), hence resulting in some form of chain reaction to
acknowledge a proper risk control. Inadequacy to control
a risk properly becomes visible if one or more of the follow-
ing occurs:
Inability to make the right decision at the right time.
Discriminative contract document which tends to pro-
vide more advantage to the project owner.
Misinformation.
Inability to provide the proper response.
Improper project planning and control.
Hierarchical relationship between the public and private
sector instead of partnership.
Ineectiveness and ineciency during construction and
operation stage.
Unsatised users.
Since most of the above circumstances occurred in this
project due to improper risk allocation, it can be concluded
that this project had not achieved good project governance.
Moreover, good project governance must be achieved to T
a
b
l
e
1
(
c
o
n
t
i
n
u
e
d
)
A
c
t
u
a
l
R
i
s
k
(
W
h
a
t
)
S
u
g
g
e
s
t
i
o
n
H
o
w
W
h
e
n
W
h
o
C
a
t
e
g
o
r
y
D
e
t
a
i
l
C
o
n
s
e
q
u
e
n
c
e
s
W
h
o
W
h
e
n
H
o
w
P
r
a
c
t
i
c
e
l
o
n
g
e
r
w
o
r
k
i
n
g
h
o
u
r
s
C
o
n
s
t
r
u
c
t
i
o
n
s
t
a
g
e
C
o
n
t
r
a
c
t
o
r
s
F
o
r
c
e
m
a
j
e
u
r
e
r
i
s
k
s
W
e
a
t
h
e
r
c
o
n
d
i
t
i
o
n
d
u
e
t
o
d
e
l
a
y
i
n
p
r
o
j
e
c
t
c
o
n
s
t
r
u
c
t
i
o
n
i
n
i
t
i
a
t
i
o
n
P
r
o
j
e
c
t
c
o
m
p
l
e
t
i
o
n
d
e
l
a
y
P
r
o
j
e
c
t
o
w
n
e
r
P
r
e
p
a
r
a
t
i
o
n
s
t
a
g
e
P
r
o
v
i
d
e
b
e
t
t
e
r
i
n
f
o
r
m
a
t
i
o
n
r
e
g
a
r
d
i
n
g
p
r
o
j
e
c
t
p
r
e
p
a
r
e
d
n
e
s
s
P
r
a
c
t
i
c
e
7
d
a
y
s
/
w
e
e
k
w
o
r
k
i
n
g
d
a
y
s
I
n
c
r
e
a
s
e
p
r
o
j
e
c
t
c
o
s
t
I
m
p
r
o
v
e
c
o
o
r
d
i
n
a
t
i
o
n
b
e
t
w
e
e
n
p
r
o
j
e
c
t
o
w
n
e
r
a
n
d
c
o
n
t
r
a
c
t
o
r
s
O
n
-
s
i
t
e
c
o
n
s
t
r
u
c
t
i
o
n
m
e
t
h
o
d
i
m
p
r
o
v
i
z
a
t
i
o
n
I
n
c
r
e
a
s
e
p
r
o
b
a
b
i
l
i
t
y
o
f
q
u
a
l
i
t
y
p
r
o
b
l
e
m
s
C
h
a
n
g
e
s
i
n
c
o
n
s
t
r
u
c
t
i
o
n
m
e
t
h
o
d
s
A
d
d
i
t
i
o
n
a
l
c
o
n
s
t
r
u
c
t
i
o
n
w
o
r
k
S
t
r
u
c
t
u
r
e
f
a
i
l
u
r
e
632 M.P. Abednego, S.O. Ogunlana / International Journal of Project Management 24 (2006) 622634
increase projects performance and project success. How-
ever, these were absent in this project and the project can-
not be considered as a resounding success in terms of both
management process and project governance.
4.3. Better project performance
In the following section, better project performance is
discussed using the case study on second stage Cipularang
tollway in Indonesia.
4.3.1. Project success
Financial achievements in terms of prot is considered
by PT. Jasa Marga as one of the most important elements
in determining the projects level of success due to its
change of status from being a government agent to a busi-
ness oriented enterprise. The other components considered
to have the same level of importance are project quality
achievement and on-time project completion. However, it
was discovered that there are other factors that have played
a signicant part in determining the success of this project.
According to PT. Jasa Marga, a tollway project can be
considered to be successful if it is functioning according
to its planned purpose of providing service to end-users sat-
isfactorily. Nevertheless, the success of a project cannot be
valued only by its nal product since there are several other
factors that need to be considered during the preparation
as well as construction stages of the project.
During the preparation stage, it is necessary for PT. Jasa
Marga to receive support from the Indonesian central gov-
ernment which could be in the form of government policy,
government warranty or provision of information regard-
ing the national infrastructure network development plan.
These kinds of supports would enable them to produce a
more accurate project estimate and prepare a more proper
project plan. Consequently, proper project estimates and
plannings are also considered to be signicant in determin-
ing the success of this project. Furthermore, good coordi-
nation between the parties involved in the project is also
essential to ensure an eective and ecient project develop-
ment process, which can be achieved if all stakeholders
have a sense of trust.
Another valuable component for ensuring project suc-
cess is to have a proper system for selection of the most
capable contractor for constructing the project. The term
capable does not only mean having technical expertise
and possessing sucient nancial strength, but also possess
a sense of professionalism which was actually lacking in
this project. This lack of professionalism inuenced the e-
ciency and eectiveness of the particular contractor, thus
aecting project performance. As mentioned previously,
information dissemination and communication system also
played an essential part along with the project development
process. Since it is important to distribute the information
to the right party at the right time, it is necessary for the
project to have a suitable communication system to accom-
plish this objective. However, in order to achieve a success-
ful implementation of the system, it must also be supported
by compelling managerial capabilities of human resources.
Moreover, continuous control over the construction pro-
cess as well as the project management process also plays
an essential part in determining project success. Continu-
ous monitoring of the work progress in the project, proper
control on all resources required for the project and main-
taining a constructive interaction within the project will
provide contribution to achieve a successful tollway
project.
4.3.2. Project eciency
During the construction phase, value engineering was
actively practiced by PT. Jasa Marga through construction
design simplication and the application of new and inno-
vative construction technology. Such application is
expected to increase the projects eciency without reduc-
ing its product quality level, thus able to function as its
intended purpose. In addition to that, the projects e-
ciency level was also maintained by balancing the required
design change within the available budget.
However, it was also discovered that the eciency level
in this project did not reach the expectation. One major
reason is because there was no distinct dierence in terms
of obligation and responsibility between the supervisory
consultants and construction management consultants,
thus more often than not; these two dierent consultants
performed the same scope of work. One way to improve
is to upgrade the specications and requirements that are
used for selection of the consultants, experts as well as
contractors.
Another issue that causes ineciency in this project is
the insucient time for design development and project
planning. As a result of the insuciency, PT. Jasa Marga
decided to adopt a design-and-build system in some parts
of the project to be able to proceed with time schedule.
However, since only a preliminary design was produced
from the projects feasibility study, it increases the uncer-
tainty level within the system because its detail design work
is based only on a preliminary design. Although there are
basically limited limitations in the design-and-build system,
the projects circumstances make it less appropriate to
implement in the particular project. Moreover, even
though this approach also enabled acceleration in the con-
struction process, it resulted in an additional cost for repair
and maintenance work as a trade-o.
Based on the above ndings, it can be conrmed that
this project experienced diculties not only in terms of
management or day-to-day issues, but the project had to
meet with problems that had long-term consequences. This
project suers some consequences which could have been
avoided if the source of these problems had been addressed
in the earlier phase of the project. Therefore, it conrms
and supports the ndings from the previous sections
regarding the necessity for implementation of a strategic
approach in a form of good project governance that can
help achieving proper risk allocation in PPP projects.
M.P. Abednego, S.O. Ogunlana / International Journal of Project Management 24 (2006) 622634 633
5. Summary
In order to make sure a better project performance, sus-
tainable partnership must be obtained by the public (gov-
ernment) and private sectors by applying long-term
(strategic) planning through proper risk allocation in addi-
tion to short-term planning (management approach). How-
ever, in order to achieve this, both parties must rst have a
better understanding of proper risk allocation since it will
enable them to implement the most appropriate risk alloca-
tion strategy.
The case study experienced day-to-day issues which are
considered as short-term problems as well as long-term
issues which can only be solved through strategic approach.
These ndings conrm the necessity for implementation of
a strategic approach to combine both strategic and manage-
ment approaches so that the strategic approach enhances
the performance of a project in this nature. In eect, it
results in the development of good project governance.
6. Conclusions
The good project governance concept is developed since
projects under PPP procurement system experienced strate-
gic (long-term) problems in addition to the typical manage-
ment (short-term) problems. In this project the owner tends
to work with the project risks as soon as the threats of con-
sequences emerge. Generally, solutions are sought through
the application of new construction methods, on-site design
simplication, etc., to cope with particular problems during
the construction stage. Although those solutions were more
or less ecacious, it would have been better if preventive
actions had been taken. Even though the problems were
solved and the project was nished within the schedule,
actions such as on-site construction, method modication
and design simplication during the construction stage
resulted in additional project costs. These additional costs,
in eect, aect negatively the long-run maintenance costs.
These ndings demonstrate that the owner considers that
the risk had been properly allocated as long as its conse-
quences can be minimised and show that risk management
strategy is more into problem-solving rather than preven-
tive actions.
The signicant success factors considered by the owner
for this particular project are government support, proper
project planning, good coordination between parties, trust,
good tendering system, proper information dissemination
and communication system and high managerial
capabilities.
The ndings from this case study also provide evidences
that proper risk allocation can only be achieved if it consid-
ers the type of risk (what) to be allocated, which party
should accept the risk (who), when to allocate the risk as
well as application of proper strategy to prevent or mini-
mise its consequences (how). If the involved parties in such
project failed to acknowledge this, it will result in an
improper risk control. Incapability to control risk properly
will be reected in absence of good project governance,
thus resulting in an unsuccessful project. There are eight
main criteria that need to be performed to achieve good
project governance: right decision at the right time, con-
tract fairness, information transparency, responsive, con-
tinuous project control and monitoring, equality,
eectiveness and eciency, and accountability.
Since this project is a public infrastructure project pro-
cured under PPP, it had to work with tactical issues as well
as strategic issues. Therefore, the project must be assessed
in terms of its project management process and its output
achievement. These are indicated in a good project gover-
nance to determine project success.
References
[1] Ng B. Privatization of ethnic wealth redistribution in Malaysia:
experiences and lessons for developing countries. In: Montanheiro L,
Linehan M, editors. Public and private sector partnerships: the
enabling mix. Sheeld: Sheeld Hallam University; 2000. p. 4617.
[2] Sindane J. Publicprivate partnerships: case study of solid waste
management in KhayelitshaCape Town, South Africa. In: Montan-
heiro L, Linehan M, editors. Public and private sector partnerships:
the enabling mix. Sheeld: Sheeld Hallam University; 2000. p.
53964.
[3] Tanninen-Ahonen T, PPP in Finland: developments and attitude. In:
Serpell A. editor. CIB W92 procurement system symposium. Santi-
ago, Chile; 2000. p. 6319.
[4] Li B, Akintoye A. An overview of publicprivate partnership. In:
Akintoye Akintola, Beck Matthias, Hardcastle Cli, editors. Public
private partnerships: managing risks and opportunities. School of the
Built and Natural Environment. Glasgow Caledonian University,
Blackwell Science; 2003.
[5] Baietti A, Private infrastructure in East Asia: lessons learned in the
aftermath of the crisis, World Bank Technical Paper, No. 501,
Washington (DC); 2001.
[6] PT. Jasa Marga. Press Release Jasa Marga No. 05/2002.
[7] Hasanudin. Selayang pandang tentang proyek pembangunan jalan tol
Cipularang (An overview of the Cipularang tollway project devel-
opment), Majalah Teknik Jalan dan Transportasi, No. 105; February
2005.
[8] http://www.info-ri.com. Tol JakartaBandung mempersingkat waktu
tapi menambah beban di titik tertentu (The JakartaBandung toll-
road reduce traveling time but causes trac-volume increase in
several particular areas); March 21st, 2005.
[9] Baccarini D. The logical framework method for dening project
success. Project Manage J 1999;30(4):2532.
[10] Mueller Robert K. Changes in the wind in corporate governance. J
Business Strat 1981;1(4):814.
[11] Walker Anthony, Chau KW. The relationship between construction
project management theory and transaction cost economics, Engi-
neering. Construct Architect Manage 1999;6(2):16676.
[12] Standard & Poors Governance S. Standard & Poors corporate
governance scores: criteria, methodology and denitions. New York:
McGraw-Hill; 2002.
[13] Nur Wulan. Analisa kelayakan nancial proyek jalan tol: Studi kasus
jalan tol Cipularang (Feasibility study of toll-road project nancing: a
case study of the Cipularang tollway), Tugas Akhir No. 007/TS/D-IV
JT/111/2005, Politeknik Negeri Jakarta; 2005.
[14] Ward SC, Chapman CB. On the allocation of risk in construction
projects. Int J Project Manag 1991;9(3):1407.
[15] Edwards L. Practical risk management in the construction industry.
Engineering management series. London: Thomas Telford; 1995.
[16] Flanagan R, Norman G. Risk management and construction.
Oxford-Blackwell Scientic Publications; 1993.
634 M.P. Abednego, S.O. Ogunlana / International Journal of Project Management 24 (2006) 622634