Vous êtes sur la page 1sur 4

LTRC

Implementation Update
Research in Practice
Final Report 334 December 2007

Skip Paul, P.E.


Director, LTRC Evaluation of Bearing Capacity
Mark Morvant, P.E.
Assoc. Director, Research
of Piles from Cone Penetration
Sam Cooper, P.E. Test Data
Assoc. Director,
Technology Transfer
Introduction
Zhongjie “Doc” Zhang Knowledge about the underlying soil samples are assumed to be undis-
Research Manager is important in the design and con- turbed. However, sample distur-
Mike Boudreaux
struction of transportation infrastruc- bance is always possible during han-
Implementation Engineer tures. The Louisiana Department of dling, transportation and/or test
Transportation and Development preparation. Hence, the laboratory-
Murad Abufarsakh (LA DOTD) annually spends millions derived soil parameters may not
Principal Investigator of dollars on site investigation truly represent the in-situ conditions.
through subsurface exploration. The As an alternative to laboratory test-
quality of subsurface exploration di- ing, in-situ tests such as cone or pie-
Inside:
rectly impacts the quality and effi- zocone penetration tests (CPT/PCPT)
ciency of the design and construction (cont. page 2)
of foundations for bridges and other
Page 1 structures. The precast prestressed
Cone Penetration Test
concrete (PPC) pile is the primary
Data
foundation element used by LA
Page 2 DOTD to support its bridges.
Research Performed Conventional site investigation based
on soil borings and laboratory testing
Page 3
Research Results and is expensive and time consuming, of-
Recommendations ten requiring skilled, experienced
technicians. Laboratory testing is
Page 4 performed on small, intact samples
Implementation
extracted from the borings. These
4101 Gourrier Ave.
Baton Rouge, LA 70808 Fig. 1 Illustration of Cone Penetration Test System
http://www.ltrc.lsu.edu/pdf/
Pile-CPT-Final-Report.pdf Louisiana Transportation Research Center (225) 767-9131
can rapidly provide accurate and friction (and excess pore pressure tions of dense sand layers for pile
reliable results for assessment of when using the PCPT). These foundations. Soil borings were
the soil engineering properties. measurements can be used for taken during the design phase to
The CPT is a robust, simple, and detailed soil stratification and forestimate pile lengths and CPT
economical test that can provide determination of pile load capaci- tests were conducted during
continuous soundings of subsur- ties (Figure 2). bridge construction to better de-
face soil with depth. The CPT test fine pile tip elevations for plan
is conducted by advancing a cy- lengths. Additional research was
lindrical rod with a cone tip into Louisiana started implementation needed to better utilize the capa-
the soil (Figure 1). During the of the CPT technology in the mid bilities of the CPT technology.
test, the penetrometer measures 1980’s. Use of the technology was
the cone tip resistance and sleeve then limited to identifying elevat-

Research Performed
The Louisiana Transportation Re- of PPC piles that derive its pri- from pile load tests. The analysis
search Center (LTRC) has con- mary resistance from side friction. was conducted on the results of
ducted research to investigate the The CPT methods were Schmert- LA DOTD test piles with corre-
load capacity of PPC piles driven mann, DeRuiter/Berningen, Busta- sponding soil borings and CPT
into Louisiana soils. This project mante/Gianeselli (LCPC/LCP), soundings. A total of 35 friction
evaluated the performance of LA Tumay/Fakhroo, Aoki/De Alen- piles were compared during the
DOTD’s conventional alpha- car, Price/Wardle, Philipponnat, initial study with an additional 17
design method based on labora- and the penpile method. The pre- piles analyzed for verification of
tory results and eight CPT meth- dicted capacity was compared to results.
ods in predicting the load capacity load capacity results obtained
Cone resistance qc

qc1 + qc2
qt =
2
e
Depth

D
?
qc1 8D

'x'

c a
Envelope of
minimum qc values
q yD
b c2
b

Fig. 2 Soil Classification with LSC-CPT Schmertmann Method


2 LTRC
D

a=1.5 D
qca
0.7qca 1.3qca
Pile

a
a qc
D e p th

qeq
LCPC CPT Method
Fig. 3 Pile Prediction with LPD– CPT

Research Results
A statistical analysis and rank- capacity of PPC piles driven Pile Design by CPT, LPD-
ing criteria were used to com- into Louisiana soils. To facili- CPT). The program provides
pare the CPT methods and the tate the implementation of the the design engineers with pile
conventional alpha design CPT technology by LA DOTD ultimate capacity profile with
method. Based on the results, for pile design and analysis, depth (Figure 3). The LPD-
the de Ruiter/Beringen and these methods, along with the CPT and other CPT programs
LCPC methods showed the Schmertmann method, were are available for free
best capability in predicting coded into a Visual Basic MS- download on the LTRC Web
the measured load carrying Windows program (Louisiana site at www.ltrc.lsu.edu.

Research Recommendations
CPT technology should be util- tional subsurface exploration safety and performance of pile-
ized in subsurface exploration methods should be reduced, supported structures. Imple-
for soil identification and clas- and the use of CPT technology mentation of CPT technology
sification, as well as site strati- should increase. in pile design will reduce the
graphy. Test results from tra- level of uncertainties associ-
Cost-benefit analysis showed
ditional subsurface exploration ated with traditional design
that implementation of CPT
methods should be compared technology for prediction of methods.
to results interpreted from CPT pile capacity will result in cost
methods. With time and ex- reduction and time savings
perience, dependency on tradi- without compromising the

3 LTRC
Implementation Feasibility
Contracts from recent geotechnical same time period, four CPT tions are less susceptible to
exploration and engineering pro- soundings are possible. The most weather conditions.
jects were examined. When CPT significant advantage of CPT tech-
technology is utilized in lieu of a nology is that results are immedi-
conventional 200-ft depth soil bor- Cost-benefit analysis showed that
ately available, whereas the time
ing, an average cost savings of use of CPT methods for design/
required for laboratory testing of
$11,000 per boring is realized. samples from soil borings aver- analysis of square PCC piles can
Savings increase for over-water ages three weeks. reduce the cost of initial design as
exploration. Use of CPT technol- well as the cost of piling. CPT
ogy in lieu of an over-water soil soundings can be used to identify
boring saves more than $14,000. Also the effect of adverse weather location of dense sand layers for
on soil boring operations is more pile foundations, reducing the
costly than its effect on CPT need for more costly soil borings
A conventional land boring typi- soundings. Soil boring operations while providing the information
cally requires one workday for col- are typically discontinued during needed for accurate determination
lection of the soil sample. In that inclement weather. CPT opera- of required pile lengths.

Implementation Progress
Since the year 2000, CPT technol- One example of CPT implementa- Lake Pontchartrain, which was
ogy has been used with greater fre- tion is the site investigation for the damaged during Hurricane
quency for soil classification and LA 1 elevated bridge structure be- Katrina. This project used 30 soil
pile design on LA DOTD bridge tween Golden Meadow and Port borings and 80 CPT soundings.
projects. Current LA DOTD geo- Fourchon, which used 99 soil bor-
technical design guidelines require ings and 124 CPT soundings. Esti-
CPT soundings for each bridge mated savings due to the reduction The sand bearing strata varies tre-
project, subject to feasibility and in conventional borings exceed one mendously within many bridge
economics. CPT soundings have million dollars (124 x $11,000 = footings. Multiple CPT soundings
been used in lieu of soil borings at $1,364,000). are being taken at each footing to
more than 500 investigation points. increase the accuracy of the pile
Analysis of CPT data has allowed lengths. Cost savings are esti-
designers to reduce depth of CPT technology is also saving time mated to be over one million dol-
planned borings, and occasionally, and money on the reconstruction lars in pile lengths, pile cutoffs,
no borings are necessary at a site. of the I-10 Twin Span Bridge over and pile buildups.

Vous aimerez peut-être aussi