This document provides a two-week look ahead schedule from March 2-15, 2013 for inspection activities for the Yanbu Aramco Sinopec Refinery Project. It lists over 50 inspection activities across various disciplines including piping, welding, painting, and equipment. The inspections include tasks such as pre-installation checks, alignment verification, coating inspections, and welding inspections. The schedule provides details on the inspection number, description, week scheduled, reference standards, and assigned quality controller for each listed activity.
Description originale:
Titre original
2 Weeks Look Ahead RCL 2-March-2013 to 15-March-2013
This document provides a two-week look ahead schedule from March 2-15, 2013 for inspection activities for the Yanbu Aramco Sinopec Refinery Project. It lists over 50 inspection activities across various disciplines including piping, welding, painting, and equipment. The inspections include tasks such as pre-installation checks, alignment verification, coating inspections, and welding inspections. The schedule provides details on the inspection number, description, week scheduled, reference standards, and assigned quality controller for each listed activity.
This document provides a two-week look ahead schedule from March 2-15, 2013 for inspection activities for the Yanbu Aramco Sinopec Refinery Project. It lists over 50 inspection activities across various disciplines including piping, welding, painting, and equipment. The inspections include tasks such as pre-installation checks, alignment verification, coating inspections, and welding inspections. The schedule provides details on the inspection number, description, week scheduled, reference standards, and assigned quality controller for each listed activity.
141 Train 1 1 INSPECTION OF SUPPORT FOUNDATION FOR MISC PIPE RACK 1,2, T SUPPORTS SATIP-M-001-01 SAIC-M- 2006 H H W ANTOLIN ORAYA 141 Train 1 2 INSPECTION OF HIGH STRENGH BOLT TIGHTENING STRUTURE H SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 141 Train 1 3 INSPECTION OF ANCHOR BOLT TIGHTENING STR E&F,G SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 141 Train 1 4 ALIGNMENT OF MISC. PIPE RACKS SATIP-M-001-01 SAIC-M- 2007 I I S ANTOLIN ORAYA 141 Train 1 5 INSPECTION OF HIGH STRENGH BOLT TIGHTENING MISC PIPE RACK SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 141 Train 2 6 INSPECTION OF SUPPORT FOUNDATION FOR SULFUR COLLECTION DRUM,MISC PIPE RACK, T SUPPORT SATIP-M-001-01 SAIC-M- 2006 H H W ANTOLIN ORAYA 141 Train 2 7 ALIGNMENT OF STRUCTURE C,SUB PIPE RACK-2 MISC. PIPE RACKS,T SUPPORT SATIP-M-001-01 SAIC-M- 2007 I I S ANTOLIN ORAYA 141 Train 2 8 INSPECTION OF HIGH STRENGH BOLT TIGHTENING STRUTURE B,C SUB PIPE RACK-2 SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 141 Train 3 9 INSPECTION OF SUPPORT FOUNDATION FOR MISC PIPE RACK 1,2, TSUPPORTS SATIP-M-001-01 SAIC-M- 2006 H H W ANTOLIN ORAYA 141 Train 3 10 ALIGNMENT OF MISC. PIPE RACKS, STR E&F SATIP-M-001-01 SAIC-M- 2007 I I S ANTOLIN ORAYA 141 Train 3 11 INSPECTION OF HIGH STRENGH BOLT TIGHTENING STRUTURE E&F SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 140 12 ALIGNMENT OF STRUCTURE 140 MAIN PIPE RACK SATIP-M-001-01 SAIC-M- 2007 I I S ANTOLIN ORAYA 140 13 INSPECTION OF HIGH STRENGH BOLT TIGHTENING MAIN PIPE RACK SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA 142 14 ALIGNMENT OF STRUCTURE 140 MAIN PIPE RACK SATIP-M-001-01 SAIC-M- 2007 I I S ANTOLIN ORAYA 142 15 INSPECTION OF HIGH STRENGH BOLT TIGHTENING MAIN PIPE RACK SATIP-M-001-01 SAIC-M- 2009 I I W ANTOLIN ORAYA CLEANING 140 Area 1 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H S Karthikeyan AG Piping 140 Area 2 Pipe pre installation inspectin SATIP L-350-01 SAIC-L-2012 H H S Karthikeyan AG Piping 140 Area 3 Pipe laying, Pipe Spool Erection and assembly (double jointing on piperack/sleeperway) SATIP L-350-01 SAIC-L-2012 H H S Karthikeyan CLEANING 141 Train 1 4 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H S Karthikeyan AG Piping 141 Train 1 5 Pipe pre installation inspectin SATIP L-350-01 SAIC-L-2012 H H W Karthikeyan AG Piping 141 Train 1 6 Pipe laying, Pipe Spool Erection and assembly (double jointing on piperack/sleeperway) SATIP L-350-01 SAIC-L-2012 H H S Karthikeyan CLEANING 141 Train 2 7 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H S Karthikeyan AG Piping 141 Train 2 8 Pipe pre installation inspectin SATIP L-350-01 SAIC-L-2012 H H S Karthikeyan AG Piping 141 Train 2 9 Pipe laying, Pipe Spool Erection and assembly (double jointing on piperack/sleeperway) SATIP L-350-01 SAIC-L-2012 H H W Karthikeyan CLEANING 148 Area 10 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H S Karthikeyan AG Piping 148 Area 11 Pipe pre installation inspectin SATIP L-350-01 SAIC-L-2012 H H S Karthikeyan RCL Lay Down 12 Cutting & Asssembly Fitup SATIP-L-350-08 SAIC-L-2035 H H W Karthikeyan UG Piping 140 13 Inspection of Vent Piping Installation SATIP -S-20-01 SAIC-S-2001 H H W Karthikeyan UG Piping 140 14 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H W Karthikeyan UG Piping 140 15 Gravity Test of Sewer Piping SATIP -S-020-01 SATR-4001 H H H Karthikeyan UG Piping 142 16 Inspection of Vent Piping Installation SATIP -S-20-01 SAIC-S-2001 H H W Karthikeyan UG Piping 142 17 Internal Cleaning inspection of Piping spool SATIP L-350-01 SAIC-L-2017 H H W Karthikeyan UG Piping 142 18 Gravity Test of Sewer Piping SATIP -S-020-01 SATR-4001 H H H Karthikeyan RCL Lay Down 1 Prewelding Inspection SATIP-W-011-01 SAIC-W-2005 H H W VASUDEVA RCL Lay Down 2 In Process Welding Inspection SATIP-W-011-01 SAIC-W-2006 H W S VASUDEVA RCL Lay Down 3 Post Welding Inspection SATIP-W-011-01 SAIC-W-2007 H W W VASUDEVA RCL Lay Down 4 In-Process Verification of Techniques & Procedure Implementation SATIP-NDE-RT-01 SAIC-RT-2006 H W W VASUDEVA RCL Lay Down 5 Inspection of PWHT SATIP-W-011-01 SAIC-W-2004 H w W VASUDEVA RCL Lay Down 6 AWS D1.1 Pre-Welding/In-process /Post Welding Final Inspection (pipe support) SATIP-M-001-01 SAIC-M-2012 H I W VASUDEVA 141 Train 1/2/3 7 Prewelding Inspection SATIP-W-011-01 SAIC-W-2005 H H S BALA JEE 141 Train 1/2/3 8 In Process Welding Inspection SATIP-W-011-01 SAIC-W-2006 H W W BALA JEE 141 Train 1/2/3 9 Post Welding Inspection SATIP-W-011-01 SAIC-W-2007 H W S BALA JEE 141 Train 1/2/3 10 In-Process Verification of Techniques & Procedure Implementation SATIP-NDE-RT-01 SAIC-RT-2006 H W W BALA JEE 141 Train 1/2/3 11 Inspection of PWHT SATIP-W-011-01 SAIC-W-2004 H w S BALA JEE 140 Area 12 Prewelding Inspection SATIP-W-011-01 SAIC-W-2005 H H S BALA JEE 140 Area 13 In Process Welding Inspection SATIP-W-011-01 SAIC-W-2006 H W W BALA JEE 140 Area 14 Post Welding Inspection SATIP-W-011-01 SAIC-W-2007 H W S BALA JEE 140 Area 15 In-Process Verification of Techniques & Procedure Implementation SATIP-NDE-RT-01 SAIC-RT-2006 H W W BALA JEE 140 Area 16 Inspection of PWHT SATIP-W-011-01 SAIC-W-2004 H w S BALA JEE 142 Area 17 Prewelding Inspection SATIP-W-011-01 SAIC-W-2005 H H S BALA JEE 142 Area 18 In Process Welding Inspection SATIP-W-011-01 SAIC-W-2006 H W W BALA JEE 142 Area 19 Post Welding Inspection SATIP-W-011-01 SAIC-W-2007 H W S BALA JEE 142 Area 20 In-Process Verification of Techniques & Procedure Implementation SATIP-NDE-RT-01 SAIC-RT-2006 H W W BALA JEE 142 Area 21 Inspection of PWHT SATIP-W-011-01 SAIC-W-2004 H w S BALA JEE 148 Area 22 Prewelding Inspection SATIP-W-011-01 SAIC-W-2005 H H S BALA JEE 148 Area 23 In Process Welding Inspection SATIP-W-011-01 SAIC-W-2006 H W W BALA JEE 148 Area 24 Post Welding Inspection SATIP-W-011-01 SAIC-W-2007 H W S BALA JEE 148 Area 25 In-Process Verification of Techniques & Procedure Implementation SATIP-NDE-RT-01 SAIC-RT-2006 H W W BALA JEE 148 Area 26 Inspection of PWHT SATIP-W-011-01 SAIC-W-2004 H w S BALA JEE 141-E-1010 27 AWS D1.1 Application ,Pre-Welding/In-process /Post Welding Final Inspection SATIP-M-001-01 SAIC-M-2012 H I W BALA JEE 141-E-1025 28 AWS D1.1 Application ,Pre-Welding/In-process /Post Welding Final Inspection SATIP-M-001-01 SAIC-M-2012 H I W BALA JEE 141-E-0020 29 AWS D1.1 Application ,Pre-Welding/In-process /Post Welding Final Inspection SATIP-M-001-01 SAIC-M-2012 H I W BALA JEE 141-E-0020 30 AWS D1.1 Application ,Pre-Welding/In-process /Post Welding Final Inspection SATIP-M-001-01 SAIC-M-2012 H I W BALA JEE RCL Lay Down 1 Inspection of Surface Preparation & Prior to Application of liquid coating systems SATIP-H-100-01 SAIC-H-2027 H W S PHILIP RCL Lay Down 2 In-Process Inspection of Primer Coat OR First Coat Application SATIP-H-100-01 SAIC-H-2028 H w S PHILIP RCL Lay Down 3 Inspection of Primer Coat prior to top coating SATIP-H-100-01 SAIC-H-2029 H w S PHILIP RCL Lay Down 4 In-Process Inspection of Intermediate and/or Top Coat Application SATIP-H-100-01 SAIC-H-2030 H s S PHILIP RCL Lay Down 5 Inspection of Top coat Application SATIP-H-100-01 SAIC-H-2031 H w S PHILIP 141 A/B/C 6 Surface Preapiration inspection of repair of APCS-113A coating system SATIP-H-002-06 SAIC-H-2048 H H H PHILIP 142 A/B/C 7 DFT Testing of APCS-113A coating system SATIP-H-002-06 SAIC-H-2051 H H H PHILIP 143 A/B/C 8 Holiday Testing of APCS-113A coating system SATIP-H-002-06 SAIC-H-2016 H H H PHILIP Painting Welding RCL- Piping RCL- STRUCTURAL DAELIM INDUSTRIAL Co. LTD Yanbu Aramco Sinopec Refinery Project Co. (YASREF EPC-3) Contact No : YOE-YERP-6600024370(IK) Inspection Two (2) Weeks Look Ahead Schedule (2 March,2013 to 15 March,2013) Discipline # Activity Description Week 1 Week 2 SATIP No. SAIC No. Inspection level Assigned QC Date: 4-Mar-13 2 3 4 5 6 7 8 9 # # # # # # Sub-con Contractor YASREF DAELIM INDUSTRIAL Co. LTD Yanbu Aramco Sinopec Refinery Project Co. (YASREF EPC-3) Contact No : YOE-YERP-6600024370(IK) Inspection Two (2) Weeks Look Ahead Schedule (2 March,2013 to 15 March,2013) Discipline # Activity Description Week 1 Week 2 SATIP No. SAIC No. Inspection level Assigned QC 140-E-004 A 1 Preinstallation Inspection SATIP-E-004-01 SAIC-D-2006 H W S RICAFORT 140-E-004 A 2 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 B 3 Preinstallation Inspection SATIP-G-005-01 SAIC-M-2006 H W S RICAFORT 140-E-004 B 4 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 C 5 Preinstallation Inspection SATIP-G-005-01 SAIC-M-2006 H W S RICAFORT 140-E-004 C 6 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 D 7 Preinstallation Inspection SATIP-G-005-01 SAIC-M-2006 H W S RICAFORT 140-E-004 D 8 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 E 9 Preinstallation Inspection SATIP-G-005-01 SAIC-M-2006 H W S RICAFORT 140-E-004 E 10 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 F 11 Preinstallation Inspection SATIP-E-004-01 SAIC-D-2006 H W S RICAFORT 140-E-004 F 12 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 G 13 Preinstallation Inspection SATIP-E-004-01 SAIC-D-2006 H W S RICAFORT 140-E-004 G 14 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT 140-E-004 H 15 Preinstallation Inspection SATIP-G-005-01 SAIC-M-2006 H W S RICAFORT 140-E-004 H 16 Equipment Alignment and Elevation Check SATIP-E-004-01 SAIC-D-2007 H w S RICAFORT Mechanical