INSPECTION RELEASE CERTIFICATE

TWO (2) X 500MW MONG DOUNG 1 THERMAL POWER PLANT



NAME OF SUPPLIER : HYUNDAI HEAVY INDUSTRIES CO., LTD.
Purchase
Order No.
Item or Tag
No.
Quantity Description
Inspection &
Test Date
Inspection
Result
Released
VMON-
0014M-
4600041239
MD1-CEP-01 1 Barrel for CEP #1-A 27
th
Aug, 2013
Acceptable
MD1-CEP-02 1 Barrel for CEP #1-B 27
th
Aug, 2013

Acceptable

MD1-CEP-03 1 Barrel for CEP #1-C 27
th
Aug, 2013 Acceptable

MD1-CEP-04 1 Barrel for CEP #2-A 27
th
Aug, 2013 Acceptable

MD1-CEP-05 1 Barrel for CEP #2-B 27
th
Aug, 2013 Acceptable

MD1-CEP-06 1 Barrel for CEP #2-C 27
th
Aug, 2013 Acceptable

MD1-CEP-07 1
Pump Assembly for
CEP #1-A
27
th
Aug, 2013 Acceptable

MD1-CEP-08 1
Pump Assembly for
CEP #1-B
27
th
Aug, 2013 Acceptable

MD1-CEP-09 1
Pump Assembly for
CEP #1-C
27
th
Aug, 2013 Acceptable

MD1-CEP-10 1
Pump Assembly for
CEP #2-A
27
th
Aug, 2013 Acceptable

MD1-CEP-11 1
Pump Assembly for
CEP #2-B
27
th
Aug, 2013 Acceptable

MD1-CEP-12 1
Pump Assembly for
CEP #2-C
27
th
Aug, 2013 Acceptable

MD1-CEP-13 1 Motor for CEP #1-A 27
th
Aug, 2013 Acceptable

MD1-CEP-14 1 Motor for CEP #1-B 27
th
Aug, 2013 Acceptable

MD1-CEP-15 1 Motor for CEP #1-C 27
th
Aug, 2013 Acceptable

MD1-CEP-16 1 Motor for CEP #2-A 27
th
Aug, 2013 Acceptable

MD1-CEP-17 1 Motor for CEP #2-B 27
th
Aug, 2013 Acceptable

MD1-CEP-18 1 Motor for CEP #2-C 27
th
Aug, 2013 Acceptable

MD1-CEP-19 1
Suction Strainer for
CEP #1-A
27
th
Aug, 2013 Acceptable

MD1-CEP-20 1
Suction Strainer for
CEP #1-B
27
th
Aug, 2013 Acceptable

MD1-CEP-21 1
Suction Strainer for
CEP #1-C
27
th
Aug, 2013 Acceptable

MD1-CEP-22 1
Suction Strainer for
CEP #2-A
27
th
Aug, 2013 Acceptable

MD1-CEP-23 1
Suction Strainer for
CEP #2-B
27
th
Aug, 2013 Acceptable

MD1-CEP-24 1
Suction Strainer for
CEP #2-C
27
th
Aug, 2013 Acceptable

MD1-CEP-25 1 Embedded Parts 27
th
Aug, 2013 Acceptable

MD1-CEP-26 Items for Installation 9
th
Sep, 2013 Acceptable

VMON-
0014M-
4600041239
MD1-CEP-27 1
Paint for Touch-up
at Site
9
th
Sep, 2013
Acceptable

MD1-CEP-28 1 Special Tools 9
th
Sep, 2013 Acceptable

MD1-CEP-29 1
Spare Part for 2
years operation
9
th
Sep, 2013 Acceptable

MD1-CEP-30 1
Spare Part for 2
years operation
9
th
Sep, 2013 Acceptable

MD1-CEP-31 1 Lubricants 9
th
Sep, 2013 Acceptable


Released for
Completed Purchase Order
Partial Purchase Order - 100.00 % Release by this IRC
Total % Released to date 100.00%

Have the vendor submitted all drawing/data and approval given
Yes No

We hereby certify that the above mentioned item has been inspected and / or tested, and is
confirmed to be in conformity with the condition of the contract and released for shipment.

Signature of Inspector

Date of Issue 09
th
Sep, 2013

This certificate does not relieve the above mentioned vendor from the guarantees and
obligations set forth in the Purchase Order and attachments.