Vous êtes sur la page 1sur 10

METHOD STATEMENT FOR

SLURRY PLANT & GUIDE WALL


CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
1







PROPOSED DOWNTOWN LINE (DTL) PHASE 1 C907








METHOD STATEMENT FOR
SLURRY PLANT INSTALLATION
& GUIDE WALL CONSTRUCTION









Version: Initial Submission




METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
2

CONTENT

1. Introduction

2. Scope of Works

3. Essential Measures Prior to Work Commencement

4. Roles and Responsibilities of Key Personnel

5. Organization Chart

6. Curriculum Vitae

7. Site Safety

8. Health & Environmental Controls

9. Slurry Plant & Guide Wall Construction

9.1. Site Installation
9.1.1. Site Static Installation
9.1.2. Restricted Activities within the Railway Protection Zone
9.1.3. Site Mobile Plants
9.1.4. Temporary Site Installation
9.1.5. Earth Control Measures and Wash Bays

9.2. Guide Wall Construction
9.2.1. Guide Wall Construction Method
9.2.2. Essential Measures
9.2.3. Alternative to Elevated Guide Walls


10. Safe Work Practice


11. Appendix

A. Site Organization Chart
B. Key Personnel Curriculum Vitae
C. Site Utilization Plan, Silo Slab Design Calculation and Footing Anchorage
Details; Engineering Evaluation Report on Existing North South Line
Tunnel Section due to Silo Tanks Loading; Engineering Evaluation Report
on Existing North South Line Tunnel Section due to Bentonite Pond
Construction; Engineering Evaluation Report on Existing North South Line
Tunnel Section due to Machineries Loading.
D. List of Major Plant and Equipment
E. Plant and Equipment Catalogues
F. Guide Wall Settingout Cross-Section, Guide Walls Structural Adequacy
Check, Trench Stability Analysis
G. Risk Assessment


METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
3


1.0 Introduction

Diaphragm Wall is required for DTL Phase 1 C907 Landmark Station and Cut & Cover Tunnels,
constructed from ground level at approximately 103.0mRL ~103.5mRL to founding elevation at
38.0mRL ~45.0mRL, varied in thicknesses and depths at various locations according to load
bearing requirements and soil stratum.

This method statement shall describe the preceding work processes involve with diaphragm wall
construction, commencing from site installation till guide wall construction. Subsequent work
processes involve with diaphragm wall construction shall be separately addressed in the Method
Statement for Diaphragm Wall Construction.


2.0 Scope of Works

The scope of work involves setting up of slurry plant, guide wall construction for Cut & Cover
Tunnels (East & West) and Landmark Station under DTL Phase 1 Contract 907.


3.0 Essential Measures Prior to Work Commencement

3.1 Project Survey Control, Underground and Surrounding Structures Survey
It is imperative to establish Project Setting-Out Control, Existing Underground Structures and
Surrounding Development Survey, and incorporate the same with construction tolerances
provided in Section 9 of Particular Specifications into Propose Development Setting-Out Plans to
eradicate erroneous setting-out and prevent damage causes to the numerous vital underground
structures and utilities underlaying propose development. Setting out shall be carried out by
qualified surveyor.

3.2 Trial Trench
Trial trench shall be carryout by Licensed Cable Detection Worker along propose work to
ascertain physical layout and function [live, abandon] status of known utilities. Appropriate
measures [protection, diversion, termination, weep holes plugging, etc] shall be determined and
carryout prior to guide walls construction to ensure against underground utilities damages and
slurry outflow.

3.3 Restricted Activities in Railway Protection Zone and Common Service Tunnel
All works within the Railway Protection Zone and within 6m of Common Service Tunnel shall
adopt restricted activities guidelines stipulated in Code of Practice for Railway Protection and
Standard Operating Procedure for Works within 6m of CST Structure.





METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
4
4.0 Roles and Responsibilities of Key Personnel

The responsibilities of the key personnel are specified herein. The number of site personnel
will be provided according to production demand.

Project Manager - Plan and control overall project activity and budget,
- Prepare production schedule,
- Select and engage Subcontractors,
- Promote safety, quality and productivity

Construction Manager - Prepare work process methods,
- Engineering proposals with applicable measures,
- Temporary site installation structural adequacy checks and
submission to Relevant Authorities,
- Promote constructability, reduce waste and environment
pollution

Site Manager (s) - Requisite lifting appliances, construction accessories and
consumables products,
- Sequence work activities and resources availability,
- Provide safe working space,
- Work quality assurance

Site Engineer - Work process inspections,
- Coordinate all site activities,
- Prepare daily report, casting record, panel report,
consolidate data

Safety Supervisor(s) - Prepare and seek work process permits,
- Coordinate overall site activities
- Carryout and enforce safe work practice,
- Implement preventive measures to reduce risks and minimize
work accident
- Coordinate machinery and work processes
- Controlling of manpower

Draft Person - Coordinate dimensions, details,
- Prepare, submit and issue shop drawings
- Update amendments and as-built drawings

Purchaser - Ensure product specification conformance and supply
from reliable sources

Operator(s) -Service crane, grab, cutter, excavator slurry plant operators
conduct daily plant inspection and carryout works in their
specialization

Skill Worker(s) - Carrying out daily site activities.


5.0 Organization Chart
Propose Organization Chart is enclosed in Appendix A.

METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
5

6.0 Curriculum Vitae
Curriculum Vitae of the key personnel involve in this project is enclose in Appendix B.

7.0 Site Safety
Safety is an indispensable construction process. Diaphragm wall production carryout from
existing ground shall require work staffs to be provided with essential personnel protective
equipment (PPE) such as safety boots, hard hats and gloves to protect the operatives from
falling objects, hands abrasion, corrosive substances and hot works. High reflective vests
shall also be worn to highlight operative visibility to moving vehicles / plant, particularly during
night works.

Additional PPE example body harness, goggles, welding shields, filter masks shall be
provided to others working at height, or involved in specialize operations alike blazing and
welding works. All hot works shall be equipped with fire extinguisher.

All new work staffs shall attend Safety Induction Course prior to carrying out site work. This
process shall reinforce work staffs safety awareness and provide the opportunity to impart the
Restricted Activities on site.

Risk Assessment Report is enclosed in Appendix G.

Safety Supervisor shall concenciously carry out the following to promote site safety:
Issue personal protective equipment to work staffs with clear application instructions
and keep record of all safety protective equipments issued to work staffs.
Conduct toolbox meeting prior to the starting of work in the morning on a daily basis.
Ensure good housekeeping on site.
Refrain use of defective or worn lifting gears and tools and replace the same.
File and verify certificates validity of all the lifting machinery, lifting gear etc. and
inspect their condition worthiness.
Notify, conduct investigation and prepare Dangerous Occurrence and Accident
Reports.
Practice safe works inspection and attend Safety Committee Meetings.

8.0 Health & Environmental Controls

Noise
The construction equipment used for diaphragm wall works shall not exceed 65dbl Noise
limits set by the Ministry of Environment.

Air Borne Particles Control
Air pollution on site shall be effectively controlled through use of suitably power rated and
properly maintained diesel engines. Employ screw conveyor and automated bentonite
powder batching and mixing system to eliminate air borne pollution during bentonite mixing.
Situate bentonite bulk bag over opening of dry bentonite silo will stopple air borne pollution
during stock replenishment.

Waste and Recycling
The waste produced from this activity is limited to the use of Bentonite slurry. In order to
protect the environment, the bentonite shall not be discharged into the public drain and would
be disposed at the authorized disposal areas.

Pest Control
Maintain well drain working platform and drains free from stagnant water, reticulate stored
slurries will eradicate mosquito breeding. All trash bins shall be covered to prevent crows and
flies infestation. Conduct weekly inspection and carryout selective fogging and larvarciding.


METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
6


9.0 Slurry Plant Construction

9.1. Sequence of Work






COMMENCEMENT
SURVEY
CONFIRMATION
SURFACING
MOBILIZATION
TESTING
CHECKING
CAGE
EXCAVATION
REINFORCEMENT
CAGE
INTO POSITION
TREMIE PIPE
CONCRETING CONCRETING
WORK DONE
CONCRETING
STABILZER
EXCAVATION
WORK DONE DISPOSAL
SPOILS
SURVEY
REVIEW
COMMENCEMENT
PLANNING
APP. POWER/ WATER
BAR BENDING
PEINFORCEMENT REINFORCEMENT
WORKSHOP
MOBILIZATION
BENTONITE MIXTURE
SLURRY TREATMENT
FLOW CHART
RECOVERY OF
TREATMENT PLANT
SET UP OF SLURRY

METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
7
9.2. Site Installation

9.2.1. Site Static Installation

Main static installation include bentonite slurry plant (mixer, ponds, storage silos, desanding plant
and pumps); generators, site offices, workshops, store, changing rooms, steel storage and
fabrication yard. The Site Utilization Plan, Silo slab design calculation and footing anchorage
details are enclosed in Appendix C. The silo slab design shall be adopted for all remain static
plant experiencing lighter loading capacities.

The following procedures are applicable for slabs and walls construction and slurry plant erection:
Setout propose structure layout and determine slab elevation according to existing
ground level.
Remove top soils, lay, level and compact 300mm thick hardcore.
Lay required top and bottom steel reinforcement to slab with applicable spacer chairs to
maintain required covers.
Install adequately supported formwork shutters [with tie rods for walls] along propose slab
or wall layout.
Setout elevation markers at 3.0m x 3.0m intervals to maintain min. 300mm slab thickness
elevation during casting.
Place Grade 25 N/mm
2
ready mixed concrete through skips or concrete pump; vibrate
and trowel level to finish.
Provide adequate curing from 9 hours after casting.
Remove shutters after 24 hours, and proceed with propose silo and slurry plant layout
and orientation markings on slab.
Detect for presence of utilities prior to breaking ground and repeat the above steps and
for spoil pit walls construction.
Erect silos and slurry plants; properly orientated and aligned to receive pipe fittings.
Install pipes and fittings between silos, slurry plants and pumps, and extend pipelines with
control fittings to required workplace.

9.2.2. Restricted Activities within the Railway Protection Zone

The layout of plant, storage and office areas are captured in Site Utilization Plan enclosed in
Appendix C. The various Restricted Zones shall be visibly identified on plan and prominently and
sturdily set-out on site and Application for Verification of Reserve Lines & Drilling Positions
submitted for Authority verification and approval. All Restricted Activities within the Railway
Protection Zone and within similar zones to the Common Service Tunnel shall be effectively
addressed and permission obtained from the Authority prior to works execution. Engineering
Evaluation Report on Existing North South Line Tunnel Section due to Silo Tanks Loading and
Bentonite Pond Construction is enclosed in Appendix C.

9.2.3. Site Mobile Plants

Mobile plant consists of excavation rigs, backhoes, dump trucks, concrete trucks, service cranes
to hoist, splice and install steel reinforcement cages, stopends and concrete casting. The most
critical mobile plant loading from service crane and its vicinity from open trench is carryout to
determine platform capacity adequacy to undertake mobile plant loading. Engineering Evaluation
Report on Existing North South Line Tunnel Section due to Machineries Loading.is enclosed in
Appendix C. Meanwhile, all heavy machineries above 50-ton shall be kept away from the 2
nd

Reserve prior to the Authoritys grant of approval to access within the Restricted Zones. List of
Major Plant and Equipment is enclosed in Appendix D.


METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
8
9.2.4. Temporary Site Installation
All electrical installation shall be appropriately installed by Licensed Electrical Worker with
adequate earthing, and power plant shall be registered with Energy Market Authority prior to
operation. Diesel tanks shall be located within impermeable bund walls of adequate containment
capacity, and installation shall be registered with the Singapore Civil Defense Force for
Petroleum & Flammable Materials Storage Licensing. A list of fuel burning equipment together
with Temporary Bentonite Plant Installation shall be separately submitted to Pollution Control
Department, National Environment Agency. All lifting machines shall be Inspected and Certified
by Approved Persons prior to operation.

9.2.5. Earth Control Measures and Wash Bays
Earth Control Measures, treatment processes for rainwater and wash bay discharges shall be
separately addressed.


9.3. Guide Walls Construction

A pair of 0.30m thick x 1.20m deep concrete guide walls will be constructed along the near face
alignment of diaphragm wall with the other parallel leaf constructed at diaphragm wall thickness +
50mm clearance to provide sturdy reference for diaphragm wall works elevation, layout markings,
as well as guide to attain trench verticality during initial grab excavation. The guide walls shall
also sustain loads from steel reinforcement cages, stopends, tremie pipes and other equipment
suspended over the open trench. This concrete structure will further reduces soil erosion within
the splash-zone of open trench and soil raveling at trench opening highly susceptible to
mechanical notching.

The guide walls structural adequacy check, steel reinforcement details, wall thickness and depth
are enclosed in Appendix F. Trench stability analysis shall be referred for applicable guide wall
elevations.

Slurry elevations shall be maintained to at least 1m above the highest piezometric level and
guide walls will be provided to 0.20m above minimum slurry levels identified in the trench stability
analysis. The effects from equipment surcharges, widths of open trench, properties of underlain
soil stratum, piezometric level and slurry density are collectively analyzed to verify stability of
ground surrounding the open trench. Trench stability analysis is enclosed in Appendix F.

Where applicable wider open trench within the guide walls will be excavated to increase the
slurry head reservoir to minimize slurry spillage and head drop during introduction and
withdrawal of excavation equipment.

Cable detection works shall be carried out by a licensed cable detector, and report submitted to
the authority, together with Notice to Commence Excavation application. Excavation shall be
started only after Notice to Commence Excavation is approved.

9.3.1. Guide Wall Construction Method

The typical construction processes and sequence of guide walls are addressed herein.

Licensed cable detection worker shall ascertain propose layout of guide walls are free
from utilities, and Notice to Commence Excavation duly approved prior to carrying out
trench excavation.

Where existing utilities are detected the functional [live or abandon] status of such utilities
shall be verified and appropriate measures [protection, diversion and work sequencing,
termination, weep holes plugging, etc] shall be determined and implemented prior to
guide walls construction.

METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
9
Excavate to required depth and width of proposed guide walls after establishing setting
out alignment to proposed work.

Lean mix 30mm ~50mm thick, grade 10N/mm concrete to base of guide wall to provide
a firm base for guide wall formwork erection.

Re-peg positions of diaphragm wall with required tolerance and clearance from lean
concreted surfaces to provide reference for formwork erection.

Install 2 x 2 nos. of T40 steel reinforcement to bottom end of each guide wall; together
with 2 layers of A10 wire mesh [10mm x 200mm x 200mm square grid] along the faces
with 25mm concrete cover. All steel reinforcement shall be provided with 45 x bar
diameter laps.

Erect formwork along the peg alignment of proposed diaphragm wall with adequate
bracing to prevent dislodgement and distortion during casting.

Mark elevation to propose top of guide wall against the formwork to provide indication to
control elevation of guide walls during casting. Evenly introduce Grade 25N/mm concrete
into both sides of guide walls to avert displacement or movement of formwork.

Trim all under-sized inner face of guide wall until diaphragm wall thickness +minimum
25mm clearance tolerance is obtained if over-break occurs to guide wall inner faces.

Guide walls shall be constructed continuously and propped against internal faces to
reduce susceptibility to dislocation and movement. It shall be constructed against soil
faces and in firm medium.

Formwork to guide walls may be removed on the next working day or minimum12 hours
after casting. Introduce 50mm x 75mm timber props against opposite faces of constructed
guide wall at lower quarter and upper quarter at 3.0m interval before backfill with suitable
excavated soil to inner face of guide wall.



9.3.2. Essential Measures
It is imperative that essential measures in above Section 3 are addressed and approved prior to
guide walls construction to eradicate erroneous setting-out and ensure against underground
structures and utilities damages.

9.3.3. Alternative to Elevated Guide Walls
Enhanced trench stability afforded by raised slurry head from elevated guide walls will be
physically constrained by feasibility of works elevation and platform accessibility needs. Under
circumstances where increased piezometric level are caused by high ground water level within
the fill stratum, welling to reduce piezometric level may be considered a viable alternative to
substitute raising slurry and guide wall elevations to improve trench stability. Welling where
applicable shall be separately and appropriately addressed prior to works practice.







METHOD STATEMENT FOR
SLURRY PLANT & GUIDE WALL
CONSTRUCTION
DOWNTOWN LINE C907
For Approval
Mar 2008


Diaphragm Walls
Version 1 prepared by GWT
10

10.0 Safe Work Practice
To avoid any danger to life and health during diaphragm wall works the following
measures may be taken:
Protect all working and storage areas by temporary fencing clearly marking
any hazardous or dangerous areas, which shall be off limit to the public.
Cover up or protection of all trenches in progress or completed but not
backfilled during rest days and rest hours or fencing at least 1.5 m height.
Store safety and lock all tools & machinery during rest days.
Adequate platforms and lighting during night works.
Continuous maintenance and safety precautions on equipment and
machinery according to the manufactures recommendation.
Proper working attire to be worn by all persons engaged on site production.



10.1. Contingency Plan

In the unlikely event of a major trench collapse, the excavation will be immediately
back-filled with lean mix concrete. Excavation will only re-commence after a review
of and implementation of any necessary precautionary measures.

In the unlikely event of the sudden loss of bentonite slurry, the excavation will be
immediately stopped and back-filled with the excavated materials until the loss of
bentonite slurry is stopped. Excavation will only re-commence after a review of and
implementation of any necessary precautionary measures.






Saf etySupervisAmriqAl i98466798AlexCaesar98192652 J osephSew90672719Sitesuper Li m HongSuanJackNgSernLaiS Expatr iateOperator Y eou ngHayLun Chow KamTong Leun gKamHoi Ma chanicsand M ai ntai nanc Ch iaWayKeon Peter Yiu9114336 8181 8242
Saf etySupervisAmriqAl i98466798AlexCaesar98192652 J osephSew90672719Sitesuper Li m HongSuanJackNgSernLaiS Expatr iateOperator Y eou ngHayLun Chow KamTong Leun gKamHoi Ma chanicsand M ain tain anc Ch iaWayKeon Peter Yiu9114336 8181 8242

Vous aimerez peut-être aussi