This document provides a vendor data register list for a filter separator skid project. It contains:
1) An introduction with project details including title, package description, purchase order number, vendor, and job number.
2) A table listing 68 documents required to be submitted by the vendor, organized into categories including general documents, calculations, drawings, manufacturing/quality procedures, and test/inspection reports.
3) For each document, it provides information such as document number, description, type, discipline, sequence number, planned submission date, and review status.
The list is intended to provide a complete record of all required vendor submittals for the filter separator skid project.
Description originale:
Titre original
8382 3504 LG 8001 1_APEM Vendor Data Register List_Rev A
This document provides a vendor data register list for a filter separator skid project. It contains:
1) An introduction with project details including title, package description, purchase order number, vendor, and job number.
2) A table listing 68 documents required to be submitted by the vendor, organized into categories including general documents, calculations, drawings, manufacturing/quality procedures, and test/inspection reports.
3) For each document, it provides information such as document number, description, type, discipline, sequence number, planned submission date, and review status.
The list is intended to provide a complete record of all required vendor submittals for the filter separator skid project.
This document provides a vendor data register list for a filter separator skid project. It contains:
1) An introduction with project details including title, package description, purchase order number, vendor, and job number.
2) A table listing 68 documents required to be submitted by the vendor, organized into categories including general documents, calculations, drawings, manufacturing/quality procedures, and test/inspection reports.
3) For each document, it provides information such as document number, description, type, discipline, sequence number, planned submission date, and review status.
The list is intended to provide a complete record of all required vendor submittals for the filter separator skid project.
REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Rev. A
VI 1 Quality Control Procedure (Quality Plan) for Filter-Seperator Skid (FSS) IFR 2 Inspection and Test plan (ITP) for FSS IFR 3 Piping Fabrication and Installation Procedure IFR 4 Hydrotest and Flushing Procedure For Piping IFR Hydrotest and Flushing Procedure For Pressure Vessel 5 FAT Procedure IFR 6 Surface Preparation and Painting Procedure IFR 7 Radiography Testing Procedure for Pressure Vessel U stamp IFR 8 Radiography Testing Procedure for Structure & Piping 9 Ultrasonic Testing Procedure for Pressure Vessel U Stamp IFR 10 Ultrasonic Testing Procedure for Structure & Piping 11 Magnetic Particle Testing Procedure for pressure vessel U Stamp IFR 12 Dye Penetrant Testing for Pressure Vessel U Stamp IFR 13 Dye Penetrant Testing for Structure & Piping 14 Weight Procedure IFR 15 Dimension Check Procedure IFR 16 Radiation Safety Procedure IFR 17 Welding Procedure Specification & PQR IFR 18 Welder Qualification Record 19 NDT operator qualification VI Document No: 8382-3504-LG-8001/1 PROJECT TITLE: REDELIVERING THE WET GAS FROM NAM CON SON TERMINAL TO DINH CO GPP PROJECT VENDOR DATA REGISTER LIST PACKAGE DESCRIPTION: FILTER SEPARATOR SKID PO NO./CONTRACT NO: 13/2014/DAK-AECC/PC/WET GAS /X1 VENDOR: SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY JOB No. AL3017 Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Forecast Submission Date MANUFACTURING & QUALITY PROCEDURE TEST & INSPECTION REPORTS FOR STRUCTURE Deadline Remark Purpose Submit to PV GAS Rev. Return from PV GAS Rev Status Doc. No.: Rev.A Page 1 of 6 PETROVIETNAM GAS JOINT STOCK CORPORATION PVGAS PROJECT MANAGEMENT COMPANY REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Forecast Submission Date Deadline Remark Purpose Submit to PV GAS Rev. Return from PV GAS Rev Status 1 Material Receiving Inspection Report & Material Test Certificates ( MRIR) IFR 2 Material Traceability Records IFR 3 Fit-up & Visual Report IFR 4 Welding Traceability Record IFR 5 Dimension Control Report IFR 6 RT-Radioghraphic Test Report 7 UT-Ultrasonic Examination Report IFR 8 MT-Magnetic Particle Examination Report IFR 9 PT-Dye Penetrant Testing Report 10 Painting Report IFR 11 Hydrotest Report IFR 12 Leak Test Report IFR 13 Insulation Report IFR 14 Form U1A report for vessels IFR 15 FAT Report IFR 16 Inspection Release Note Note: IFR - Issue For Review, IFI - Issue For Information, N/A Not Available Review Status: -1. Approved: -2. Approved with comment: -3. Rejected: -4. For Information: -5. Hold Doc. No.: Rev.A Page 2 of 6 PETROVIETNAM GAS JOINT STOCK CORPORATION PVGAS PROJECT MANAGEMENT COMPANY REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Rev. A
I 1 8382-3504-LG-8001/1 Vendor Data Register List (VDRL) LG 8001/1 IFI 2 8382-3504-LG-8002/1 Fabrication/Production Schedule for Filter Separation Skid LG 8002/1 IFI 3 8382-3504-LG-8003/1 List Equipment welding Machine & Lifting Calibration LG 8003/1 IFI 4 8382-3504-LG-8004/1 Active Welder Qualification Register For Structure LG 8004/1 IFR 5 8382-3504-LG-8005/1 Active Welder Qualification Register For Piping LG 8005/1 IFR 6 8382-3504-LG-8006/1 Material / Equipment Procurement Plan MG 8006/1 IFI 7 8382-3504-LG-8007/1 Organization Chart GP 8007/1 IFI II 8 8382-3504-CA-8001/1 Structure Calculation for Filter Separation skid CA 8001/1 IFR 9 8382-3504-CA-8002/1 Lifting Calculation for Filter Separation skid CA 8002/1 IFR 10 8382-3504-CA-8003/1 Mechanical design Calculation for Filter Vessels CA 8003/1 IFR 11 8382-3504-CA-8004/1 Lifting Calculation for Filter Vessels CA 8004/1 IFR 12 8382-3504-CA-8005/1 Process Calculation CA 8005/1 IFR III 13 8382-3504-DS-8001/1 General Arrangement Drawing for Filter Vessels DS 8001/1 IFR 14 8382-3504-DS-8002/1 General Arrangement Drawing for Filter Separator Skid DS 8002/1 IFR 15 8382-3504-DS-8003/1 Fabrication Detail Drawing For Filter Vessels DS 8003/1 IFR 16 8382-3504-DS-8004/1 Fabrication Detail Drawing For Filter Separator Skid DS 8004/1 IFR 17 8382-3504-DS-8005/1 Weld map for Struture DS 8005/1 IFR 18 8382-3504-DS-8006/1 Weld Map For Filter Separator Skid DS 8006/1 IFR Weld Map For Filter Vessels DS 8006/1 IFR 19 8382-3504-DS-8007/1 Name plate drawing for Filter Vessels DS 8007/1 IFR 20 8382-3504-DS-8008/1 Name plate drawing for Filter Separator Skid DS 8008/1 IFR Lifting Arrangement Drawing For Filter Vessel JOB No. 8382-3504-LG-8001/1 REDELIVERING THE WET GAS FROM NAM CON SON TERMINAL TO DINH CO GPP PROJECT FILTER SEPARATOR SKID 13/2014/DAK-AECC/PC/WET GAS /X1 SOUTHERN PETROLEUM CONSTRUCTION J.S COMPANY AL3017 VENDOR DATA REGISTER LIST Document No: PROJECT TITLE: PACKAGE DESCRIPTION: PO NO./CONTRACT NO: VENDOR: Deadline Return from PV GAS Rev. Remark Rev Status GENERAL DOCUMENT DRAWING FOR STRUCUTRE CALCULATION Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Submit to PV GAS Forecast Submission Date Purpose Doc. No.: Rev.A Page 3 of 6 PETROVIETNAM GAS JOINT STOCK CORPORATION PVGAS PROJECT MANAGEMENT COMPANY REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Deadline Return from PV GAS Rev. Remark Rev Status Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Submit to PV GAS Forecast Submission Date Purpose Lifting Arrangement Drawing For Filter Separator Skid IV 21 8382-3504-DX-8001/1 Drawing For Piping Support DX 8001/1 IFR 22 8382-3504-DX-8002/1 Piping Isometric drawing for Filter Separator Skid DX 8002/1 IFR V 23 8382-3504-DE-8001/1 Drawing For E&I Support DE 8001/1 IFR 24 8382-3504-DE-8002/1 Electronic Cable Details DE 8002/1 IFR 25 8382-3504-DE-8003/1 Wiring Diagram for Filter Separator Skid DE 8003/1 IFR 26 8382-3504-DE-8004/1 Cable tray layout drawing DE 8004/1 IFR VI 27 8382-3504-YQ-8001/1 Quality Control Procedure (Quality Plan) YQ 8001/1 IFR 28 8382-3504-YQ-8002/1 Inspection and Test plan for Structural Skid YQ 8002/1 IFR 29 8382-3504-YQ-8003/1 Inspection and Test plan for Piping Skid YQ 8003/1 IFR 30 8382-3504-YQ-8004/1 Inspection and Test plan for Coating YQ 8004/1 IFR 31 8382-3504-YQ-8005/1 Welding Consumable Control Procedure YQ 8005/1 IFR 32 8382-3504-YQ-8006/1 Welding Control Procedure YQ 8006/1 IFR 33 8382-3504-YQ-8007/1 Post Weld Heat Treatment Procedure YQ 8007/1 IFR 34 8382-3504-YQ-8008/1 Piping Fabrication and Installation Procedure YQ 8008/1 IFR 35 8382-3504-YQ-8009/1 Structural Fabrication Procedure YQ 8009/1 IFR 36 8382-3504-YQ-8010/1 Hydrotest and Flushing Procedure YQ 8010/1 IFR 37 8382-3504-YQ-8011/1 FAT Procedure YQ 8011/1 IFR 38 8382-3504-YQ-8012/1 Surface Preparation and Painting Procedure YQ 8012/1 IFR 39 8382-3504-YQ-8013/1 NDE Procedure - Radiography Testing YQ 8013/1 IFR 40 8382-3504-YQ-8014/1 NDE Procedure - Ultrasonic Testing YQ 8014/1 IFR 41 8382-3504-YQ-8015/1 NDE Procedure - Magnetic Particle Testing YQ 8015/1 IFR 42 8382-3504-YQ-8016/1 NDE Procedure - Dye Penetrant Inspection YQ 8016/1 IFR 43 8382-3504-YQ-8017/1 Weight Procedure YQ 8017/1 IFR 44 8382-3504-YQ-8018/1 Dimension Check Procedure YQ 8018/1 IFR 45 8382-3504-YQ-8019/1 Radiation Safety Procedure YQ 8019/1 IFR 46 8382-3504-YQ-8020/1 HSE Plan YQ 8020/1 IFR 47 8382-3504-YQ-8021/1 Welding Procedure Specification For Structure Skid YQ 8021/1 IFR 48 8382-3504-YQ-8022/1 Welding Procedure Specification For Piping Skid YQ 8022/1 IFR 49 8382-3504-YQ-8023/1 Document Control Procedure YQ 8023/1 IFR MANUFACTURING & QUALITY PROCEDURE DRAWING FOR PIPING DRAWING FOR E&I Doc. No.: Rev.A Page 4 of 6 PETROVIETNAM GAS JOINT STOCK CORPORATION PVGAS PROJECT MANAGEMENT COMPANY REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Deadline Return from PV GAS Rev. Remark Rev Status Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Submit to PV GAS Forecast Submission Date Purpose 50 8382-3504-YQ-8024/1 Material Control Procedure YQ 8024/1 IFR 51 8382-3504-YQ-8025/1 Coordination Procedure YQ 8025/1 IFR 52 8382-3504-YQ-8026/1 Execution Plan YQ 8026/1 IFR VI 53 8382-3504-RQ-8001/1 Material Receiving Inspection Report & Material Test Certificates ( MRIR) RQ 8001/1 IFR 54 8382-3504-RQ-8002/1 Material Traceability Records For Structure Skid RQ 8002/1 IFR 55 8382-3504-RQ-8003/1 Fit-up & Visual Report For Structure Skid RQ 8003/1 IFR 56 8382-3504-RQ-8004/1 Welding Traceability Record For Structure Skid RQ 8004/1 IFR 57 8382-3504-RQ-8005/1 Dimension Control Report For Structure Skid RQ 8005/1 IFR 58 8382-3504-RQ-8006/1 Ultrasonic Examination Report For Structure RQ 8006/1 IFR 59 8382-3504-RQ-8007/1 Magnetic Particle Examination Report For Structure RQ 8007/1 IFR 60 8382-3504-RQ-8008/1 Painting Report For Skid RQ 8008/1 IFR 61 8382-3504-RQ-8009/1 Inspection Release Note RQ 8009/1 IFR VII 62 8382-3504-RQ-8010/1 Material Traceability Records For Skid Piping RQ 8010/1 IFR 63 8382-3504-RQ-8011/1 Fit-up & Visual Report For Skid Piping RQ 8011/1 IFR 64 8382-3504-RQ-8012/1 Welding Traceability Record For Skid Piping RQ 8012/1 IFR 65 8382-3504-RQ-8013/1 Ultrasonic Examination Report For Skid Piping RQ 8013/1 IFR 66 8382-3504-RQ-8014/1 Magnetic Particle Examination Report For Skid Piping RQ 8014/1 IFR 67 8382-3504-RQ-8015/1 Gradiographic Examination Report For Skid Piping RQ 8015/1 IFR 68 8382-3504-RQ-8016/1 Liquid Penetrant Examination Report For Skid Piping RQ 8016/1 IFR 69 8382-3504-RQ-8017/1 Puring Report For Skid Piping RQ 8017/1 IFR 70 8382-3504-RQ-8018/1 Hydrotest Report For Skid Piping RQ 8018/1 IFR 71 8382-3504-RQ-8019/1 Leak Test Report RQ 8019/1 IFR 72 8382-3504-RQ-8020/1 Post Weld Heat Treatment Report RQ 8020/1 IFR 73 8382-3504-RQ-8021/1 Insulation Report RQ 8021/1 IFR 74 8382-3504-RQ-8022/1 Painting Report RQ 8022/1 IFR 75 8382-3504-RQ-8023/1 Pre-Commissioning Dossier RQ 8023/1 IFR 76 8382-3504-RQ-8024/1 FAT Report RQ 8024/1 IFR VIII 77 8382-3504-RE-8001/1 E& I Check Sheet RE 8001/1 IFR TEST & INSPECTION REPORTS FOR STRUCTURE TEST & INSPECTION REPORTS FOR PIPING TEST & INSPECTION REPORTS FOR E&I Doc. No.: Rev.A Page 5 of 6 PETROVIETNAM GAS JOINT STOCK CORPORATION PVGAS PROJECT MANAGEMENT COMPANY REDELIVERING THE WET GAS FROM NCS TERMINAL TO DC GPP PROJECT VENDOR DATA REGISTER LIST Deadline Return from PV GAS Rev. Remark Rev Status Item No. Document Code Number No. Drawing / Document Description Document Type Code & Discipline Sequence No. Submit to PV GAS Forecast Submission Date Purpose 78 8382-3504-RJ-8001/1 Instrument Test and Calibration Certificate RJ 8001/2 IFR Note: IFR - Issue For Review, IFI - Issue For Information, N/A Not Available Review Status: -1. Approved: -2. Approved with comment: -3. Rejected: -4. For Information: -5. Hold Doc. No.: Rev.A Page 6 of 6