List of CIP Projects - Status Printed:07/01/2014

Project Name Condition Status Next Step Start


Construction
Complete Total Fund Project Manager
Retreat Avenue Green Active Design Keith Rapoza
Traffic Signal & Camera Upgrade & Replacement $2,500,000 Rajat Mathur
Burgdorf Environmental Yellow Active Predesign 6-15-13 1-15-14 $2,650,000.00 Bob Umashankar
Pope Park Rec. Center Building Shell / Park Imp. Green Active Construction 9/22/2011 3/1/2013 $1,200,000.00 Mark Tamaccio
Hyland Park Spray Pool and Playground Green Active Close Out 5/7/2012 10/1/2012 $600,000.00 Mark Tamaccio
Streetlight Replacement Mapping Green Active Design 6-15-2013 1-15-14 $1,625,000.00 Bob Umashankar
Municipal Facility Renovations - City Hall Securit Daniel Haim
Replacement or Repair of Various Roofs Green Active Predesign 6-21-2013 12-01-2013 $500,000.00 Bob Umashankar
Burgdorf Roof Replacement Green Complete 1-09-2012 11-20-2012 $350,000.00 Bob Umashankar
DOJ ADA Improvements Daniel Haim
Old North Cemetery - Phase 1 Green Active Construction 10/6/2011 11/31/2012 $1,000,000.00 Mark Tamaccio
Brookfield Street Yellow Active Predesign N/A N/A Keith Rapoza
Park Terrace Roundabout Rajat Mathur
Old North Cemetery-Phase 2 Monument Restoration Green Active Construction 5/4/2012 12/1/2013 $250,000.00 Mark Tamaccio
Goodwin Park Pond House Improvements Green Active Construction 5/28/2013 4/1/2013 $450,000.00 Mark Tamaccio
Sigourney Square Park Green Active Construction 9/7/2012 7/15/2013 $700,000.00 Mark Tamaccio
Hyland 1st Floor Early Learning Center Green Active Close Out 11/11/2011 11/20/2012 $600,000.00 Mark Tamaccio
Citywide Guardrail & Traffic Island Repair Green Active Predesign 07/15/2013 9/25/2013 $700,000.00 Aaron Nash
Connect Regional and National Multi-Use Trails Yellow Active Predesign Khara Dodds
Flood Control - North and South Pond Dredging Green Active Close Out 8-25-2012 TBD $3,888,282.00 Bob Umashankar
High Street Yellow Active Construction 8/1/12 5/1/2013* $1,000,000 Keith Rapoza
Flood Control - Pump Station Improvements Green Active Construction Marc 2013 July 2014 $240,000.00 Bob Umashankar
Batterson Dam Bob Umashankar
Critical Pump Station Repairs Bob Umashankar
Levee Closure Structures Modernization Bob Umashankar
North & South Meadows Mechanical Screen Installati Bob Umashankar
Park Ponds Restoration - Pope Green Active Design 9/1/2014 12/30/2014 Keith Rapoza
Green Active Construction 5/7/2012 11/15/2013 $1,700,000.00 Mark Tamaccio
Hartford Public Safety Complex Green Active Close Out 3/2/09 Ph1 TBD $ 77,000,000 Daniel Haim
Coltsville Streetscape - Phase I Yellow Design 4/1/2014 11/30/2014 Keith Rapoza
Sidewalk Replacement Mike Deane
Energy Projects Other Ongoing Ongoing $725,000.00 Daniel Haim
Construction of a Sand Salt Storage Building Green Active Construction 11-01-2012 4-23-2013 $1,325,000.00 Bob Umashankar
Farmington Avenue Streetscape Yellow Active Design 4/1/2014 5/1/2015 $6,466,837.86 Keith Rapoza
Albany Avenue Road Safety Improvements Design
McDonough School Ramp Green Active Construction 9/17/12 TBD $ 140,000
Ruby Long Playground / Cronin Park Fields Green Active Construction 9/6/2012 8/1/2013 $1,170,000.00 Mark Tamaccio
525 Main Street - ADA, RTU's Elevator Red Inactive TBD TBD $2,000,000 Daniel Haim
Keney Golf Course Fairway Improvements Green Active Design May 2014 3/15/15 $3,500,000. Mark Tamaccio
Wethersfield Avenue Streetscapes Keith Rapoza
Park Street Pope Commons Streetscape Keith Rapoza
DOJ ADA Improvements - Keney Golf Club House Mark Tamaccio
Design & Repair of City Bridges (New Park Ave) Keith Rapoza
Street Paving Program Keith Rapoza
Park Ponds Restoration (Bushnell) Keith Rapoza
Park Ponds Restoration (Goodwin) Keith Rapoza
Asylum/Farmington/Broad Intersection STP-Urban Keith Rapoza
Maple Ave II Keith Rapoza
Maple III Keith Rapoza
Tower Avenue Keith Rapoza
Library Renovations - Billings Forge Cafe Alan Strong
Library Renovations - Barbour St. Relocation Alan Strong
Library Renovations - Foundations Alan Strong
Library Renovations - Computers Alan Strong
Library Renovations - Lawn Irrigation Alan Strong
Library Renovations - Miscellaneous Alan Strong
Library Renovations - HPL Toilet Room Alan Strong
Library Renovations - Roofs Alan Strong
Quirk West Green Active Predesign TBD TDB 13,000,000 Daniel Haim
Artist Collective - CDBG Alan Strong
Roof Replacement - City Hall Mark Tamaccio
Library Renovations - Branch Tech Upgrades Alan Strong
Library Renovations - Downtown Library Floor Alan Strong
Library Renovations - YOUmedia Alan Strong
Misc. Structural & Surface Repairs USACE Inspectio Bob Umashankar
Weston Street Drainage Phase II Bob Umashankar
Main/Retreat, Main/Maple Accident Reduction Rajat Mathur
Signal Upgrades - 14 Locations Rajat Mathur
Advanced Traffic Management Software Rajat Mathur
DECD Traffic Calming Rajat Mathur
Asylum Hill Neighborhood Traffic Calming Study Rajat Mathur
Fairfield Ave. Traffic Calming Study Rajat Mathur
Design & Repair of City Bridges (Columbus St.) Keith Rapoza
City Hall Energy Improvements Green Active Construction Daniel Haim
Coltsville Streetscape - Phase II Keith Rapoza
Albany Avenue Road Safety Improvements Keith Rapoza
Albany/North/Main STP - Urban Keith Rapoza
Project Name Condition Status Next Step Start
Construction
Complete Total Fund Project Manager
Broad Street STP - Urban Keith Rapoza
Wethersfield II Keith Rapoza
Keney Golf Clubhouse Green Active Predesign 9/1/14 3/15/15 $2,000,000. Mark Tamaccio
ADA Parks - Ebony Horsewomen/Police Horse Stables Mark Tamaccio
Citywide Monument Study Green Active N/A $50,000. Mark Tamaccio
Ancient Burying Ground - West Wall Green Active Design 9/1/2013 12/31/2013 $750,000.00 Mark Tamaccio
DOJ ADA Improvements City Hall Active Close Out 5/5/13 12/23/13 $500,000 Daniel Haim
Cal Ripken Field - Annie Fisher Green Active Design April 2014 Aug. 1, 2014 1,700,000. Mark Tamaccio
Fire Training Facility Green Active Predesign 12/8/2014 $ 800,000 Daniel Haim
Firehouse #11 Yellow Active Predesign Daniel Haim
Journalism and New Media at Barbour School Green Active Close Out 03/01/2012 Daniel Haim
40 Jennings Bathroom Improvements Green Active Design Daniel Haim
Opportunity High School Green Active Construction TBD $700,000 Daniel Haim
Goodwin Park Fencing Green Complete Close Out 5/15/2012 9/1/2012 $125,000.00 Mark Tamaccio
City Hall Exterior Shell Red Inactive Predesign $500,000. Mark Tamaccio
Asian Studies Academy at Bellizzi School Green Active Close Out 3/1/2012 7/1/2013 $13,000,,000 Daniel Haim
Milner School Improvements Green Active $ 2,000,000 Daniel Haim
Parkville Parking Lot Green Active Construction Daniel Haim
Cal Ripken Field - Hyland Green Active Design 6/1/14 9/15/14 $1,850,000. Mark Tamaccio
Elizabeth Park East Playground Green Active Design 2/28/14 demo 6/15/14 $350,000. Mark Tamaccio
Baby Pope (Pope North) Playground and Spray Pool Green Active Construction 9/15/13 5/1/14 $570,000. Mark Tamaccio
Burns Language Lab Active Design 6/23/2014 700,000 Daniel Haim
Cemetery Master Plans Green Active N/A $130,000. Mark Tamaccio
Citywide Parks Courts Green Active Design 6/15/14 $500,000. Mark Tamaccio
Parkville Senior Center Improvements Red Active Predesign $250,000. Mark Tamaccio
Public Safety Complex Parking Garage Green Active Predesign 10/6/2014 Daniel Haim
Central Library - Auditorium/Adult Learning/ Tunne Green Active Construction 12/3/11 April 2014 Daniel Haim
International Baccalaureate at Quirk Middle School Green Active Close Out 11/16/2011 9/1/2013 $55,050,000 Arcadis / O&G
Kinsella High School Red Active Consultant Selection 33,000,000 Daniel Haim
Roof Replacement - Colt Green Active 4/1/14 $200,000. Mark Tamaccio
Burns Masonry Green Complete Close Out Daniel Haim
Parkville Microgrid Green Active Design Daniel Haim
Wexford Skate Park Green Active Construction 10/1/2013 6/1/2014 $150,000.00 Mark Tamaccio
Goodwin Park Spray Pool Green Active 4/1/15 8/1/14 $190,000.00 Mark Tamaccio
Bellizzi Air Conditioning Yellow Active Design 2,200,000 Daniel Haim
Dwight Branch Library Red Complete 10/30/2011 7/30/2012 $ 2,000,000 Daniel Haim
MD Fox Elementary School Green Active Close Out 09/01/2011 54,400,000 Daniel Haim
Htfd. Magnet Middle School / Trin. College Academy Green Active TBD, 2014 29,440,000 Daniel Haim
George Day Park Improvements Green Active Construction 9/9/2013 5/1/2014 $870,000.00 Mark Tamaccio
Pulaski Mall Improvements Green Active Construction 8/11/2012 5/15/2013 $350,000.00 Mark Tamaccio
Batterson Park Trails Green Active Out to Bid 5/1/14 9/1/14 $400,000. Mark Tamaccio
Keney Clock Tower Green Active Design $100,000.00 Mark Tamaccio
Dillon Stadium Green Active Design $1,000,000.00 Mark Tamaccio
Weaver High School Yellow Active Predesign Daniel Haim
Cal Ripken Field - Quirk West Green Active Construction 11/19/13 5/1/14 $1,300,000. Mark Tamaccio
Police Shooting Task Force Move Green Active Design Mark Tamaccio
Urban Bird Treaty Green Active Construction 5/1/2012 10/1/2013 $70,000.00 Mark Tamaccio
DPW Move - Improvements to 50 Jennings Road Green Active Close Out Mark Tamaccio
South Green Ornamental Fence - Phase 1A Red Active Other N/A N/A $200,000.00 Mark Tamaccio
The "Farmstead" at Elizabeth Park (West) Green Active August 2014 April 2015 $642,150. Mark Tamaccio
Library Improvements Green Active Construction 11/18/13 Daniel Haim
Northend Senior Center Green Active Out to Bid 7/1/13 7/1/14 $2,287,095 Mark Tamaccio
Bushnell Park Carousel Green Active Design 4/15/14 11/21/14 $900,000.00 Mark Tamaccio
ADA PARKS Green Active Construction 10/5/2012 8/1/2013 $500,000.00 Mark Tamaccio
Colt Park Soccer Red Active Out to Bid On Hold On Hold $500,000.00 Mark Tamaccio
West Middle School Green Active Construction 01/21/2014 07/17/2015 54,600,000 Daniel Haim
ADA IMPROVEMENTS: Dillon Stadium Green Active Design $500,000.00 Mark Tamaccio