Vous êtes sur la page 1sur 34

Case Studies of

Rock-socketed piles
Sedimentary rocks
Case studies (Leung, 1996) involving
a good number of load tests carried
out in instrumented piles socketed in
weak sedimentary rock mainly in
Alexandra and Keppel areas
0 4 8 12 16 20
Load (MN)
0
4
8
12
16
S
e
t
t
l
e
m
e
n
t

(
m
m
)
Load-settlement response is reasonably linear up to working load of 10 MN
0 5 10 15 20
Load (MN)
0
4
8
12
16
D
e
p
t
h

b
e
l
o
w

g
r
o
u
n
d

l
e
v
e
l

(
m
)
0 200 400 600
Unit shaft friction (kPa)
Firm
silty clay
(N = 12)
V. dense
clayey silt
(N = 130)
Weak
siltstone
(q
u
=6.5 MPa)
Fill
Marine clay
Weak
siltstone
(q
u
=3.5 MPa)
(a) (b)
(c)
1
2
3
4
1
2 3 4
Applied load
1: 5 MN
2: 10 MN
3: 15 MN
4: 20 MN
Results show that a large percentage of shaft friction can
be mobilised even for piles not tested to ultimate failure.
Alexandra Distripark(after Radhakrishnan& Leung, 1989)
Rock socket adhesion factor
Pile load test results reveal that
majority of socket shaft friction can be
mobilised even for piles not tested to
ultimate failure.
Rock socket adhesion factor
= f
s
/q
u
Sedimentary rocks
For q
u
< 5 MPa (i.e. very weak rock)
rock socket adhesion factor is
reasonably close to theoretical values.
For q
u
> 5 MPa (i.e. weak rock & above),
value is considerably lower than the
theoretical values. This is caused by
heavy chiselling that had significantly
weakened the rock.
1 10 100
Unconfined compressive strength q
u
(MPa)
0.0
0.2
0.4
0.6
R
o
c
k

s
o
c
k
e
t

a
d
h
e
s
i
o
n

f
a
c
t
o
r
Williams and Pells
Rowe and Armitage
Rosenberg and J ourneaux
Horvath and Kenny
Field data in
sedimentary rocks
All piles installed by chiselling.
Chiselling affects sockets with q
u
> 5 MPa
Granite
Load tests are mainly carried out in the
Woodlands area (Leung, 1996).
Load-settlement curve
Load transfer
Unit shaft friction
t-z curves
Rock socket adhesion factor
0 2 4 6 8 10
Load (MN)
0
5
10
15
20
25
S
e
t
t
l
e
m
e
n
t

(
m
m
)
Load-settlement response is linear up to pile working load
0 2 4 6 8 10
Load (MN)
0
10
20
30
D
e
p
t
h

b
e
l
o
w

g
r
o
u
n
d

l
e
v
e
l

(
m
)
0 200 400 600 800
Unit shaft friction (kPa)
Clayey
silt
(N =14)
Clayey silt
with sand
(N = 25)
Dense silty
sand
(N = 120)
Granite
q
u
=12.5 MPa
(a)
(b)
(c)
1
2 3
4
1
2 3 4
Applied load
1: 3.6 MN
2: 6.3 MN
3: 8.1 MN
4: 9.0 MN
0 4 8 12 16 20
Shaft movement (mm)
0
200
400
600
800
U
n
i
t

s
h
a
f
t

f
r
i
c
t
i
o
n

(
k
P
a
)
Depth below
ground level
6.5 m
9.5 m
12.5 m
15.5 m
18.5 m
21.5 m
24.5 m
27.5 m
29.5 m
t-z curves (much of the load transfer in the granite socket)
Granite
For all q
u
values, is considerably
lower than the theoretical values.
Heavy chiselling, that had significantly
weakened the rock, need to done on
all classes of granite as they are
generally less fractured.
[Most of the load tests were
conducted in the Woodlands area.]
1 10 100
Unconfined compressive strength q
u
(MPa)
0.0
0.2
0.4
0.6
R
o
c
k

s
o
c
k
e
t

a
d
h
e
s
i
o
n

f
a
c
t
o
r
Williams and Pells
Rowe and Armitage
Rosenberg and J ourneaux
Horvath and Kenny
Field data
in granite
Chiselling disturbs granite more than sedimentary rocks
Construction concern
As the studies revealed heavy
chiselling process can badly damage
the rock, it is believed that better
construction tool (e.g. down the hole
hammer) will result in less rock
damage and hence higher shaft
resistance. [Further studies are
required to confirm this.]
Settlement of socketed piles
The load-settlement response under
working load is found to be
reasonably linear in most cases
reported earlier.
The load-settlement responses of all
the previous cases are back-analysed
using a FEM program and a Elastic
theory model (Leung & Chow, 1998).
FEM
mesh
Settlement of socketed piles
Granite
E
s
= 2N (unit in MPa)
E
s
= E
m
(need more data to confirm)
Sedimentary rocks
E
s
= E
m
(needs more data to confirm)
E
s
< 2N (exact values hard to
determine as degree of rock fracture
highly variable)
0 2 4 6 8
Measured pile settlement (mm)
0
2
4
6
8
P
r
e
d
i
c
t
e
d

p
i
l
e

s
e
t
t
l
e
m
e
n
t

(
m
m
)
N value
Pressuremeter modulus
Figure 4 Comparison of predicted and measured pile settlements
(Singapore granite)
0 4 8 12
Measured pile settlement (mm)
0
4
8
12
P
r
e
d
i
c
t
e
d

p
i
l
e

s
e
t
t
l
e
m
e
n
t

(
m
m
)
Figure 5 Comparison of predicted and measured pile settlements
(Singapore sedimentary rocks)
N value
Pressuremeter modulus
Pile group, cap & creep
Case studies:
PSA Building
Alexandra District Park
The presence of rigid pile cap, pile group
effect and possibly rock creep will cause
the less load being transferred to the pile
shaft in the long term. I.e. more load is
transferred to the pile base.
PSA
Building
(Case
study by
Leung et
al., 1998)
Foundation layout and instrument plan
Alexandra Distripark(after Radhakrishnan& Leung, 1989)
Load transfer under short term test load is different
form that under long term service loads condition.
Summary of findings
(1) Majority of shaft friction is almost
fully mobilised for all piles [See Table
1 earlier]
(2) Observed f
s
is close to those
predicted by Williams & Pells and
Horvath et al. But lower than those of
Rowe & Armitage and Rosenberg &
J ourneaux [see Table 2]
Summary of findings
(3) More load transferred to the pile
base under long term service loading
condition than short term load test
condition due to
interaction between piles in a group
inetraction between piles and pile cap
pile and soil/rock creep
[See previous figure and Table 3]

Vous aimerez peut-être aussi