PETROVIETNAM GAS JOINT STOCK CORPORATION

PETROVIETNAM STEEL PIPE JOINT STOCK COMPANY

PRODUCTION SCHEDULE OF NCSII PROJECT


ID No. Task Name Start Finish Duration Qtr 4, 2013 Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 NSCII PROJECT Thu 31-10-13 Sun 11-01-15 438 days
2 1 Procurement Plan Thu 31-10-13 Sun 09-11-14 375 days
3 1.1 Steel Plate Fri 14-03-14 Sun 09-11-14 241 days
4 1.1.8 Negotiation, Signing Contract (PV Gas) Fri 14-03-14 Fri 14-03-14 1 day 14-03 14-03
5 1.1.9 Delivery to HCM Port Thu 12-06-14 Sun 09-11-14 150 days
6 1.1.9.1 1st shipment (WT19.1mm; 9122 tons) Thu 12-06-14 Thu 12-06-14 0 days 12-06
7 1.1.9.2 2nd shipment (WT19.1mm; 9122 tons) Fri 11-07-14 Fri 11-07-14 0 days 11-07
8 1.1.9.3 3rd shipment (WT19.1mm, WT23.8mm, Mon 11-08-14 Mon 11-08-14 0 days 11-08
WT25.4mm ; 9641 tons)
9 1.1.9.4 4th shipment (WT19.1mm; 9634 tons) Wed 10-09-14 Wed 10-09-14 0 days 10-09
10 1.1.9.5 5th shipment (WT19.1mm; 9630 tons) Sun 09-11-14 Sun 09-11-14 0 days 09-11
11 1.2 Necessary Material (Welding Thu 31-10-13 Sat 07-06-14 219 days
comsumable, Tool, NDT, Pipe Protector,
12 1.2.1 Make of Bidding Plan and Bidding Documents Thu 31-10-13 Fri 29-11-13 30 days 31-10 29-11
13 1.2.2 Notice of Quatation Invitation Sat 30-11-13 Tue 03-12-13 4 days 30-11 03-12
14 1.2.3 Sale of Bidding Documents Wed 04-12-13 Tue 10-12-13 7 days 04-12 10-12
15 1.2.4 Bid Closing / Bid Opening Wed 11-12-13 Wed 11-12-13 1 day 11-12 11-12
16 1.2.5 Bid Evaluation Thu 12-12-13 Wed 25-12-13 14 days 12-12 25-12
17 1.2.6 Review and Approval of Bidding Results Thu 26-12-13 Mon 30-12-13 5 days 26-12 30-12
18 1.2.7 Notice of Bidding Results Tue 31-12-13 Tue 31-12-13 1 day 31-12 31-12
19 1.2.8 Negotiation and Signing Contract Wed 01-01-14 Tue 07-01-14 7 days 01-01 07-01
20 1.2.9 Delivery to Pipe Mill Tue 20-05-14 Sat 07-06-14 18 days 20-05 07-06
21 2 Qualification Sat 14-06-14 Thu 19-06-14 6 days
22 2.1 Welder Qualification Sat 14-06-14 Tue 17-06-14 4 days 14-06 17-06
23 2.2 MPQT / WPQT Sat 14-06-14 Tue 17-06-14 4 days 14-06 17-06
24 2.3 Approval by TPI, Client Wed 18-06-14 Thu 19-06-14 2 days 18-06 19-06
25 3 Production Sun 15-06-14 Thu 08-01-15 208 days
26 3.1 OD 660 x WT 19.1mm (1656 pipes; 5999 tons) Sun 15-06-14 Wed 09-07-14 25 days 15-06 09-07
27 3.2 OD 660 x WT 19.1mm (2500 pipes; 9056 tons) Thu 10-07-14 Fri 08-08-14 30 days 10-07 08-08
28 3.3 OD 660 x WT 19.1mm (2010 pipes; 7281 Sat 09-08-14 Mon 08-09-14 31 days 09-08 08-09
tons); OD 669.4 x WT 23.8mm (466 pipes,
2119 tons); OD 672.6 x WT 25.4mm (24 pipes,
29 3.4 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Tue 09-09-14 Thu 09-10-14 31 days 09-09 09-10
30 3.5 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Fri 10-10-14 Sat 08-11-14 30 days 10-10 08-11
31 3.6 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Sun 09-11-14 Tue 09-12-14 31 days 09-11 09-12
32 3.7 OD 660 x WT 19.1mm (1523 pipes; 5517 tons) Wed 10-12-14 Thu 08-01-15 30 days 10-12 08-01
33 4 Steel Pipe Transportation to Phu My Port Wed 18-06-14Sun 11-01-15 208 days
34 4.1 OD 660 x WT 19.1mm (1656 pipes; 5999 tons) Wed 18-06-14 Sat 12-07-14 25 days 18-06 12-07
35 4.2 OD 660 x WT 19.1mm (2500 pipes; 9056 tons) Sun 13-07-14 Mon 11-08-14 30 days 13-07 11-08
36 4.3 OD 660 x WT 19.1mm (2010 pipes; 7281 Tue 12-08-14 Thu 11-09-14 31 days 12-08 11-09
tons); OD 669.4 x WT 23.8mm (466 pipes,
2119 tons); OD 672.6 x WT 25.4mm (24 pipes,
37 4.4 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Fri 12-09-14 Sun 12-10-14 31 days 12-09 12-10
38 4.5 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Mon 13-10-14 Tue 11-11-14 30 days 13-10 11-11
39 4.6 OD 660 x WT 19.1mm (1524 pipes; 5521 tons) Wed 12-11-14 Fri 12-12-14 31 days 12-11 12-12
40 4.7 OD 660 x WT 19.1mm (1523 pipes; 5517 tons) Sat 13-12-14 Sun 11-01-15 30 days 13-12 11-01

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Rev C
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
28/11/2013
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress