COMPANY : PAN ENGINEERING SDN. BHD. SUBJECT : POTENTIAL RISK and MITIGATION PLAN FOR FIRE PROTECTION SYSTEM DATE : JUNE 14, 2014 REVISION : 1 No. Description of Potential Risk Mitigation Action Remarks 1. Major equipments may end up as long lead-time delivery. To expedite the technical submission and get approval from the Consultants for all the major equipments, material and systems. To liaise closely with vendors to expedite delivery or explore option for the transportation method. Main fire pump, gaseous suppression FM200 and fire alarm panel 2. Limitation of working hour may jeopardize the installation progress as planned in the work schedule. To get ready and familiar with the procedures of applying night work permit from DBKL if it is necessary to catch up the schedule. To monitor closely workers in punctuality, discipline and be more organized to perform efficiently.
3. Restriction of heavy transportations on the road by DBKL may affect the logistic planning. To coordinate closely with vendor and workshop for their delivery of equipments and material to suit the site traffic conditions from time to time.
4. Harsh sound level condition imposed by DBKL may impact on the installation method and progress. To maximize fabrication works that may generate high noise level in workshop to reduce impact to the site environment. Metal cutting and hammering 5. Late handover of important rooms may shorten the erection schedule granted in the master schedule. To coordinate with the structural contractor and closely observe their progress. To locate off-site space for temporary storage if the dedicated room is not ready for occupancy. MSB room, fire pump room & substation Page 2 of 2
No. Description of Potential Risk Mitigation Action Remarks 6. Delay of utilities supply may cause the testing and commissioning plan deviated from its original schedule. To find alternation source such as generator and water truck to support testing and commissioning. Electric power and water supply 7. Confusion of power source of fire alarm panel in the interlocking with other trades may incur unforeseen modification or additional works during testing and commissioning. To call a coordination meeting among all trades such as electrical, ACMV, security system, roller shutter and lift contractor to finalize the input & output signal design prior to any fabrication of control panel or starter board. Voltage and current requirements for input & output signal with other trades