Académique Documents
Professionnel Documents
Culture Documents
Introduction
1.1 Background
Canada and the United States. More than 16 million cars, trucks and
Canadian and American trade and tourism increase through the years,
Bridge currently spans across the Detroit River and links up Detroit
This means that before a driver can reach the border crossing they
need to cross several street lights within the city core. This causes
large traffic jams and impede on the overall traffic ease of the city.
1
the Canadian and American highway systems, such that traffic flow
built in stages such that the traffic flow matches the facility capacity.
Once the preliminary design is complete, the project will be ready for
Border Crossing Plaza site. This report will contain two parts: Firstly, a
report .In addition to that the technical report should follow best
2
outlined in the 2003 Ministry of the Environment storm water
management guideline.
1.3 Methodology
In order to properly assess the potential use of various alternative
4) Economics; and
6) Site elevation
are:
3
within a site and to compare potential conceptual drainage systems.
Figure 1-1).
4
It is used to summarize the results obtained from Tables A and B,
conceptual system
i) Groundwater recharge
v) Thermal reduction
subgroups:
5
i) Sediment removal
6
1.4 Preliminary Conclusions
Based on the results from UDSST and the site conditions, the
7
2. Site Description
The western edge of the proposed site runs along the Detroit River.
site, the pre-existing site terrain inclines towards the South Eastern
edge of the proposed site. At the same time, it is fairly flat; the rough
8
obtained from Google EarthTM.
9
2.1 Existing Land Use and Vegetation
The 54.3 hectare area to be used for the proposed Canadian Plaza
condition are C = 0.34 and 0.47 for 5 year & 100 year storm event
Character of
Return Period (years)
Surface
Undeveloped 5 100
Cultivated land
0.34 0.47
Flat, 0 – 2%
Developed
10
condition
Flat, 0 – 2%
Source: Water Resources Engineering by Larry Mays 2005
sand
be located about 3 metres below ground surface in the clayey silt and
silty clay materials. The silty clay, clayey silt, sand and gravel and
sands are considered to be slightly erodible and the silty sands are
11
development does not cause excess rainwater to fall into neighboring
properties and cause them flood damage. The proposed site is built
off coefficient for the soil would increase. The runoff coefficient of
asphalt is 0.90, this means that during a typical storm, 10% of the
water on the asphalt will be absorbed by the ground, 90% of the water
Border crossing plaza site and its surrounding area. This map was
outlined on Figure 2-2 is based on the natural flow path of water and
piece of neighboring land has a slope facing the border crossing site,
with a slope facing the border crossing plaza site, the land will not be
12
will lead into the border crossing plaza area, it will be considered part
rainwater. Figure 2-3 also outlines the existing flow path of water
with arrows. The runoff from total drainage area will naturally flow into
13
Figure 2-3 - Existing flow path of water
system with 5 and up to 100 year storm capacity. Runoff will need to
crossing plaza site. Figure 2-4 outlines how the drainage areas will
be divided.
14
This area is the most important drainage area of this project. The
rainwater that lands on this area will need to be processed for quality
discussed in the Preliminary report, this area (68.9 ha) will include a
main channel which will divert all runoff into the main ponds.
project area. The Runoff from these areas will simply need to be
15
3. Stormwater Management Design
Overview
Water Quality:
chemicals can make their way into the leachate and contaminate the
water system i.e: the Detroit River. This will ultimately endanger the
Sediment Control:
Water is a highly abrasive medium and with enough time, water will
earth under the roads can compromise the structural integrity of any
and landslides. For the safety of drivers these large driving surfaces
16
In addition to this, it is important to note that, storm water from
the North and the East sides of the site may contain large amounts of
can cause sewers to be filled with sediment and destroy fish habitat in
the river.
Road Safety:
properly drained such that driving surfaces are un-slippery and safe
3.2 Considerations
the Plaza requires quality, quantity and erosion controls for runoff
flows from the Plaza, as the increase in impervious area will increase
the overall peak flows from the site, as well as the overall pollutant
The principle concern for large sites with a high imperiousness and
17
garbage (gravel, sand, and cigarette butts), infrequent pollutant spills,
Based on the results and the site conditions, the solutions retained
were storage SWMP’s and oil/grit separators. The storage SWMP’s will
facility in the green spaces south of the proposed plaza and a linear
channel. The pond system provides closer outlets for the sewer
18
open portion to ensure that there is no restriction to the conveyance
of flow from one pond to the other. The pond system would control
spill with the Plaza, a shut off valve or alternative damming procedure
19
4. Main Channel Design
This section will include the technical design of the major storm
site. The design portion will be split into two parts the design of
The quality and quantity pond would be located at the most western
20
The main storm water channel leading up to the pond will be placed
along the southern edge of the site. The channel will be in this
configuration because:
21
3. The border crossing plaza has the greatest free space
Pre-development conditions:
obvious to see that the site is highly flat. The existing elevation
2.72m over a 1110m span. The MOE 2003 storm water management
management structures for flat terrain. Thus the main channel leading
edge of the site. The elevation data was obtained from the City of
Design Constraints
The design constraints of the proposed site are mainly the flatness
and ground water table elevation. Figure 4-2 describes the design
22
constraints of the channel. The highest elevation at the eastern swale
profile
Figure 4 -2 - Existing main channel elevation
at which the Main Swale will enter the pond. The Detroit River Website
measured that the highest water level of the ground water table to be
2.25m
23
4.3 Runoff Routing Drainage Area A
This section will roughly describe the post development runoff pattern.
and C will flow into Main Drainage Area A. However because there will
drainage area B and C directly into the Detroit River, the excess runoff
direction of the Main Drainage Swale. This terrain will force runoff
24
Figure 4-3 - Post Development Drainage Pattern For Drainage Area
Now that the elevation profile for the main swale is known, a swale
between the swale floor at the pond entrance and the ground level of
the most eastern point of the swale is 2.98m. The MOE also states
that a one foot clearance between the 100 year water elevation of the
swale and the ground level above the swale is required. Thus, the
swale design requires that the sum of the 100 year water level of the
swale and the elevation difference due to the channel slope not
described below it was found that the swale would not exceed 1m in
depth for a 100 year storm and that the optimal slope is 0.125%.
determine the water level of our channel for a 100 year storm. The
V=1n*R23*S0.5
25
By multiplying both sides by the area of the channel the modified
Q=1n*AR23S0.5
= 0.03
most optimal.
MOE 2003 STMWTR Guideline specifies that the swale will need a
A=(B+Zy)y
26
Where
that the site is very flat 7m were used as the base of the
swale.
2.5m
R=(B+Zyy/(B+2*y1+Z20.5)^(23)
Now that all values are defined, solve for y in the following
equation:
0=B+ZyyB+ZyyB+2*y1+Z20.523-Q*n/S0.5
Due to the fact that many channels were designed in this project,
YMDS=1.00m.
Y5MDS=0.67m
27
For a 100 year storm, Q=9.3305m3/s was used
Y100MDS=1.00m
Now that the water level is found, Figure 4-5 outlines the
Foot
6m
2.5:1m
Unknown:
Base
Clearance
Side
(MOE
Y
Slope
2003)
Swale has a 5 year and a 100 year storm rainfall capacity. All excess
28
rain rater from Drainage Area A will be routed towards the Main
Main Drainage Swale will lead into the Wet/Dry pond designed in
Section 5.
29
Figure 4-5 – Post Development Swale Elevation
Figure 4-6 - Main Drainage Swale Cross sectional Dimensions in
5. End of Pipe Extended Detention
Facilities
Meters
Overview
30
control cell was designed as an artificial wet pond, and the quantity
control cell was designed as a dry detention area to receive flows only
• Quantity/Flood Control
levels for the lands draining to the facility for 5 to 100 year
• Erosion Control
incorporated.
• Water Quality
31
This active storage was in addition to that provided for flood
10
20
30
40
50
5.1
Appendix 2
Rational method was used in determining for the peak flows of both
32
i = Average rainfall intensity (mm/hr) for a duration
frequency.
The drainage area to be used in the design should include all those
The area term in the Rational Method formula represents the total
Figure 2-4).
pre-developed flows are C = 0.34 for 5 year event, and C = 0.47 for
composite runoff coefficient value of 0.5472 for 5 year and 0.7009 for
33
drainage area breakdown for the post-development condition, along
Runoff Coefficient
Description Area (m2) Area (ha)
5 year 100 year
34
35
Crossing Study Website
Figure 5 -1 – Layout of the Canadian Plaza
5.1.4 Rainfall Intensity and Time of Concentration
concentration is the time required for flow to reach the pond from the
most remote part of the drainage area. Upland method was used for
Tc = L / (3600 * V)
36
Where Tc = time of concentration (hrs)
V = velocity (ft/s)
The velocity can be estimated by knowing the land use and the slope
IDF curve used for this project was obtained from Atmospheric
37
Figure 5.2 – Velocities for upland method of estimating tc
Source: U.S Department of Agriculture Soil Conservation
Service 1986
38
Figure 5.3 – Intensity Duration-Frequency Curve (IDF Curves)
- City of Windsor
39
Source: Environment Canada – Atmospheric Environment
Services
40
4.1
The tributary area of the pond will be 63.9 hectares of which 33.2
hectares will be covered by grass. Drainage will enter the pond via a
via an overland flow swale (see Figure 5-5). The outfall from the
large rip-rap placed over filter cloth. Outlet control will be provided
possibility of ponding during low flow run-off events. The pond invert
(175.2m) at the outlet is above the level of the local water table
(173.5 m), and the side slope gradient has been reduced to 4:1 to
vegetation.
The proposed pond was calculated into the 5 and 100 year post-
40
flows. The pre-developed flows are 2.7759 m3/s and 6.2564 m3/s for 5
year and 100 year storm events respectively with an existing runoff
coefficient of 0.34 for 5 year and 0.47 for 100 year storm events and a
are 4.4675 m3/s and 9.3305 m3/s for 5 year and 100 year storm events
coefficient of 0.5472 for 5 year and 0.7009 for 100 year storm events
41
42
43
Figure 5-4 – Layout of the ponds and channels
Figure 5-5 – Cross-Section of Overflow Swale – to Quantity Pond
enclosed in the Appendix 2. Table 5.2 shows the design
volumes.
The maximum water level during the 1:100 storm event will be
Pre-development Post-development
Items
5 yr 100 yr 5 yr 100 yr
Runoff
0.34 0.47 0.5472 0.7009
Coefficient
44
Peak Flows (m3/s)
Storm
Storage Volume (m3) Pre- Post-
Events
development development
A flow splitter or flow diversion structure was used to direct the first
fraction of runoff (commonly called the “first flush”) into the quality
pond, while bypassing excess flows from 100 year event around the
detention/quantity pond.
Runoff water is conveyed to the quality pond via the main open
channel. Once the main open channel reaches its 5 year water
capacity, water backs up in the channel and into the flow splitter
itself. When the water level reaches the bypass elevation, stormwater
45
pond. The bypass is created and controlled by a weir in the flow
splitter structure.
5 year storm event – 176.42m). Using this method, the flow will only
start to bypass the weir once the channel has conveyed the design
46
Figure 5-6a – Plan View of Flow Diversion Structure
47
5.2 Water Quality Control
Design Criteria
48
Based on the above information, and with reference to Table 3.2 in
suspended solids and oils. The detailed design of OGS will not be
Like the quantity pond, the drainage will enter the pond via a 12m
(see Figure 5-8). The outfall from the channel to the pond shall be
pipe to quantity pond. The pond bottom will also be graded at 0.23%
The pond invert at the outlet is 173.9 and the side slope gradient has
The maximum water level during the 5 year storm event will be
49
at 175.42m and its storage is 13418.08 m3. Detailed calculations can
be found in Appendix 2.
Quality Pond
Figure 5–8 – Cross-Section of Overflow Swale- to
50
Figure 5.9 – Cross-Section of Quality and Quantity Ponds
51
potential for re-suspension and to prevent the conveyance of re-
along the aquatic bench, the safety bench and side slopes or
52
6 Secondary Drainage Channels
of runoff draining around the border crossing plaza site due to the pre
standards and law, new construction cannot interfere with the natural
the border crossing site, the runoff does not need to be processed and
This design section will consider all runoff predicted to enter the site
swales of the site which will route the runoff for up to a 100 year
53
Figure 6-1 - Secondary Drainage Channels Layout
P11 will route runoff from Secondary Drainage Area C into the
runoff from MajDS into the Major and Minor Drainage Swale
54
does not mix with the runoff expected to land on the main
route runoff from MajDC and MinDS into the Detroit River.
Secondary Drainage Area B and route it to point P2. Figure 6-3 is pre
55
existing elevation profile of Line P6-P5-P4-P3-P2. This line will
The line representing P6-P7 will collect the water from Secondary
56
major drainage culvert MajDC. In addition to that, the line
major drainage culvert MajDC as well. Figure 6.4 the pre existing
57
Major Drainage Swale MajDS.
58
Figure 6-4 - Pre existing elevation profile of Line P6-P7-P8-P9-P10-P11,
MajD
The line representing P2-P7 will collect the water from MajDS and
Line P2-P7 which will represent the Major Drainage Culvert MajDC.
59
Figure 6.5 - Pre existing elevation profile of Line P2-P7, MajDC
60
Figure 6-6 - Pre existing elevation profile of Line P1-P2, MMDS
The line representing P1-P2 will collect the water from MinDS and
MajDC and route it directly into the Detroit River. Figure 6-6 is the
pre existing elevation profile of Line P1-P2 which will represent the
61
main channel design section 4.2.1 the Ground Water Table was the
the Detroit River water level is the design constraint. The channel floor
must be higher than the highest Detroit water elevation. The highest
water level report of the Detroit River is 175.00m. Thus the channel
River Water Level and slope elevation difference. The design begins
elevation profile.
between the highest and the lowest point of the Secondary Drainage
0.125% slope as the Main Channel Design used this slope. The
62
Figure 6.7 - Elevation Profile For P11-P10-P9-P8-P7-P2-P1.
remaining elevation availability for the 100 year storm water level in
the swales and culvert is 83.25cm. The 0.125% slope was obtained by
the Appendix 1.
equation
63
The MinDS will route all the excess rainwater from Minor Secondary
MinDS cross section and Figure 6-9 is the Post Development MinDS
Elevation Profile.
64
Figure 6-9 - Post Development MinDS Elevation Profile
The MajDS will route all the excess rainwater from Major Secondary
Drainage area to MMDS, P7. The Major Secondary drainage area was
Figure 6-10 outlines the MajDS cross section and Figure 6-11
65
Figure 6-10 - MajDS cross section
The Culvert will route all the excess rainwater from MajDS to the
concrete with strength able to sustain the weight of the largest truck
66
multiplied by a safety factor of 3. The culvert will be trapezoidal as all
67
Figure 6-12 outlines the MajDC cross section and Figure 6-13
The Swale will route all the excess rainwater from surrounding sites,
P2, to the Detroit River. The flow value is simply the sum of the 100
peak flow for MinDS and the MajDS which is Q=7.6628m3/s. The
y=0.68m. Figure 6-14 outlines the MMDS cross section and Figure
68
Figure 6-15 - Post Development MMDS Elevation Profile
water channels system has a 100 years rainfall capacity. All excess
rain rater from surrounding areas B and C will be routed into the
Figure 6-9, Figure 6-11, Figure 6-13, Figure 6-15 earth filling is
minimized.
69
7. Conclusions and Recommendations
such that the development of this site will not result in adverse effects
report will ensure that the natural habitat of the area is not disturbed
in the long term and that the sediment transported on site does not
conveyance systems.
70