Dynamic testing is not expensive but problem foundations
are. All construction depends upon a firm foundation. Deep foundation designers require either piles or drilled shafts to support increasingly higher loads. With use of deep foundations more thorough and reliable inspection methods are essential. Traditional pile testing methods have serious drawbacks; energy formulae are dangerously unreliable, while static load tests are expensive, time consuming and in many cases physically impossible to conduct. Static load tests not run to failure provide only a limited amount of information. The need for cost effective quality assurance has been widely acknowledged. Dynamic testing has satisfied this need as evidenced by a rapidly growing number of specifications and test standards, resulting in worldwide routine and comprehensive dynamic testing programs. Pile Driving Analyzer (PDA) The PDA uses signals from reusable strain and acceleration transducers (see Fig. 1) which are quickly bolted or anchored to steel, concrete or timber piles, or to drilled shafts. A PDA unit of the latest model (PAK) is shown in Fig. 2. PDA utilizes closed form solutions to wave propagation theory to solve the following: hammer performance to qualify pile driving equipment preliminary estimates of activated bearing capacity (CASE Method Estimates) during driving, or later by restrike to include time dependent soil strength changes driving stresses to investigate potentially damaging situations, and assess effects of changes to the driving system structural integrity of pile shaft Immediate display of these values is generated for each impact from a hammer. This produces more information than by conventional static loading test, at a fraction of the cost and time. CASE Method estimates suitable for the general pile-soil combination are readily available on site. Detailed modeling by CAPWAP analysis on selected records is required to determine the most representative CASE Method for the tested piles and to verify the activated bearing capacity. Using dynamic testing, the number of static load tests can be reduced or even completely eliminated. For small projects, large piles or locations over water, where static testing is prohibitively expensive or physically impossible, dynamic testing can be a low cost tool for inspection and evaluation of the foundation piles. For large projects, some static tests can be replaced by several dynamic tests, increasing quality control and optimizing the driving criteria with potentially substantial savings in time and money. For example, special test programs prior to or at the beginning of production piling have often detected poor hammer performance, dangerous driving stresses, inadequate driving criteria or excessive pile lengths. Furthermore, occasional monitoring for quality control often provides a basis for quick remedial action and therefore reduced construction claims.
Fig. 1 Schematic of PDA testing system
Fig. 2 PDA unit (PAK Model) and gages ASI Wave Equation Analysis of Pile Driving (WEAP)
The Wave Equation Analysis of Pile driving (WEAP) is a computer program that simulates motions and forces in a foundation pile when struck by an impact pile driving hammer. In a Bearing Graph Analysis (most commonly used), a pile at the design embedment depth is modeled to simulate its response to impact by the specified hammer and driving system. Dynamic soil parameters used in the modeling are based on available soil information. When actual dynamic testing data is available, more representative dynamic soil parameters determined by CAPWAP analysis can be substituted to produce a Site-Specific WEAP Analysis. Fig. 1 below shows Bearing Graph results, done as a band with the upper and lower boundaries (dashed lines) representing the ranges for optimistic and pessimistic expected pile behavior. A site-specific bearing graph produced following the actual dynamic testing is also shown as a solid line plot. In a Bearing Graph analysis the WEAP program computes the following (see sample output in Fig. 2):
The blow count (number of hammer blows per unit length of permanent set) of a pile under one or more assumed ultimate resistance values and other dynamic soil resistance parameters, given a hammer and driving system (helmet, hammer cushion, pile cushion) The axial stresses in a pile (tension and compression) corresponding to the computed blow count The energy transferred to a pile Based on the results, the following can be indirectly derived: The piles bearing capacity at the time of driving or restriking, given its penetration resistance (blow count) The stresses during the pile driving The expected blow count if the actual static bearing capacity of the pile is known in advance (i.e. from static soil analysis) WEAP Bearing Graph analysis is the best available tool to produce criteria for pile driving termination. Combined with Dynamic Testing and CAPWAP analysis, a Site-specific Bearing Graph offers the most reliable correlation between observed blow count and pile capacity. Another application of the WEAP program is the Driveability Analysis. This analysis is performed to simulate the actual driving of the pile and can be described as a series of Bearing Graph analyses performed at different depths of penetration (see sample output in Fig. 3). A Driveability Analysis can simulate construction details such as splicing, soil set-up during waiting time when driving is interrupted, change in pile cushion stiffness during driving, and other aspects. Sample driveability analysis results for initial driving and restrike conditions are shown in Figs. 3 and 4, respectively. Combined with a static analysis of pile capacity, WEAP driveability analysis is a very useful tool for pile design, driving system selection, and estimated driving time. 0 200 400 600 800 1000 Penetration resistance (Blows/m) 0 500 1,000 1,500 2,000 2,500 3,000 Site-specific Bearing Graph Lower bound (pessimistic behavior) Upperr bound (optimistic behavior) Site-specific Bearing Graph
Fig. 1 WEAP prediction and Site-specific Bearing Graph
ASI ASI Fig. 4 Sample WEAP Driveability Analysis output Restrike conditions
CASE Pile Wave Analysis Program (CAPWAP)
Case Pile Wave Analysis Program (CAPWAP) combines measured force and velocity data with wave equation analysis to calculate the soil resistance forces acting on the pile. Because force and velocity measurements are the pile top input excitation, it is not necessary to model the hammer and driving system as in a wave equation analysis. CAPWAP models the pile as a series of continuous and uniform segments. Each segment is of uniform cross-section but segments may be different from each other (for modeling non-uniform piles). A soil model similar to Smiths wave equation model is assumed, which includes the total resistance and its distribution, damping constants, and quakes. Fig. 1 shows a simplified illustration of the CAPWAP soil model for a single segment along the pile shaft. A similar model is used for the toe segment. In summary, the CAPWAP results are based on best possible match between a computed pile top variable (i.e. the pile top force) and its measured equivalent. When the match is unsatisfactory, the process of iteratively changing the soil resistance parameters and computing the pile top variable is repeated. The potentially large number of unknowns in the soil model could make signal matching a frustrating effort. The PDA measurements need analysis and expertise to be useful. After dynamically testing a pile with the Pile Driving Analyzer (PDA), preliminary CASE Method Estimates of capacity are reported. The accuracy and reliability of a CASE method is dependant on many variables such as: resistance distribution, soil damping, pile penetration velocity, etc... To determine the applicable Case Method Estimate, CAPWAP analysis must be performed.
Fig. 1 CAPWAP soil model The traces of force and velocity measured in the field will be matched with force and velocity computed by CAPWAP to provide the foundation engineer with the following wave equation parameters: Applicable Case Method Estimates of capacity Shaft resistance, magnitude and distribution Toe resistance Shaft and toe damping Shaft and toe quake Simulated pile behavior under static analysis Fig. 2 shows a sample distribution of computed shaft resistance. A typical graphical output of CAPWAP analysis is presented in Fig. 3 Fig. 2 Computed shaft resistance distribution
ASI ASI
Fig. 3 Sample graphical output of CAPWAP analysis results
Typical Dynamic Testing Program
Dynamic testing and monitoring is not an off-the-shelf product bought at the lowest price possible, but a professional service provided by highly trained engineers and adapted to the project. The Pile Driving Analyzer is not a black box with all the answers popping out when gages are attached to the pile, but a tool to use with skill and experience of the PDA and CAPWAP engineer. The measurements need to be adapted to the project and properly analyzed and reported. Using it simply as low cost replacement for a static loading test and neglecting all other information coming out of proper records and analyses is wasteful. The designer should think through the testing program and the specifications should spell out the extent of the testing and reporting required for the project. CAPWAP Analysis: Activated bearing capacity is given by CASE Method estimates which are dependant on factors such as resistance distribution, soil damping, early unloading, and other factors. This dependency may result in a wide range of estimated capacity by the various methods, many of which may not be applicable. CAPWAP analyses of properly selected test records would confirm the true activated capacity and would narrow the range of CASE Methods representative of the test piles and site conditions. The number of CAPWAP analyses required is dependant on variations in soil conditions, pile details, and pile behavior. When testing at end of initial driving and at restrike, both tests should be subject to CAPWAP analysis. Site Specific WEAP Analysis: Dynamic soil parameters determined by CAPWAP analysis should be used as input to WEAP to determine a site specific bearing graph that can guide the piling inspector during production piling. Any production pile that is not within reasonable agreement with the site specific bearing graph should be subject to PDA monitoring for additional investigation. Dynamic Testing Program WEAP Analysis: Wave equation analysis will marry the hammer to the pile and soil and to the particular driveability conditions and desired capacity to obtain values of energy, force, stresses, and blow count. The result should be the Bearing Graph as a band with the upper and lower boundaries representing the ranges for optimistic and pessimistic expected behavior. When hammer selection and pile embedment are to be optimized, a Driveability analysis may be an ideal tool. Dynamic Testing Report: The representative CASE Methods and CAPWAP results are reported along with important PDA data such as: Transferred energy: to verify hammer performance Maximum compressive stress in the pile: important at initial driving to investigate damage potential due to prolonged hard driving Dynamic testing and monitoring: Testing program should be before or at the beginning of piling activities Maximum compressive stress at the toe: important when driving to bedrock or if boulders are encountered Test piles should be spread across the site to represent the subsurface conditions of the site as much as possible Maximum tensile stress: crucial when driving concrete piles Number of test piles should be in proportion to the area of the site as well as to the number of production piles (i.e. 5 to 15 percent of production piles or in case of a small bridge, at least two test piles at each abutment and each pier) Observed penetration resistance: (blow count), to correlate with measured activated capacity Fig. 1 shows a typical presentation of PDA and CAPWAP data.
PDA monitoring of test piles at end of initial driving and later at restrike (wait time depending on soil conditions) to determine time-dependent soil strength changes (set-up/relaxation). Monitoring during initial driving is particularly important for developing driving and termination guidelines, and when potential pile damage is high. ASI ASI