AbstractGrid connected distributed generation (DG) can not
only increase reliability, but also provide additional benefits for
consumers as well as utilities. Microturbine (MT) generation system is regarded as the best way of distributed generation for its excellent performance. The paper introduces microturbine as a back-up power supply during power system black-start. It emphasizes on analyzing the characteristics of the microturbine as a back-up power supply, simulating the inrush current of the transformer and the load disturbance of asynchronous motor. The results indicate that the microturbine show excellent performance as a back-up power supply.
Index Terms-- microturbine, back-up, inrush current, load disturbance, simulation I. INTRODUCTION S power grid grows to be a huge and complicated system, more and more attention has been put on the stability of power system. During PES General Meeting 2004, experts discussed the causes of black-outs and how to deal with them. Generally they agreed that the causes of blackouts were complicated, and black-outs were impossible to completely avoid. Measures could only narrow the range of power failure and speed up system restoration. Almost all the papers on blackouts emphasize the importance of system restoration which is regarded as the last defense line of the power system [1]. Setting down black-start project is always extremely important before the system breaks down after major failure. In those areas with high load density there is always no hydropower plant, such as Pearl River Delta in China. Oil- fired and gas-fired plant is regarded as the main generation unit in these load centers. When power system fails down, the oil-fired plant is the only dependable resource [2]. According to the Eleventh Five-year Planning of Guangdong province, small thermal power generating units with low efficiency and high pollution will withdraw operation, and emphasis is put on
This work is supported by the National Natural Science Funds Project (50807016) and the Guangdong Natural Science Funds Project (06300091). The authors gratefully acknowledge the support of the Hong Kong Polytechnic University under Project G-U494. Dr. Tao Yu is with the College of Electrical Engineering, South China University of Technology, Guangzhou ,Guangdong 510641, China (e-mail: taoyu1@scut.edu.cn). Mr. Jia-peng Tong is with the College of Electrical Engineering, South China University of Technology, Guangzhou ,Guangdong 510641, China (e- mail: bird841011@163.com). Dr. K. W. Chan is with the Hong Kong Polytechnic University, Hong Kong, China (e-mail: eekwchan@polyu.edu.hk). developing high efficiency and huge size nuclear power units, supercritical coal-fired units and gas-steam combined cycle units. Because these newly developed units are generally above 300MW, the standby diesel generator can only supply the emergency lighting for its limit in capacity. The start-up of these units seriously relies on power grid. These areas are going into an embarrassing situation of losing black-start resource. Look back to US-Canada 8.14 blackout, one of the largest natural gas transmission and storage corporations use Capstone Microturbine at several of their facilities. Dominion Transmission kept the gas flowing when they lost power for more than a day [3]. Microturbine generation system is a new developed thermal generator. Because it has the characteristics of high reliability, excellent dynamic performance, longevity of service and high efficiency, it is regarded as one of the best promising ways of distributed generation. Typical MT generation system is show in figure 1. It has shown excellent performance as backup power supply during emergency. The paper proposes a technique for operation of MT to participate power system recovery control as a back-up power supply in black-start. Emphasis is put on analyzing the stand-by ability, structure and improvement of MT in black-start. Then the paper does some research on inrush current when energizing no-load transformer and load disturbance of asynchronous motor. The results show that inrush current can be restricted within a lower level, and load disturbance will not cause too much influence to the generation system. MT is a good choice for back-up power supply.
Fig.1. Microturbine generation system diagram
Study on Microturbine as a Back-up Power Supply for Power Grid Black-start Tao YU, Jia-peng TONG, K. W. Chan A 978-1-4244-4241-6/09/$25.00 2009 IEEE
Fig. 2. Microturbine model II. MICROTURBINE GENERATION SYSTEM There are two types of microturbine design. One is a high- speed single-shaft with the compressor and turbine mounted on the same shaft as the alternator. And the other is a split- shaft design that uses a power turbine rotating at 3600 rpm (or 3000 rpm) and a conventional generator (usually induction generator) connected via a gearbox [4]. This paper studies on the former design. MT produces electric power while operating at a high speed, generally in the range of 5,000 to 120,000 rpm. Electric power is produced in high frequency, and converted to DC voltage, then inverted back to grid frequency and AC voltage by the inverter [5]. If it is assumed that the microturbine is operated at all times close to its rated speed, and the start up and shut down processes are ignored at the same time. A simple model can be built [6] as it is shown in figure 2. The model is made up of speed control; accelerate control; temperature control and fuel system. The exhaust temperature function f 1 and torque function f 2 is given by ) 1 ( 550 ) 1 ( 700 1 + = f R W T f (1) ) 1 ( 5 . 0 ) 23 . 0 ( 3 . 1 2 + = f W f (2) Where denotes turbine speed, W f denotes fuel flows signal, T R denotes exhaust temperature. The torque function is accurate to within 5 percent at part load, and is significantly accurate at rated value. The exhaust temperature function is some what less accurate at part load. But it is only active at the design point, and the impact of the part load inaccuracy can be ignored [7]. The detail model of MT generation system is shown in reference [8], and reference [9] does some research on MT control strategy. The Auto disturbance rejection control (ADRC) can improve the stability and robustness of MT. A. Structure As previously mentioned, the MT is designed integrated with permanent magnet generator. The compressor impeller, turbine rotor, and generator rotor are mounted on a single shaft, which comprises the only moving part in the engine. It needs little maintenance, usually operates above 8000h continuously. Voltage source inverter (VSI) applied to MT system. It can operate connected to a utility grid of provide stand alone power to critical loads. Transition time between these two operating modes is less than 10 seconds. Traditional backup resource such as diesel engine just sits there as idle asset. But MT system can serve as continuous power supply, not only supply power during normal situation to the network as distributed generation, but also quickly transit to serve as emergency power supply during black-start. It can save money for black-start ancillary service. Besides, its compact structure can save much space. B. Back-up ability A MT unit can produce 25-500kW of electrical power [10], and larger size of MT range from 600kW to 1000kW has been developed. MT has played an important role in CERTS microgird. The CERTS has done some research on the behavior of two Capstone MTs [11]. A nature gas fuel pod which is easily obtained can operate the two MTs at full load for about 7 hours. Apparently single unit can not provide enough back-up ability. But Capstone PowerServe CPS100 can integrate up to 100 Capstone MT into a single generation system with one point of control and higher efficiency system dispatching. With efficiency and reliability, the PowerSever delivers a new level of clean, versatile Capstone power to serve loads from a few kilowatts to a few megawatts [12]. MT units can not only serve as auxiliary motor to start generators of several megawatts capacity, but also have the ability to start larger units. C. Black-start units Hydro power plants are always used for power system restoration. They need very low cranking power which can be easily supplied by auxiliary turbines, small diesel generators or battery storage system. They have high reliability and only need few minutes for starting. These plants are of relatively low regulating capability due to the slow response of the speed control system. Whats more, they are usually at remote location [12]. Small oil-fired plant and heavy duty gas turbine can also be used as black-start resource. But small oil-fired plant is going out of operation, and heavy duty gas turbine always needs more cranking power. All these units including
the supercritical coal-fired units and gas-steam combined cycle units need cranking power to achieve the self-starting ability. Its uneconomical to provide such a large standby capacity, especially diesel generator. Recognizing that black- start facilities are often not economic in normal grid operation, the grid operator has commercial agreements in place with some generators to provide black-start capacity. MT generation system can solve this problem. Typical MT efficiencies are 25% to 35%. When in a combined heat and power cogeneration system, efficiencies of greater than 80% are commonly achieved. And Capstone C200 can limit NO x
emissions under 9ppmV [12]. D. Black-start strategy There are two basic strategies have been adopted worldwide for defining the procedures for system restoration: restoration by zones and by paths. The criteria for choosing an approach are strongly affected by the generation mix and by the number of black-start units. The restoration by zones better fits to systems with several black-start resources, while restoration by paths fits to the cases where black-start capacity is small or clustered in restricted areas [13]. As mentioned in the introduction, there are not enough black-start resources. The first strategy is not suitable. Sometimes the black-start paths are very long, and there are no generators along the path to sustain voltage. Whats more, the path may be cut off for some reasons. The second strategy is difficult to accomplish. By applying MT to modify some plants, more black-start resources are obtained. Not only restoration by zones can be realized, but also restoration by paths is suitable. III. CASE STUDY AND SIMULATION There are four important issues need to be solved during black-start: inrush current when energizing no-load transformer; no-load closing over voltage; generator self- excitation and load disturbance of asynchronous motor. Inrush current will gradually reduces to the steady condition through a few periods. With permanent magnet generator there is no risk of self-excitation. Switching over-voltage is caused by breaker operation and various faults, and power frequency over-voltage is caused by capacitive effect. Inrush current will not bring deadly damage to the transformer, because it will not last long. But during black- start process it must be safe enough to keep stable. The DC system of MT can eliminate the influence of inrush current to some extent. In order to start the large capacity unit without self-starting ability, power plant load should be start first, usually accompany with large starting current. MT system can withstand the disturbance for its excellent dynamic performance. A. Sequence of Action for Black-start with MT During the process of black-start, a set of rules and action needs to be followed, which can be identified in [14]. Reference [15] provides a project on how to use a 250kW diesel generator to start a 38MW gas turbine, and then use the gas turbine to start two larger generators with capacity 130MW and 300MW. With the participation of MT the 250kW diesel generator can be replaced, and the operation sequence can be established through the following three major stages: building low voltage network; forming island and re- synchronous. The paper concentrates on the first stage. Considering the most serious situation, all the power supplies including MT are cut off. Firstly, the MT can be started with the help of its own permanent magnet generator which is used as starter motor during start-up. The starting power is provided by its own battery. The complete start sequence from front panel initiation to full power output is about 2 minutes. The current MT units is able to ramp from 0 to full load in about 20 seconds when in stand-alone mode, while in grid-connect mode it need another 10 seconds [16]. The battery can provide power during load changes, load disturbance can be restrained to some extant to achieve a good dynamic performance. Secondly, the MT is used as auxiliary motor to start larger generators (of several megawatts to several tens megawatts capacity). Finally, the started generator can be used to start the main power station generators or other station generators which is not far away. During this stage, the above three important issues should be paid high attention to. As more power plants are started, an island is formed. Several islands need to be resynchronized with the upper-stream network by following the conditions of synchronization. B. Practical Cases Study During early stages of power system restoration, over- voltage and self-excitation usually makes it impossible to energize long transmission line. As the oil-fired units withdraw operating, there are not enough black-start resources that can depend on. Take DongGuan for example, there is only one plant have the ability of self-starting in northwest. It is impossible to energize such long transmission line to start middle and east network [17]. In order to accomplish power system restoration, more black-start resources are required. MT can be applied to modify those units without self-starting ability in the middle and east of DongGuan. It is possible to sectionalize a system into subsystems to allow parallel restoration of islands, and thus reduce restoration duration [18]. On December 26, 2005, large portions of Hainan province, China, experienced an electric power blackout as a result of Damery typhoon. As main power plants, Haikou plant did not equip with emergency power supply. Hainan power grid temporarily changed path to supply power to Haikou plant from other successfully starting plants [19]. This always causes failure. But MT system can improve the situation. According to the cases above, two solutions can be made. Firstly, if the MT units locate a distance away from the plant, electrical power can be transmitted to the 10kV bus of the plant through 10kV transmission line after voltage transformation, as it is shown in figure 3. The MT units can be some large enterprises owned power supply. The power grid company can make commercial agreements with them to
provide black-start ancillary service. Secondly, the plant and power grid company can reach some agreements to install MT units in the plant. The MT units can not only serve as a standby power supply, but also play an important role in power supply to some critical plant load.
Fig. 3. Using MT units to start a plant C. Simulation of Inrush Current The rated capacity of MT system is 30kW. The MT generation system first operates at one third of its capacity, then a 50kW 380V/10.5kV transformer is energized at t=10 seconds. Figure 4 shows the simulation results.
(a) Inrush current
(b) Speed
(c) Torque
(d) Load voltage Fig. 4. Simulation results of inrush current
The results show that the inrush current will not cause commutation failure if MT system energizes the transformer with its capacity no more than two times of generation capacity. The DC system made up of rectifier and inverter can well isolate inrush current from affecting MT system. The inrush current will completely attenuate in 10 periods. MT units can resist more serious disturbance of inrush current than single MT unit. MT units have the ability to energize the 10kV/380V station service transformer, but dont have the ability to energize 10kV/110kV or higher level voltage transformer. D. Load disturbance of asynchronous motor The rated capacity of MT system is 30kW. The MT generation system first operates one third of the capacity, then a 15kW asynchronous is energized at t=15 seconds. Simulation results are shown in figure 5.
(a) Torque
(b) Speed
(c) Direct current
(d) Load voltage Fig. 5. Load disturbance of asynchronous motor
Simulation results indicated that MT system based on voltage source inverter can withstand asynchronous motor load disturbance. A relatively long oscillation happens to the speed because of the transit plus current. Because the asynchronous motor absorbs plenty of reactive power, and the load voltage decreases. However, the speed will not go instable, and the load voltage goes back to its rated value after a relatively long oscillation process. IV. CONCLUSION The paper does some analysis on the MT system structure and performance. Emphasis is put on how to apply MT system to black-start process. The second half part does some validation. It includes: The capacity of single MT generation system is small, but up to 100 microturbines can be integrated into a single generation system. And more effective control strategy can be applied to it to obtain better performance. It can not only meet the demand for emergency power supply during black-start, but also provide a safe and reliably station power supply. Voltage source inverter is applied to MT system. In can control both active power and reactive power simultaneously and separately. With good regulation performance it can withstand various kinds of disturbances during black-start, especially asynchronous motor load disturbance. Inrush current caused by energizing no-load transformer can be well inhibited by the voltage source inverter. The load voltage can be well regulated at rated value. The DC system can isolate inrush current from impacting on the microturbine. MT can be applied to modify the plants without self- starting ability. More black-start sources are obtained. It can not only speed up the black-start process, but also sectionalize a system into subsystems to allow parallel restoration of islands. But the paper does not find a good solution on simulating a group of MT units. Further research should focus on researching on MT units performance. V. REFERENCES [1] FU Shu-ti, Summary on power system security problems on 2004 IEEE PES meeting and recommendation for developing defense measures, Automation of Electric Power Systems, vol. 29, pp. 1-4, Apr. 2005. [2] YU Tao, WEI Man-fang, and CHANG Ka-wing, Simulation and experimental study on transformer excitation inrush current in black-start of oil-fired thermal plants, RELAY, vol. 34, pp. 32-36, May. 2006. [3] D. Engle, The benefits of onsite power, Distributed Energy [Online], Nov. 2003, pp. 47-50. Available: http://www.DistributedNRG.com. [4] Y. Zhu, K. Tomsovic, Development of models for analyzing the load- following performance of microturbines and fuel cells, Electric Power System Research, vol. 62, pp. 1-11, Dec. 2002. [5] Amer Al-Hinai and Ali Feliachi, Dynamic model of a microturbine used as a distributed generator, in Proceedings of the Thirty-Fourth Southeastern Symposium on System Theory, pp. 209-213. [6] Rowen W. J., Simplified mathematical representation of heavy duty gas turbines, ASME Journal of Engineering for Power, vol. 105, pp. 865- 869, Jul. 1983. [7] F. Jurado, Modeling micro-turbines using Hammerstein Models, International Journal of Energy Research, vol. 29, pp. 841-85, Otc. 2005. [8] Tao YU, Jia-peng TONG, Modeling and simulation of the microturbine generation system, Power System Protection and Control, to be published. [9] Tao YU, Jia-peng TONG, Auto disturbance rejection control of microturbine system, in Proceedings of IEEE/PES 2008 General Meeting: Conversion and Delivery of Electrical Energy in the 21st Century, pp. 1-6. [10] Amer Al-Hinai, Ali Feliachi, Dynamic model of a microturbine used as a distributed generator, in Proceedings of the Thirty-Fourth Southeastern Symposium on System Theory, pp. 209-213. [11] Robert J. Yinger, Behavior of two capstone 30kW microturbines operating in parallel with impedance between them, California Energy Commission, California. [Online]. Available: http://certs.lbl.gov/pdf/55907.pdf [12] www.microturbine.com. [13] S. Barsali, D. Poli, A. Pratico, et al, Restoration islands supplied by gas turbines, Electric Power Systems Research, vol. 78, pp. 2004-2010, Aug. 2008. [14] J. J. Ancona, A framework for power system restoration following a major power failure, IEEE Transactions on Power Systems, vol. 10, pp. 1480-1458, Aug. 1995.
[15] LI Su-ning, Operation mode arrangement of generator during black-start experiment, Automation of Electric Power Systems, vol. 31, pp. 104-107, Sep. 2007. [16] Robert J. Yinger, Behavior of Capstone and Honeywell microturbine generators during load changes, California Energy Commission, California. [Online]. Available: http://certs.lbl.gov/pdf/49095.pdf [17] Dongguan Electricity Supply Branch Company, "Black-start project revision 2008," Otc. 2008. [18] M. M. Adibi and L. H. Fink, Power system restoration planning, IEEE Trans. On Power Systems, vol. 9, pp.22-28, Feb. 1994. [19] TANG Si-qing, ZHANG Mi, LI Jian-she, et al, Review of blackout in Hainan on September 26th---causes and recommendations, Automation of Electric Power Systems, vol. 30, pp. 1-8, Jan. 2006. VI. BIOGRAPHIES YU Tao was born in Kunming, China, on January 11, 1974. He received the bachelors degree from Electrical Power System from Zhejiang University, China. He received the M.S. degree in Hydroelectric Engineering from Yunnan Polytechnic University, China, in 1999, and received the Ph.D degree in Electrical Engineering from Tsinghua University, China, in 1999. Now, he is an associate professor in the electrical power college, South China University of Technology, China. His special fields of interest include artificial intelligence techniques in planning and operation of power and industrial systems. TONG Jia-peng was born in Longyan, China, on October 11, 1984. He has received the bachelors degree from College of Electrical Engineering and continues his master program at South China University of Technology in 2007. His research interests are power system control and distributed generation technology.
K.W. Chan received his BSc and PhD Degrees in Electronic and Electrical Engineering from the University of Bath (UK) in 1988 and 1992, respectively. His doctoral research study was in the area of real-time power system simulation using parallel processing techniques. From 1993 to 1997 Dr Chan was with the Power System and Energy Group at the University of Bath as a research officer. During this period, he successfully completed two EPSRC/ERCOS co-funded research projects. Extensive works has been done in the area of on-line dynamic security assessment of large complex power systems. A scalable distributed security assessor, which ran on a network of heterogeneous computers, was developed as a product of this work.Dr Chan joined the department of Electrical Engineering of the Hong Kong Polytechnic University in 1998 as a lecturer and promoted to Assistant Professor in 2005. His general research interests include power system stability, analysis, control, security and optimization, real-time simulation of power system transients, distributed and parallel processing, artificial intelligence techniques.