1. You gave the software for independent testers. You are responsible for Unit, Integration,
System and Acceptance testing. Explain about each testing methods and tell which
testing can be given to Independent Testing and Which for development team.

2. Any 3 tools and vendor of the tools.

3. One question on Optimum testing

4. You developed Risk Plan, Test Plan, Test Scripts. You are doing testing. At this point you
got major requirements change. What changes are required to in-corporate these
changes in your plan.

5. Explain about
Complexity Measures
Data Flow Analysis
Symbolic Execution

6. Acceptance Test Plan for “Inventory Control Software” contents and explanation.

7. What are CSF s. What are the CSFs that u ll look for in a contactor delivered software.
Define them.

8. Security Vulnerabilities for e-comm application

9. E-commerce project is newly developed in your organization. You are not able to test all
types of Operating Systems and Browsers. Prepare mitigation plan.

10. V-Model

11. Reliability and maintainability are certain Quality factors given explicitly in the
requirements. If so, list a few other QFs for a web based project and write the rationale
for selecting the same.

12. 5 important things you consider for writing test plan, why do you think they are
important.

13. The UI for a defect management tool.

14. Difference between Acceptance and System Testing

15. Mention and write on a few techniques for the defect prevention - internal control
testing.

16. 3 important issues for wireless technology.

17. One question on Pareto Charts - Like gave a scenario for no. of critical, minor and major
bugs and no. of days to fix the bugs. Analyze the scenario.
18. What are important Quality factors that u will test for in a multiple workstation scenario
that u will not do in a single work station scenario.
19. The contents of a system test report.

20. List 5 test metrics and explain how u can use them.

21. Which steps in a testing process are defect prone- explain why?

22. What according to you are the important docs that u would refer when u r testing a
change that has been made in a project that has been released.(i.e. operational)

23. What do u mean by defect expectation. How can u use it for improving the testing
process.

24. Mention three techniques for unit testing. State an objective for unit testing, Based on
those, how will ensure that the unit testing has complied to the expectations.

25. Steps involved in testing for security.

26. What are the important things that u ll look for during a demo of a contractor software.

27. How do u use control charts for controlling the testing process. Explain control charts.

28. If the code to be delivered will be delivered after a week but no change in release date,
how will you as test manager plan yr test. (a question that has appeared in lot of previous
question papers. the phrasing is wrong here. but the same)

29. As a test manager - test skill set relates question (I am not sure).

Objective Questions:

1. Which communication skill will be neglected by most


a. Reading
b. Listening
c. Writing

2. Therapeutic listening is
a. Sympathetic listening
b. Listening to pieces of information…

3. Which model demonstrates relation between 2 or more parameters of effort, duration or


resource?
a. Cost
b. Constraint
c. Function Point

4. In which model expertise can be used to estimate cost


a. Top-Down
b. Expert Judgment
c. Bottom-Up
5. Two objective questions on responsibility
Like who is responsible in issuing IT policy, work policy etc.

6. Fit for use is


a. Transcendent
b. Product Based
c. User Based
d. Value Based

7. Re-Use of data is done in which type of testing (Similar type 2 questions. Re-Use,
Retesting sort of qs.)
a. Capture/Play back
b. System Testing
c. Regression Testing
d. Integration Testing

8. 1 qs. On configuration management / Change Management / Version Control

9. In Acceptance testing, which data is used.


a. Test Cases
b. Use Case
c. Test Plan

10. In four components of FIT, reliability is included in (Similar type 2 qs)


a. Data
b. People
c. Structure
d. Rules

11. Obligations of both contractual parties should be spelled out in


a. What is done
b. Who does it
c. When it is done
d. How it is done

12. Dates on which Obligations need to be filled out should be specified in


a. What is done
b. Who does it
c. When it is done
d. How it is done

13. Two questions on Internal Auditor, Internal Control responsibilities

14. One question on ERM model

15. One question on Control Frame Work Model

16. Two questions on CMM 5 levels of maturity (Like in which level controls are
implemented…)