Dr shyamaprasad mukharjee thermal power station is operated by Chhattisgarh state power Generation Company limited. It has a installed capacity of 5oo megawatts consisting of two coal fired Bhel boilers of 250 megawatts each. During the changing of bearing the bearing sitting area of the gear box cracked due to miss handling. The gear box contains oil inside for lubrication of gears. A buffering layer of eutec
Dr shyamaprasad mukharjee thermal power station is operated by Chhattisgarh state power Generation Company limited. It has a installed capacity of 5oo megawatts consisting of two coal fired Bhel boilers of 250 megawatts each. During the changing of bearing the bearing sitting area of the gear box cracked due to miss handling. The gear box contains oil inside for lubrication of gears. A buffering layer of eutec
Dr shyamaprasad mukharjee thermal power station is operated by Chhattisgarh state power Generation Company limited. It has a installed capacity of 5oo megawatts consisting of two coal fired Bhel boilers of 250 megawatts each. During the changing of bearing the bearing sitting area of the gear box cracked due to miss handling. The gear box contains oil inside for lubrication of gears. A buffering layer of eutec
At Dr SHYAMA PRASAD MUKHARJEE THERMAL POWER STATION
Submitted by NARENDRA PATEL EASE KORBA
DR SHYAMA PRASAD MUKHARJEE THERMAL POWER STATION AT A GLANCE
Dr Shyama Prasad Mukharjee thermal power station is operated by Chhattisgarh state power Generation Company limited. Dr Shyama Prasad Mukharjee thermal power station, Korba is situated in the heart of the city. It is built in the place where the first power plant of Korba was built in 1958. It has a installed capacity of 5oo megawatts consisting of two coal fired Bhel boilers of 250 megawatts each. The first unit was commissioned on 30 th March 2007 and the second unit was commissioned on December 11 of the same year. Dr Shyama Prasad Mukharjee thermal power station has always welcomed new ideas and concepts for improvising its efficiency. Reformation of process is a regular feature at KTPS. The plants officials are always ready to adopt newer technologies and believe in continual improvement and setting newer bench marks. EWAC Association goes hand in hand from last 3 decades. EWAC services are regarded very high at Dr Shyama Prasad Mukharjee thermal power station. Various technologies have been offered to the plant which has been very well accepted by the plant
ABOUT THE JOB The gear box is situated in the primary air fan area to reduce the rpm of electrical motor to that required for fan. During the changing of bearing the bearing sitting area of the gear box cracked due to miss handling.
(crack of air preheater gear box)
Application details Nature of problem- crack developed due to improper handling Base metal- cast iron Recommended electrode- Eutectrode 27 and Xuper 2240 Reason for recommending these electrodes The gear box contains oil inside for lubrication of gears. Since the base metal is cast iron, it soaks oil so a buffering layer of eutectrode 27 is required because it can seal the impurities and the bonding between the base metal and required joining electrode should be perfect.
Xuper 2240 has a nodular cast iron deposit which provides improved crack resistivity. It is highly machinable. It provides a tensile strength of 57000 Psi which ensures a high safety of margin. The weldability of the electrode is excellent.
STEP BY STEP WELDING PROCEDURE 1st step- The cracked metal part is removed by grinding. The grinding is done till the complete crack is removed.
2nd step Dye penetration test is done to check that the crack is removed completely.
3 rd step The preheating is done with oxy- acetylene flame to 200 degree Celsius and welding is started.
A single layer of eutectrode 27 is deposited to seal the contaminants inside. Due to use of eutectrode 27 the next phase of welding become easier because it sealed all the oil and impurities.
4 th step Welding current is set to as low as possible to burn the electrode to preserve the quality of weld deposit and to prevent over heating of electrode. Short stringer beads of Xuper 2240 are welded and after welding the bead peening is done with a ballpin hammer to remove the internal stress and flux is removed with the help of a chipping hammer and with the help of stainless steel wire brush. This process is done till a complete layer is overlaid and then the weld overlay is slightly grinded to remove any flux residues. Then temp of job is checked and preheating is done once again to bring the job temp to again 200 degree Celsius. The process is continued till the total area is completly buildup to required thickness.
Final view of job after welding
For Further Information Please Contact NARENDRA PATEL EASE KORBA Ph-07509572413 Mail- np.ewac@gmail.com