The impact from regulatory regimes on the WACC Executive Summary 1 1 Background and scope of the study 7 1.1 Context....................................................................................... 7 1.2 Scope of the study ..................................................................... 7 1.3 Structure of the report ................................................................ 8 2 Regulation of energy network in Czech Republic 9 2.1 Regulation of energy networks 2010 to 2014 .......................... 9 2.2 EROs actions during 3 rd regulatory period .............................. 10 2.3 EROs action and the regulatory climate .................................. 11 3 Relationship between regulation and risk 13 3.1 Channels for transmitting changes in risk to the WACC .......... 13 3.2 Role of regulation in the cost of financing ................................ 15 3.3 Regulation and risk the view from rating agencies ................ 19 3.4 Key findings Regulation and risk ........................................... 22 4 Regulation and risk selected European countries 23 4.1 UK ............................................................................................ 24 4.2 Germany .................................................................................. 33 4.3 France ...................................................................................... 40 4.4 Key findings Regulation and risk in UK, Germany and France ................................................................................................. 48 5 Regulation and risk Czech Republic 49 5.1 Stability and Predictability of the Regulatory Regime ............... 49 5.2 Cost and Investment Recovery and Revenue Risk ............. 55 5.3 WACC Cost recovery for cost of capital at risk ..................... 61 5.4 Key findings Regulation and Risk for CZ gas distribution companies ................................................................................ 67 ii Frontier Economics | September 2013
Contents
6 Conclusion 69 7 References 73
September 2013 | Frontier Economics iii
Tables & Figures
The impact from regulatory regimes on the WACC Figure 1. Channels for transmission of risk changes to the WACC 14 Figure 2. Principal outputs under RIIO GD1 30 Figure 3. Investment indicators 44 Figure 4. Quality of service indicators 45
Table 1. Regulation and Risk and the impact on cost of capital 2 Table 2. Regulation and Risk and the impact on cost of capital 5 Table 3. Moody's methodology for rating regulated electricity and gas networks 20 Table 4. Regulatory parameters RIIO-GD1 29 Table 5. WACC parameter UK 32 Table 6. Regulatory parameters Germany 36 Table 7. Cost of equity parameter Germany 38 Table 8. Regulatory parameters France 42 Table 9. WACC parameter France 46 Table 10. Regulation and Risk and the impact on cost of capital 48 Table 11. Stability and Predictability of Regulatory Regime from 3 rd to 4 th regulatory period 55 Table 12. Regulatory components CZ gas distribution companies 56 Table 13. Cost and Investment Recovery and Revenue Risk from 3 rd to 4 th regulatory period 59 Table 14. WACC 3 rd to 4 th regulatory period 62 Table 15. Frontiers assessment Rating factors from 3 rd to 4 th
regulatory period 63 Table 16. Regulation and Risk and the impact on cost of capital 70
September 2013 | Frontier Economics 1
Executive Summary
September 2013 | Frontier Economics 1
Executive Summary
Executive Summary ERO proposes substantial adjustments and changes for 4 th regulatory period The Czech regulator ERO is responsible for the regulation of the electricity and gas network companies. The current revenues are set according to the decision on the 3 rd regulatory period (2010-2014) from December 2009, which was the result of a consultation process with all relevant stakeholders starting in 2008. In March 2013 ERO made a first proposal for the regulatory framework of the 4 th
regulatory period including substantial adjustment compared to the previous one, in particular the reversal of former partially acknowledged asset revaluation and a shortening of the 3 rd regulatory period. In August 2013 ERO issued a new proposal including new regulatory instruments and a reduction in the WACC compared to the March 2013 document. RWE Gasnet asked Frontier to compare the regulatory and legal regime and their main components for European peers with the CZ regime with regard to the risk profile regulated entities face and to assess the alignment of the proposed WACC by ERO with the potential increase in risk since the start of the 3 rd regulatory period. Regulatory actions will influence the cost of capital by altering the risks faced by equity and debt investors The cost of capital represents the minimum rate of return companies must pay in order to attract capital from investors. Changes in risk will affect equity investors and debt investors via different channels. Risk will feed into the cost of equity via the beta; and cost of debt via the debt premium. Regulatory actions and regulatory design will influence the cost of capital by altering the risks faced by businesses. Credit rating indicators can reflect the various aspects of the regulatory environment. Moodys covers the regulatory environment by: Stability and Predictability of the Regulatory Regime; Cost and Investment Recovery; and Revenue Risk. Regulatory systems can be compared by analysing how they perform against these indicators and how business risks influence the beta and debt premium. 2 Frontier Economics | September 2013
Executive Summary
Regulation and risk in selected European countries UK, Germany and France In order to assess the return/risk profile of the Czech Republic we compared the regulatory framework with regard to the three Moodys factors covering the regulatory environment for UK, Germany and France. UK sets the benchmark (Aaa) for Stability and Predictability of Regulatory Regime. Germany (A) and France (Aa) get a slight lower rating by Moodys. For Cost and Investment Recovery Moodys rated the countries in the range of A to Baa, Revenue risk in the range of Aaa to A. The corresponding beta and debt premium set by the regulatory authorities in UK, Germany and France are: asset beta in the range of 0.38 to 0.46; equity beta in the range of 0.76 to 0.90; as well as debt premium in the range of 0.60% to 0.90%. Table 1. Regulation and Risk and the impact on cost of capital UK (2013-2021) Germany (2013-2017) France (2012-2015) Stability and Predictability of Regulatory Regime Aaa A Aa Cost and Investment Recovery A Baa A Revenue Risk Aaa A Aa Asset beta 0.38 0.39 0.46 Equity beta 0.90 0.79 0.76 Debt premium 0.90% na 0.60% Source: UK Moodys; Germany and France and Frontier assessment based on Moodys ratings for HSE Netz (Germany) and TIGF (France) Deterioration of Stability and Predictability of CZ Regulatory Regime between 3 rd and 4 th regulatory period First, we compared the regulatory framework of the 3 rd regulatory period for gas distribution companies with the draft proposal from ERO for the 4 th regulatory period. Based on this comparison, we assess the potential impact on risk faced by the companies. We also take EROs action during the 3 rd regulatory period into account. Second, we compared the new draft proposal from ERO for the 4 th
regulatory period and its corresponding return/risk profile with the relevant profiles from UK, Germany and France. September 2013 | Frontier Economics 3
Executive Summary
With regard to Stability and Predictability of Regulatory Regime we conclude that EROs actions may be classified as a non consistent application of the regulatory framework for the 3 rd
regulatory period; or even a significant change compared to the 3 rd regulatory period. We assess a significant downgrading of Stability and Predictability of Regulatory Regime in the 4 th regulatory period. Cost and Investment Recovery and Revenue Risk also affected by EROs proposal There are various factors having a potential adverse direct impact on the Cost and Investment Recovery and Revenue Risk. The main impact stems from the Network utilisation factor, where the specification and application is still pending. We note that the Network utilisation factor depending on its final specification may induce even a sharp downgrade due to asset stranding and/or high exposure to volume risk. In addition, the new mechanism for network losses may have an adverse impact, as well, if ERO is reluctant on increasing network losses. As long as this is still an unresolved issue we make the assumption that the new parameter will slightly increase the risk of cost recovery and the revenue risk resulting in a small downgrade compared to the 3 rd regulatory period. Finally, the efficiency assessment of operating expenditure which allows a retrospective reduction of costs may jeopardize cost recovery, as well. Cost Recovery for cost of capital at risk in 4 th regulatory period In order to assess if the current WACC proposal covers the risks borne by investors in the Czech gas distribution sector it is necessary to compare the risks faced by companies between the 3 rd and 4 th regulatory period. Applying the logic of Moodys rating factors, we assess that the risk faced by gas distribution companies increased between the 3 rd and 4 th regulatory period due to increased uncertainty on the Stability and Predictability of Regulatory regime; and new proposed regulatory parameters which are yet unspecified and may have an adverse effect on Cost and Investment Recovery and Revenue Risk In addition, we assessed a potential adverse effect on selected Moodys key credit metrics, Adjusted Interest Coverage Rate and Retained Cash Flow/Capex from the reversal of asset revaluation. Hence, in order to allow cost recovery for equity and debt investors the increased risk should be reflected in the asset (equity) beta and debt premium. 4 Frontier Economics | September 2013
Executive Summary
Adjustments of beta and debt premium in 4 th regulatory period to allow cost recovery In order to allow cost recovery for the cost of capital the relevant parameters through which this increased risk flows into the WACC beta and debt premium should follow the principles outlined below. Cost of equity The level of the asset (equity) beta from the 3 rd regulatory period should serve as the starting point for the 4 th regulatory period. In order to allow cost recovery a mark-up on this value covering the increased risk between the 3 rd and 4 th regulatory period should be applied. This implies an asset (equity) beta in the range of 0.45 to 0.50 (0.69 to 0.77) for the 4 th regulatory period. Compared with the respective values for UK, Germany and France and taking into account the higher rating in particular for the important factor Stability and Predictability of Regulatory Regime in all three countries this range seems to be a reasonable risk adjusted asset beta and equity beta (Table 2) taking into account the lower notional gearing (40%) proposed by ERO compared with UK (65%), Germany (60%) and France (50%). Cost of debt The risk faced by debt investors between the 3 rd and 4 th
regulatory period did not decrease (in contrary the risk increased). This implies that the implicit debt premium from the 3 rd regulatory period should serve as the starting point for the 4 th regulatory period. However, we further identified a systematic problem in the way ERO currently determines the cost of debt. ERO sets the cost of debt based on a short-term interest rate (1-5years) which is in contrast with the longer term financing and investment horizon for networks and European regulators best practice (substantially above 5 years). Hence, the overall level of the regulatory cost of debt may be substantially below market cost of debt. Hence, the adjustment of the debt premium should reflect the switch from a short-term to a longer-term interest rate. This results in a substantial higher debt premium in the range of 0.70% to 1.30%, which is more in line with the respective values used in UK and France. In addition, ERO should consider including cost of raising debt in the debt premium in the range of 0.10% to 0.20%. September 2013 | Frontier Economics 5
Executive Summary
Table 2. Regulation and Risk and the impact on cost of capital 3 rd reg- period (2010-2014) 4 th reg-period (Aug 2013) UK (2013-21) Germany (2013-17) France (2012-15) Stability and Predictability of Regulatory Regime Aa A * Ba B* Aaa** A** Aa** Cost and Investment Recovery A* Baa Ba* A** Baa** A** Revenue Risk Aa* A Baa* Aaa** A** Aa** adjICR and RCF/Capex Potential downward pressure* - - - Asset beta 0.40 0.35 0.38 0.39 0.46 Equity beta 0.62 0.54 0.9 0.79 0.76 Debt premium (implicit) 0.31% 0.23% 0.90% na 0.60% Frontier adjustments 3 rd reg- period (2010-2014) 4 th reg-period (Aug 2013)
Source: Frontier based on Moodys methodology, Moodys * Assessment by Frontier ** Assessment by Moodys Regulatory principles guiding the specification of the 4 th regulatory period Provided that ERO still insisted in changing the regulatory framework in the 4 th
regulatory period in particular with regard to the reversal of asset revaluation then at least ERO should adopt a more refined logic that explicitly considers the following principles: Avoidance of retrospective interventions Regulators and regulated companies play a repeated interaction game, coming together periodically to agree new cost allowances and incentive mechanisms that will apply for the 6 Frontier Economics | September 2013
Executive Summary
next period. Regulators credibility is therefore key: this also includes that retrospective interventions shall be avoided. Specification of regulatory framework The current ERO proposal for the 4 th regulatory period introduces various new regulatory changes and regulatory instruments, e.g. the Network utilisation factor. However, there is a low degree of specification which hampers companies to assess the specific impact on their costs and/or revenues. In order to increase predictability for companies and also investors a detailed description which can be translated into companies business plans should be provided by ERO as soon as possible. Transparent decision rules In order to maximise the regulatory commitment and stability, ERO should base any new measure announced in the decision for the 4 th regulatory period on transparent decisions rules, which are known to the regulated companies ex ante. This means that the regulated companies must know in advance, which behaviour will induce measures by ERO. For example, this refers to the announced audits on the efficient utilisation of funds from the Network obsolescence factor.
September 2013 | Frontier Economics 7
Background and scope of the study
1 Background and scope of the study 1.1 Context The Czech regulator ERO is responsible for the regulation of the electricity and gas network companies. The current revenues are set according to the decision on the 3 rd regulatory period (2010-2014) from December 2009, which was the result of a consultation process with all relevant stakeholders starting in 2008. In March 2013 ERO made a first proposal for the regulatory framework of the 4 th
regulatory period including substantial adjustment compared to the previous one, in particular the reversal of former partially acknowledged asset revaluation. In August 2013 ERO issued a new proposal including new regulatory instruments and a reduction in the WACC compared to the March 2013 document. ERO stick to the reversal of the asset revaluation, however, it stated that the new regulatory instruments proposed in August 2013 increase the incentives to invest and decrease the risk compared to the March 2013 proposal. 1.2 Scope of the study RWE Gasnet is concerned on the potential impact from the proposed adjustments on risk and the alignment of the risk with the proposed WACC by ERO. In addition, RWE Gasnet is concerned on the long-term stability of the proposed regulatory framework. RWE Gasnet has asked Frontier to Benchmark of the WACC parameters for European peers compared to the CZ figures. Compare the regulatory and legal regime and their main components for European peers compared with the CZ regime with regard to the risk profile regulated entities face in the CZ republic compared to European peers. This includes e.g. predictability of the behavior of the regulator; possibility of legal actions against regulators decisions; as well as regulatory components and their impact on various risks, e.g. volume risk, cost risk. Assess the WACC proposed by ERO in relation to the potential increase in risk since the start of the 3 rd regulatory period. 8 Frontier Economics | September 2013
Background and scope of the study
RWE Gasnet provided Frontier with the respective EROs draft proposals for the 4 th regulatory period from March 2013 (ERO 2013a) and August 2013 (ERO 2013b). 1.3 Structure of the report The report is structured as follows: Section 2 describes the regulatory system for CZ gas distribution companies and the proposed changes for the 4 th regulatory period. Section 3 describes the relationship between regulation and risk and how a change in the risk may feed into the cost of equity and the cost of debt. Section 4 describes the relationship between the regulatory framework and the WACC for three selected European countries, UK, Germany and France. Section 5 analysis behaviour of ERO since the start of the consultation process for the 3 rd regulatory period and the proposed changes for the 4 th
regulatory period with regard to the implication on the risks faced by the gas distribution companies. The section analysis to what extent the proposed WACC in ERO (2013b) aligns with the underlying risk exposure of the companies. Section 6 concludes the results. September 2013 | Frontier Economics 9
Regulation of energy network in Czech Republic
2 Regulation of energy network in Czech Republic This section describes the Czech regulatory regime until the 3 rd regulatory period (2010-2014) and the proposed regulatory framework for the 4 th regulatory period (2015-2019) by the Czech regulator, ERO, with regard to asset revaluation. 2.1 Regulation of energy networks 2010 to 2014 The energy networks are regulated using a revenue cap. The regulatory period is 5 years. The Czech revenue cap is a combination of incentive regulation and cost-plus regulation, where the first applies to operating costs and the latter to capital costs. In 2006 there was an one-off revaluation of the assets based on current costs during the process of unbundling, which resulted in roughly a doubling of the asset value compared to historic costs (step-up) which had to be reflected in the accounting books of the company. Already in the 2 nd regulatory period ERO started a process of gradual acknowledgement of revaluated depreciation which was accomplished in the 3 rd regulatory period. 1 Allowing depreciations based on revaluated assets at current cost in 2006 was a means of providing cash to the companies in order to finance necessary investments. The decision by ERO to acknowledge revaluated depreciation as allowed one was taken after an intense assessment by the ERO and discussion between ERO and the regulated companies on their long-term investment plans. For this a period of 15 years was evaluated. The submitted investment plan in 2009 forecasted for the years 2010 2013 (already) lower investment than depreciation with growing investments exceeding depreciation after 2014. Other aspect of the ERO strategy of providing cash to the companies in the regulatory period was slower depreciation of RAB via deduction of only a share of the allowed depreciation. This share was determined by a ratio of RAB to the revaluated asset value. ERO (2009: 16) stated in 2009 that if companies do not reinvest revaluated depreciation in asset upgrades in a way to preserve their level and the quality of supply, the Office will introduce a mechanism into regulation, which will ensure that allowed depreciation is used solely for investment purposes under the respective licence.
1 Energy Regulatory Office, Final Report of the Energy Regulatory Office on the regulatory methodology for the third regulatory period, including the key parameters of the regulatory formula and pricing in the electricity and gas industries, December 2009. 10 Frontier Economics | September 2013
Regulation of energy network in Czech Republic
The initial value of the regulatory asset base for the 3 rd regulatory period (2010- 2014) has been based on the RAB 2009 which was acknowledged in the previous regulatory period (based more or less on historical costs), which was then adjusted by an initial revaluation coefficient. This revaluation coefficient was calculated by dividing the previous RAB 2009 value with the revaluated asset value in 2009 (comprising the one-off current cost revaluation in 2006 plus new investments at historical costs between 2007 and 2009). Only, if the asset value at historic costs is less than 50% of the revalued assets there is a step up of the assets at historical costs to reach 50% of the revalued assets. In other cases the initial RAB is set at the residual asset value 2009. EROs hybrid approach in relation to asset revaluation differs from approaches used by other European regulators. In countries where revaluation was applied either based on historic or replacement costs , e.g. Norway, Netherlands, Finland, Sweden, the revaluated assets were used to calculate depreciation and also the allowed RAB (and not only to calculate depreciation as in the CZ republic). However, EROs objective for asset revaluation seemed to be similar: supporting a long-term sustainable asset value and signalling investors the long-term stability of the regulatory system with regard to the regulated asset base. 2.2 EROs actions during 3 rd regulatory period We understand that during the 3 rd regulatory period a new head of ERO was appointed by the Czech government with effect from August 1 st , 2011. ERO fundamentally changed its position in relation to asset revaluation. In 2012 ERO made the legal assessment that the regulatory decision for the 3 rd regulatory period contradicts the Czech energy law, which according to the new interpretation of ERO grants depreciation only for realized investments and not on revaluated assets. 2
ERO started actions during the 3 rd regulatory period to comply with its legal assessment with the goal to reverse the impact from asset revaluation. This introduced a substantial discontinuity with the regulatory framework set out in the 3 rd regulatory period:
2 Article 19a Energy act: (1) Pi regulaci cen penosu elektiny, pepravy plynu, distribuce elektiny a distribuce plynu postupuje Energetick regulan ad tak, aby stanoven ceny pokrvaly eln vynaloen nklady na zajitn spolehlivho, bezpenho a efektivnho vkonu licencovan innosti, dle odpisy a pimen zisk zajiujc nvratnost realizovanch investic do zazen sloucch k vkonu licencovan innosti [].
September 2013 | Frontier Economics 11
Regulation of energy network in Czech Republic
ERO proposed a change in the regulatory formula for the 3 rd regulatory period at the end of year 2012. The change was planned to come into force in 2014, hence, during the 3 rd regulatory period. ERO proposed the so called Investment Debt Factor (IDF) which shall be applied for the period 2010- 2025 and would decrease allowed revenues on 2014 by accumulated differences of investments and depreciation since 1.1.2010. ERO did not implement this factor, because the Governments Legislative Council dismissed this new parameter as retroactive and therefore incompatible with the legislative order. Instead ERO proposed in March 2013 to shorten the 3 rd regulatory period by one year and start with the 4 th regulatory period as of 1.1.2014 (instead of 1.1.2015). In addition ERO proposed to reverse the revaluation of the assets (step up) and to base the depreciation on the lower historic book values. In August 2013 ERO when ERO dismissed its previous March intention to shorten the 3 rd regulatory period, they published a new proposal for the 4 th
regulatory period, which included some differences compared to the regulatory formula for the 3 rd regulatory period and the ERO proposal from March 2013. It still includes the reversal of the step up from 2006. However, it further includes reduction of the WACC compared to March 2013; introduction of the Network obsolescence factor, which is yet to be specified; introduction of a network utilisation factor, which is yet to be specified; introduction of the so called investment fund which retrospective claws back revenues from the companies. 2.3 EROs action and the regulatory climate We understand that ERO is aware that the CZ gas and electricity network companies are facing substantial investments in the future. Hence, it is still well accepted by ERO that the companies need additional financial resources and a reliable investment climate to implement their ambitious long-term investment plans. A stable regulatory environment is the key prerequisite that companies can and will raise capital at reasonable costs. However, EROs actions during the 3 rd regulatory period and the draft proposal for the 4 th regulatory period issued on August 2013 may have affected the stability of the investment and regulatory climate for CZ energy network companies by increasing the uncertainty on regulatory actions, on the future 12 Frontier Economics | September 2013
Regulation of energy network in Czech Republic
regulatory framework and the cost of capitals investors demand for providing equity and debt for investments into energy networks.
September 2013 | Frontier Economics 13
Relationship between regulation and risk
3 Relationship between regulation and risk In this section we explore the links between regulation, risk and return. It describes the mechanisms through which regulation affects the risk faced by debt and equity investors and considers the importance of regulation relative to other risk factors for investors in utilities. 3.1 Channels for transmitting changes in risk to the WACC The cost of capital represents the minimum rate of return firms must pay in order to attract capital from investors. As such, it is recognised widely as the rate of profit that firms operating in a competitive market could be expected to earn. The rate of return earned by firms in competitive markets could, in any given year, deviate from the cost of capital. However, on average, firms in such markets could be expected to cover their cost of capital. The cost of capital needs to cover the risks (and opportunity costs) borne by investors in the business. A return that just covers the cost of capital is therefore commensurate with a normal economic return. Regulatory allowances of the cost of capital aim to ensure that the firm can cover its expected financing needs in order to undertake efficient investments and asset maintenance that sustain the provision of services. The cost of capital is typically measured by the Weighted Average Cost of Capital (WACC). WACC has two basic components: the cost of equity capital; and the cost of debt capital. The cost of equity is the expected rate of return required by investors in equity that compensates them for the risk they bear, and the opportunities they forgo by committing funds to the firm. The cost of debt measures the expected cost of borrowing to the business. The WACC calculation weights these two components according to the proportion of debt and equity capital within the businesss financing structure, i.e. its gearing. Changes in risk can affect equity investors and debt investors via different channels. In order to understand the full implications of a regulatory change on the cost of capital, it is necessary to understand the impact on the cost of equity and the cost of debt separately. Figure 1 illustrates how a regulatory change could flow through to WACC by altering a risk parameter within the cost of equity (beta) and/or a risk parameter within the cost of debt (the debt premium). 14 Frontier Economics | September 2013
Relationship between regulation and risk
Figure 1. Channels for transmission of risk changes to the WACC
Source: Frontier Economics The cost of equity to be used in the WACC formula is usually estimated using the Capital Asset Pricing Model (CAPM). The CAPM formula to be applied for this purpose is: ost of euity iskfree rate eta uity risk remium The risk-free rate represents the return on a completely riskless asset and is generally proxied by the yield on government securities. The equity risk premium measures the premium (over and above the risk-free rate) that investors might expect to earn by investing in a fully diversified portfolio of all risky assets in the economy (i.e. the market). eta measures the resonsiveness of the comanys euity returns to changes in overall market returns. It therefore captures the riskiness of the equity invested in the given company. A change in regulatory circumstances that alters the risk that equity investors expect to bear will feed through to the cost of equity by causing the beta to change. The cost of debt may be represented as follows: ost of debt iskfree rate ebt remium The debt premium reflects, among other things, the credit risk of a comany. Any regulatory change that alters the riskiness of a comanys debt will do so by altering the debt premium. A companys credit risk depends, in part, on its capital structure (i.e. gearing level). In general, the higher Change in risk resulting from a regulatory change Cost of equity Change in beta? Change in cost of equity Yes Change in Weighted Average Cost of Capital Change in debt premium? Cost of debt / leverage Yes Change in cost of debt or gearing September 2013 | Frontier Economics 15
Relationship between regulation and risk
the level of gearing, the greater is the credit risk and, therefore, the higher is the cost of debt. In practice, a companys debt is observable directly, for example by examining the yields on bonds issued by the firm. However, a companys cost of equity cannot be observed in the same way. It needs to be estimated using asset pricing models such as the CAPM. 3
The foundation of all asset pricing models is the risk-return trade-off, which says that, all else being equal, the greater the risk borne by investors, the higher the returns they expect in exchange for supplying capital. 3.2 Role of regulation in the cost of financing This section considers how regulatory action, and regulatory design, can influence the cost of capital by altering the risks faced by businesses. In this regard, there are three distinctions to be made: Firstly, the system of regulation may, itself, impose a certain risk profile on companies. Relevant regulatory parameters may be length of regulatory period, way how costs are determined (backward/forward looking), the degree of incentives and/or uncertainty of cost recovery in the regulatory system. Secondly, regulatory actions, that either increase or lower uncertainty about how the system of regulation will work in future, can alter the risks faced by companies. This would include regulatory reform processes in relation to future price control reviews. Thirdly, the legal framework has an impact on the risk profile of companies as it may limit the degree of freedom of regulators behaviours. This includes how detailed rights and obligations of regulated companies are fixed in primary and secondary energy legislation. Essential part of this is the appeal process against regulatory actions which gives the regulated companies the possibility to challenge regulatory decisions. 3.2.1 The system of regulation can influence risk and the cost of capital A companys risk profile can be influenced by the nature of the regulatory system it faces. 4 To help illustrate this concept we discuss the theoretical effect of two
3 Other asset pricing models considered by UK regulators include the Fama-French three-factor model, and the Dividend Growth Model. 4 See, for example, Parker, D. (2003), Performance, risk and strategy in privatised, regulated industries: The UKs experience, International Journal of Public Sector Management 16(1), 75 100; Wright, S., Mason, R., Miles, D. (2003), A study into certain aspects of the cost of capital for 16 Frontier Economics | September 2013
Relationship between regulation and risk
alternative pure systems of regulation rate-of-return and price-cap on firms cost of capital. Rate-of-return regulation and price-cap regulation could be viewed as two extremes of a spectrum of possible regulatory systems. Under pure price-cap regulation, prices are set for a number of years, based on a forecast of efficient costs. If a company manages to reduce costs below these forecast levels, it may keep the profits from doing so for the remainder of the control period. Therefore, price-cap regulation provides firms with incentives to improve efficiency. The efficiency incentives provided by a price-cap system exposes regulated firms to cost outturns deviating from forecasts. In order to be compensated for this risk, theoretically investors will demand a higher rate of return, which will be reflected in a higher cost of capital. We note that empirical evidence may be in contrast to this theoretical argument. For example, Frontier (2008/2011) 5
compared asset betas for energy network companies grouped in countries with cost-plus and incentive-based regulation and could not find differences based on statistical tests. There may be various reasons for this. In principle cost-plus and incentive regimes applied are not pure systems, e.g. the incentive regimes include also cost-pass through mechanism. In addition, even if cost-plus regulation is applied, the companies will be exposed to regulatory scrutiny when setting reasonable costs. 3.2.2 Regulatory action can alter the risk faced by companies Apart from the broader regulatory system itself, the actual behaviour of the regulator within a given system can influence the risks borne by the regulated firm and investors. There are a number of reasons why regulatory risk can be correlated with market risk. In periods of unfavourable economic conditions, regulators might be less inclined to raise allowed rates of return for regulated firms in order to avoid increasing the burden on consumers. 6 This would cause regulatory actions to be correlated with general macroeconomic conditions. This
regulated utilities in the U.K., a Smith & Co. Ltd. report to the OFT and U.K. economic regulators.; Guthrie, G. (2006), Regulating infrastructure: the impact of risk and investment, Journal of Economic Literature XLIV, 925972. 5 Frontier Economics, Ermittlung des Zuschlages zur Abdeckung netzbetriebsspezifischer Wagnisse im Bereich Strom und Gas, Report for Bundesnetzagentur, 2008; Frontier Economics, Wissenschaftliches Gutachten zur Ermittlung des Zuschlages zur Abdeckung netzbetriebsspezifischer unternehmerischer Wagnisse im Bereich Gas, Report for Bundesnetzagentur, 2011. 6 In fact, an asymmetry may arise because pressure from consumer groups and industrial customers may make it difficult for regulators to raise prices in bad times, and the regulator could justify disallowances of price increase. September 2013 | Frontier Economics 17
Relationship between regulation and risk
in turn would mean that the effect of regulatory decisions will be difficult to diversify, so such changes will affect the cost of capital. 7
In relation to the impact of regulatory actions on company risk, it is useful to distinguish between two categories for regulatory action. First, predictable regulatory changes can increase the correlation of the regulated firm with market risk. This is not necessarily a source of harm for society. For example, regulatory action that introduces competition into a sector may increase the risks faced by firms regulated within that sector, but the change may nevertheless raise overall welfare to society. Second, regulatory action can create uncertainty about how the system will work in future. This is potentially more harmful to society. Unpredictable regulatory conduct can create uncertainty for firms and, ultimately, for investors. Depending on the source and nature of the uncertainty, this could raise the firms cost of capital. Several empirical studies find significant effects of regulation on the regulated firms cost of capital. Trout (1996) 8 , Archer (1981) 9 and Dubin and Navarro (1982) 10 compared utilities in different US states, to investigate the effect of variations in state-level regulations on the cost of capital. All these studies find that regulatory climate has a significant effect on the cost of capital. Uncertainty over the future expected behaviour of the regulator can also affect the cost of capital for the regulated firm. A number of studies have examined the effect of regulatory uncertainty. Buckland and Fraser (2001) studied the impact of the 1992 UK general election on the betas of 12 regional electricity companies, which were privatised in 1990. The Conservative victory at those elections was one of the more unexpected results during the 20 th century and in the month leading up to the election on 10 April, speculation of a Labour victory was intense. Buckland and Fraser found statistically-significant evidence of the betas of the Regional Electricity Companies (RECs) rising significantly during this period, peaking on the day of the election, in anticipation of stricter regulation to come. This would have had the effect of raising the RECs costs of capital, all else being equal.
7 Burkhard, p., 2010. Regulatory risk and the cost of capital. Determinants and implications for rate regulation. Springer Berlin- Heidelberg 2010. Pp. 37. 8 Trout, R., R., 1979. The regulatory factor and electric utility common stock investment values. Public Utilities Fortnightly, November 22 1979, pp.28-31. 9 Archer, S., H., 1981. The regulatory effects on cost of capital in electric utilities. Public Utilities Fortnightly, February 26 1989, pp. 36-9. 10 Dubin, J., A., and Navarro, P., 1982. Regulatory climate and the cost of capital. In: regulatory reform and public utilities, ed. By Michael A. Crew, Boston/Dordrecht/London 1982, 141-66. 18 Frontier Economics | September 2013
Relationship between regulation and risk
3.2.3 Legal certainty, appeal process, regulated companies and regulatory action The possibility for regulated companies to legally appeal a regulatory decision, with which they disagree, may influence the behaviour of regulators in two ways: Ex ante limitation The threat of a potential legal appeal may force the regulator to put more emphasis on reasoning its decisions. For example, this may result in a transparent consultation/decision process, where regulated companies and/or other stakeholders have the possibility to comment the regulators proposals. Ex post limitation In principle the regulatory process is a balancing of various and sometime conflicting interests. In some cases the regulatory action may overemphasize one interest or is supposed not compliant with the law. Hence, the legal appeal institution has the task to decide on the legitimacy of the regulatory action and will approve or disapprove it ex post. We note that the degree of the ex ante and ex post limitation depends on various factors in relation to the legal appeal process: Rules defining the regulatory framework detailed rules for setting the regulatory components will more easily allow assessing the compliance of regulatory decisions with the law. 11
Clear structure of legal appeal institutions allows all stakeholders to know the respective legal enforcement institution. In addition the legal character of the regulatory decision should comply with the principle legal appeal process, e.g. in some countries a regulatory contract may not fit into legal appeal process; and Track record of legal appeal institutions the legal appeal institution should have a track record (credibility) to decide in time and with a balanced view for all stakeholders. This is important as companies will only use the costly legal appeal process if they can expect a positive decision in their case. In particular, the credibility of the legal appeal institution has an important impact on the ex ante limitation of regulatory actions. Only if the regulator expects an overruling of her decision, she will take into account the expected opinion of the legal appeal institution.
11 However, we note that detailed rules may have an adverse effect on risk, as well. This is the case if a change in the economic environment of regulated companies, e.g. increase in investment need due to connection of renewables, requires flexible regulatory actions. September 2013 | Frontier Economics 19
Relationship between regulation and risk
3.3 Regulation and risk the view from rating agencies The regulation/risk exposure of regulated companies to the capital market can be reflected by the rating methodologies published by credit rating agencies. The level of risk embedded in companies regulatory framework plays a crucial role in these methodologies and differentiates the regulated sector from most other corporate sectors. In the following we illustrate Moodys rating methodology for regulated electric and gas networks 12 , which hinges on four rating factors with different weights on the final result: Regulatory environment and asset ownership model, which reflect the companys expected ability to recover cost in a consistent manner over time; Operational characteristics and asset risk, which reflects the companys capacity to carry out its investment plan; Stability of business model and financial structure, which capture the exposure of lenders from the company engaging in new or unregulated activities; and Key credit metrics, which account for the financial parameters that best reflects the likelihood of default. The four rating factors are further categorised into sub-factors illustrated in Table 3 again with different weights on the final result.
12 Moodys Investors Service, Rating Methodology Regulated Electric and Gas Networks, 2009. However, we note that Standard&Poors and Fitch are using similar financial indicators. 20 Frontier Economics | September 2013
Relationship between regulation and risk
Table 3. Moody's methodology for rating regulated electricity and gas networks Broad Rating Factors Broad Rating Factor Weighting Rating Sub-Factor Sub- Factor Weighting 1. Regulatory environment and asset ownership model 40% Stability and Predictability of Regulatory Regime 15% Asset Ownership Model 10% Cost and Investment Recovery 10% Revenue Risk 5% 2. Efficiency and execution risk 10% Cost Efficiency 6% Scale and Complexity of Capital Programme 4% 3. Stability of business model and financial structure 10% Ability and Willingness to Pursue Opportunistic Corporate Activity 3.33% Ability and Willingness to Increase Leverage 3.33% Targeted Proportion of Operating Profit Outside Core Regulated Activities 3.33% 4. Key credit metrics 40% Adjusted ICR (or FFO Interest Cover) 15% Net Debt/RAV 15% FFO/Net Debt 5% RCF/Capex 5% Source: Moody's In the following we focus on the sub-factors which correspond to our discussion on the role of regulation in the cost of financing in Section 3.2. Stability and Predictability of Regulatory Regime (15%) Reflects the characteristics of the regulatory environment in which a network operates. This includes the transparency of the regulatory framework, the regulators track record for predictability and stability in terms of decisions making and its independence from politics. In addition this sub-factor takes into account the overall robustness of institutions and the rule of law in relevant jurisdiction. Hence, this sub-factor corresponds with the discussion on regulatory action and risk (Section 3.2.2) and the possibility of the legal appeal process (Section 3.2.3). September 2013 | Frontier Economics 21
Relationship between regulation and risk
Cost and Investment Recovery (10%) Focuses on the supportiveness of the regulatory system on cost recovery with regard to operating and capital expenditures. For example this includes the degree of incentives on costs, the degree and timing of the cost-pass through mechanism, etc. In other words, it measures the risk allocation between the company and its customers. Hence, this sub-factor corresponds with the discussion on the system of regulation (Section 3.2.1). Revenue Risk (5%) Refers to the mechanism of revenue generation by the company, in more detail on the volumes transported by a network as a driver of potential volatility and uncertainty of future revenues. The regulatory framework can mitigate this risk e.g. by introducing tariffs based on capacities (which tend to be more stable) instead of volume or a revenue cap. Hence, this sub-factor corresponds with the discussion on the system of regulation (Section 3.2.1). As the three sub-factors discussed above make up 35% of the overall assessment the effect on the credit rating by an up-/downgrade will be substantial. In addition, it is straightforward that the factor Cost and Investment Recovery and Revenue Risk will affect other rating factors, e.g. Key credit metrics by influencing the cash flow profile of the regulated companies. 22 Frontier Economics | September 2013
Relationship between regulation and risk
3.4 Key findings Regulation and risk Changes in risk will affect equity investors and debt investors via different channels. Risk will feed into the cost of equity via the beta; and cost of debt via the debt premium. Regulatory actions and regulatory design will influence the cost of capital by altering the risks faced by businesses. We identified three sources of potential regulatory influence and categorised them to three Moodys key credit rating indicators reflecting the regulatory environment: Stability and Predictability of Regulatory Regime; Cost and Investment Recovery; and Revenue Risk. Regulatory systems can be compared by analysing how they perform against these indicators and how this may influence business risks influence the beta and debt premium.
September 2013 | Frontier Economics 23
Regulation and risk selected European countries
4 Regulation and risk selected European countries In the following we describe and analyse selected European countries with regard to the Stability and Predictability of Regulatory Regime; Cost and Investment Recovery; and Revenue Risk. In addition we illustrate the allowed cost of capital (WACC) for these countries. The European countries we selected are: UK Introduced a new regulatory framework, RIIO 13 , for the electricity and gas networks. The first application of RIIO for the UK gas distribution companies came into force on 1 April 2013. The main changes from RIIO on the companies are the extension of the regulatory period from 5 to 8 years (RIIO-G1 for gas distribution companies is from 1 April 2013 to 31 March 2021) and the strong focus on providing outputs. Hence, UK provides as an example of a recent regulatory decision applying a new regulatory framework. Germany Started the 2 nd regulatory period for gas distribution companies with 1 January 2013. As the main principles of the regulatory framework are set out in law the 2 nd regulatory period is mainly an extension of the revenue cap framework from the 1 st regulatory period. However, with regard to the cost of capital the regulator decided to deviate from the more mechanistic approach used in the 1 st regulatory period to a more flexible one in favour of the regulated companies. Hence, Germany provides as an example of a recent regulatory decision, as well. France Started the 4 th regulatory period for gas distribution companies with 1 July 2012. The regulation in France is characterised by a combination of incentive regulation for operating expenditures and cost-plus regulation for investments. In addition the regulation includes incentive-based mechanism for certain output objectives, e.g. promotion of gas use and quality of service. Hence, France provides as an example of a regulatory framework compared to UK and Germany with a lower degree of incentives.
13 RIIO stand for Revenues = Incentives + Innovation + Outputs. 24 Frontier Economics | September 2013
Regulation and risk selected European countries
We make the following disclaimer in relation to the below stated Moodys assessment for gas distribution companies in Germany and France: France The assessment of Moodys rating is taken out from the rating of the French gas TSO, TIGF 14 . Although TIGF being a gas TSO we assume a similar assessment with regard to gas distribution networks, as the same regulatory principles are applied. Germany The assessment of Moodys rating is taken from the rating of HSE Netz AG 15 , which owns and operates gas and electricity distribution networks. Although HSE Netz AG operates gas and distribution networks we assume a similar assessment with regard to gas distribution networks only, as the same regulatory principles are applied for gas and electricity networks. 4.1 UK 16
4.1.1 Stability and Predictability of Regulatory Regime Regulation in UK for electricity and gas networks has a track-record of more than 20 years. The process of price control for a regulatory period is transparent and lasts between 18 months to 2 years. During this period the regulator, Ofgem, obtains information from the companies and consults on the methodology that will be used to set the price control. Ofgem publishes a draft determination, which is also open to consultation, and then presents the company with a final determination of the tariff control for the next regulatory period. When reaching the determination, Ofgem must ensure that it is consistent with her legal duties. Specifically, the regulator has a primary duty to protect the interests of consumers and a number of secondary duties including the need to secure that licence holders are able to finance the activities which are the subject of obligations imposed 17 . Once presented with the final determination, a company has a pre-specified period of time to decide whether to accept Ofgems decision. If the decision is accepted, the companys licence is modified to reflect the new tariff. If the
14 Moodys, Credit Opinion: TIGF SA, August 2013. 15 Moodys, Credit Opinion: HSE Netz AG, August 2013. 16 We note that this section refers to gas (and electricity) networks regulated by Ofgem. These are the networks in England, Wales and Scotland. The networks in Northern Ireland are not included as they are regulated by the Northern Ireland energy regulator (UR). 17 Utilities Act 2000. September 2013 | Frontier Economics 25
Regulation and risk selected European countries
decision is not accepted within the specified time period, Ofgem refers the case to the Competition Commission (the appeals body in UK). The conditions under which a company can reject the regulators decision and thereby seek an appeal are laid out in legislation. Formally, the company will reject the proposed tariff if it is unable to finance the proper carrying out of its function. That is, the company can reject the decision if it believes that the revenues allowed by the regulator are not sufficient to cover the costs of delivering required outputs. If a company rejects Ofgems proposal the case is referred to the Competition Commission (CC). The duties of the CC are laid out in the legislation relevant to the particular sector (The Utilities Act 2000 in the case of energy). In addition, the companies have the possibility to make a legal appeal to the High Court. However, since the beginning of regulation no company has rejected Ofgems proposal. The CC is also responsible for the decisions from the Northern Ireland energy regulator (UR). There was a recent case where a company rejected the decision from UR, in which CC analysed the impact from regulatory actions on risk and the cost of capital (see box below). In November 2008 Ofgem started its review of the then regulatory approach (RPI-X@20). The main task was to incentivise networks to support sustainability objectives and sector decarbonisation, while maintaining high quality of service and low costs. RPI-X@20 included an extensive consultation and interaction process with all stakeholders. The goal of this process was increase the transparency on the objectives of all relevant stakeholders and to include them in the new approach. In addition, the consultation was meant to specify the new regulatory measures proposed. The process resulted in the new regulatory approach RIIO Revenue set with Incentives for delivering Innovation and Outputs in October 2010. Its key innovation is the central focus on outputs, not inputs. The principle is simple. Customers care primarily about the end result and so this is what network operators should be incentivised to provide. In 2013 RIIO was first applied to the gas distribution companies (RIIO-GD1), electricity and gas transmission companies (RIIO-T1). 26 Frontier Economics | September 2013
Regulation and risk selected European countries
Competition Commission Phoenix Natural Gas In February 2012 Phoenix Natural Gas Limited (PNGL) rejected the price control proposed by the Northern Ireland energy regulator (UR). UR subsequently referred the price control to the CC investigate whether the price control conditions operated against the public interest. The dispute was focussed on URs proposal to write off approximately 25% of PNGLs regulated asset base (RAB). PNGL argued that this proposal was unexpected, unjustified, and contrary to the principles of incentive regulation, since it retrospectively altered the previously agreed value of PNGLs asset base. UR argued that it was acting in line with regulatory practice, and protecting the interests of customers, by removing unspent allowances from the asset base after 5 years. The CC 18 found that URs proposal had not been adequately signalled and that the rationale for it was not sufficiently well communicated or understood. Changes to the regulatory framework that were enacted in this way would lead to a perception of regulatory uncertainty, as investors may assume that URs future actions could be unpredictable.Investors may anticipate that in addition to normal commercial risks there could be greater uncertainty in the future about the regulatory environment, and thus increased risks that returns on investment will not be realized in the way or to the extent that is expected. This is likely adversely to affect investment decisions in the future. The CC identified the ways in which customers could be harmed by retrospective interventions in the long-run. It highlighted three possible mechanisms by which the willingness to invest and the cost of finance could be adversely affected by URs proposals: The credit ratings agencies may view the regulatory regime as less favourable and, as a result, may demand higher credit metrics for a given credit rating, which may lead to a downgrade of a companys debt. This may have the effect of decreasing the amount of debt that a company can have in its capital structure and/or increasing the cost of the companys debt, both of which could lead to an increase in the overall WACC. Equity investors may consider that the regulatory regime is less attractive, and as a result may increase the return that they require for investing in a given project. This may have the effect of increasing the required rate of return. Finally, a perception of regulatory uncertainty may deter investment if companies are unable to form judgements or are very uncertain of what the regulatory environment will be and if, how or when they will receive a return on investments.
18 Competition Commission, Phoenix Natural Gas Limited price determination, November 2012. September 2013 | Frontier Economics 27
Regulation and risk selected European countries
Therefore, the CC considered that regulatory uncertainty would affect both the cost of debt and the cost of equity. It stated that any effects on the cost of equity could be long-lived because the investment community may be expected to take into account URs track record over a relatively long time period when investing in infrastructure assets with a similarly long life. [para 8.94] The CC did not quantify the scale of the impact of regulatory uncertainty on the cost of capital. Nevertheless it concluded that it is our judgement that these effects could be significant. As an illustrative example, applying a 50 basis point uplift to the cost of capital to NIEs and PNGLs combined RABs of approximately 1.8 billion would equal 9 million a year. This does not take into account any effects on other regulated investments and on future greenfield investments. [para 8.99] Moodys assessment Stability and Predictability of Regulatory Regime with Aaa rating With regards to Stability and Predictability of Regulatory Regime Moodys uses the UK regulatory framework as the benchmark and applies an Aaa rating. In particular Moodys placed special attention to the Ofgem project RPI-X@20 started in 2008, which evaluated Ofgems past regulatory approach for future application. This process finally resulted in the new RIIO regime. In October 2010 Moodys raised its concern about Ofgems announcement that the new regulatory model RIIO is the biggest change to the regulatory framework for 20 years. Moodys was concerned that the regulators track record for stability and predictability could be quickly undone. Moodys welcomes this review and recognises that the challenges facing network companies are clearly evolving against the backdrop of the changing way in which energy is likely to be delivered in the future. The current regulatory framework for energy companies was developed when they were purely infrastructure companies with a somewhat fixed role in the industry. This is no longer the case and network companies will clearly need to evolve to meet new technological challenges. However, the UK regulatory framework and, in particular the RPI-X concept, has been adopted all over the world and is held in high regard for its predictability, support and good track record. Moodys scores the UK regulatory framework for the energy sector as one of the most transparent in the world. Therefore, any material change to the regime could potentially weaken that view until a good track record of performance has been re-established. We also note that a changing regulatory framework and new processes may represent a significant management challenge for companies, particularly in the first few years. 19
19 Moodys (2010: 3). 28 Frontier Economics | September 2013
Regulation and risk selected European countries
However, after the first application of RIIO to the UK gas distribution companies (RIIO-GD1), electricity and gas transmission companies (RIIO-T1) Moodys notes that RIIO is more a rebranding of the previous RPI-X regime and represents a natural evolution in regulation that has continued since the utilities were first privatised. 20
Due to the evolutionary development from RPI-X to RIIO Moodys assessed that the transition to RIIO for the gas distribution companies has no impact on the Aaa rating.
20 Moodys (2013: 1). September 2013 | Frontier Economics 29
Regulation and risk selected European countries
4.1.2 Regulatory system Cost and Investment Recovery and Revenue Risk Table 4. Regulatory parameters RIIO-GD1 Regulatory component Description Type of regulation Revenue cap regulation Length of price control 8 years (mid-period review) Opex Split in to Controllable costs (subject to efficiency analysis) ;and Non-controllable costs. RAB RAB is based on Asset value of end year of previous period (rolled forward); Annual net additions to RAB (fixed percentage of Totex) Cost of capital WACC approach Real WACC Depreciation Sum-of-year digits (front loading) Depreciation based on asset live of 45 years (sum-of-digits) Investment Business plans serve as basis for RAB growth rate of 1%/a Efficiency analysis Totex benchmarking based on four models (average efficiency): Historical Totex; Forecast Totex; Historical disaggregated activity level expenditure; and Forecast disaggregated activity level expenditure. DSOs have to close 75% of their assessed gap between the cost forecast and the upper quartile (75%-quartile). Treatment of network losses DSOs are expected to improve gas transport losses over RIIO-GD1 through rolling incentive mechanism Companies receive forecast allowance for shrinkage based on actual volumes and forecasted prices Ex post alignment between forecast and outturn prices, therefore no commodity price risk for operators Incentives Incentive rates in cost allowances IQI (Information Quality Incentive) provides ex-ante incentives to submit accurate cost forecasts. Companies receive bonus if submitted business plan is closely aligned to Ofgems forecast. Innovation stimulus packages Source: Frontier 30 Frontier Economics | September 2013
Regulation and risk selected European countries
The key element of the new RIIO framework is represented by an output oriented, instead of in input-oriented, definition of cost-allowances. Under RIIO, companies are required to submit business plans setting out future investment plans and define how the set of outputs will be achieved. Those plans serve as key input in setting the price control elements. Figure 2 shows the principal outputs under RIIO GD1 which can be allocated to different output categories. Figure 2. Principal outputs under RIIO GD1
Source: Frontier The biggest expenditure item under RIIO GD1 is represented by replacement expenditure 21 (repex) which is an obligation derived from UKs Health&Safety Executive that requires gas distribution companies to replace iron mains located within 30 meters of buildings within 30 years (30/30 program). In order to overcome the inherent principal-agent problem that lies within business plans as source of information being submitted by regulated companies, Ofgem introduced mechanisms (Information quality incentive, IQI) that aim at incentivising the operators to submit accurate plans and reveal their true costs: Incentive rates for outperformance IQI allows companies to retain part of cost outperformance during a regulation period. The incentive rate has been set between 65% and 70%, allowing companies to retain two thirds of the achieved cost outperformance.
21 Ofgem changed the capitalisation principles for repex and introduced a stepped transition for repex capitalisation, from 50% capitalisation in 2013-14 to 100% in 2020-21. Principal outputs in RIIO GD1 (extract) Percentage of biomethane capacity connected 15-20% reduction of gas transport losses Reduction of carbon footprint satisfactory survey, complaints metrics, stakeholder engagement Connection of 80,000 energy poor households Increase public awareness for carbon monoxide Maintain connection standards New connection standards for gas entry costumers Reduce safety risks by 40-60% Compliance with statutory requirements Expected number of interruptions Asset load / Capacity utilisation Maintaining operation performance Environ- ment Customer service Social obligation Customer connection Safety Reliability September 2013 | Frontier Economics 31
Regulation and risk selected European countries
Reward for accuracy in business plans Cost rewards are granted (penalties charged) of maximal 2.5% of total expenditure for companies that provide costs forecasts equivalent to Ofgems assessment of efficient costs. As to provide further incentive to innovate, RIIO GD1 includes an innovation stimulus package to fund innovation. Further, the submitted business plans are subject to a comparative efficiency analysis based on four cost measures of total expenditure, two based on historical costs and two based on forward looking cost assessment. The average over all four measures serves as base line cost allowance. Companies will have to close 75% of the assessed gap between their forecast and the efficient costs 22 . Moodys assessment Cost and Investment Recovery with A rating and Revenue Risk with Aaa rating With regards to Cost and Investment Recovery Moodys still applies an A rating on the gas distribution companies after the first application of RIIO. The main reasons are: the extension of the price control period from five to eight years is a key change of RIIO as there is the potential for companies having to wait longer for prices to be reset if specific costs increase. However, Moodys notes that this risk is largely mitigated by the number of uncertainty mechanisms (such as true-ups and the move to a cost of debt index) included; the nature of the allowed expenditure is very much in line with the existing price control and represents business as usual for the companies; the companies will face a similar risk due to cost performance under RIIO-GD1; as well as Moodys is of the opinion that the presence of new incentives in relation to outputs is more than offset by the new uncertainty mechanisms with regards to costs, hence, making the overall credit risk balance broadly neutral for RIIO-GD1. With regards to Revenue Risk Moodys applies an Aaa rating. This is due to the structure of the tariffs as fixed capacity charges make up a big proportion of the overall revenue in gas and that the companies are not exposed to volume risks.
22 Efficient costs are defined as the upper quartile (75%) of efficiency scores. 32 Frontier Economics | September 2013
Regulation and risk selected European countries
Moodys rating for Cost and Investment Recovery and Revenue Risk under RIIO indicates a low risk exposure for gas distribution companies with regard to these factors which will feed into the overall credit rating assessment. 4.1.3 WACC Table 5. WACC parameter UK Parameter Parameter value Risk-free rate (real) 2.0% Asset-Beta 0.38 Equity-Beta 0.9 Market risk premium 5.25% Cost of equity (real, post-tax) 6.7% Gearing 65.0% Tax 21.0% Debt premium 0.9% Cost of debt (iBoxx 10-year simple trailing average index) (real, pre-tax) 2.9% Inflation rate 3.1% WACC (real, vanilla) 4.2% Source: Frontier Ofgem used the Capital Asset Pricing Model (CAPM) including a relative risk analysis to determine the cost of equity for RIIO-GD1. Compared to the previous price control regime (gas distribution price review - GDPCR1), Ofgem decided to lower the equity beta from 1 to 0.9 based on the argument that gas distribution network operators face lower risks than in GDPCR1. The equity beta of 0.9 translates into an asset beta of 0.38. Further, Ofgem reduced the real risk-free rate from 2.5% to 2% and increased the market risk premium from 4.75% by 0.5% pp to 5.25%. Under the RIIO model Ofgem decided to base the cost of debt on a long-term trailing average of forward interest rates, and the revenues allowed under the price control will be adjusted each year for changes in this trailing average. Ofgem notes that the allowed return on debt in price controls before RIIO has closely tracked the long-term cost of debt average rather than current rates. This is a strong indication that long-term averages remain an appropriate basis for calculating the cost of debt going forward irrespective of current (or indeed September 2013 | Frontier Economics 33
Regulation and risk selected European countries
forecast) market rates. 23 Hence, this approach should allow cost recovery for cost of debt in the long run. For RIIO-GD1 Ofgem decided to use a trailing 10-year average of two iBoxx indices for the cost of debt. The respective iBoxx indices are the iBoxx Non-Financials A 10+ 24 This index includes bonds with a an average remaining time to maturity (weighted by outstanding amount) of 21.6 years for A rated companies. iBoxx Non-Financials BBB 10+ 25 This index includes bond with a an average remaining time to maturity (weighted by outstanding amount) of 17.2 years for BBB rated companies. The unweighted average of both indices is then deflated by using a break-even inflation figure. The break-even inflation figure is derived from the yield from British Government Securities 10 year real and nominal zero coupons. 26 Ofgem does not explicitly display the debt premium. However, using the risk-free rate and the cost of debt implies a debt premium of 0.9 % at the beginning of RIIO- G1. 4.2 Germany 4.2.1 Stability and Predictability of Regulatory Regime The regulatory framework for incentive regulation for gas and electricity networks is set out in the Incentive regulation decree (Anreizregulierungsverordnung 2012, ARegV). In addition the Gas network tariffs decree (Gasnetzentgeltverordnung, GasNEV) defines how the costs are determined to set the network tariffs for gas transmission system operators (TSO) and distribution system operator (DSO) companies. These decrees include e.g. regulatory formula; size of productivity factors; or calculation of allowed depreciation, asset values and cost of equity and limit the actions from the regulator, Bundesnetzagentur (BNetzA).
23 See Ofgem, RIIO Handbook, 2010. 24 Series reference: DE000A0JY837. 25 Series reference: DE000A0JZAH1. 26 10 year nominal zero coupon, series reference IUDMNZC; 10 year real zero coupon, series reference IUDMRZC. 34 Frontier Economics | September 2013
Regulation and risk selected European countries
In cases where the decree leaves open the explicit details of the design of certain regulatory parameters, e.g. detailed specification of benchmarking analysis, detailed calculation of the risk premium (equity beta) for the cost of equity, BNetzA uses a public consultation process including all relevant stakeholders. BNetzA sets the allowed costs and the application of the regulatory formula for each company by an individual decision. This individual decision also includes the details, e.g. for the specification of the benchmarking analysis the resulting efficiency score. The companies have the possibility for a legal appeal against this decision. The legal appeal first goes to Court of appeal which is Oberlandesgericht Dsseldorf against decisions from BNetzA; as well as Supreme court which is the Bundesgerichtshof against decisions from the court of appeal. The principle Reformatio in peius applies for decisions at Courts of Appeal. This means that no appellant can be put in a worse position for filing and appeal. The judgment of the higher court cannot amend the decision of the lower one in harm of the defendant or plaintiff who turns to the higher court for a new decision. Hence, companies cannot loose when appealing a decision. Companies tend to use their right for legal appeal against decisions from BNetzA since the start of incentive regulation. In the past the courts of appeals issued various decisions reflecting an in-depth evaluation of the raised issues from companies, which were either in favour of the arguments raised by Companies, e.g. on the application of the industry-wide productivity factor, indices used for revaluation of the assets; or BNetzA, e.g. on the level of the cost of equity for the 1 st regulatory period. There were amendments of the ARegV since the beginning of incentive regulation taking into account the future investment needs in particular of electricity TSOs. For example, the time lag for including expansion investment in the allowed revenues during the regulatory period was removed. In addition the decision of BNetzA on the allowed cost of equity for the 2 nd regulatory period also took into account the future investment needs of the energy sector (see below). September 2013 | Frontier Economics 35
Regulation and risk selected European countries
Moodys assessment 27 Stability and Predictability of Regulatory Regime with A rating With regards to Stability and Predictability of the Regulatory Regime Moodys considers the German regulatory framework as modestly riskier in terms of transparency and predictability than the UK framework used as the benchmark and applies an A rating to this sub-factor. The reasons are: Key principles of the incentive-based regulatory framework are enshrined in law. However, being a relatively new form of regulation that is still undergoing material changes, the outcome of future developments is less predictable. Whilst the experience to date shows that in many cases regulatory changes have resulted in additional clarity and reduced risk for regulated companies, Moodys expects to see a longer track record of consistent application of regulatory principles before aligning the score with those of more established regimes.
27 The assessment of Moodys rating is taken from the rating of HSE Netz AG , which owns and operates gas and electricity distribution networks. Although HSE Netz AG operates gas and distribution networks we assume a similar assessment with regard to gas distribution networks only, as the same regulatory principles are applied for gas and electricity networks. 36 Frontier Economics | September 2013
Regulation and risk selected European countries
4.2.2 Regulatory system Cost and Investment Recovery and Revenue Risk
Table 6. Regulatory parameters Germany Regulatory component Description Type of regulation Revenue cap regulation Length of price control 5 years (2 nd regulatory period 2013-2017) Opex Controllable operating expenditures (e.g. direct manpower costs; expenditures for goods and services) fixed value from photo year (t-3) which is adjusted annually by CPI and productivity factor Uncontrollable operating expenditures (e.g. costs for using transmission network) cost-pass through either t-2 or t-0 RAB RAB refers only to equity financed part, as cost of debt taken from P&L account Distinction into old assets (pre 1.1.2006) and new assets (post 1.1.2006) Old assets (new assets) are valued at replacement (historic) costs Cost of capital No WACC approach as cost of debt taken from P&L statement Cost of equity based on CAPM model Real (nominal) cost of equity for old assets (new assets) Depreciation Fixed value from photo year (t-3) which is adjusted annually by CPI and productivity factor Old assets equity financed part (capped at 40%) based on replacement values; debt financed part based on historic values New assets based on historic values Investment No forecasts used for regulatory period to assess investment needs during regulatory period Expansion investments covered by growth factor based on development of supply area, peak demand and number of connection points Efficiency analysis Efficiency analysis on total costs using two benchmarking methodologies (DEA and SFA) Treatment of network losses Costs for network losses are not part of distribution companies revenues. The costs are covered via purchasing of balancing energy by traders Incentives Only controllable costs are incentivised, where capital costs are defined as controllable, as well Two types of targets are applied cumulatively: (i) Industry-wide productivity target; and (ii) Company-specific efficiency targets based on efficiency of each firm Companies can retain cost savings that go beyond the efficiency targets Source: Frontier September 2013 | Frontier Economics 37
Regulation and risk selected European countries
BNetzA does not use cost forecasts to set the costs operating costs and capital costs for the following regulatory period. Instead the costs from a photo year are used. The starting point is the values from P&L statements and balance sheets from the annual reports of the companies. According to 6 ARegV the relevant photo year is based on the t-3 costs, where t is the start of the following regulatory period. For the 2 nd regulatory period for incentive regulation of gas DSOs starting at 1 January 2013 this means that the relevant costs for the period 2013-2017 are the accounting data from 2010. The ARegV defines three categories of costs with different treatment during the regulatory period: Non-controllable costs (11 (2) ARegV) defined by an exhaustive list which are cost-pass through items; Volatile costs (11 (5) ARegV) defined by an exhaustive list which are cost-pass through items; and Controllable costs costs not falling under non-controllable and volatile costs are by default controllable. This includes operating costs and capital costs (depreciation and cost of capital). Controllable costs are adjusted during the regulatory period by inflation and a productivity factor. The productivity factor consist of two parts: Industry-wide productivity target which applies to all companies and is set at 1.5% for the 2 nd regulatory period; and Company-specific efficiency targets based on the efficiency for each company, which is derived from a total cost benchmarking analysis. The companies have to reduce all their inefficiencies during 5 years. In order to dampen the impact from the company specific target a best-of approach from different benchmarking models and a cap on the maximum inefficiency is used. With regard to investments during the regulatory period one has to differentiate between Replacement investments the implicit assumption is that the allowed depreciation in the photo year is sufficient to generate sufficient cash flows for replacement investments for the coming regulatory period; and Extension investments which are covered by the so-called expansion factor. The expansion factor allows companies further revenues if their supply task increases during the regulatory period. The increase of the supply task is reflected by the change in the supply area, peak load and number of connection points. 38 Frontier Economics | September 2013
Regulation and risk selected European countries
The revenue cap places no volume risk on the companies. Hence, the regulatory formula does not include any measures for network utilisation. In principle quality regulation may also apply to the gas distribution companies. However, BNetzA, did not implement quality regulation yet. Hence, there is no exposure of gas distribution companies on quality. Moodys assessment 28 Cost and Investment Recovery with Baa rating and Revenue Risk with A rating With regards to Cost and Investment Recovery we assume the same Baa rating Moodys applies to HSE Netz AG, because: the application of the industry-wide productivity factor and the company-specific efficiency targets on total costs; and the limited track record of the application of the tariff formula. With regards to Revenue Risk we assume the same A rating Moodys applies to HSE Netz AG, because volume risk is largely mitigated through an adjustment mechanism, whereby any over- or under-recoveries of revenues are recorded in a regulatory account and adjusted at the next regulatory period. 4.2.3 WACC The German regulator BNetzA sets a separate allowance for return on equity and cost of debt (i.e. there does not exist a WACC approach in Germany). BNetzA stipulates the parameters that are used to calculate the cost of equity for the 2 nd
regulatory period for gas networks (2013-2017). BNetzA based its decision on a report from an external expert that examines the costs of equity for gas and electricity networks in Germany. 29
Table 7. Cost of equity parameter Germany Parameter Parameter value Risk-free rate (nominal)* 3.8% Asset-Beta (taken from first regulatory period)** 0.39 Equity-Beta (taken from first regulatory period)** 0.79
28 The assessment of Moodys rating is taken from the rating of HSE Netz AG, which owns and operates gas and electricity distribution networks. Although HSE Netz AG operates gas and distribution networks we assume a similar assessment with regard to gas distribution networks only, as the same regulatory principles are applied for gas and electricity networks. 29 Frontier Economics (2011), Wissenschaftliches Gutachten zur Ermittlung des Zuschlages zur Abdeckung netzbetriebsspezifischer unternehmerischer Wagnisse im Bereich Gas, Gutachten im Auftrag der BNetzA. September 2013 | Frontier Economics 39
Regulation and risk selected European countries
Market risk premium** 4.55% Equity risk Premium 3.59% Cost of equity (nominal, pre-tax for new assets)*** 9.05% Cost of equity (real, pre-tax for old assets)*** 7.14% Gearing 60% Tax**** 29.48% Inflation rate 1.56% Source: Frontier Economics based on BNetzA (2011) * Weighted average yield of outstanding Bundesbank bonds of the past ten years. ** BNetzA decided against the CAPM approach and used instead the betas and market risk premium from the first regulation period. The asset beta/equity beta originally published in its proposal submitted for consultation for the second regulatory period amounts to 0.32/0.66 and the market risk premium to 4.40% (corresponding to the average of the recommended range for asset beta provided by Frontier Economics (2011)). *** Cost of equity for new installations are nominal pre-tax and for old installations real pre-tax. **** The tax covers trade tax of 13.65% and corporate tax of 15.825%. BNetzA lowered the cost of equity compared to the 1 st regulatory period for gas networks and justifies this with the general level of interest rates. The parameters for the cost of equity for the 2 nd regulatory period are set out in Table 7 below. The commissioned expert report defined a potential range for the equity beta (asset beta) of 0.62 and 0.71 (0.30 and 0.35) and a potential range for the market risk premium of 3.8% and 5.0% (geometric and arithmetic mean). In its decision BNetzA however decided to deviate from the CAPM approach as applied in the external expert report and instead adhered to the higher betas and market risk premium derived in the 1 st regulatory period. The higher equity beta in the 1 st
regulatory period amounts to 0.79 (which implies an asset beta of 0.39) and the market risk premium to 4.55%. BNetzA reasoned the deviation from the CAPM approach by the exceptional situation on the financial markets and Germanys specific energy policy change in recent years following the incident in Fukushima that was also followed by changes in the legal framework in Germany. In particular BNetzA emphasises the considerable need for extension and modernisation of the German distribution grids to enable them to accommodate a larger amount of renewable energy in line with Germanys revised Renewable Energy Sources Act (EEG). By deciding against lowering the risk premium 40 Frontier Economics | September 2013
Regulation and risk selected European countries
BNetzA aims to provide greater regulatory incentives for essential investments needed due to the turnaround in German energy policy. 30
4.3 France 4.3.1 Stability and Predictability of the Regulatory Regime The gas and electricity sector in France is regulated by the Commission de Rgulation de lEnergie (CRE), under a law of February 2000. As an administrative authority, the CRE is independent of government. The mission of CRE is Guaranteeing the right of access to public electricity grids and natural gas networks and facilities; Ensuring the proper functioning and development of electricity and liquefied natural gas networks and infrastructure; Ensuring the independence of system operators; Contributing to building the European Internal Market for electricity and gas. The French Energy Code, in force since 1 June 2011, implements the Directive 2009/73/EC into French law. Articles L.452-2 and L.452-3 of the French Energy Code determine the CREs remit over tariffs. Article L.452-2 states that CRE sets the methods used to establish the tariffs for use of natural gas networks. Furthermore, Article L.452-3 states that The Energy Regulatory Commission considers tariff changes [] with, as appropriate, amendments to the level and structure of tariffs that it believes justified in light particularly of an analysis of operators' accounts and foreseeable changes in operating and investment costs. CRE first applied a long-term regulatory framework including incentives on gas distribution companies in 2008. CRE did not change the regulatory framework for the 2 nd regulatory period. Although not obliged by law CRE undertakes extensive consultations on everything it considers doing. Hence, CRE has the reputation of setting out the rules of the price control clearly and in great detail at the beginning of each regulatory period. CRE submits its decisions on tariffs and the reasoning behind them to the ministries with responsibility for energy and the economy. The ministries have
30 BNetzA explicitly mentions in its decision that it will return to apply CAPM approach in the third regulation period if conditions for network operates improved by predictability and a more stable legal framework. September 2013 | Frontier Economics 41
Regulation and risk selected European countries
the power to veto within 2 months if they consider that the tariffs are not in line with current energy policy. In case of no veto the new tariffs and underlying regulatory framework come into force. The companies and other stakeholders have the possibility to appeal the decision from CRE at the Conseil dEtat. We are not aware of an appeal from the gas sector. However, in 2009 a group of local authorities appealed the tariff decision for electricity distribution companies. They argued that the tariffs should be reduced because the capital costs were set too high. The Conseil dEtat overruled the CRE decision on 28 November 2012, which was replaced retrospectively by an ex-post cost-plus regime. The consultation for the next regulatory period is currently under way taking into account the ruling of the Conseil dEtat. Overall, this shows that the appeals mechanism in France can lead to a price control being overruled. Moodys assessment 31 Stability and Predictability of the Regulatory Regime with Aa rating With regards to Stability and Predictability of the Regulatory Regime Moodys considers the French regulatory framework as modestly riskier in terms of transparency and predictability than the UK framework used as the benchmark and applies an Aa rating to this sub-factor. The reasons are: CRE regulator has commitments in terms of stability of the framework, which in Moody's view reduces the likelihood of any sudden changes to it. CREs methodology and models are published and transparent in terms of capital expenditure and operating expenditures and RAB remuneration.
31 The assessment of Moodys rating is taken out from the rating of the French gas TSO, TIGF. Although TIGF being a gas TSO we assume a similar assessment with regard to gas distribution networks, as the same regulatory principles are applied. 42 Frontier Economics | September 2013
Regulation and risk selected European countries
4.3.2 Regulatory system Cost and Investment Recovery and Revenue Risk Table 8. Regulatory parameters France 32
Regulatory component Description Type of regulation Revenue cap regulation Length of price control 4 years 1 st regulatory period: 2008-2011 2 nd regulatory period: 2012-2015 (reviewed 2-yearly) Opex DSO forecasts operating expenditures, NRA defines OPEX trajectory based on forecast, annual productivity target and inflation RAB Initial RAB: Historical assets (before 2003) revaluated using market-sektor GDP price index and linearly depreciated. Updated RAB: Assets in operation since 2003 included at their gross value (excluding third party contributions and subsidies) Depreciation Assets included in RAB revaluated on 1 st January using the rate of inflation; linear-depreciation on basis of their economic lifetime 33
Investment Planned investment included in RAB at forecasted gross value (CRE fully accepted GrDFs investment forecast) Efficiency analysis No efficiency analysis is conducted Treatment of network losses Expenses and Revenue clawback account (CRCP) reimburses operator for 80% 34 of the differences between purchasing costs for gas and the balance of supplier variance account and inter-operator variance account (GrDF TSO), (calculated ex-post on, based on actual figures); and estimated purchasing costs. In the Event of variation of over 5% between the market price of gas to cover losses and other discrepancies and the forecasted purchase price adopted in the tariff, the benchmarking figure will be reviewed.. Incentives Expenses and Revenue clawback account (CRCP) takes account of variances between actual and forecasted expenses and revenues; increase/decrease of income to be recovered through tariffs (max. 2%/a)
32 CRE, Deliberation of the French Energy Regulatory Commission of 28 February 2012 forming a decision on the equalised tariff for use of GrDF public natural gas distribution networks, 2012; CRE, CREs tariff proposal of 28 February 2008 for use of public natural gas distribution networks, 2008. 33 Economic lifespan of assets: Gas pipes and connections 45-50 yrs.; depressurisation stations 40 yrs.; compression/metering 20 yrs.; other techn. equipment 10 yrs.; buildings 30 yrs. 34 Reduced from 90% in ARTD3 to 80% in ARTD4. September 2013 | Frontier Economics 43
Regulation and risk selected European countries
Annual productivity target for operating expenses Incentive-mechanism on investment (max 2 Mio./a) Incentive-based quality of service regulation mechanism Financial incentives to promote usage of gas (i.e. in new house building) Source: Frontier For a period of 4 years, CRE defines tariffs through which GrDF is allowed to recover its costs. The tariffs are calculated based on forecasted operating and capital expenses. Opex are annually indexed by inflation and subject to an annual productivity target 35 . The allowed capital costs consist of depreciation and financing costs (WACC multiplied with RAB), which are based on the opening RAB and forecasted investments. The RAB is revaluated annually by inflation. In the 1 st regulatory period (ARTD 3) a correction mechanism (Compte de rgulation des charges et des produits, CRCP) was introduced. This mechanism adjusts the tariffs to take into account the differences between specific outturn expenditures (e.g. investments)/revenues and forecasted expenditures/revenues. The CRCP balance is cleared annually and automatically reduces or increases the income that is to be recovered through the tariffs (capped at 2%/a + carry-over in next year). In addition to annual productivity target for the operating expenditures, incentives for efficient operation are provided by the incentive-based cost control for investment; the incentive-based quality of service regulation; and the incentive-based mechanisms for promoting the use of gas. In the following we illustrate these mechanisms. Incentive-based cost control for investments this instrument was introduced in the 2 nd regulatory period and is new and may increase or decrease the income from tariffs, depending on the positive or negative difference between the forecasted and outturn investments. In addition CRE implemented several quantitative indicators to monitor the investment programme, all of which are reported annually (Figure 3).
35 Fourth regulatory period (ATRD 4): 1,3%. 44 Frontier Economics | September 2013
Regulation and risk selected European countries
Figure 3. Investment indicators
Source: Frontier Incentive-based quality of service regulation CRE implemented an extensive system of indicators monitoring the quality of service provided by the gas network. For each indicator, a trajectory is defined that is monitored on weekly, monthly, quarterly or yearly basis. Indicators being the most important to the functioning of the market are subject to financial penalties and incentives, e.g. the proportion of connections established within the deadline agreed. For this indicator, a basic objective of 82% (85%) of connections <6-10 m/h (>10m/h) and a target objective of 87% (90%) was defined. If the operator does not achieve to meet the basic objective, a penalty of 10,000 per month below the target will become effective. If the operator meets or exceeds the target objective, a bonus of 10,000 per month above the target ratio will be credited to the CRCP. Figure 4 illustrates an extract of the quality of service indicators in place in ATRD4. Investment indicators Length in km of new network development Number of biomethane facilities connection Number of new delivery points (new or replaced) Number of periodic checks and calibrations of industrial meters Number of periodic checks and calibrations of domestic meters Length in km of network replaced Length in km of network laid as restructuring extensions Facilities moved at third party request Number of plans geo-referenced over the year September 2013 | Frontier Economics 45
Regulation and risk selected European countries
Figure 4. Quality of service indicators
Source: Frontier Incentive-based mechanism to promote the use of gas CRE made provisions of 45 Mio. in the operating expenditure for covering additional spending from GrDF related to intensifying the use of its network. These measure aim at promoting the use of gas in the residential and tertiary and industrial-market. A reference trajectory is defined and monitored at the end of the regulatory period for: Residential market: new housing units with gas heating; and Tertiary and industrial market: sum of total new customers. If either of the trajectories is not fulfilled at the end of 2015, the mechanisms induced a penalty payment (max. 30m across the whole regulatory period), in return, GrDF is allowed to retain any surplus if the trajectories are reached at lower costs. Moodys assessment 36 Cost and Investment Recovery with A rating and Revenue Risk with Aa rating With regards to Cost and Investment Recovery we assume the same A rating Moodys applies to TIGF, because:
36 The assessment of Moodys rating is taken out from the rating of the French gas TSO, TIGF. Although TIGF being a gas TSO we assume a similar assessment with regard to gas distribution networks, as the same regulatory principles are applied. Quality of service monitoring indicators (extract) Number of scheduled appointments missed by DSO Start-ups completed within deadline requested Shut-downs within deadline requested Connections completed within deadline requested Actually taken half-yearly reading Quality of reading submitted to TSO DSOs portal availability rate Responses to supplier complaints within 15 days Responses to supplier complaints within 30 days Publication rate of reading on online portal Variance from contract scope of alternative suppliers Size of imbalance account Level of corrected meter figures Atmospheric emissions of GHG 46 Frontier Economics | September 2013
Regulation and risk selected European countries
Operating costs and capital costs are set for 4-years, providing a clear and transparent view on revenue allowance; Transparent pass-through mechanism for uncontrollable costs; Reasonably incurred investment is automatically added to RAB; Factoring in incentives from efficiency targets, new treatment of investment under-/overspent and quality targets. With regards to Revenue Risk we assume the same Aa rating Moodys applies to TIGF, because volume risk is largely mitigated through an adjustment mechanism, whereby any over- or under-recoveries of revenues are recorded in a regulatory account and adjusted at the next regulatory period. 4.3.3 WACC Table 9. WACC parameter France Parameter Parameter value Risk-free rate (real) 2.2% Asset-Beta 0.46 Equity-Beta 0.76 Market risk premium 5.0% Cost of equity (real, pre-tax) 9.2% Gearing 50.0% Tax 34.4% Debt premium 0.60 Cost of debt 2.8% Inflation rate 2% WACC (real, pre-tax) 6.0% Source: Frontier For each tariff ruling 37 , CRE reassess the various parameters that are used to calculate the WACC. In addition, CRE commissioned a report from an external
37 CRE, Deliberation of the French Energy Regulatory Commission of 28 February 2012 forming a decision on the equalised tariff for use of GrDF public natural gas distribution networks, 2012; CRE, CREs tariff proposal of 28 February 2008 for use of public natural gas distribution networks, 2008. September 2013 | Frontier Economics 47
Regulation and risk selected European countries
provider that examines the costs of capital for gas and electricity networks in Europe. The commissioned report of CRE defined a potential range for the asset beta between 0.35 and 0.45. In its decision for the fourth regulatory period, CRE set the asset beta at 0.46, which is lower than the value used in the previous regulatory period (0.58). With regard to the debt spread CRE increased the value by +20% to 60%. Further changes compared to the previous regulatory period are an increased market risk premium (+0,5pp) and decrease of the real risk-free rate by 0.2 pp (constant nominal risk-free rate). The debt gearing has been increased from 40% to 50%. 48 Frontier Economics | September 2013
Regulation and risk selected European countries
4.4 Key findings Regulation and risk in UK, Germany and France UK (Aaa) sets the benchmark for Stability and Predictability of Regulatory Regime. Germany (A) and France (Aa) get a slight lower rating by Moodys. This results in a range of Aaa to A. The regulatory frameworks result in Cost and Investment Recovery in the range of A to Baa and Revenue Risk in the range of Aaa to A. The corresponding beta and debt premium set by the regulatory authorities in UK, Germany and France are asset beta in the range of 0.38 to 0.46; equity beta in the range of 0.76 to 0.90; debt premium in the range of 0.60% to 0.90%. Table 10. Regulation and Risk and the impact on cost of capital UK (2013-2021) Germany (2013-2017) France (2012-2015) Stability and Predictability of Regulatory Regime Aaa A Aa Cost and Investment Recovery A Baa A Revenue Risk Aaa A Aa Asset beta 0.38 0.39 0.46 Equity beta 0.90 0.79 0.76 Debt premium 0.90% na 0.60% Source: UK Moodys; Germany and France and Frontier assessment based on Moodys ratings for HSE Netz (Germany) and TIGF (France)
September 2013 | Frontier Economics 49
Regulation and risk Czech Republic
5 Regulation and risk Czech Republic In the following we compare the regulatory framework of the 3 rd regulatory period for gas distribution companies with the draft proposal from ERO for the 4 th regulatory period and the potential impact on risk faced by the companies. The comparison follows Moodys rating methodology illustrated in Table 3 on the following factors: Stability and Predictability of Regulatory Regime; Cost and Investment Recovery; and Revenue Risk. We draw on the arguments for the selected European countries in Section 4 to draw conclusions on the likely rating impact from EROs proposals and actions on these three rating factors. In addition, we assess the potential effect on selected Moodys key credit metrics from EROs proposed regulatory framework for the 4 th regulatory period. Disclaimer We note that the following ratings are based on Frontiers assessment based on Moodys methodology. Frontiers assessment may be in contrast to Moodys own assessment. 5.1 Stability and Predictability of the Regulatory Regime In the following we will discuss the development of the regulatory environment between the start of the 3 rd regulatory period and the August 2013 proposal from ERO for the 4 th regulatory period. 5.1.1 Frontiers assessment for 3 rd regulatory period rating between Aa and A At the start of the 3 rd regulatory period in 2010 the Czech regulatory system had a history since 2002. During this time ERO showed its ability to react on changing circumstances e.g. due to future investment needs, in a pragmatic way. This eight year history is comparable with Germany and France, as described in Section 4. ERO in principle applied the same regulatory framework as in the 2 nd regulatory period, stated a predictable 15 year assessment period for the replacement investment plans of the companies and there was no change in the market model. The possibility of legal appeal for companies was (and is) restricted in the Czech Republic. We understand from RWE Gasnet that price decisions are considered as a legal regulation/enactment as opposed to individual decisions issued by the competent authorities in individual cases. The conformity of legal regulations/enactments (either decree as statutory instrument or price decision) 50 Frontier Economics | September 2013
Regulation and risk Czech Republic
with the constitutional order or a statue may be reviewed by the Constitutional Court. However, we understand from RWE Gasnet that this procedure is very complicated and a right of appeal seems to be rather illusionary. This legal appeal process differs from those in UK, Germany and France. This will not be an issue if the regulator acts in a predictable way. With regard to Moodys assessment of Stability and Predictability of Regulatory Regime we assess a similar rating for the 3 rd regulatory period as for Germany and France in the range of A and Aa, with a slight bias to A due to the legal appeal process: A means that regulation is generally independent and developed (published methodologies set out principles of risk allocation between companies and customers and are based on established precedents in the same jurisdiction) 38 ; Aa means that regulation is independent, reasonably well established (>10 years of being predictable and stable) and transparent (published methodologies clearly define risk allocation between companies and customers and are generally consistently applied) 39 . 5.1.2 Frontiers assessment for 4 th regulatory period (August 2013 proposal) downrating to Ba or B The time period from 2011 until August 2013 was characterised by various interferences from ERO in the regulatory setting. The main objective of these actions was to reverse the impact on companies revenues from depreciation based on revaluated assets, which was introduced for the 3 rd regulatory period. ERO reasoned these actions by stating that companies investments were below allowed depreciation which contradicts the intention of the asset revaluation. As mentioned in Section 3.2.2 only unpredictable regulatory actions may be potentially harmful by increasing the uncertainty for companies and, ultimately, for investors, which feed into higher cost of capital. 40 Hence, in the following we assess to what extent EROs actions during the 3 rd regulatory period can be classified as unpredictable.
38 Moodys (2009: 11). 39 Moodys (2009: 11). 40 There may be arguments that EROs action were predictable, as already outlined in 2009: If companies do not reinvest revaluated depreciation in asset upgrades in a way to preserve their level and the quality of supply, the Office will introduce a mechanism into regulation, which will ensure that allowed depreciation is used solely for investment purposes under the respective licence (Energy Regulatory Office, Final Report of the Energy Regulatory Office on the regulatory methodology for the third regulatory period, including the key parameters of the regulatory formula and pricing in the electricity and gas industries, p 16, December 2009.). September 2013 | Frontier Economics 51
Regulation and risk Czech Republic
Moodys definition of a lower rating than A for Stability and Predictability of the Regulatory Regime serves as the starting point for this assessment: Ba means that regulatory framework is defined but not consistently applied. 41
B means that regulatory framework is unclear, untested or undergoing significant change, with a history of political interference. 42
Non consistent application of the regulatory framework for the 3 rd
regulatory period ERO launched a consultation process for the 3 rd regulatory period in July 2008. There were extensive discussions between all relevant stakeholders which resulted in the decision from ERO in December 2009. Appendix 2 43 of the decision document included the starting regulatory values for the 3 rd regulatory period. In addition, the companies capital expenditures plans (used to calculate depreciation and the RAB for the period 2010 to 2014) were documented in Appendix 2. This means, companies could expect that investments in line with the documented capital expenditures plan will not induce ERO to take any correcting measures. End of 2011 ERO informed the regulated companies on its intention to assess the way how depreciation was calculated for the 3 rd regulatory period and to analyse companies investment behaviour. In May 2012 (two years after the start of the 3 rd regulatory period) ERO completed the analysis claiming that regulated companies had not reinvested depreciations (from revaluation) and asked companies for respective measures. ERO rejected companies measures and published a proposal to amend the decree on price regulation. This included a new parameter, the so-called Investment Debt Factor (IDF), in the calculation of allowed revenues of electricity and gas network companies for the period 2010 2014. However, on 1 October 2012 Governments Legislative Council dismissed this new parameter as retroactive and therefore incompatible with the legislative order. On 27 November 2012 ERO published a draft amendment of the Decree on Price Regulation proposing a new IDF. In addition, ERO claimed that the existing decree was not in line with the Energy Act when providing regulated entities with revaluated depreciations that were not invested back into the
41 Moodys (2009: 11). 42 Moodys (2009: 11). 43 Energy Regulatory Office, Final Report of the Energy Regulatory Office on the regulatory methodology for the third regulatory period, including the key parameters of the regulatory formula and pricing in the electricity and gas industries, p 68ff, December 2009. 52 Frontier Economics | September 2013
Regulation and risk Czech Republic
regulated business. Again, the Governments Legislative Council dismissed the proposal. On 19 March 2013 ERO published a proposal for the 4 th regulatory period which included a shortening of the 3 rd regulatory period for the gas sector by one year. This proposal also included the reversal of the revaluation of assets accepted in the 3 rd regulatory period. ERO justified its actions with the claimed non- compliance of regulated gas companies with an alleged obligation of annual investment into the gas infrastructure that should equal the approved regulatory depreciations in the given year. On 1 August 2013 ERO published its second proposal for a methodology of the 4 th regulatory period that included a retrospective Investment Debt Fund comparable to the twice dismissed IDF. In addition ERO tried to force the companies to tender all services including services provided internally or by group service companies. Given this history, we conclude that EROs actions can be classified as an unpredictable non-consistent application of the regulatory framework because ERO proposed measures to interfere in the 3 rd regulatory period, e.g. IDF in November 2012, soon after the start of this period. ERO neglected the compliance of gas distribution companies with their planned investments documented in Appendix 2 in ERO (2009). We understand from RWE Gasnet that the outturn investments for 2010 and 2011 at that time were above the planned investments. Hence, companies like RWE Gasnet could not expect this interference by ERO, because they behaved consistent with the regulatory decision for the 3 rd regulatory period. ERO proposed to shorten the 3 rd regulatory period from 5 to 4 years in March 2013. Although ERO reversed this proposal again in the August 2013 document, there were 6 months of unclear application of the current rulings faced by the companies. Undergoing significant change in the 4 th regulatory period In Section 4.1.1 we discussed in relation to the RIIO process in UK that rating agencies are concerned about significant changes in the regulatory framework because of the adverse effect on regulators track record for stability and predictability. We note that it is common practice by regulatory authorities to adjust and change regulatory parameters over time. Hence, the important question is if the proposed changes from ERO for the 4 th regulatory period can be classified as a significant change, from which an impact on Stability and Predictability of Regulatory Regime can be expected. The main changes proposed for the 4 th regulatory period are: September 2013 | Frontier Economics 53
Regulation and risk Czech Republic
Reversal of asset revaluation (both for depreciation and RAB) ERO reversed the revaluation of assets introduced in the 3 rd regulatory period which was meant to mitigate the financing needs due to increasing investments in the coming 15 years. From the 4 th regulatory period onwards the allowed depreciations and the RAB will be derived from a much lower asset value mainly based on historic costs. New split of Regulated Asset Base (RAB) into old and new A The new RAB consists of the investments undertaken from 2007-2013. The old RAB consists of the difference between the RAB 2009 plus investments 2010-2013 and the new RAB. Depreciation for the old RAB is calculated by using a residual lifetime, where we understand from RWE Gasnet that ERO targets for about 10 years. Network obsolescence factor ERO introduced this factor in August 2013 (it was not included in the March 2013 document). ERO acknowledges the need to mitigate the financing needs of the companies due to increasing investments. We understand that this factor should close the gap between investments and the lower allowed depreciation in the 4 th regulatory. The factor will be determined on the annual replacement needs outlined in ten- year investment plans submitted by regulated entities. However, ERO has not fully specified the calculation of the Network obsolescence factor in detail, yet. Investment fund ERO introduced this fund in August 2013 (it was not included in the March 2013 document). The investment fund records the revenues generated from the Network obsolescence factor not used for replacement investments. As long as the Investment fund is positive the company will not be entitled to receive funds from the Network obsolescence factor. In addition, the initial value of the Investment fund at the start of the 4 th regulatory period is based on the difference between outturn investments and allowed depreciation during the 3 rd regulatory period. Hence, the initial funding results from a retrospective interference into the previous regulatory period. Efficient network use factor This factor should stimulate the use of capacity in the distribution system. We understand that the design of this factor is yet to be decided and the impact on revenues/costs still unclear. There are various reasons to classify the proposal in August 2013 as a significant change, because ERO fundamentally changed its position with regard to asset revaluation compared to the 3 rd regulatory period (and actually also the 54 Frontier Economics | September 2013
Regulation and risk Czech Republic
2 nd regulatory period) introducing substantial discontinuity between regulatory periods; we understand that the legal reasoning for the reversal of the asset revaluation referring to Art 19a Energy Act is disputable jeopardizing the stability of the regulatory framework for the 4 th regulatory period; the reversal of asset revaluation significantly impacts the allowed depreciation and the RAB and is the major difference compared to the 3 rd regulatory period; ERO seems to be aware of the significant impact and tries to mitigate it by the Network obsolescence factor, whereas the detailed design is not clearly outlined in ERO (2013b) 44 ; the initial funding of the Investment fund is based on a retrospective action, which has no precedent in the CZ regulation. In addition, the initial funding of the Investment fund by a retrospective action may jeopardize the legal stability of the 4 th regulatory period. We understand that the Governments Legislative Council dismissed a similar parameter as incompatible with the legislative order. The Constitutional Court may take a similar stance with regard to the price decision for the 4 th
regulatory period; the network utilization factor is a new parameter in the regulatory framework, where the outcome for regulated companies on costs and revenues is yet unclear but based on the initial description in ERO (2013b) tends to result in a downside for companies; the time period to develop and implement these substantial changes and new regulatory parameters is rather short (from August 2012 Mid/End 2013) compared to the RPI-X@20 process by Ofgem with extensive consultations and interactions with all relevant stakeholders lasting more than 5 years (November 2008 to 2013) before the first application.
44 In addition ERO states that it will evaluate the efficient use of the resources derived from this factor and may abolish it. However, it is unclear how ERO defines efficient utilization placing further uncertainty on the long-term stability of this factor. September 2013 | Frontier Economics 55
Regulation and risk Czech Republic
5.1.3 Conclusion Deterioration of Stability and Predictability of Regulatory Regime between 3 rd and 4 th regulatory period Table 11. Stability and Predictability of Regulatory Regime from 3 rd to 4 th regulatory period Factor Weight 3 rd regulatory period 4 th regulatory period (August 2013) Stability and Predictability of Regulatory Regime 15% Aa A Ba B Source: Frontier based on Moodys methodology We note that EROs actions may be classified as a non consistent application of the regulatory framework for the 3 rd
regulatory period; or even a significant change compared to the 3 rd regulatory period. This implies a downgrading on Stability and Predictability of Regulatory Regime from Aa-A to Ba-B with regard to the 4 th regulatory period. Given the value of the weights assigned to this metric, we expect an adverse effect on the overall credit ratings of the gas distribution companies and hence, an impact on the cost of capital. 5.2 Cost and Investment Recovery and Revenue Risk In the following we will discuss the potential impact on Cost and Investment Recovery and Revenue Risk between the 3 rd regulatory period and the August 2009 proposal for the 4 th regulatory period (Table 12). When assessing the impact on risk, we differentiate if the adjustment has a direct impact on Cost and Investment Recovery and Revenue Risk; indirect impact on Cost and Investment Recovery by deteriorating key credit metrics which feed into higher cost of capital. We refer to Section 5.3 for the discussion on the cost recovery with regard to the cost of capital. 5.2.1 Frontiers assessment Cost and Investment Recovery and Revenue Risk with potential for downgrade in 4 th regulatory period Table 12 illustrates the main regulatory parameters and the proposed changes between 3 rd and 4 th regulatory period. 56 Frontier Economics | September 2013
Regulation and risk Czech Republic
Table 12. Regulatory components CZ gas distribution companies Regulatory component 3 rd regulatory period 4 th regulatory period Impact on rating Type of regulation Revenue cap regulation (restricted) Revenue cap regulation Potential adverse direct impact depending on design of network utilisation factor Length of price control 5 years 5 years No impact expected Opex Average 2007-2008 Annual adjustment by inflation factor plus market service index and efficiency factor Economically substantiated costs Exclusion/decreasing of profit margins from intra-group service level agreements Adjustment for extraordinary or non- standard costs Possibility to retroactively decrease the allowed OPEX basis based on ERO cost inspections even during the period Potential adverse direct impact RAB In principle based on historic costs with the partial revaluation step- up and slower RAB depreciation In principle based on historic costs fully depreciated by allowed depreciation including the Network obsolescence factor Claw-back of the former revaluation step-up Potential adverse indirect impact via Key credit metrics (see Section 5.2.2) Depreciation Based on revaluated assets Based on non- revaluated assets and split between old and new RAB Accelerated depreciation on old RAB Network obsolescence factor included as an tool for depreciation enhancement Investment fund introduced as an retroactive measure to decrease depreciation until the previous depreciation to investment gap is compensated via new Potential adverse indirect impact via Key credit metrics (see Section 5.2.2) September 2013 | Frontier Economics 57
Regulation and risk Czech Republic
investment spendings Investment Planned investments rolled into RAB with later correction/adjustment to actuals Outturn investments rolled into RAB with t-2 time lag, later compensation via a correction factor with a special interest rate
No impact expected Efficiency analysis / Network utilisation factor No explicit efficiency analysis Possible retrospective efficiency assessment of operating expenditures Possible efficiency assessment of network utilization with possible ERO intervention to whole allowed revenue setting 45
Potential adverse direct impact Treatment of network losses Planned costs and quantitiy with ex post correction Price for losses determined by tendering procedure conducted according to the Public Procurement Act Quantity derived from 5 years average for 2014-2016 average from 2007-2011. For 2017-2018 average from 2009-2013 No correction ex post Potential adverse direct impact Incentives Cost targets for opex by X-factor Cost targets for opex by X-factor but level not yet presented
No impact expected Source: Frontier The revenue cap applied in the 3 rd regulatory period can be classified as a combination of incentive regulation for operating expenditures; cost plus regulation for capital costs; as well as limited volume exposure.
45 Information from RWE Gasnet. 58 Frontier Economics | September 2013
Regulation and risk Czech Republic
This regulatory approach is comparable to the one for gas distribution companies in France described in Section 4.3.2 indicating a rating of at least A for Cost and Investment Recovery and Aa for Revenue Risk. In the following we discuss the proposed changes between the 3 rd and 4 th
regulatory period which may have a direct impact on Cost and Investment Recovery and Revenue Risk: Network utilisation factor ERO (2013b) is vague on the design and impact of the network utilisation factor. However, we note that the specification of this factor may be crucial for companys risk with regard to volume and stranded investments. For example, if the recovery for investment costs depends in part on the utilisation of the physical infrastructure then this will expose the gas distribution company to an uncontrollable risk, which should be somewhere reflected in the cost of capital. The same applies if the utilisation factor has an impact on the volumes used to set tariffs. Network losses The cost for network losses is a substantial part of operating expenditures. ERO (2013b) proposed a change in how the costs for network losses are calculated. The price of gas to cover losses and own technological consumption will result from tendering procedure conducted according to the Public Procurement Act. ERO will establish criteria for candidate eligibility and tender conditions so as to ensure transparency and will monitor the procedure. We understand that ERO will accept outturn prices from this tender process as reasonable. However, the detailed specification from ERO on the tender process is still pending. With regard to the quantity for losses ERO proposes to use 5-years averages to determine the reasonable amount. ERO refers for 2014-2016 on the average from 2007-2011 and then recalculated the quantities for 2017-2018 from the average for 2009-2013. We understand that ERO will apply the recalculated quantities for 2017-2018 even if they are higher. In contrast to the 3 rd
regulatory period no ex post correction for network loss price is applied. Opex assessment ERO proposes efficiency assessments for operating costs. These assessments can take place when setting allowed costs at the beginning of the 4 th regulatory period. In addition, ERO states that such assessments will also be undertaken during the regulatory period. If ERO detects inefficiencies, ERO will reduce cost accordingly (and also retrospectively). In particular, the planned efficiency assessment during the regulatory period is critical. For example, if companies are on or even below the ex ante fixed cost path, this does not guarantee cost recovery, because ERO may assess the cost ex post as inefficient. September 2013 | Frontier Economics 59
Regulation and risk Czech Republic
We conclude that there are various factors having a potential adverse direct impact on the Cost and Investment Recovery and Revenue Risk. The main impact stems from the Network utilisation factor, where the specification and application is still pending. We note that the Network utilisation factor depending on its final specification may induce even a sharp downgrade due to asset stranding and/or high exposure to volume risk. In addition, the new mechanism for network losses may have an adverse impact, as well, if ERO is reluctant on increasing network losses. As long as this is still an unresolved issue we make the assumption that the new parameter will slightly increase the risk of cost recovery and the revenue risk resulting in a small downgrade compared to the 3 rd regulatory period. Finally, the efficiency assessment of operating expenditure which allows a retrospective reduction of costs may jeopardize cost recovery. Table 13. Cost and Investment Recovery and Revenue Risk from 3 rd to 4 th
regulatory period Factor Weight 3 rd regulatory period 4 th regulatory period (August 2013) Cost and Investment Recovery 10% A Baa-Ba Revenue Risk 5% Aa A-Baa Source: Frontier based on Moodys methodology 5.2.2 Frontiers assessment for 4 th regulatory period reversal of asset valuation puts key credit metrics at risk Moodys explicitly rewards measures which increase the cash inflow for regulated companies with a higher credit rating as these measures will have a positive effect for example on adjusted Interest Coverage Ratio (adjICR) and Retained Cash Flow/Capex (RCF/Capex). Moodys values the financial flexibility enjoyed by regulated network companies to fund investment generated by internal cash flows 46 . The asset revaluation applied by ERO in the 3 rd regulatory period provided regulated companies with higher cash inflow by revaluated depreciation and incremental cost of capital on the RAB step-up. In addition, the depreciation rules applied to the RAB indicated a transition phase to increase the RAB to the
46 Such a company would not need to access the markets to raise additional finance and may have a wider range of options to react to changing regulatory assumptions (e.g. reduction in the cost of capital allowed). (Moodys, 2009: 19) 60 Frontier Economics | September 2013
Regulation and risk Czech Republic
revaluated asset figure. Hence, internal cash flow generation should be kept at constant rates in the long-term. The proposed reversal of asset revaluation and the calculation of depreciation based on the lower historic cost value will reduce cash inflows from deprecation in the 4 th regulatory period. In addition the reversal of the RAB step-up will reduce the cash-inflow from the incremental cost of capital on the RAB step-up. Hence, ceteris paribus this will have an adverse impact on the credit metrics, adjICR and RCF/Capex. However, ERO (2013b) explicitly states the objective of securing sufficient source of liquidity for regulated companies to ensure that they have the capacity to finance the investments required. As opposed to the proposal in March 2013, where the reversal of asset revaluation was first proposed, ERO (2013b) includes some measures to mitigate the cash impact. ERO (2013b) proposes to split the RAB into an old and new RAB with different depreciation rules. Depreciation for the old RAB is based on the residual lifetime of the assets. We understand from RWE Gasnet that a target value of around 10 years is planned. Hence, there is a mitigating impact by accelerating depreciation on the old RAB, which may close or narrow the gap between depreciation before and after reversal of asset revaluation. We can not assess the size of this effect. However, we note that accelerated depreciation tends to be a short term solution to a long term investment problem, as an eroded old RAB in around 10 years will trigger refinancing risks in the future and will induce necessary regulatory actions in the near future again. To say it in other words: ERO does not solve the problem, but only shifts the problem to the future. Another proposed instrument by ERO to mitigate the cash impact from lower depreciation is the Network obsolescence factor. The factor provides companies with additional cash inflows based on their replacement needs. However, as mentioned above the detailed specification is still pending. In addition, the statement from ERO on the evaluation of the functioning of the Network obsolescence factor and the possibility to abolish the factor is rather vague. This may jeopardize the expected positive effect on the planning security for investments again. On the other hand, the proposed Investment fund has the potential when first implemented to partly reverse the cash impact from accelerated depreciation and the Network obsolescence factor. Hence, at the beginning of the 4 th regulatory period companies may be confronted with a deterioration of cash flows. September 2013 | Frontier Economics 61
Regulation and risk Czech Republic
We conclude that the impact on Moodys key credit metric like adjICR and RCF/Capex
depends on the interaction between cash reducing and cash increasing parameters proposed for the 4 th regulatory period, where the outcome is yet unclear. However, we would at least expect a slight downward pressure on the credits metrics compared to the 3 rd regulatory period. In addition, the long- term stability of the proposed regulatory framework may be at risk due to the fast eroding old RAB from accelerated depreciation resulting in long-term financing problems. 5.3 WACC Cost recovery for cost of capital at risk The cost of capital represents the minimum rate of return companies must pay in order to attract capital from investors. Regulatory allowances of the cost of capital aim to ensure that the firm can cover its expected financing needs. In this section we analyse if the current WACC proposal by ERO allows cost recovery for cost of equity and debt. In order to assess if the current WACC proposal covers the risks borne by investors in the Czech gas distribution sector it is necessary to compare the risks faced by companies between the 3 rd and 4 th regulatory period. In the following we discuss the WACC applied and proposed by ERO for gas distribution companies for the 3 rd and 4 th regulatory period; the overall development of risk faced by the companies between the 3 rd
and 4 th regulatory period; and the likely impact on the cost of equity and cost of debt. 62 Frontier Economics | September 2013
Regulation and risk Czech Republic
5.3.1 WACC 3 rd and 4 th regulatory period Table 14. WACC 3 rd to 4 th regulatory period 3 rd regulatory period (first year) 4 th regulatory period (March 2013) 4 th regulatory period (August 2013) Risk-free rate 4.60% 4.49% 4.49% Asset beta (unlevered) 0.40 0.50 0.35 Equity beta (levered) 0.62 0.674 0.54 Equity Risk Premium 6.40% 6.09% 6.09% Cost of equity (post tax) 8.54% 8.59% 7.77% Debt premium (implicit)* 0.31% 0.23% 0.23% Cost of Debt (pre tax) 4.91% 4.72% 4.72% Gearing 40% 30% 40% Tax rate 19% 19% 19% WACC (post-tax) 6.72% 7.16% 6.19% WACC (pre-tax) 8.29% 8.84% 7.65% Source: Frontier based on Moodys methodology *Debt premium (implicit) ERO determines the cost of debt by referring to a total cost of debt figure. We calculate the implicit Debt premium by Cost of Debt minus Risk-free rate. Table 14 illustrates the components of the WACC used in the first year of the 3 rd
regulatory period 47 and EROs proposals for the 4 th regulatory period. The WACC proposal of ERO differed between March and August 2013. ERO argued that the new measures proposed in August 2013, e.g. the Network obsolescence factor, reduced the risk of the companies compared to March 2013 indicating a reduction in the cost of capital. As a result ERO decreased the asset beta from 0.50 to 0.35 (which is below the value used in the 3 rd
regulatory period set at 0.40); and
47 The WACC is annually adjusted during the 3 rd regulatory period with regard to the risk-free rate and the cost of debt, while the asset beta and gearing is fixed. However, we note that the following arguments are not affected by this rolling adjustment. September 2013 | Frontier Economics 63
Regulation and risk Czech Republic
increased the notional debt share from 30% to 40%. The current WACC proposal is lower than the WACC for the 3 rd regulatory period (as opposed to the value in March 2013), as well. 5.3.2 Increase in risk between 3 rd and 4 th regulatory period faced by gas distribution companies Based on the discussion in Section 5.1 and 5.2 with regard to Moodys rating factors there are strong indications that the risk faced by gas distribution companies increased between the 3 rd and 4 th regulatory period due to increased uncertainty on Stability and Predictability of Regulatory Regime; and new proposed regulatory parameters which are yet unspecified and may have an adverse effect on Cost and Investment Recovery and Revenue Risk. In addition, we assessed a potential adverse effect on selected Moodys key credit metrics, Adjusted Interest Coverage Rate and Retained Cash Flow/Capex. Table 15. Frontiers assessment Rating factors from 3 rd to 4 th regulatory period Factor Weight 3 rd regulatory period 4 th regulatory period (August 2013) Stability and Predictability of Regulatory Regime 15% Aa A Ba B Cost and Investment Recovery 10% A Baa-Ba Revenue Risk 5% Aa A-Baa adjICR 15% Potential downgrading pressure RCF/Capex 5% Source: Frontier based on Moodys methodology As the factors illustrated in Table 15 sum up to 50% for the relevant factors used by Moodys a downward impact on the credit rating should be expected feeding into the cost of equity by an increase in the beta; and cost of debt by an increase in the debt premium. 64 Frontier Economics | September 2013
Regulation and risk Czech Republic
5.3.3 Cost of equity equity (asset) beta from 3 rd regulatory period plus mark-up for increased risk ERO (2013b) does not include a description how the WACC parameters and in particular the asset beta of 0.35 used to calculate the equity beta of 0.54 are determined. In the following we rely on the description from March 2013 set out in ERO (2013a). ERO proposes to set the WACC parameters in such a way that the WACC is not affected by the expansionary monetary policy in the years 2010 to 2013. Hence, ERO specifies the relevant period for setting the parameters, including the asset beta, with 2005-2009. As opposed to the 3 rd regulatory period ERO calculated the asset beta in March 2013 on a peer-group using vertically integrated energy companies instead of network companies. Due to the higher risk of vertically integrated companies this results per se in a higher asset beta of 0.5. Unfortunately, ERO does not explicitly state the asset beta for pure network companies based on 2005-2009 data. However, the decision for the 3 rd regulatory period may serve as an indication for the respective asset beta for gas network companies for the period 2005-2009. ERO (2009) used data published by Reuters from December 2008 on 20 month asset beta for European gas transmission and distribution companies. This resulted in an average asset beta of 0.37. In addition, ERO compared asset betas used by European regulators to assess the appropriate level, which resulted in an average beta for gas distribution companies of 0.39. As a result, ERO set the asset beta for the gas distribution companies at 0.40 for the 3 rd regulatory period. This implies that the asset beta of 0.35 in ERO (2013b) and the resulting equity beta of 0.54 may be too low because ERO states that 2005-2009 should be the relevant time period for setting the WACC parameters. This means that the asset beta used in the 3 rd regulatory period may serve as a good indication for the market circumstances in the time period 2005-2009. The respective asset beta was 0.40; and the risk faced by equity investors increased in the last years. This should impact the beta, at least by the share of the additional risk which is not diversifiable. We conclude that the asset beta of 0.40 and the resulting equity beta of 0.62 used in the 3 rd regulatory period should be used as starting point for the 4 th regulatory period. In order to allow cost recovery a mark-up on this value covering the increased risk between the 3 rd and 4 th regulatory period should be applied. The upper range of the beta including the mark-up may be derived from the asset beta from ERO (2013a). This asset beta of 0.50 was derived from integrated energy companies September 2013 | Frontier Economics 65
Regulation and risk Czech Republic
reflecting a systematically higher risk than pure network companies. The lower range may be simply derived from the average of 0.40 and 0.50. This implies an asset (equity) beta in the range of 0.45 to 0.50 (0.69 to 0.77) for the 4 th regulatory period. This reflects the fact that the risk for gas distribution companies has not decreased since 2010 (in contrast the risk actually increased). A lower value may put Cost and Investment Recovery for the cost of equity at risk. 5.3.4 Cost of debt short term debt in contrast to long-term commitment for network investments ERO does not calculate the cost of debt by using the risk-free rate plus a debt premium. Instead ERO uses data from the Czech National bank, namely the interest rates provided to non-financial companies in excess of CZK 30 Mio. and fixed for one to five years. In the 3 rd regulatory period ERO adjusted the cost of debt annually based on the one year average of the respective interest rate. For the 4 th regulatory period ERO proposes to fix the cost of debt for the whole period and the monthly averages in the years 2005 to 2009 will be used. ERO specifies the relevant period for setting the cost of debt with 2005-2009, as well. Hence, the market environment relevant for determining the cost of debt for the 3 rd and 4 th regulatory period tends to cover a similar time period. The (implicit) debt premium decreases from 0.31% to 0.23% in the 4 th regulatory period indicating a reduction in the risk faced by debt holders. However, this contradicts the likely downward pressure on the credit rating due to increasing risks. Hence, the same argument as for the beta applies. As the risk for the gas distribution companies did not decrease the (implicit) debt premium of 0.31% should be used as a starting point for the debt premium in the 4 th regulatory period. In line with the cost of equity a mark-up on the debt premium is necessary, as well, covering the increased risk between the 3 rd and 4 th regulatory period. In the following we discuss the potential range of this debt premium. In Section 4.1.3 we discussed that Ofgem is using a total figure for the cost of debt, as well. However, to reflect the long-term character of investments into energy networks Ofgem uses two corporate bonds indices with a maturity exceeding 10 years. Using corporate bonds with a maturity around 10 years is also in line with the calculation of the debt premium in France. Other European countries are using similar approaches, e.g. Netherlands, Austria. For the first year in RIIO-GD1 this implies an implicit debt premium of 0.90% which is substantially above the implicit value applied (0.31%) and proposed (0.23%) by ERO. The difference is mainly driven by the unusual application of short-term interest rates (1-5 years) by ERO when setting the allowed cost of debt. 66 Frontier Economics | September 2013
Regulation and risk Czech Republic
Using short-term interest rates to determine the cost of debt seems to be a CZ specific feature. However, we understand from RWE Gasnet that the application of the short-term interest rate must be seen in a historic perspective. It was part of a regulatory package for the 3 rd regulatory period agreed between ERO and the companies which included allowed depreciation based on revaluated assets; and cost of debt based on short-term interest rates. However, we note that assuming no regulatory package in place, the cost of debt should be set based on long-term interest rates in line with European best practice. Using relevant market data around 2009 allows to proxy an appropriate cost of debt for the 3 rd and 4 th regulatory period based on the respective risk free rate; plus debt premium. OXERA (2011) 48 calculated debt premiums for 2009 in the range of 0.70% to 1.30% based on traded bonds from energy companies with a maturity of around ten years and a credit rating of or close to A. Given the risk-free rates applied for the 3 rd and proposed for the 4 th regulatory period, this implies a long-term cost of debt for the 3 rd regulatory period in the range of 5.30% to 5.90%; as well as 4 th regulatory period in the range of 5.19% to 5.79%. We conclude that the way how ERO currently determines the cost of debt based on a short-term interest rate is in contrast with the long-term investment horizon for networks and European regulators best practice. Hence, the overall level of the regulatory cost of debt is below the market cost of debt indicating a debt premium substantially above the proposed 0.23% in the range of 0.70% to 1.30% in order to allow cost recovery for cost of debt. In addition, ERO may consider including cost of raising debt in the debt premium. In particular, if companies can expect increasing need of new debt due to rising investments in the future. OXERA (2011) 49 showed debt issuance costs for 2009 in the range of 0.10% to 0.20%.
48 OXERA, Cost of capital for GTS: annual estimates from 2006 onwards, Report prepared for NMa, May 2011. 49 OXERA, Cost of capital for GTS: annual estimates from 2006 onwards, Report prepared for NMa, May 2011. September 2013 | Frontier Economics 67
Regulation and risk Czech Republic
5.4 Key findings Regulation and Risk for CZ gas distribution companies EROs actions and the draft regulatory framework from August 2013 may be classified as a non-consistent application of the regulatory framework for the 3 rd regulatory period and significant change compared to the 3 rd
regulatory period. This in addition with other factors indicates an increase in the risk faced by gas distribution companies compared to the 3 rd regulatory period in 2010. The level for asset (equity) beta and debt premium of the 4 th regulatory period should be above the figures used in the 3 rd regulatory period. Cost recovery for equity investors in the 4 th regulatory period implies a range for the asset (equity) beta of 0.45 to 0.50 (0.69 to 0.77). Cost recovery for debt investors implies switching to longer term interest rates in line with European best practice, which results in a substantial higher debt premium in the range of 0.70% to 1.30% compared to the proposed premium proposed for the 4 th regulatory period. In addition, ERO may consider including cost of raising debt in the debt premium in the range of 0.10% to 0.20%. In particular, if companies can expect increasing need of new debt due to rising investments in the future. Adjusted beta and debt premium are in line with respective values in UK, Germany and France, which have higher ratings in particular with regard to Stability and Predictability of Regulatory Regime.
September 2013 | Frontier Economics 69
Conclusion
6 Conclusion Our analysis finds that EROs actions during the 3 rd regulatory period and the draft proposal for the 4 th regulatory period issued on August 2013 has affected the stability of the investment and regulatory climate for CZ energy network companies. We conclude that this resulted in an increase in the risk faced by gas distribution companies compared to the start of the 3 rd regulatory period in 2010. In order to allow cost recovery for the cost of capital the relevant parameters through which this increased risk flows into the WACC beta and debt premium should follow the principles outlined below. Cost of equity The level of the asset (equity) beta from the 3 rd regulatory period should serve as the starting point for the 4 th regulatory period. In order to allow cost recovery a mark-up on this value covering the increased risk between the 3 rd and 4 th regulatory period should be applied. This implies an asset (equity) beta in the range of 0.45 to 0.50 (0.69 to 0.77) for the 4 th regulatory period. Compared with the respective values for UK, Germany and France and taking into account the higher rating in particular for the important factor Stability and Predictability of Regulatory Regime in all three countries this lower bound seems to be a reasonable risk adjusted asset beta and equity beta (Table 16) taking into account the lower notional gearing (40%) proposed by ERO compared with UK (65%), Germany (60%) and France (50%). Cost of debt The risk faced by debt investors between the 3 rd and 4 th
regulatory period did not decrease (in contrary the risk increased). This implies that the implicit debt premium from the 3 rd regulatory period should serve as the starting point for the 4 th regulatory period. However, we further identified a systematic problem in the way ERO currently determines the cost of debt. ERO sets the cost of debt based on a short-term interest rate (1-5years) which is in contrast with the longer term financing and investment horizon for networks and European regulators best practice (substantially above 5 years). Hence, the overall level of the regulatory cost of debt may be substantially below market cost of debt. Hence, the adjustment of the debt premium should reflect the switch from a short-term to a longer-term interest rate. This results in a substantial higher debt premium in the range of 0.70% to 1.30%, which is more in line with the respective values used in UK and France. In addition, ERO should consider including cost of raising debt in the debt premium in the range of 0.10% to 0.20% (Table 16). 70 Frontier Economics | September 2013
Conclusion
Table 16. Regulation and Risk and the impact on cost of capital 3 rd reg- period (2010-2014) 4 th reg-period (Aug 2013) UK (2013-21) Germany (2013-17) France (2012-15) Stability and Predictability of Regulatory Regime Aa A * Ba B* Aaa** A** Aa** Cost and Investment Recovery A* Baa-Ba* A** Baa** A** Revenue Risk Aa* A-Baa* Aaa** A** Aa** adjICR and RCF/Capex Potential downward pressure* - - - Asset beta 0.40 0.35 0.38 0.39 0.46 Equity beta 0.62 0.54 0.9 0.79 0.76 Debt premium (implicit) 0.31% 0.23% 0.90% na 0.60% Frontier adjustments 3 rd reg- period (2010-2014) 4 th reg-period (Aug 2013)
Source: Frontier based on Moodys methodology, Moodys * Assessment by Frontier ** Assessment by Moodys Provided that ERO still insisted in changing the regulatory framework in the 4 th
regulatory period in particular with regard to the reversal of asset revaluation then at least ERO should adopt a more refined logic that explicitly considers the following principles: Avoidance of retrospective interventions Regulators and regulated companies play a repeated interaction game, coming together periodically to agree new cost allowances and incentive mechanisms that will apply for the next period. But the more scope a regulator gives itself to revisit parameters and change the rules of the game after the event, the more clouded the networks effort/reward trade-off becomes, and the more uncertain September 2013 | Frontier Economics 71
Conclusion
investors are of their expected return. Regulators credibility is therefore key: this also includes that retrospective interventions shall be avoided. Specification of regulatory framework The current ERO proposal for the 4 th regulatory period introduces various new regulatory changes and regulatory instruments, e.g. the Network utilisation factor. However, there is a low degree of specification which hampers companies to assess the specific impact on their costs and/or revenues. In order to increase predictability for companies and also investors a detailed description which can be translated into companies business plans should be provided by ERO as soon as possible. Transparent decision rules In order to maximise the regulatory commitment and stability, ERO should base any new measure announced in the decision for the 4 th regulatory period on transparent decisions rules, which are known to the regulated companies ex ante. This means that the regulated companies must know in advance, which behaviour will induce measures by ERO. For example, this refers to the announced audits on the efficient utilisation of funds from the Network obsolescence factor.
September 2013 | Frontier Economics 73
References
7 References Archer, S., H., The regulatory effects on cost of capital in electric utilities. Public Utilities Fortnightly, February 26 1989, pp. 36-9. Burkhard, Regulatory risk and the cost of capital. Determinants and implications for rate regulation. Springer Berlin- Heidelberg 2010. Competition Commission, Phoenix Natural Gas Limited price determination, November 2012. CRE, CREs tariff proposal of 28 February 2008 for use of public natural gas distribution networks, 2008. CRE, Deliberation of the French Energy Regulatory Commission of 28 February 2012 forming a decision on the equalised tariff for use of GrDF public natural gas distribution networks, 2012. Dubin, J., A., and Navarro, P., Regulatory climate and the cost of capital In: regulatory reform and public utilities, ed. By Michael A. Crew, Boston/Dordrecht/London 1982, 141-66. ERO (2009), Final Report of the Energy Regulatory Office on the regulatory methodology for the third regulatory period, including the key parameters of the regulatory formula and pricing in the electricity and gas industries, p 16, December 2009 ERO (2013a), METODIKA REGULACE IV. REGULANHO OBDOB PRO ODVTV PLYNRENSTV, March 2013. ERO (2013b), AKTUALIZOVAN: METODIKA REGULACE IV. REGULANHO OBDOB PRO ODVTV PLYNRENSTV, August 2013. Frontier Economics (2008), Ermittlung des Zuschlages zur Abdeckung netzbetriebsspezifischer Wagnisse im Bereich Strom und Gas, Report for Bundesnetzagentur, 2008. Frontier Economics (2011), Wissenschaftliches Gutachten zur Ermittlung des Zuschlages zur Abdeckung netzbetriebsspezifischer unternehmerischer Wagnisse im Bereich Gas, Report for Bundesnetzagentur, 2011. Gandolfi, Jenkinson and Mayer, 1996. Regulation and the cost of capital, Working Paper, School of Management Studies, University of Oxford. 74 Frontier Economics | September 2013
References
Guthrie, G. (2006), Regulating infrastructure: the impact of risk and investment, Journal of Economic Literature XLIV, 925972. Moodys Investors Service, Rating Methodology Regulated Electric and Gas Networks, 2009. Moodys (2010), RPI-X@20: A Welcome Review of the UK Regulatory Framework but a Step Change Could Raise Credit Risk, Special Comment, June 2010. Moodys (2013), UK Gas Distribution Networks: Transition to RIIO Is Credit Neutral, Special Comment, August 2013. Moodys, Credit Opinion: HSE Netz AG, August 2013 Moodys, Credit Opinion: TIGF SA, August 2013. Ofgem, RIIO Handbook, 2010. Parker, D. (2003), Performance, risk and strategy in privatised, regulated industries: The UKs experience, International Journal of Public Sector Management 16(1), 75 100. Trout, R., R., 1979. The regulatory factor and electric utility common stock investment values. Public Utilities Fortnightly, November 22 1979, pp.28- 31. Wright, S., Mason, R., Miles, D. (2003), A study into certain aspects of the cost of capital for regulated utilities in the U.K., a Smith & Co. Ltd. report to the OFT and U.K. economic regulators.
September 2013 | Frontier Economics 75
References
Frontier Economics Limited in Europe is a member of the Frontier Economics network, which consists of separate companies based in Europe (Brussels, Cologne, London & Madrid) and Australia (Melbourne & Sydney). The companies are independently owned, and legal commitments entered into by any one company do not impose any obligations on other companies in the network. All views expressed in this document are the views of Frontier Economics Limited.
FRONTIER ECONOMICS EUROPE BRUSSELS | COLOGNE | LONDON | MADRID
Frontier Economics Ltd 71 High Holborn London WC1V 6DA Tel. +44 (0)20 7031 7000 Fax. +44 (0)20 7031 7001 www.frontier-economics.com