ADDRESS: SF-1, 1 st FLOOR BHIKAJI CAMA BHAWAN, BHIKAJI CAMA PLACE NEW DELHI -110066 PREFACE
The Concept of Hydro Power development in India has undergone tremendous change since last decade. The new environment for Hydro Power development is the outcome of: 50,000 MW Hydro Power initiative of government of India. Indian Electricity Act, 2003. Concept of allotment of Projects on BOOT basis. EIA notification, 2006. Forest Dwellers Act, 2008.
Need for bringing a document, titled Hydro Power Made Easy was felt to summarize technical, environmental as well as statutory aspects of hydro power development in India for the benefit of Developers, CEO and general public. It is hoped that this document will help in overall understanding of Hydro Power development.
TABLE OF CONTENTS SNO. DESCRIPTION PAGE NO 1. Hydro Power - General 1 4 Annexure 1.1 Major Hydro Electric Power Stations around the World 3 Annexure 1.2 Major Power Stations in India 4 2. Type of Projects 5 9 3. Regulatory Framework 10 11 Annexure 3.1 Structure of the Detailed Project Report according to CEA guidelines, March 07 11 4. Implementation Process 12 16 Annexure 4.1 Preparation of DPR 15 Annexure 4.2 Examination & Approval of DPR 16 5. Hydrology and Power Potential 17 22 Annexure 5.1 10 Day Daily Discharge 18-19 Annexure 5.2 Graph/Table Increment MU/MW 22 6. Design Aspects 23 27 Annexure 6.1 Check List for Site Visit 27 7. Land and Infrastructure Aspects 28 29 Annexure 7.1 Land Requirement Table 29 8. Cost Economics 30 9. Environmental Impact Assessment and Environmental Management Plans 31 43 Annexure 9.1 Model TOR for River Valley and Hydro Power Projects 32 10. Construction Aspects 44 11. Books & Websites 45 46
HYDRO POWER MADE EASY________________________________________________________________________________ 1
1. HYDRO POWER - GENERAL Hydro Power is considered to be clean, non-polluting and renewable source of energy. Estimated Hydro Power Potential of India is estimated at 84000 MW (at 60% load factor) and ultimate possible installed capacity as 150000 MW. Majority of Hydro Power stations are concentrated in five Himalayan states. An approximate distribution of Hydropower Potential in prominent states and prominent rivers is as below: STATE RIVER SYSTEM ESTIMATED CAPACITY (MW) (APPROX.) J ammu and Kashmir J helum Chenab 800 8000 Himachal Pradesh Ravi Beas Sutlej 2300 4600 9400 Uttarakhand Ganga/Yamuna Basin 2400 Sikkim Teesta 3500 Arunachal Pradesh Siang Lohit Subhansiri Dibang Kameng Tawang 18000 7000 15000 11000 4000 1500
Rest of hydro power potential is in other states.
HYDRO POWER MADE EASY________________________________________________________________________________ 2
Between 1950 to 1970, numbers of multipurpose Projects with Hydro Power, an important component were executed. Examples: Bhakra Nangal Dam (1948- 1963), Hirakud Dam (1948-1957), Koyna Dam (Completed in 1963). Between 1970 to 2000, various Hydroelectric Projects were executed by various public sector companies of central government. Examples: Salal I 690 MW (J &K), Chamera I 540 MW (HP), Uri I 480 MW (J &K), Nathpa J hakri 1500 MW (HP) Since 2000, Private sector has started playing major role in Hydro Power sector development. HYDRO POWER MADE EASY________________________________________________________________________________ 3
Annexure 1.1 MAJOR HYDRO ELECTRIC POWER STATIONS AROUND THE WORLD S NO. NAME YEAR OF COMPLETION COUNTRY TOTAL CAPACITY (MW) 1 Three Gorges Dam 2011 China 22500 2 Itaipu 2003 Brazil 14000 3 Guri 1986 Venezuela 10200 4 Tucurui 1984 Brazil 8370 5 Grand Coulee 1980 United States 6809 6 Sayano Sushenskaya 1989 Russia 6400 7 Langton 2009 China 6300 8 Krasnoyarskaya 1972 Russia 6000 9 Robert Bourassa 1981 Canada 5616 10 Churchill Fall 1971 Canada 5429
HYDRO POWER MADE EASY________________________________________________________________________________ 4
Annexure 1.2 MAJOR HYDRO POWER STATIONS IN INDIA S NO. NAME OF THE POWER STATION TOTAL CAPACITY (MW) 1. Bhakra Nangal 1325 MW 2. Koyna 1920 MW 3. Nathpa J hakri 1500 MW 4. Dehar 990 MW 5. Chamera 540 MW 6. Tehri 1000 MW 7. Pong 396 MW 8. Uri 480 MW 9. Salal 690 MW 10. Omkareshwar 520 MW
HYDRO POWER MADE EASY________________________________________________________________________________ 5
2. TYPE OF PROJECTS Hydro Power Projects harness the Hydro Power Potential of rivers in mountains. Most Hydro Projects are run-of-river type. They are provided with small live storage capacity reservoirs enough to meet the requirement of one day storage. Typical components of a Hydro Power Project are: A Diversion Structure (either a Dam or a Barrage) across the river A Water Conductor System A Power House
Depending upon the gradient of the river, Projects can be broadly divided into following two categories: For Rivers with Flat Gradient - Projects with Power House at the toe of the Dam. For Rivers with Steep Gradient - Projects with long Water Conductor System and Power House location away from the Dam.
Capacity of a Power Plant is decided by product of discharge of water flow and head difference between Full Reservoir Level and Power House Tail Water Level. HYDRO POWER MADE EASY________________________________________________________________________________ 6
With different combinations of discharges and heads, Projects with different configurations are possible as illustrated in the following table: TYPE ORDER OF DISCHARGE (CUMECS) ORDER OF HEAD (M) ORDER OF INSTALLED CAPACITY (MW) Type A1, Low Discharge, High Head 5-10 cumecs 400 - 600 m 15 - 50 MW Type A2, Medium Discharge, High Head 20-50 cumecs 400 - 600 m 60 - 250 MW Type A3, High Discharge, High Head 100-200 cumecs 400 - 600 m 350 - 1000 MW Type B1, Low Discharge, Medium Head 20-50 cumecs 200 - 300 m 50 - 120 MW Type B2, Medium Discharge, Medium Head 100-200 cumecs 200 - 300 m 150 - 500 MW Type B3, High Discharge, Medium Head 400-600 cumecs 200 - 300 m 700 - 1500 MW Type C1, Low Discharge, Low Head 100-200 cumecs 50 -100 m 40 - 150 MW Type C2, Medium Discharge, Low Head 400-600 cumecs 50 - 100 m 150 - 500 MW Type C3, High Discharge, Low Head 800-2000 cumecs 50 - 100 m 300 - 1800 MW
HYDRO POWER MADE EASY________________________________________________________________________________ 7
Typical layouts of some of the projects are given below:
CHAMERA POWER STATION
Features: Location: Chamba district, Himachal Pradesh Capacity 540 MW (3 x 180 MW), Underground Power House containing 3 units of 180 MW each Annual Generation: 1664.55 million units Project Cost Rs. 2114.02 Crores, (March'94 price level) Year of Commissioning/Completion Schedule: 1994 140 m high, 295 m long concrete Arch Gravity Dam 6.4 Km long, 9.5 m diameter Head Race Tunnel 2.4 Km long, 9.5 m diameter Tail Race Tunnel HYDRO POWER MADE EASY________________________________________________________________________________ 8
SEWA HYDROELECTRIC POWER PLANT
Features: Location:- State - J &K, District - Kathua, River - Sewa (a tributary of Ravi) Capacity:- 120 MW (3 X 40) Annual Generation:- 533.52 MU (90% dependable year) Year of Commissioning/Completion Schedule: J uly 2010 53 m high Concrete Gravity Dam 6.0 m Horse Shoe Shaped, 289 m length Diversion Tunnel 3.3 m Horse Shoe Shaped concrete lined Head Race Tunnel (HRT), 10.02 Km length. 3 x 40 MW, vertical Pelton Turbine Rated Net Head =560 m, Max. Gross Head =599 m Rated Net Head =560 m, Max. Gross Head =599 m HYDRO POWER MADE EASY________________________________________________________________________________ 9
DHAULIGANGA POWER STATION
Features: Location:- District Pithoragarh in Uttarakhand. Capacity:- Underground Power House containing 4 units of 70 MW each Annual Generation:- 1134.70 MUs Year of Commissioning/Completion Schedule:- October 2005 56 m high concrete faced rock fill Dam 6.5 m Dia., 5.29 km long Head Race Tunnel 6.5 m Dia., 437 m long Tail Race Tunnel HYDRO POWER MADE EASY________________________________________________________________________________ 10
3. REGULATORY FRAMEWORK While water is a state subject, electricity is a subject in concurrent list. Development of hydro power in India is governed by Indian Electricity Act, 2003. As per Electricity Act, 2003, technical concurrence for a Project with Project installed capacity of 100 MW or less and with capital cost less than Rs 500 crores is to be accorded by respective State Government. Projects below 25 MW capacity are generally covered under Small Hydro. Small Hydro is generally dealt at State level by the department of Non Conventional Energy Resources. For Project costing more than 500 crores and with installed capacity of 100MW and more, the technical approval is to be accorded by Central Electricity Authority. A Detailed Project Report is to be prepared for each Project following CEA guidelines (J an 2007) Table of content of a typical DPR is as enclosed in Annexure 3.1 As per Environment protection Act, 1986, all Hydropower Projects shall be required to obtain mandatory Environment Clearance. Therefore besides Detailed Project Report, mandatory Environment Impact Assessment (EIA) Report and Environment Management Plans (EMP) are to be prepared. Refer Section 9. Other approvals /clearance required are: Forest Clearance under Forest Conservation Act, 1980. Land Availability, Water Use etc permissions from State government. HYDRO POWER MADE EASY________________________________________________________________________________ 11
Annexure 3.1 Structure of the Detailed Project Report according to CEA guidelines, March, 2007 The DPR should include the following chapters: Chapter 1 Introduction Chapter 2 J ustification of Project from Power Supply Angle Chapter 3 Basin Development Chapter 4 Inter State/Inter National Aspects Chapter 5 Survey & Investigation Chapter 6 Hydrology Chapter 7 Geology Chapter 8 Reservoir Chapter 9 Power Potential & Installed Capacity Chapter 10 Design of Civil Structures Chapter 11 Electrical & Mechanical Designs Chapter 12 Transmission of Power &Communication Facilities Chapter 13 Construction Programme & Plant Planning Chapter 14 Project Organization Chapter 15 Infrastructure Facilities Chapter 16 Environmental & Ecological Aspects Chapter 17 Cost Estimates Chapter 18 Allocation of Cost Chapter 19 Economic Evaluation Chapter 20 Future Utilisation of Buildings Chapter 21 Recommendations Chapter 22 Clearances Annex 3 (a) List of relevant documents/ references Annex 3 (b) Abstract of Cost Estimates Annex 3 (c) Phasing of expenditure Annex 3 (d) Project estimated cost & financial package summary HYDRO POWER MADE EASY________________________________________________________________________________ 12
4. IMPLEMENTATION PROCESS A) Approval Phase PROCESS DETAIL Project Allotted by State Government MOA with State Government A Pre-Feasibility Report A base document outlining Project concept SPV Formation Project Specific Company Techno-Economic concurrence (Compliance To Indian Electricity Act, 2003) A Detailed Project Report a) Preparation (Annexure 4.1) b) Getting it approved (Annexure 4.2) Environmental Clearance (Compliance to Environment Protection Act, 1986) a) TOR b) EIA/EMP Report c) Public Hearing d) Environment Clearance Forest Clearance (Compliance to Forest Conservation Act, 1960) a) Application at State Level b) Site Visits and Recommendation c) Approval of Central Govt. d) Tree counting e) Deposition of Tree Compensation f) Tree felling g) Land possession Compliance to Forest Dwellers (Act, 2008) Gram Sabha Resolutions for the land to be used for project purposes. Land Acquisition a) Application to State Government b) Field survey c) Section 4 d) Compensations e) Land Possession Other Approvals a) Magazine Sanction Under Explosives Act b) Labour Registration c) Approval/Clearances/NOC from State Departments such as irrigation, fisheries. Quarries and Borrow Areas Approval of State Mining Department.
HYDRO POWER MADE EASY________________________________________________________________________________ 13
B) Financials and Commercials and Others
PROCESS DETAIL DETAILS Transmission Line MOA with State Govt./Power Grid Power Purchase Agreements PTC and other electricity utilities Equity Partners Tie ups Lenders Tie ups
C) Tendering and Award
PROCESS DETAILS Pre-Qualifications Civil, Hydro-Mech and Electro-Mech Tender Document Civil, Hydro-Mech and Electro-Mech Tendering Civil, Hydro-Mech and Electro-Mech Award Civil, Hydro-Mech and Electro-Mech
HYDRO POWER MADE EASY________________________________________________________________________________ 14
D) Execution
PROCESS DETAILS Detailed Engineering EPC Consultant Project Management, Construction Supervision and Quality Assurance Owners Engineer Construction Contractors Attending to Oversight/Monitoring by External Agencies and Submit Progress Reports Monitoring by CEA Monitoring By State Government Monitoring by Environment Panel Monitoring by Forest Department Monitoring by Lenders Monitoring by Equity Partners Local Public/RTI/PIL/Media Implementation of Environment Management Plans under EIA/EMP Good Relations with Locals Coordination with State Govt. and District Administration and Local Panchayats Owners Core Team Financial, Commercial and Technical Management of the Project Overall Owners Core Team HYDRO POWER MADE EASY________________________________________________________________________________ 15
Annexure 4.1 PREPARATION OF DPR OWNERS TEAM FIELD INVESTIGATION AGENCY (AGENCIES) DESIGN CONSULTANT Local Environment Camps and Site Facilities Award, Coordination, Monitoring, payment of field investigation works. Collection of data regarding cost of local inputs for rate analysis Pathways Topographical Surveys Drilling Drift Geophysical Hydrological Measurements Rain Gauges and Weather Station Silt Measurements Construction Material Testing Seismic Parameters Petrography Remote Sensing Data Field Tests Requirements and Supervision of Investigations Hydrological Studies Geological Mapping Geological Report Layout Studies Hydraulic Design of Barrage Hydraulic Design of WCS Design of Powerhouse Power Potential Studies Construction Planning and Equipment Planning Infrastructure Planning Quality Estimates Rate Analysis Cost Estimates Financial Analysis Drawings Volume Review, Comments and Discussion through Independent Consultants First Draft Compilation Discussions Second Draft Final Version HYDRO POWER MADE EASY________________________________________________________________________________ 16
Annexure 4.2 EXAMINATION & APPROVAL OF DPR PROCESS DETAIL Submission of Hydrology Volume in CEA CWC Hydrology Directorate DPR Submission in CEA (4 copies) PAC (CEA) Presentation to CEA HPA (CEA) Submission of 18 copies PAC,HPA (CEA) Examination of Dam Design Dams Directorate, CWC Examination of WCS and PH HCD Directorate, CWC Gates Aspects Gates Directorate Geology GSI Power Potential HPA (CEA) E&M CEA (E&M Designs) Switchyard CEA (Power Systems) Instrumentation CWC Equipment Planning CWC Foundation & Seismicity CWC Qty Aspects CEA, Thermal Civil Design Rate Analysis CWC, Cost Directorate Escalation & IDC CEA,TCD Authority Meeting CEA Updated DPR CEA Concurrence Letter CEA
HYDRO POWER MADE EASY________________________________________________________________________________ 17
5. HYDROLOGY & POWER POTENTIAL Estimating the water availability at Dam Site/ Barrage Site/ Weir Site is one of the most vital inputs for Hydropower planning. Catchment area of the river upto Dam/Barrage/Weir Site and distribution of rainfall in the catchment are two important factors (besides other factors such as snow catchment, vegetation, shape and slope of catchment etc.) influencing the water availability. Water availability is expressed as average of 10 days flow. Thus there will be 36 values in a year and water availability of 10 to 25 years is estimated. It is either based on direct observations at that site or transferred from upstream or downstream sites or from adjoining catchment etc. An example 10 daily series of water availability of a site is given in Annexure 5.1. Variation of flow during monsoon period and during winter period should be particularly noted. To establish the installed capacity of the Project, following two parameters are required: Design Discharge (Q in cumecs) Rated Head (H in meters) Installed capacity is given by P (MW) ={Efficiency *Q*H}/100 Efficiency is the combined efficiency of turbine and generator and can be approximately taken as 0.9 Head is the difference of average reservoir level at the Dam site and Tail water level in the river at the Power House site. Head losses in the water conductor system due to friction and other reasons are to be duly accounted for. HYDRO POWER MADE EASY________________________________________________________________________________ 18
Annexure 5.1 AVERAGE 10-DAILY DISCHARGE (BASED ON DAILY DATA) IN CUMEC (CA=1850 SQKM) YEAR MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 1978 I 466.86 304.92 548.64 854.26 2392.50 3886.49 1744.71 2752.77 1838.93 1256.10 639.81 564.77 II 412.16 421.46 548.75 723.61 2990.12 2676.06 2467.57 2969.70 2444.44 975.06 801.73 140.16 III 379.58 250.47 698.61 2856.63 4907.57 3521.66 1995.70 1780.14 2265.69 403.14 949.55 177.67 1979 I 303.10 365.01 336.16 699.69 2286.69 2169.33 6035.12 7135.28 7656.44 493.28 944.62 504.60 II 178.63 348.36 330.92 757.54 2075.44 3205.31 7231.91 4398.77 4512.50 2252.25 769.36 184.99 III 214.01 435.06 1676.88 997.32 2276.73 7113.74 10073.91 6317.62 1428.84 1025.13 651.61 542.99 1980 I 571.00 401.60 653.85 1122.41 1518.50 2461.00 1485.25 10232.91 3419.53 4107.21 714.84 439.87 II 373.79 298.93 682.96 1312.85 1678.22 2034.85 7553.31 16181.63 3662.47 3096.96 852.56 587.81 III 484.82 285.33 980.98 1273.98 1957.99 2250.64 3377.59 6386.45 4596.45 2248.71 605.90 275.09 1981 I 466.86 417.34 653.85 1122.41 555.54 1870.93 9192.22 6355.21 5808.00 4755.14 1949.10 1461.31 II 412.16 424.42 682.96 1013.32 1655.57 3491.86 8416.24 7322.45 6508.58 2934.34 1370.24 1716.75 III 379.58 391.57 980.98 495.87 2702.45 4874.58 5778.52 6977.48 4847.76 2196.65 1631.97 1408.20 1982 I 1119.35 417.34 653.85 1445.31 1518.50 4028.54 2228.39 4153.55 3999.36 4753.14 2964.76 989.15 II 812.96 424.42 527.74 1633.11 1678.22 3579.03 3869.03 2308.92 7154.08 3807.79 1062.21 1262.12 III 219.13 391.57 541.76 1113.13 1957.99 3912.88 8537.27 4834.03 5603.46 444.21 1001.87 973.77 1983 I 416.44 557.87 513.40 977.67 407.68 1106.41 1206.75 939.99 2126.00 1383.08 139.81 91.98 II 547.68 577.74 548.18 947.63 630.13 114.39 1331.07 1186.84 1477.13 1630.99 145.07 133.43 III 610.38 687.83 584.23 295.19 743.45 4208.03 3167.46 1341.79 1973.43 362.21 106.10 100.01 1984 I 76.90 139.19 315.02 568.56 197.12 2263.69 5807.05 3863.91 2967.79 3119.75 1117.10 1088.28 II 153.88 98.07 438.12 217.98 631.90 2005.18 4383.66 3320.43 3516.31 1894.96 892.80 936.86 III 122.02 128.20 726.54 248.36 1660.69 3037.07 5333.74 2418.83 3118.31 3703.00 817.62 1020.01 1985 I 811.86 591.71 1720.14 4207.54 4058.07 4948.11 2531.01 5463.90 3249.54 4958.76 1117.10 629.28 II 694.42 543.74 1677.27 4117.22 4342.16 4282.26 3521.27 3623.14 5345.87 3004.97 892.80 587.81 III 626.98 542.20 2596.72 3323.28 4214.08 5412.14 3005.44 4357.26 5395.04 2981.91 817.62 532.24 1986 I 466.86 1164.34 1086.65 548.40 1242.52 2188.64 765.05 2226.24 2600.53 3042.92 1441.17 297.81 II 412.16 1114.86 1255.57 637.28 1027.16 2319.57 1902.19 2031.68 3281.83 2658.88 1741.15 174.60 III 379.58 1130.95 921.22 1001.69 1059.16 3650.39 4731.54 2709.85 2752.49 1546.60 1214.69 532.24 1987 I 466.86 417.34 653.85 445.18 678.57 568.11 5445.84 6322.44 6733.21 2413.56 2305.54 1032.89 HYDRO POWER MADE EASY________________________________________________________________________________ 19
HYDRO POWER MADE EASY________________________________________________________________________________ 20
Design discharge is arrived as below: a) From the given hydrological series on water availability, determine 90% dependable year. b) After giving allowance to environmental release, carry out incremental installed capacity vis a vis a incremental energy studies. (by assuming different design discharges and a given rated head) c) The installed capacity and corresponding design discharge are decided considering following factors: Ratio of incremental energy to incremental installed capacity (MU)/(MW) should be between 1.5 to 2. Load factor should be around 50 % A three hour peaking should be desirably available in leanest period. Design energy is generally defined as energy in 90 % dependable year corresponding to 95 % dependable year. For clarity, a solved example is given in Annexure 5.2. HYDRO POWER MADE EASY________________________________________________________________________________ 21
HYDRO POWER MADE EASY________________________________________________________________________________ 22
Incremental v/s Installed Capacity
HYDRO POWER MADE EASY________________________________________________________________________________ 23
6. DESIGN ASPECTS 6.1 General Hydro Powers are site specific. A comprehensive site visit enables the technical team to take suitable decisions regarding site & components (Refer Annexure 6.1 for a typical check list for site visit for better outcome.) Location of Dam and Power House sites and general layout of the Project is evolved considering various factors: River gradient and various tributaries joining the river on either bank Limits defined by upstream and downstream projects Accessibility and existing roads and bridges Topography, Geology and Hydrology
A few typical layouts of existing projects are given as reference.
6.2 Requirement of Live Capacity of the Reservoir A minimum live capacity is the volume of water needed for three hour generation. Higher as well lower volumes are many times accepted.
6.3 Area - Capacity Curve of the Reservoir Area capacity curve of the reservoir is prepared based on topographical survey in suitable scale say 1 in 10000.
6.4 Submergence Aspects and Height of Diversion Structure Due to environmental reasons, excessive submergence is not acceptable. Therefore height of structure is kept to minimum required. HYDRO POWER MADE EASY________________________________________________________________________________ 24
6.5 Whether Dam or Barrage If the height of structure is planned in 20 m 25 m range or below, a Barrage structure on permeable foundation is preferred provided rock foundation in river bed is not too shallow. This is more likely for projects of 100 MW or similar size. In other cases, a Dam of appropriate height is selected. Spillway Capacity and no of gates is fixed based upon design flood which is estimated based upon catchment area size and nature, amount of rainfall etc. Spillway Crest is fixed close to river bed to allow easy flushing of sediments in reservoir.
6.6 Power Intake and Desilting Basin Power Intake consists of a trashrack structure, a bell mouth entrance and gate slots for intake gate. The intake weir is kept sufficiently above spillway crest. Minimum Draw Down Level is fixed based upon water seal criteria to avoid vortex formation. Design discharge for intake is generally 120 % of design discharge for power generation. Extra 20 % discharge is for flushing in desilting basins. Desilting basins shall be either surface or underground. One or more basins shall be provided. For medium and high head schemes, criteria of 90 % removal of 0.2 mm and above particles is used. For low head schemes, criteria of 90 % removal of 0.3 mm and above particles is generally specified. Separate Desilting basins are not provided if suspended silt concentration in the river is quite low or if the reservoir itself can act as a Desilting Basin.
6.7 Head Race Tunnel Alignment, Length and Diameter HRT alignment is based upon prevailing topography and geology. Length of HRT is based upon location of surge shaft besides other factors. HYDRO POWER MADE EASY________________________________________________________________________________ 25
Size of HRT is based upon economic diameter studies. HRT can be both lined and unlined. Geological conditions play important role in the decision. Velocity of water flow in a lined HRT shall be of the order of 3 to 4 m/sec.
6.8 Surge Shaft Location, Diameter and Height Surge Shaft location is determined based upon topographical considerations. A flat topography is preferred. Size is determined based upon Thoma criteria. Maximum upsurge and downsurge levels are computed to determine the height of surge shaft.
6.9 Penstock Alignment, Length and Size Whether Underground or Surface Penstock is to be provided shall depend upon topography, geology as well as economics. Length of Penstock is determined by Surge Shaft and Power House locations. Penstocks shall generally be steel lined, but RCC lined. Pressure Shafts are sometimes provided, when head is low and geological conditions are favourable. Size of Penstock is determined based upon economic diameter considerations. A generally adopted velocity for steel lined penstocks is 5 to 7 m/sec.
6.10 Powerhouse Location, Type and Machine Centre Line Decision to have a Surface or Underground Power House shall depend upon topography, geology and economics. Suitable location shall depend upon geology, topography as well as head to be harnessed. No. of machines shall depend upon type, maximum size as well as flexibility in generation consistent with economy. Machine centre line and other parameters HYDRO POWER MADE EASY________________________________________________________________________________ 26
are determined based upon various established formulae. The Specific Speed as well as Rated Speed both are important considerations. Power House layout is worked out based upon experience and past practices.
6.11 Tail Race and River Joining Works Tail race joins the water from draft tubes back to the river. An upstream slope is given from draft tube to end of weir in the tailrace.
6.12 Hydro- Mechanical Works Hydro mechanical works include both gates and hoists. Radial gates are provided for spillways. Gates are also provided at Power Intake, Surge Shaft and draft tubes which are generally vertical fixed wheel type gates.
6.13 Electro Mechanical Works Electro- mechanical works include turbines, generators, MIV valves, governors and transformers. This also includes control system as well as all auxiliaries in the Power House.
HYDRO POWER MADE EASY________________________________________________________________________________ 27
Annexure 6.1 CHECK LIST FOR SITE VISIT S NO. LIST 1. Find out limits of Upstream Project 2. See Reservoir area 3. See extent of submergence and houses 4. Note river gradient and river width 5. Appreciate left bank and right bank along the river 6. Appreciate possible HRT route 7. Note down various nalas along the route 8. Collect Local information 9. See Surge Shaft area 10. See Pressure Shaft/Penstock route 11. See Power House area 12. See Tail Race area 13. Find out limits of Downstream Project 14. Find out transmission aspects 15. Note down routes and accessibility 16. Find out sources of Construction materials 17. Find out general geological aspects 18. See possible locations of Muck disposal sites 20. See possible location of Facility Areas
Note A GPS and a camera should be necessarily carried during site visit along with toposheet. HYDRO POWER MADE EASY________________________________________________________________________________ 28
7 LAND & INFRASTRUCTURE ASPECTS In a Hydro Power Project, land is required for various purposes as below: Permanent works (Dam, HRT Power House, Pothead Yard etc.) Reservoir submergence Access Roads Construction facilities such as aggregate plants, batching plants and stores and equipment yards Contractors camps Permanent office and township Muck disposal sites Quarry and River shoals for construction materials Explosive magazines
The land can be private land, community land, Govt. land or forest land. Land is either acquired or taken on lease. An example of land requirement statement for a Hydro Project is given in Annexure 7.1
HYDRO POWER MADE EASY________________________________________________________________________________ 29
Annexure 7.1 LAND REQUIREMENT TABLE S NO. PROJECT COMPONENTS TOTAL AREA (IN HA) 1. Barrage Complex a) River Bed b) Surface
0.5 Ha 1.3 Ha
1.8 Ha 2. Penstock, Power House Site, Switch Yard & Tail Race Channel 3.5 Ha 3.5 Ha 3 Surge Shaft 0.3 Ha 0. 3 Ha 4 Under Ground Structure a) Portals (HRT) b) Portals (Ss & Penstock) c) HRT Area (Not Required To Be Acquired)
2 Ha 2 Ha 2.6 Ha
6.6 Ha 5 Muck Disposal Area 10 Ha 10 Ha 6 Magazine Area 0.03 Ha 0.03 Ha 7 Construction Facilities & Contractors Camp 11.5 Ha 11.5 Ha 8 Permanent Colony & Office 3.5 Ha 3.5 Ha 9 Approach Roads a) Roads in Barrage Complex b) Roads in Power House Complex c) Other Roads for Adits, etc. 1.3 Ha 2.6 Ha 0.6 Ha
4.5 Ha 10 Borrow Area 3 Ha 3.0 Ha 11 Submergence a) River Bed b) Surface
0.9 Ha 1.5 Ha
2.5 Ha TOTAL 47.23 Ha HYDRO POWER MADE EASY________________________________________________________________________________ 30
8 COST ECONOMICS Cost of the Project is generally grouped in the following heads: A - Prelimi nary B - Land C - Works (This includes cost of Dam, river diversion and related hydro mechanical works) J - Power Plant (This includes cost of civil and hydro mechanical works of Power Intake, Desilting basin, HRT, Surge Shaft, Pressure Shaft , Penstocks, Power House, Tailrace and Switchyard) Communications (Roads and Bridges) K - Buildings O - Miscellaneous X - Envi ronment and Ecology Establishment costs Electrical works
Once the hard cost is determined, escalation and Interest during construction are calculated based upon construction period and phasing of expenditure. The Tariff of electricity produced is calculated by first working out the annual cost and dividing by the estimated energy produced in a year. Guidelines provided by CERC are generally followed.
HYDRO POWER MADE EASY________________________________________________________________________________ 31
9 EIA & EMP ASPECTS a) Environment Impact Assessment includes: Study of base line data Impact Prediction because of project construction
The study area to be considered is 10 km radius both from Dam and Power House.
The scope of study is as per standard terms of reference sanctioned by Expert Appraisal committee for Hydro Electric Projects constituted by MOEF. (Annexure 9.1) Base line data includes three season data of air, water, noise, traffic, soil as well as study of river hydrology, geology, seismicity, flora and fauna as well as socio- economic and cultural aspects. Impact prediction includes both those during construction as well as during operation. b) Environment Management Plans i nclude: Catchment area treatment Reservoir rim treatment Muck disposal plans R & R Compensatory Afforestation Local area development Public Health management Minimum Release of water for sustenance of aquatic life Cost estimate for the same
HYDRO POWER MADE EASY________________________________________________________________________________ 32
Annexure 9.1 MODEL TOR FOR RIVER VALLEY AND HYDRO POWER PROJECTS
EIA Studies Policy, Legal and Administrative Framework Review of the Country's legislative and administrative frame work within which the Environment Impact Assessment (EIA) is to be undertaken to ensure that the Project is in compliance with national environmental and social requirements. Scoping and Assessment of Alternatives Scoping should be done before EIA, using suitable standard matrices. All the alternatives explored by Project proponent should be studied from the environmental angle. Scoping matrix, likely impacts identified for various aspects of environment (aquatic, terrestrial and socio-economic) during construction and operation phase of the Project must be discussed in brief for each alternative and reasons for selecting the best and optimum alternative on social and environmental considerations, and reasons for rejecting other alternatives be mentioned. Methodology Methods used for collecting data must be mentioned. In analysis of Air, Water and Noise, methodology adopted, instruments used etc., should be mentioned. The land-use/land-cover pattern of the area should be determined through remote sensing studies, interpretation of satellite imagery, topographic sheets coupled with ground truthing. In analysis of terrestrial as well as aquatic biota, the references used as guidelines should be cited. Standard methods must be used for characterizing the diversity and other significant features of the biota and details of field survey given. HYDRO POWER MADE EASY________________________________________________________________________________ 33
The baseline studies will consist of 3 seasonal studies (Pre-monsoon, monsoon and winter seasons) and will be conducted in the following study area.
Study Area: The study area should include the following areas:
Catchment Area Submergence Area Project Area to be acquired for various appurtenant works area within 10 km from main project components (i.e. Dam/Barrage/Diversion structure, Power house etc). To examine the cascading effect, a clear map showing the approved/under construction/completed HEPs on the both U/S and D/S to this project. Connect such information to establish the total length of interference of natural river flow, the total length of tunnelling of the river and the committed unrestricted release from the site of diversion into the main river. Adverse impact on land stability, catchment soil erosion, reservoir sedimentation and spring flow (if any) due to (a) considerable road construction/ widening activity (b) interfere of reservoir with the in- flowing streams (c) blasting for commissioning the HRT, TRT and some other structures should be studied Various maps providing salient features of the project need to be depicted in proper scale map of at least 1:15,000 like
1. The location map of the proposed project. 2. The Project layout shall be superimposed on a contour map of ground elevation showing main project features (viz. location of Dam, head works, main canal, branch canals, quarrying etc.) shall be depicted in a scaled map. 3. Drainage map of the catchment up to the project site. HYDRO POWER MADE EASY________________________________________________________________________________ 34
4. Soil map of the study area. 5. Geological and seismo-tectonic maps of the study area showing main project features. 6. Remote sensing studies, interpretation of satellite imagery, topographic sheets along with ground verification shall be used to develop the land use/land cover pattern of study area using overlay mapping techniques viz. Geographic Information Systems (GISs). False colour composite (FCC) generated from satellite data of study area should be presented.
A. BASELINE DATA 1. Geological and Geophysical Aspects Geography & Physiography of the project area Design discharge & its RI (Recurrence interval) Regional Geology and structure of the catchment Seismicity, tectonics and history of past earthquakes in the area Critical review of the geological features around the project area Impact of project on geological environment. J ustification for location & execution of the project in relation to structural components (Dam/barrage height) 2. Seismo-Tectonics Study of Design Earthquake Parameters A site specific study of earth quake parameters will be done. The results of the site specific earth quake design parameters will be sent for approval of the NCSDP (National Committee of Seismic Design Parameters, Central Water Commission, New Delhi for large Dams.
HYDRO POWER MADE EASY________________________________________________________________________________ 35
3. Hydrology of the basin Hydro Meteorology, drainage systems Catastrophic events like cloud bursts and flash floods, if any would be documented. For estimation of Sedimentation rate direct sampling of river flow is to be done during EIA to get actual silt flow rate (to be expressed in ha-m km-2 year-1). The one year of EIA study will provide an opportunity to do this for ascertaining the actual silt flow rate. Water availability for the project and the aquatic fauna Design discharge and its recurrence interval 4. Biological Resources I. Flora General vegetation pattern and floral diversity viz. trees, shrubs, grasses, herbs, significant microflora etc. Vegetation should cover all groups of plants including lichens and orchids. Forests and forest types Water body inundating forest area Vegetation profile, no. of species in the project area, etc. Community Structure through Vegetation mapping Species Diversity Index (Shanon - Weaver Index) of the biodiversity in the project area as well as plant fossil & phytoplankton Documentation of economically important plants, medicinal as well as timber, fuel wood etc. Endemic, endangered and threatened species Impact of impoundment and construction activities on the vegetation Cropping and Horticulture pattern and practices in the study area. Location of any Biosphere Reserve, National Park or Sanctuary in the vicinity of the project, if any HYDRO POWER MADE EASY________________________________________________________________________________ 36
For categorization of sub-catchments into various erosion classes and for the consequent CAT plan, the entire catchment (Indian portion) is to be considered and not only the directly draining catchment, II. Fauna Fauna study should be carried-out for all groups of animals Inventorisation of terrestrial wildlife and present status Zoogeographic distribution/affinities, Endemic, threatened and endangered species and animal fossil III. Avifauna Fauna study should be carried-out for all groups of animals Status Resident/Migratory/Passage migrants Zoogeographic distribution/affinities, endemic, threatened and endangered species & animal fossils Impact of project on threatened/endangered taxa, if any Inventorisation of terrestrial wildlife and present status along with schedule of the species IV. Aquatic Ecology Aqua- fauna like macro-invertebrates, zooplankton, phytoplanktons, benthos etc. Conservation Status Fish and Fisheries Fish migrations, if any Breeding grounds Impact of Dam building on fish migration and habitat degradation HYDRO POWER MADE EASY________________________________________________________________________________ 37
Overall ecological impact up to 10 Km d/s from the confluence of the TRT with the river and the impact of untreated and waste water in to the river and the alternatives explored. V. Conservation areas and status of threatened/endangered taxa Biotic Pressures Management plan for conservation areas and threatened/endangered taxa VI. Remote Sensing & GIS studies Various maps providing salient features of the project need to be depicted in proper scale map of at least 1:15,000 like
The project layout shall be superimposed on a contour map of ground elevation showing main project features (viz. location of Dam, head works, main canal, branch canals, quarrying etc.) shall be depicted in a scaled map. Delineation of critically degraded areas in the directly draining catchment on the basis of Silt Yield Index as per the methodology of AISLUS. The location map of the proposed project. Land use and land cover mapping. Drainage pattern/map Soil map of the study area Geo-physical features, slope and relief maps Geological and seismotectonic maps of the study area showing main project features. Remote sensing studies, interpretation of satellite imagery, topographic sheets along with ground verification shall be used to develop the land use/land cover pattern of study area using overlay mapping techniques viz. Geographic Information Systems (GISs). HYDRO POWER MADE EASY________________________________________________________________________________ 38
False colour composite (FCC) generated from satellite data of study area should be presented. Demarcation of Snow fed and rain fed areas for a realistic estimate of the water availability. VII. Socio-economic aspects Land details* Demographic profile Ethnographic Profile Economic structure Development profile Agricultural practices Cultural and aesthetics sites Infrastructure facilities: education, health and hygiene, communication network, etc. Impact on socio-cultural and ethnographic aspects due to Dam building report. *Report would include list of all the Project Affected Families with their names, education, land holdings, other properties, occupation, etc.
VIII. Collection of data pertaining to water (Physico-chemical and biological parameters), air and noise environment and likely i mpact during construction and post construction periods. HYDRO POWER MADE EASY________________________________________________________________________________ 39
IX. Air Environment Baseline Information on ambient air quality in the project area covering aspects like SPM, RSPM, Sox, NOx Noise Environment Traffic density in the project area
X. Construction Methodology and Schedule including the tunnel driving operations, machinery and charge density, etc.
B. IMPACT PREDICTION Air Changes in ambient levels and ground level concentrations due to total emissions from point, line and area sources Effects on soils, material, vegetation, and human health Impact of emissions DG sets used for construction power if any, on air environment. Noise Changes in ambient levels due to noise generated from equipment, blasting operations and movement of vehicles Effect on fauna and human health Water Changes in quality Sedimentation of reservoir Impact on fish fauna Impact of sewage disposal HYDRO POWER MADE EASY________________________________________________________________________________ 40
Land Changes in land use and drainage pattern Changes in land quality including effects of waste disposal Riverbank and their stability Impact due to submergence Biological Deforestation and shrinkage of animal habitat Impact on fauna and flora (including aquatic species if any) due to decreased flow of water Impact on rare and endangered species, endemic species, and migratory route of animals, if any Impact on breeding and nesting grounds, if any Impact on animal distribution, migration routes (if any), habitat fragmentation and destruction due to Dam building activity Socio-economic Aspects Impact on the local community including demographic changes Impact on economic status Impact on human health Impact on increased traffic Impact on Holy Places and Tourism Downstream impact on water, land & human environment due to drying up of the river in the stretch between Dam site and Power House site. Positive as well as negative impacts likely to be accrued due to the project are to be listed.
HYDRO POWER MADE EASY________________________________________________________________________________ 41
I. ENVIRONMENTAL MANAGEMENT PLAN (EMP) a) Catchment Area Treatment Plan Delineation of micro-watersheds in the river catchment and mapping of critically degraded areas requiring various biological and engineering treatment measures. Identification of area for treatment based upon Remote Sensing & GIS methodology and Silt Yield Index (SYI) method of AISLUS coupled with ground survey. The prioritization of watershed for treatment based upon SYI. Spatial Information in each micro watershed should be earmarked on maps in the scale of 1:50,000. The Cat plan would be prepared with year-wise Physical and financial details. b) Creation of Green Belt Plan around the Periphery of the Reservoir and Compensatory Afforestation Scheme in consultation with the State Forest department. c) Biodiversity Conservation and Wild life Management Plan for conservation and preservation of endemic, rare and endangered species of flora and fauna (in consultation with the State Wildlife Department) c) Fisheries Development plan for the conservation/management of reveri ne fishes. d) Resettlement & Rehabilitation (R&R) along with social/community development would be framed in consultation with the Project Affected Persons (PAPs), Project Authorities and the State Government. R & R Plan would be drafted according to the NPRR 2003 and the policy of State Government. e) Muck Disposal Plan Suitable sites for dumping of excavated material would be identified in consultation with the State Pollution Control Board and Forest Department)
HYDRO POWER MADE EASY________________________________________________________________________________ 42
f) Energy Conservation Measures g) Dam Break Analysis & Disaster Management Plan. h) Restoration and landscaping of working Areas: reclamation of borrow pits (quarry sites) and construction areas. i) Public Health Delivery System including the provisions for drinking water facility for the local community. j) Management during the Road Construction k) Sanitation & Solid Waste Management Plan for domestic waste from colonies and labour camps, etc. l) Water and Air Quality & Noise Environment Management duri ng construction and post-construction periods. m) Forest Protection Plan n) Reservoir RIM Treatment Plan o) Environmental Monitoring Programme (With physical & financial details covering all the aspects form EMP). p) For such a large and high budget project, neglecting drinking water component may not be justified. Therefore, if supplying safe drinking water to the population surrounding the project area is not to be considered, a clear justification for this may be given q) Option assessment study to show that are the option available for fulfilling the needs of the people that the project hopes to fulfill. This section should also show if and how the proposed project is the least cost option and also include reducing the transmission and distribution losses to the minimum. HYDRO POWER MADE EASY________________________________________________________________________________ 43
r) A summary of Cost Estimate for all the plans (Cost for implementing all the Environmental Management Plans including the cost for implementing Environmental Monitoring Programme, aforesaid compensation, mitigation and management measures, etc.)
In respect of North-East, the following should be added Tribal area development plan as the area is predominantly tribal. Mitigations measures to check shifting cultivation (Zhum Cultivation) in the catchment area with provision for alternative and better agricultural practices In addition to Socio-economic aspects of the study area, a separate chapter on socio-cultural aspects based upon study on Ethnography of the area.
HYDRO POWER MADE EASY________________________________________________________________________________ 44
10 CONSTRUCTION ASPECTS Construction aspects of a hydro electric project can be divided as below: (a) Development of Infrastructure (b) Mobilization of plant and equipments (c) Posting of specialists and workmen (d) Construction materials availability including spares for equipments (e) Availability of design and drawings (g) Execution of civil, mechanical and electro mechanical works Work on all components starts simultaneously. Rainy season affects the work seriously. Manufacture of mechanical and electrical items is generally at the factory. A 4 to 5 years period for construction is considered optimum. Work execution for both surface and underground works can be divided in following different phases: Infrastructure and mobilization phase
Excavation phase
Concrete and reinforcement phase
Grouting and finishing phase
Erection and dry commissioning phase
Reservoir filling, HRT filling and wet testing phase HYDRO POWER MADE EASY________________________________________________________________________________ 45
11 BOOKS & WEBSITES A) Books 1) Brown, Gutherie, "Hydro Electric Engineering Practice" 2) Masonyi, Emil "Water Power Development", Vol I and II 3) Nigam P.S, "Handbook of Hydroelectric Engineering" 4) Varshney R.S," Hydro Power Structures 5) Design of Small Dams HYDRO POWER MADE EASY________________________________________________________________________________ 46
B) Websites
1. MOP www.powermin.nic.in
Indian Electricity Act, 2003 Acts &Notifications New Government Policies & Programmes 2. CEA www.cea.nic.in
Guidelines for Formulation of DPR for HE schemes Best Practices Document Guidelines for accord of concurrence to HE schemes Co-operation with neighboring Countries PFR under 50,000 MW Hydro initiative 3. CERC www.cercind.gov.in
Guidelines vetting the capital cost of HE schemes Procedures for calculating the expected revenues from tariff & charges Regulations,2010 Sharing of interstate transmission charges & losses Regulations,2010 4. CWC www.cwc.nic.in Information on Major Projects of India 5. MOEF www.moef.nic.in
Water (prevention and control of pollution) Act,1974 Air (prevention and control of pollution) Act,1981 Environment Protection Act, 1986 Forest Conservation Act,1980 EIA Notification Act, 2006 6. Ministry of Tribal Affairs www.tribal.gov.in Forest Dwellers Act, 2008 7. BIS www.bis.org.in List of BIS codes under Water Resource Division 8. NHPC www.nhpc.india.com Layout and Salient features of various HE Projects under operation and under construction.