1 Pressure Test Diagram



2 Punch List

3 Data Sheet

4 Pre-pressure test Check list

5 Pressure Test Certificate

6 Post-pressure test Check list (Incl.Reinstatement)

After Hydro test
7 Pipeline Alignment Sheet

8 P&ID

9 Weld Map

10 Pipe Book

11 Threadolet joint details

12 Cold bend Report

13 Launcher & receiver Pressure test report

14 Cathodic Protection report

15 Internal cleaning report

16 Dewatering Diagram

After Hydro test
17 Internal gauging report

18 Test water analysis (CS pipe only)

19 Calibration record of Instrument

20 Filling & Inhibition report

21 Pressurization record

22 Pressure & Temperature log

23 Depressurization record

24 Pipeline Swabbing report

After Hydro test
25 External HBP Coating report

26 Holiday test report (CS Coated UG Pipe only)

27 Inspection check list for Lowering

28 NDE reports

WARA PRESSURE MAINTENANCE PROJECT
Contractor No. : 11050146
Kuwait Oil Company (K.S.C)
TABLE OF CONTENTS
Ser.
No.
Description
Applicable
Remarks
Yes No
1 Pressure Test Diagram
2 Punch List
3 Data Sheet
4 Pre-pressure test Check list
5 Pressure Test Certificate
6 Post-pressure test Check list (Incl.Reinstatement)
After Hydro test
7 Pipeline Alignment Sheet
8 P&ID
9 Weld Map
10 Pipe Book
11 Threadolet joint details
12 Cold bend Report
13 Launcher & receiver Pressure test report
14 Internal cleaning report
15 Dewatering Diagram
16 Internal gauging report(If required)
17 Test water analysis (If required)
18 Calibration record of Instrument
19 Stringing report
20 Survey report
21 Filling & Inhibition report(If required)
22 Pressurization record(If required)
23 Pressure & Temperature log(If required)
For U/G pipeline only
24 Depressurization record(If required)
25 Pipeline Swabbing report
After Hydro test
26 External HBP Coating report
27 Holiday test report (CS Coated UG Pipe only)
28 Inspection check list for Lowering
29 NDE reports
WARA PRESSURE MAINTENANCE PROJECT
Contractor No. : 11050146
Kuwait Oil Company (K.S.C)
TABLE OF CONTENTS
Ser.
No.
Description
Applicable
Remarks
Yes No
1 Pressure Test Diagram
2 Punch List
3 Data Sheet
4 Pre-pressure test Check list
5 Pressure Test Certificate
6 Post-pressure test Check list (Incl.Reinstatement)
After Hydro test
7 Pipeline Alignment Sheet
8 P&ID
9 Weld Map
10 Pipe Book
11 Threadolet joint details
12 Cold bend Report
13 Launcher & receiver Pressure test report
14 Internal cleaning report
15 Dewatering Diagram
16 Test water analysis (If required)
17 Calibration record of Instrument
18 Stringing Report
19 Survey Report
20 Water injection Piping plan
23 Pipeline Swabbing Report
After Hydro test
24 External HBP Coating Report
25 Holiday test report (CS Coated UG Pipe only)
26 Inspection check list for Lowering
27 NDE reports
WARA PRESSURE MAINTENANCE PROJECT
Contractor No. : 11050146
Kuwait Oil Company (K.S.C)
TABLE OF CONTENTS
Ser.
No.
Description
Applicable
Remarks