6 Post-pressure test Check list (Incl.Reinstatement)
After Hydro test 7 Pipeline Alignment Sheet
8 P&ID
9 Weld Map
10 Pipe Book
11 Threadolet joint details
12 Cold bend Report
13 Launcher & receiver Pressure test report
14 Cathodic Protection report
15 Internal cleaning report
16 Dewatering Diagram
After Hydro test 17 Internal gauging report
18 Test water analysis (CS pipe only)
19 Calibration record of Instrument
20 Filling & Inhibition report
21 Pressurization record
22 Pressure & Temperature log
23 Depressurization record
24 Pipeline Swabbing report
After Hydro test 25 External HBP Coating report
26 Holiday test report (CS Coated UG Pipe only)
27 Inspection check list for Lowering
28 NDE reports
WARA PRESSURE MAINTENANCE PROJECT Contractor No. : 11050146 Kuwait Oil Company (K.S.C) TABLE OF CONTENTS Ser. No. Description Applicable Remarks Yes No 1 Pressure Test Diagram 2 Punch List 3 Data Sheet 4 Pre-pressure test Check list 5 Pressure Test Certificate 6 Post-pressure test Check list (Incl.Reinstatement) After Hydro test 7 Pipeline Alignment Sheet 8 P&ID 9 Weld Map 10 Pipe Book 11 Threadolet joint details 12 Cold bend Report 13 Launcher & receiver Pressure test report 14 Internal cleaning report 15 Dewatering Diagram 16 Internal gauging report(If required) 17 Test water analysis (If required) 18 Calibration record of Instrument 19 Stringing report 20 Survey report 21 Filling & Inhibition report(If required) 22 Pressurization record(If required) 23 Pressure & Temperature log(If required) For U/G pipeline only 24 Depressurization record(If required) 25 Pipeline Swabbing report After Hydro test 26 External HBP Coating report 27 Holiday test report (CS Coated UG Pipe only) 28 Inspection check list for Lowering 29 NDE reports WARA PRESSURE MAINTENANCE PROJECT Contractor No. : 11050146 Kuwait Oil Company (K.S.C) TABLE OF CONTENTS Ser. No. Description Applicable Remarks Yes No 1 Pressure Test Diagram 2 Punch List 3 Data Sheet 4 Pre-pressure test Check list 5 Pressure Test Certificate 6 Post-pressure test Check list (Incl.Reinstatement) After Hydro test 7 Pipeline Alignment Sheet 8 P&ID 9 Weld Map 10 Pipe Book 11 Threadolet joint details 12 Cold bend Report 13 Launcher & receiver Pressure test report 14 Internal cleaning report 15 Dewatering Diagram 16 Test water analysis (If required) 17 Calibration record of Instrument 18 Stringing Report 19 Survey Report 20 Water injection Piping plan 23 Pipeline Swabbing Report After Hydro test 24 External HBP Coating Report 25 Holiday test report (CS Coated UG Pipe only) 26 Inspection check list for Lowering 27 NDE reports WARA PRESSURE MAINTENANCE PROJECT Contractor No. : 11050146 Kuwait Oil Company (K.S.C) TABLE OF CONTENTS Ser. No. Description Applicable Remarks